EP2171103A1 EP08784929A EP08784929A EP2171103A1 EP 2171103 A1 EP2171103 A1 EP 2171103A1 EP 08784929 A EP08784929 A EP 08784929A EP 08784929 A EP08784929 A EP 08784929A EP 2171103 A1 EP2171103 A1 EP 2171103A1
Authority
EP
European Patent Office
Prior art keywords
slab
furnace
rolling
temperature
train
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP08784929A
Other languages
German (de)
English (en)
Inventor
Jürgen Seidel
Joachim Ohlert
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SMS Siemag AG
Original Assignee
SMS Siemag AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SMS Siemag AG filed Critical SMS Siemag AG
Publication of EP2171103A1 publication Critical patent/EP2171103A1/fr
Withdrawn legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D8/00Modifying the physical properties by deformation combined with, or followed by, heat treatment
    • C21D8/02Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of plates or strips
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D8/00Modifying the physical properties by deformation combined with, or followed by, heat treatment
    • C21D8/02Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of plates or strips
    • C21D8/0221Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of plates or strips characterised by the working steps
    • C21D8/0226Hot rolling
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B1/00Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations
    • B21B1/46Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling metal immediately subsequent to continuous casting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B1/00Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations
    • B21B1/46Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling metal immediately subsequent to continuous casting
    • B21B1/466Metal-rolling methods or mills for making semi-finished products of solid or profiled cross-section; Sequence of operations in milling trains; Layout of rolling-mill plant, e.g. grouping of stands; Succession of passes or of sectional pass alternations for rolling metal immediately subsequent to continuous casting in a non-continuous process, i.e. the cast being cut before rolling
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D8/00Modifying the physical properties by deformation combined with, or followed by, heat treatment
    • C21D8/12Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of articles with special electromagnetic properties
    • C21D8/1216Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of articles with special electromagnetic properties the working step(s) being of interest
    • C21D8/1222Hot rolling
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D8/00Modifying the physical properties by deformation combined with, or followed by, heat treatment
    • C21D8/02Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of plates or strips
    • C21D8/021Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of plates or strips involving a particular fabrication or treatment of ingot or slab
    • C21D8/0215Rapid solidification; Thin strip casting
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D8/00Modifying the physical properties by deformation combined with, or followed by, heat treatment
    • C21D8/12Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of articles with special electromagnetic properties
    • C21D8/1205Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of articles with special electromagnetic properties involving a particular fabrication or treatment of ingot or slab
    • C21D8/1211Rapid solidification; Thin strip casting
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D9/00Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
    • C21D9/46Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for sheet metals

