CN102425941A - 一种回转窑内衬侧面支撑砌块列砌筑方法 - Google Patents

一种回转窑内衬侧面支撑砌块列砌筑方法 Download PDF

Info

Publication number
CN102425941A
CN102425941A CN2011103754238A CN201110375423A CN102425941A CN 102425941 A CN102425941 A CN 102425941A CN 2011103754238 A CN2011103754238 A CN 2011103754238A CN 201110375423 A CN201110375423 A CN 201110375423A CN 102425941 A CN102425941 A CN 102425941A
Authority
CN
China
Prior art keywords
building block
row
kiln
stones
lateral support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103754238A
Other languages
English (en)
Other versions
CN102425941B (zh
Inventor
赵家贵
刘守城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201110375423.8A priority Critical patent/CN102425941B/zh
Publication of CN102425941A publication Critical patent/CN102425941A/zh
Application granted granted Critical
Publication of CN102425941B publication Critical patent/CN102425941B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Muffle Furnaces And Rotary Kilns (AREA)
  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

本发明公开了一种回转窑内衬侧面支撑砌块列砌筑方法,其特征在于沿焊接基准线焊接第一组第一列砌块的锚固件,砌筑第一列砌块,再焊接第二列砌块的锚固件,砌筑第二列砌块,以此类推砌筑完第一组砌块。在第一列砌块外侧面安装侧面支撑、盘窑、砌筑下一组砌块,以此类推,直至合门。拆除侧面支撑、浇注刚玉浇注层、对砌块进行勾缝。侧面支撑由立杆、顶杆、旋转扣件、微调和木跳板组成。立杆竖直满焊立在窑壳上,立杆平行于砌块列,每隔6米一端焊在窑壳上。顶杆通过旋转扣件与立杆连接,一端与微调连接;在砌块侧面安放木跳板,调整微调,使顶杆通过木跳板顶紧砌块列。本发明避免了砌块松动和投产后窑壳发红的可能性,确保回转窑使用寿命,缩短了砌筑工期。