Definitions

  • the invention relates to a method for producing strips of steel, preferably of silicon steel, in particular of grain-oriented silicon steel, or of multi-phase steel or of a steel with comparatively high alloy contents (eg microalloyed steel), in which initially in a casting machine a slab is cast, which is then rolled in at least one rolling train to the strip and wherein before and / or behind the at least one rolling line is carried out a heating of the slab in at least one furnace. Furthermore, the invention relates to an apparatus for producing a strip of silicon steel and multiphase steel.
  • Grain-oriented silicon steel is currently being rolled in conventional hot strip mills.
  • process routes here.
  • the slab is first pre-rolled after being heated.
  • Pre-rolling increases the process window and has a positive effect on the magnetic properties of the final product.
  • a renewed heating to higher furnace temperatures takes place.
  • the different types of exemption are fertilize, which are to act as inhibitors during the later process steps, as completely as possible brought into solution. This results in a favorable structure formation for the subsequent process.
  • the slab is then rolled in a roughing and finishing line to the thin hot strip finished.
  • Multiphase steels are usually produced in conventional hot strip mills. Due to the temperature difference over the length when entering the finishing train, it must be accepted that the rolling speed changes over the length in order to set a constant final rolling temperature. The increasing speed along the length of the strip leads to difficulties in setting a homogeneous structure over the length in the cooling section, since multiphase steels must be subjected to complicated temperature-time cycles.
  • the heating before rolling is also used, among other things, the relatively rough and uneven moderate homogenization of castings, but this is only possible to a limited extent. Overall, the manufacturing processes for the production of multiphase steels are still not satisfactory.
  • the solution of this problem by the invention is procedurally characterized in that the slab is heated behind the casting machine and a roughing mill in a first furnace to a rough rolling temperature, that the slab is then rolled in the roughing mill, that the slab behind the roughing mill in a second oven to a defined temperature, which is higher than the rough rolling temperature, is heated and then that the slab is rolled in a finishing train to the final strip thickness.
  • the first oven is dispensed with, and the slab is rolled in the roughing line, using the casting temperature directly in-line with the casting machine. Subsequently, as described above, the heating to a higher temperature and the finish rolling.
  • Vorwalztemperatur is between 1,000 and 1,200 C 0 0 C, and the temperature defined in front of the finishing train between 1,150 and 1,350 C 0 0 C, for silicon steel in particular above 1,200 0 C and for multiphase steel below 1,300 0 C.
  • the strip may be maintained at the elevated temperature, preferably at 1150 ° C to 1300 ° C, for a predetermined hold time in the case of processing multiphase steel until uneven distributions of Alloying elements (segregations) at least partially, preferably completely degraded.
  • the band in case of processing of grain-oriented silicon steel for a predetermined holding time at the elevated temperature, preferably maintained at 1200 0 C to 1350 ° C until the different kinds of precipitates at least partially, preferably completely, placed in solution.
  • the belt can be stored in a ferry or in a furnace in or next to the main transport line during the predetermined holding time.
  • the heating to the higher temperature can be done at least partially by induction heating. It can also be done at least partially by direct flame impingement of the slab. In the latter case, it is preferably provided that the flame is applied directly to the slab by means of a gas jet with at least 75% oxygen into which a gaseous or liquid fuel is mixed. However, it is also an indirect flame application of conventional type with use of oxygen-fuel mixture (oxyfuel process) is provided.
  • a further embodiment of the invention proposal provides that the WaIZ zen of the slab is carried out in batch mode.
  • the rolling of the slab in the endless operation depends on the final thickness to be rolled, the casting speed and the material.
  • the procedure described above with the steps of casting, pre-rolling at a first temperature and subsequent heating to an elevated temperature and finish rolling can be carried out in silicon steels as well as in microalloyed steels and multiphase steels.
  • the device for producing a strip of silicon steel, in particular of grain-oriented silicon steel, as well as of multiphase steel according to the invention is characterized in that between the casting machine and a Vorwalz No. a first furnace is arranged, with which the slab can be heated to a Vorwalztemperatur.
  • the casting heat is utilized and arranged the Vorwalz tiles directly behind the caster.
  • a second furnace is arranged, with which the slab can be heated to an elevated temperature, wherein the second furnace is designed as a high-temperature furnace.
  • a coil box is additionally arranged behind the roughing train as Vorband immediately.
  • the second oven preferably comprises a combination of conventional oven and induction heating. It may also include means for direct flame impingement of the slab. Furthermore, the second furnace may comprise a conventional furnace.
  • a conventional oven and then an induction heater or a device for direct flame impingement of the slab can be arranged first.
  • An alternative provides that in the conveying direction of the slab initially an induction heater or a device for direct flame impingement of the slab and then a conventional furnace are arranged.
  • a further alternative provides that in the conveying direction of the slab initially a conventional oven, then an induction heater or a device for direct flame exposure of the slab and then another conventional oven are arranged.
  • Parts of the first furnace or of the second furnace may also be at least partially designed as a ferry (in particular a pendulum or transverse ferry or coiled ferry), so that in a 2-strand caster both thin slabs are conveyed into the waiver. can never be pushed and rolled on the rolling mill (or rolling mills).
  • a ferry in particular a pendulum or transverse ferry or coiled ferry
  • a 1-strand caster with at least one pendulum or transverse ferry or Coilfähre is possible to allow storage of a thin slab or deformed thin slab in a ferry or in a parallel oven.
  • a pair of scissors is preferably arranged in front of the first oven.
  • the first rolling mill may consist of a single roll stand or of a plurality of rolling stands.
  • It can be used a vertical casting machine or a sheet-casting machine.
  • a further embodiment provides that a roller shutter encapsulation is provided which can be swiveled or introduced into the production line instead of a conventional furnace.
  • a coil box can be placed behind the roughing mill.
  • the at least one induction heater or the at least one device for direct flame impingement of the slab can be displaceably arranged in the direction transverse to the conveying direction of the slab.
  • at least one conventional furnace is provided, which is arranged displaceably in the direction transverse to the conveying direction of the slab to replace the induction heating or the device for direct flame application.
  • the first furnace arranged upstream of the rough rolling mill comprises a device for direct flame impingement of the slab or partly consists of an inductive heating.
  • the roughing train can be arranged directly behind the casting installation without the presence of the first furnace.
  • Parts of the first furnace or the second furnace may be designed as a ferry. It is preferably provided that the ferry is designed as a pendulum or transverse ferry or as Coilfähre to allow storage of a thin slab or a deformed thin slab in an oven next to the main transport line of a 1- or 2-strand caster.
  • the furnace can be used as a production buffer during z. B. serve a roll change. Furthermore, the furnace is provided for purposefully holding the slabs at the elevated temperature prior to finish rolling for metallurgical reasons (for example, compensation of segregation, removal of precipitates into solution).
  • means for high-pressure descaling can be arranged. These are preferably designed for operation with a pressure between 400 and 600 bar.
  • the device may further comprise directional or hold-down rollers and / or a camera for ski detection.
  • the Rieht- or Niederhalterollen and / or the camera are preferably arranged in front of an induction heater.
  • At least one crop shear is located immediately before the induction heating (instead of behind the induction heating).
  • the inventive concept is based on the known CSP technology. This is to be understood as meaning thin-slab thin-strip casting rolling mills which enable efficient production of hot strip if the rigid connection of the continuous casting plant and rolling train and their temperature control are mastered by the entire plant. Following the procedure in the conventional hot strip mill so after casting the thin slab is heated again slightly or exploits the casting temperature, then pre-rolled, brought to a higher temperature for the second time and then finished rolled.
  • FIG. 1 is a schematic view of a casting and rolling plant according to a first embodiment of the invention with a casting machine, a first furnace, a roughing mill, a second furnace and a finishing train;
  • FIG. 3 shows a further embodiment of the cast roll mill, alternative to FIG. 1
  • FIG. 4 shows the second furnace of the casting and rolling plant in an alternative embodiment
  • Fig. 5 shows the second furnace of the casting rolling mill in a further alternative embodiment
  • Fig. 6 shows schematically a casting mill without first furnace with in-line arrangement of casting machine and Vorwalz No.
  • Fig. 1 an embodiment of a thin slab plant is sketched on which the inventive method for producing strips 1 of grain-oriented silicon steel and multi-phase steel can be performed.
  • a vertical casting machine 2 are poured in the slabs 3, for example, 70 mm thickness.
  • a pair of scissors 12 cutting takes place on the desired slab length.
  • a first oven 6 in which the thin slab 3 is brought to about 1,000 to 1,200 0 C Vorwalztemperatur Ti and in which there is a certain temperature compensation in the width direction.
  • a rough rolling 4 which consists of one or more stands and in which the slab 3 is rolled to an intermediate thickness. It is flexible, the rolling of a smoothing pass or a high decrease of z. B. 65% possible.
  • a second furnace 7 is arranged in the form of a holding furnace or temperature compensation furnace.
  • the second oven 7 offers at least as much space to accommodate a pre-formed thin slab. It can also be provided that there is a commuting or lingering of the pre-formed thin slab in the oven.
  • a holding furnace 7 is also a Rollgangkapselung possible in this place (for processing, for example, from normal steel).
  • a coil box is placed behind the Vorwalz
  • an induction heater 8 is arranged, with which the thin slab 3 can be brought to the desired elevated temperature T 2 , relatively uniformly over the cross section.
  • T 2 desired elevated temperature
  • a temperature range of about 1200 to 1350 0 C behind the induction heater 8 is provided.
  • the inductive heating is provided for the intensive heating above 1,150 0 C so the inductive heating is provided.
  • the finish rolling takes place in the finishing train 5, ie in a multi-stand finishing roll on the desired finished strip thickness and finished strip temperature and then the strip cooling in a cooling section 14 and ultimately the winding on a reel 15th
  • the Thin slab can be flexibly heated - if necessary - to high or lower temperatures after pre-deformation.
  • the induction heater 8 is designed to be transversely displaceable, so that alternatively instead of the induction heater 8, a conventional oven (such as the first oven 6) can be pushed into the transport line.
  • DFI direct flame admission
  • conventional oxyfuel process instead of the induction heater 8.
  • DFI direct flame admission
  • the DFI oxyfuel process can advantageously be used for thin-slab heating also in plant variants which have no roughing stand. This is especially true when there is little scale and the kiln length should be short.
  • FIGS. 3, 4 and 5 Other alternatives, especially different furnace arrangements behind the rough rolling mill 4, are shown in FIGS. 3, 4 and 5.
  • FIG. 3 shows the arrangement of an induction heater 8 directly behind the pre-deformation in the framework of the rough rolling mill 4.
  • the induction heater 8 is followed by a conventional furnace 9. With this constellation, a longer stay (hold) at high temperatures can be accomplished. This is intended for the adjustment of desired metallurgical properties for silicon steel and multiphase steel.
  • the inductive heating is divided, namely in a front in the conveying direction F induction heater 8 and a rear induction heater 11, wherein between the two induction heaters 8, 11, a conventional oven 9 is arranged.
  • the proposed plant constellation shows the possibilities of a high-temperature furnace behind a pre-deformation group, which consists of the combination of a conventional furnace with an inductive heating or a special furnace with DFI oxyfuel technology.
  • This makes it possible to produce normal materials, but also special materials, in particular grain-oriented silicon steels.
  • the temperature control can be flexibly adapted, so that here the special grain-oriented silicon steel but also normal steel, such.
  • conventional ovens, roller box casings, special ovens and / or induction heaters may be arranged in any order between pre-forming and finish rolling.
  • the induction heating is optionally transversely displaceable so that replacement with a conventional oven can take place.
  • the temperature control in the furnace after the pre-deformation can be adjusted individually depending on the material produced (grain-oriented silicon steel, multiphase steel or normal steel).
  • the descaling of the grain-oriented steel shortly before the pre-deformation takes place if at all, preferably at a low water quantity of less than 50 m 3 / h / m and a high pressure of more than 400 to 600 bar.
  • a DFI oxyfuel furnace is optionally also provided for the heating of the thin slab directly behind the casting machine 2, for CSP plants with and without pre-deformation.
  • Fig. 6 an alternative embodiment of a thin slab system is shown schematically.
  • the heating in a first furnace before the first rolling train 4 is dispensed with and instead the casting heat is utilized.
  • a casting system 2 Directly after a casting system 2, after the high-pressure descaling 13 3 inline the thin slab rolled at a temperature Ti of about 1000 0 C to 1200 0 C in the roughing train. 4
  • the control of the inlet temperature Ti is done by adjusting the continuous casting cooling and casting speed.
  • the casting plant and the roughing group are coupled.
  • cutting takes place on the shears 12 behind the rough rolling mill 4.
  • the furnace 7 can be dimensioned such that the intermediate strip can fit into it.
  • the further processing ie heating to the elevated temperature T 2 , and finish rolling, etc., takes place in the manner described above.
  • a coil box is arranged behind the pre-rolling line 4 and Scheere 12 as a space-saving Vorband immediately.
  • the system shown can also be operated alternatively or alternatively in endless mode.
  • D. h. The casting machine and the roughing and finishing mill are then coupled together and the rolling is done with casting speed.
  • the cutting to the desired tape length takes place during continuous rolling just before the reel.
  • the roll change is previously switched from continuous operation back to batch mode.
  • the casting speed can be reduced and / or the prefabricated road pull-in speed can be increased.
  • the mechanical protection of the induction heater from damage Rieht- or hold-down rollers and / or a camera for ski detection behind the pre-deformation or before the induction heating and an individual influence on the working roll speeds and different diameters on the roughing stand for avoiding skiing are provided.
  • the temperature control is adjusted and different defined temperatures T 2 are set in front of the finishing train 5 and the components described in the second furnace 7 are used or activated.
  • the second furnace 7 primarily serves as a holding furnace at normal steel
  • a defined elevated temperature is in silicon steel but also in addition to various micro-alloyed steels or multi-phase steel according to the roughing train (z. B. greater than 1150 0 C to 1350 ° C) in the second furnace 7 adjusted and thus positively influenced the properties. That is, the invention or setting the increased intermediate temperature T 2 is not limited to silicon steel, but is also provided for microalloyed steels and multi-phase steels.

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Materials Engineering (AREA)
  • Crystallography & Structural Chemistry (AREA)
  • Thermal Sciences (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Electromagnetism (AREA)
  • Manufacturing & Machinery (AREA)
  • Metal Rolling (AREA)
  • Manufacturing Of Steel Electrode Plates (AREA)
  • Continuous Casting (AREA)

Abstract

La présente invention concerne un procédé de réalisation de bandes (1) en acier au silicium, en particulier en acier au silicium à grains orientés, et en acier à plusieurs phases, une brame (3) étant tout d'abord coulée dans une machine de coulée (2), puis laminée dans au moins un train de laminage (4, 5) pour donner une bande (1), un chauffage de la brame (3) dans au moins un four (6, 7) ayant lieu en amont et/ou en aval du ou des trains de laminage (4, 5). Selon l'invention, afin d'améliorer la qualité et les possibilités de réalisation offertes par l'acier au silicium à grains orientés ou l'acier à plusieurs phases, la brame (3) est portée à une température de prélaminage (T1) dans un premier four (6) en aval de la machine de coulée (2) et en amont d'un train de prélaminage (4), ou la brame (3) se retrouve dans le train de prélaminage (4) par utilisation de la chaleur de coulée, sans impliquer la présence du premier four (6); la brame (3) est ensuite laminée dans le train de prélaminage (4); la brame est alors portée à une température (T2) définie supérieure à la température de prélaminage (T1), dans un second four (7) en aval du train de prélaminage (4); et la brame (3) est laminée dans un train de laminage final (5) pour avoir l'épaisseur de bande définitive.
EP08784929A 2007-07-21 2008-07-21 Procédé et dispositif de laminage à chaud de bandes d'acier au silicium ou d'acier à plusieurs phases Withdrawn EP2171103A1 (fr)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
DE102007034124 2007-07-21
DE102007035149 2007-07-25
DE102008029581A DE102008029581A1 (de) 2007-07-21 2008-06-21 Verfahren und Vorrichtung zum Herstellen von Bändern aus Silizum-Stahl oder Mehrphasenstahl
PCT/EP2008/005964 WO2009012963A1 (fr) 2007-07-21 2008-07-21 Procédé et dispositif de laminage à chaud de bandes d'acier au silicium ou d'acier à plusieurs phases

Publications (1)

Publication Number Publication Date
EP2171103A1 true EP2171103A1 (fr) 2010-04-07

Family

ID=40149245

Family Applications (1)

Application Number Title Priority Date Filing Date
EP08784929A Withdrawn EP2171103A1 (fr) 2007-07-21 2008-07-21 Procédé et dispositif de laminage à chaud de bandes d'acier au silicium ou d'acier à plusieurs phases

Country Status (14)

Country Link
US (1) US8137485B2 (fr)
EP (1) EP2171103A1 (fr)
JP (1) JP2010534137A (fr)
KR (1) KR20100006565A (fr)
CN (1) CN101809173A (fr)
AR (1) AR067868A1 (fr)
AU (1) AU2008280462A1 (fr)
BR (1) BRPI0812549B1 (fr)
CA (1) CA2687434A1 (fr)
DE (1) DE102008029581A1 (fr)
MX (1) MX2009012654A (fr)
RU (1) RU2435657C2 (fr)
TW (1) TW200927313A (fr)
WO (1) WO2009012963A1 (fr)

Families Citing this family (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT507475B1 (de) * 2008-10-17 2010-08-15 Siemens Vai Metals Tech Gmbh Verfahren und vorrichtung zur herstellung von warmband-walzgut aus siliziumstahl
DE102009036378A1 (de) * 2009-08-06 2011-02-17 Sms Siemag Ag Verfahren und Vorrichtung zum Herstellen eines mikrolegierten Stahls, insbesondere eines Röhrenstahls
IT1400002B1 (it) 2010-05-10 2013-05-09 Danieli Off Mecc Procedimento ed impianto per la produzione di prodotti laminati piani
IT1405344B1 (it) * 2010-06-14 2014-01-03 Danieli Off Mecc Linea di laminazione e relativo procedimento
IT1400629B1 (it) * 2010-06-22 2013-06-14 Danieli Off Mecc Procedimento ed impianto di colata e laminazione per realizzare prodotti laminati metallici lunghi
DE102010063279A1 (de) 2010-12-16 2012-06-21 Sms Siemag Ag Walzstraße zur Röhrenstahl- und Dünnbanderzeugung
EP2524971A1 (fr) * 2011-05-20 2012-11-21 Siemens VAI Metals Technologies GmbH Procédé et dispositif de préparation de produits de laminage en acier avant le laminage à chaud
AT511429B1 (de) * 2011-06-10 2012-12-15 Siemens Vai Metals Tech Gmbh Verfahren und vorrichtung zur vorbehandlung eines walzguts vor dem warmwalzen
AT511674B1 (de) * 2011-06-24 2013-04-15 Siemens Vai Metals Tech Gmbh Inbetriebnahme einer fertigwalzstrasse in einer giess-walz-verbundanlage
JP5790276B2 (ja) * 2011-08-08 2015-10-07 東芝三菱電機産業システム株式会社 方向性電磁鋼板の製造ライン及び誘導加熱装置
KR101376565B1 (ko) * 2011-12-15 2014-04-02 (주)포스코 연속 소둔라인 급냉대의 스트립 온도제어 방법 및 장치
TWI552812B (zh) * 2012-01-25 2016-10-11 Sms Group Gmbh 製造金屬帶的方法與設備
CN102764761B (zh) * 2012-07-26 2015-02-25 武汉钢铁(集团)公司 难加工材料近终成形制造方法
KR101828560B1 (ko) * 2014-01-17 2018-02-12 다니엘리 앤드 씨. 오피시네 메카니케 쏘시에떼 퍼 아찌오니 금속 제품 제조를 위한 플랜트 및 방법
JP6152839B2 (ja) * 2014-10-09 2017-06-28 Jfeスチール株式会社 熱延鋼板の製造設備および製造方法
DE102015216512A1 (de) 2015-08-28 2017-03-02 Sms Group Gmbh Anlage nach dem CSP-Konzept sowie Verfahren zum Betreiben einer solchen Anlage
MX2019001962A (es) 2016-08-18 2019-11-28 Karsten Mfg Corp Tratamiento termico localizado.
DE102016216727A1 (de) 2016-09-05 2018-03-08 Sms Group Gmbh Im Endlosbetrieb betreibbare Produktionsanlage und Verfahren zum Betrieb der Produktionsanlage im Störfall
JP6684968B2 (ja) 2016-11-10 2020-04-22 エス・エム・エス・グループ・ゲゼルシャフト・ミト・ベシュレンクテル・ハフツング 連続鋳造圧延設備内において、金属的なストリップを製造するための方法
IT201800004170A1 (it) * 2018-04-03 2019-10-03 Impianto di colata continua e laminazione per la produzione di prodotti metallurgici
DE102019207459A1 (de) * 2018-05-23 2019-11-28 Sms Group Gmbh Gieß-Walzanlage für den Batch- und Endlosbetrieb
WO2021038108A1 (fr) * 2019-08-30 2021-03-04 Sms Group Gmbh Procédé de traitement thermique d'un précurseur d'acier
WO2021115900A1 (fr) * 2019-12-11 2021-06-17 Sms Group Gmbh Train de laminage modulaire, en particulier train de laminage à chaud, de préférence conjointement avec une installation de coulée en amont
DE102021211339A1 (de) * 2020-10-13 2022-04-14 Sms Group Gmbh Vorrichtung und Verfahren zur Herstellung von warmgewalzten Metallbändern
CN112337968B (zh) * 2020-10-29 2023-02-03 中冶南方工程技术有限公司 一种多功能热轧板带生产机组及其生产方法
CN113020283B (zh) * 2021-03-18 2023-01-17 鞍钢股份有限公司 一种取向硅钢热轧钢带的板形控制方法
DE102022208498A1 (de) 2022-08-16 2024-02-22 Sms Group Gmbh Verfahren zum Herstellen metallischer Bänder durch Gießwalzen

Family Cites Families (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1270728A (fr) * 1985-02-25 1990-06-26 Armco Advanced Materials Corporation Methode de production de l'acier au silicium, a grain oriente de structure cubique a faces centrees, a partir de brames
JPS6289501A (ja) * 1985-10-14 1987-04-24 Nippon Kokan Kk <Nkk> スケ−ルフリ−鋳造圧延設備
JP2726919B2 (ja) 1988-05-26 1998-03-11 マンネスマン・アクチエンゲゼルシャフト 連続鋳造により帯鋼又は板鋼を連続製造する方法及び装置
JPH02121704A (ja) 1988-11-01 1990-05-09 Nkk Corp 電磁鋼板の熱間圧延方法
US4898628A (en) * 1989-01-19 1990-02-06 Armco Advanced Materials Corporation Hot working method for producing grain oriented silicon steel with improved glass film formation
CA2020933C (fr) * 1989-07-12 1993-12-21 Kishio Mochinaga Methode de laminage a chaud en continu de brames d'acier a grain oriente
JPH0763725B2 (ja) * 1991-03-29 1995-07-12 新日本製鐵株式会社 一方向性電磁鋼板の連続式熱間圧延設備列
JP3536304B2 (ja) * 1992-01-07 2004-06-07 Jfeスチール株式会社 表面性状に優れ、磁気特性の安定した方向性けい素鋼板の製造方法
DE4234455A1 (de) * 1992-10-13 1994-04-14 Schloemann Siemag Ag Verfahren und Anlage zum Auswalzen von Warmbreitband aus stranggegossenen Dünnbrammen
SE9400807D0 (sv) * 1994-03-09 1994-03-09 Aga Ab Behandling av stål
JP3174457B2 (ja) * 1994-05-17 2001-06-11 株式会社日立製作所 連鋳直結熱間圧延設備およびその圧延方法
DE19524082B4 (de) 1995-07-01 2004-02-26 Sms Demag Ag Anlage zur Herstellung von warmgewalztem Stahlband
JPH10291016A (ja) * 1997-02-21 1998-11-04 Nkk Corp 熱間圧延設備列及び熱延鋼帯の圧延方法
JPH1133601A (ja) * 1997-07-16 1999-02-09 Ishikawajima Harima Heavy Ind Co Ltd 圧延設備
DE19745445C1 (de) * 1997-10-15 1999-07-08 Thyssenkrupp Stahl Ag Verfahren zur Herstellung von kornorientiertem Elektroblech mit geringem Ummagnetisierungsverlust und hoher Polarisation
PL197050B1 (pl) 2001-09-13 2008-02-29 Ak Properties Inc Sposób wytwarzania stali elektrotechnicznej z ziarnem o orientacji (100) [001] przy zastosowaniu walcowania taśm
ITMI20021996A1 (it) * 2002-09-19 2004-03-20 Giovanni Arvedi Procedimento e linea di produzione per la fabbricazione di nastro a caldo ultrasottile sulla base della tecnologia della bramma sottile
TWI248977B (en) * 2003-06-26 2006-02-11 Nippon Steel Corp High-strength hot-rolled steel sheet excellent in shape fixability and method of producing the same
DE602004018942D1 (de) * 2004-11-24 2009-02-26 Giovanni Arvedi Warmgewalztes magnetisches Stahlband zur Herstellung von gestapelten magnetischen Kernblechen
SI1752548T1 (sl) * 2005-08-03 2016-09-30 Thyssenkrupp Steel Europe Ag Metoda za proizvodnjo magnetnega zrnato usmerjenega jeklenega traku

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See references of WO2009012963A1 *

Also Published As

Publication number Publication date
AU2008280462A1 (en) 2009-01-29
RU2010106017A (ru) 2011-08-27
US8137485B2 (en) 2012-03-20
RU2435657C2 (ru) 2011-12-10
DE102008029581A1 (de) 2009-01-22
TW200927313A (en) 2009-07-01
AR067868A1 (es) 2009-10-28
WO2009012963A1 (fr) 2009-01-29
BRPI0812549A2 (pt) 2015-09-01
CN101809173A (zh) 2010-08-18
US20100116380A1 (en) 2010-05-13
KR20100006565A (ko) 2010-01-19
BRPI0812549B1 (pt) 2019-12-31
MX2009012654A (es) 2009-12-14
JP2010534137A (ja) 2010-11-04
CA2687434A1 (fr) 2009-01-29

Similar Documents

Publication Publication Date Title
EP2171103A1 (fr) Procédé et dispositif de laminage à chaud de bandes d&#39;acier au silicium ou d&#39;acier à plusieurs phases
EP1960131B1 (fr) Procede et dispositif pour produire des bandes metalliques par coulee continue et laminage
DE69730750T2 (de) Verfahren zur herstellung eines stahlbandes
EP2162557B1 (fr) Procédé de laminage à chaud et de traitement thermique d&#39;une bande en acier
EP1982134B1 (fr) Four à rouleaux destiné au chauffage et/ou à la compensation de température de produits de coulée continue en acier ou en alliages d&#39;acier et disposition d&#39;un tel four en amont d&#39;un train finisseur à feuillards à chaud
EP2035587B1 (fr) Procédé et dispositif de production de matériau de laminage de feuillards à chaud en acier au silicium à base de brames fines
EP1469954B2 (fr) Procede de production de feuillard lamine a chaud a partir d&#39;aciers austenitiques inoxydables
EP2183065A1 (fr) Procédé et dispositif permettant la fabrication d&#39;une bande métallique par coulée et laminage en continu
DE60004233T2 (de) Verfahren und anlage für inline wärmebehandlung von warmgewalztem walzgut
EP1752549A1 (fr) Procédé de fabrication de bande d&#39;acier magnétique à grains orientés
AT504782A4 (de) Verfahren zur herstellung eines warmgewalzten stahlbandes und kombinierte giess- und walzanlage zur durchführung des verfahrens
EP1305122A1 (fr) Procede et installation de fabrication de produits plats minces
WO2010121763A1 (fr) Procédé et dispositif de coulée continue d&#39;une brame
DE102009036378A1 (de) Verfahren und Vorrichtung zum Herstellen eines mikrolegierten Stahls, insbesondere eines Röhrenstahls
WO2012045629A2 (fr) Procédé et dispositif de fabrication d&#39;une bande métallique par coulée continue et laminage
EP2376240B1 (fr) Procédé de production de bandes métalliques et installation de production pour la mise en oeuvre du procédé
EP3206808B1 (fr) Installation et procédé de fabrication de tôles fortes
DE19913498C1 (de) Verfahren zum Herstellen eines Warmbandes und Warmbandlinie zur Durchführung des Verfahrens
WO1999058263A1 (fr) Procede et systeme pour produire un feuillard d&#39;acier
EP1641573A2 (fr) Dispositif pour la production de feuillard d&#39;acier lamine a chaud, en particulier a partir d&#39;ebauche en bande coulee en continu
DE102006010137A1 (de) Verfahren und Vorrichtung zum Herstellen eines Metallbandes durch Gießwalzen
AT525283B1 (de) Verfahren zur Herstellung eines Dualphasenstahlbands in einer Gieß-Walz-Verbundanlage, ein mit dem Verfahren hergestelltes Dualphasenstahlband und eine Gieß-Walz-Verbundanlage
DE19639298A1 (de) Verfahren und Vorrichtung zur Erzeugung von dünnen Brammen mit direkt anschließendem Walzprozeß/Walzwerk
WO2023016965A1 (fr) Procédé et dispositif pour produire un acier multiphase à haute et ultra-haute limite d&#39;élasticité
DE102008061206A1 (de) Verfahren zur Herstellung von Bändern aus Metall und Produktionsanlage zur Durchführung des Verfahrens

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20100222

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA MK RS

DAX Request for extension of the european patent (deleted)
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN WITHDRAWN

18W Application withdrawn

Effective date: 20110524