Description

一种回转窑内衬侧面支撑砌块列砌筑方法
技术领域
本发明涉及回转窑内衬砌筑方法,具体说是一种回转窑内衬侧面支撑砌块列砌筑方法,应用于球团、水泥生产线高温、高压、磨损大的回转窑耐火砌块内衬砌筑施工领域。
背景技术
现有球团、水泥生产线回转窑耐火砌块内衬的砌筑,是在回转窑内部安装径向钢管和微调组合支撑,经双向微调顶紧回转窑耐火内衬,使得回转窑盘窑时耐火内衬不松动。由于径向支撑交错林立,使得回转窑内水平运输受到制约,安装和拆除花费时间较长,影响工期。同时,在安装径向钢管和微调组合支撑时,局部耐火内衬砌块会松动,砌块之间灰缝粘结不好,投产后极易出现回转窑窑壳发红,影响正常生产和回转窑的使用寿命。
发明内容
本发明的目的,就是针对现有技术存在的上述缺点,提供一种回转窑内衬侧面支撑砌块列砌筑方法,不仅要有效预防耐火内衬砌块松动、砌块之间灰缝粘结不好的问题,而且要有利于窑内水平运输,缩短砌筑工期。
本发明提供的一种回转窑内衬侧面支撑砌块列砌筑方法,它是这样实现的:在回转窑窑壳内壁弹设一条与中心线平行的焊接基准线。沿焊接基准线焊接第一组第一列砌块的锚固件,砌筑第一列砌块。再焊接第二列砌块的锚固件,砌筑第二列砌块,以此类推砌筑完第一组砌块。在第一列砌块外侧面安装侧面支撑,盘窑,砌筑下一组砌块,以此类推,直至合门。拆除侧面支撑,浇注刚玉浇注层,对砌块进行勾缝,完成回转窑内衬的砌筑。回转窑内衬侧面支撑砌块列砌筑方法按如下步骤进行:
1、弹设焊接基准线
用木楔对插在回转窑窑体支撑面与窑体滚轮之间,固定回转窑窑体。在回转窑窑壳内壁弹设一条与中心线平行的焊接基准线,所弹直线需经校核合格。
2、砌筑第一组砌块
沿焊接基准线焊接第一组第一列砌块的锚固件,逆时针方向砌筑第一列砌块,用木棰逐个将第一列锚固件与第一列砌块凹槽敲紧背实。再焊接第二列砌块的锚固件,用木棰逐个将第二列锚固件与第一列砌块凹槽敲紧背实,砌筑第二列砌块,以此类推完成第一组砌块砌筑。r型不锈钢锚固件焊接时采用不锈钢焊条氩弧焊,每个锚固件分别固定同一环相邻2块砌块2个角,每块砌块的4个角都用锚固件固定。垂直高度1.5m所对应的弦切窑壳弧长为一组砌块。窑头至窑尾分段同时砌筑每一列砌块。
3、安装侧面支撑
砌筑完第一组砌块后,在第一列砌块外侧面每隔6米安装1个侧面支撑。所述侧面支撑由立杆、顶杆、旋转扣件和微调组成。立杆为长约60公分的Φ48脚手钢管,竖直满焊立在窑壳上。顶杆为长约80公分的Φ48脚手钢管,通过旋转扣件与立杆连接,一端与微调连接。在砌块侧面安放木跳板,调整微调,使顶杆通过木跳板顶紧砌块列。
4、砌筑下一组砌块
用施工平台上的卷扬机向顺时针方向盘窑至下一组砌筑位置,卷扬机销住固定。用木楔对插在窑体滚轮与回转窑支撑面之间,塞紧固定。砌筑下一组砌块。再盘窑,再砌筑,以此类推,直至砌筑完成最后一组的最后一列砌块,合门,
5、拆除侧面支撑
将最后一列砌块盘窑至水平位置,在窑体滚轮与回转窑支撑面之间对插塞紧木楔,使窑体稳定。拆除侧面支撑和木跳板,在未砌筑砌块的区域浇注刚玉浇注层。对砌块进行勾缝,清扫窑体内部,验收合格,完成回转窑内衬的砌筑。灰浆饱满度要求达到95%,灰缝控制在2mm±1。 
与现有技术相比本发明的优点是:砌块与锚固件、砌块与砌块之间都背紧靠实,避免了砌块松动和投产后窑壳发红的可能性,确保回转窑使用寿命。改善了窑内水平运输环境,节省了安装和拆除支撑的时间,缩短了砌筑工期。
附图说明
图1是回转窑内衬侧面支撑砌块列砌筑示意图。
图中1.立杆  2.顶杆  3.旋转扣件  4.微调  5.砌块  6.锚固件7.木跳板  8.木楔  9.  窑体滚轮  10卷扬机  11.回转窑  12.盘窑方向  13.砌筑方向。
具体实施方式
为进一步描述本发明,下面结合图1和实施例对本发明一种回转窑内衬侧面支撑砌块列砌筑方法作进一步描述。
第一步,弹设焊接基准线。
用木楔(8)对插在回转窑(11)窑体支撑面与窑体滚轮(9)之间,固定回转窑(11)窑体。在回转窑(11)窑壳内壁弹设一条与中心线平行的焊接基准线。
第二步,砌筑第一组砌块。
沿焊接基准线焊接第一组第一列砌块的锚固件(6),同一环相邻2块砌块之间焊接1个锚固件(6)。逆时针方向(13)砌筑第一列砌块(5),用木棰逐个将第一列锚固件与第一列砌块凹槽敲紧背实。再焊接第二列砌块(5)的锚固件(6),用木棰逐个将第二列锚固件(6)与第一列砌块(5)凹槽敲紧背实,砌筑第二列砌块(5),以此类推完成第一组砌块砌筑。砌块每组长度为垂直高度1.5m所对应的弦切窑壳弧长。窑头至窑尾分段同时砌筑每列砌块。 
第三步,安装侧面支撑。
砌筑完第一组砌块后,在第一列砌块外侧面每隔6米安装1个侧面支撑。所述侧面支撑由立杆(1)、顶杆(2)、旋转扣件(3)、微调(4)和木跳板(7)组成。立杆(1)竖直满焊立在回转窑(11)窑壳上。顶杆(2)通过旋转扣件(3)与立杆(1)连接;一端与微调(4)连接。在砌块侧面安放木跳板(7),调整微调,使顶杆(2)通过木跳板(7)顶紧砌块列。
第四步,砌筑下一组砌块。
用施工平台上的卷扬机(10)向顺时针方向(12)盘窑至下一组砌筑位置,盘窑卷扬机(10)销住固定。用木楔(8)对插在窑体滚轮(9)与回转窑支撑面之间,塞紧固定,砌筑下一组砌块。再盘窑,再砌筑,以此类推,直至完成最后一组的最后一列砌块,合门。
第五步,拆除侧面支撑。
将最后一列砌块盘窑至水平位置,在窑体滚轮(9)与回转窑支撑面之间对插塞紧木楔(8),使窑体稳定。拆除侧面支撑和木跳板(4),在未砌筑砌块的侧面支撑区浇筑刚玉浇注层。对砌块进行勾缝,清扫窑体内部,验收合格,完成回转窑内衬的砌筑。
2006年某工地120万t/a球团工程和2009年某工地5000t/d水泥生产线工程施中应用本发明,回转窑窑壳内径Φ5000mm,耐火内衬厚度245mm,与传统的回转窑径向支撑砌筑方法相比,分别缩短工期25天和30天,降低成本25万元和60万元。

Claims (4)

1.一种回转窑内衬侧面支撑砌块列砌筑方法,其特征在于在回转窑窑壳内壁弹设一条与中心线平行的焊接基准线,沿焊接基准线焊接第一组第一列砌块的锚固件,砌筑第一列砌块;再焊接第二列砌块的锚固件,砌筑第二列砌块,以此类推砌筑完第一组砌块;在第一列砌块外侧面安装侧面支撑;盘窑,砌筑下一组砌块,以此类推,直至合门;拆除侧面支撑,浇注刚玉浇注层,对砌块进行勾缝,完成回转窑内衬的砌筑;按如下施工步骤进行: 
(1).弹设焊接基准线,包括固定窑体、弹设焊接基准线;
(2).砌筑第一组砌块,包括焊接锚固件、砌筑砌块;
(3).安装侧面支撑,包括在第一列砌块外侧面安装侧面支撑;
(4).砌筑下一组砌块,包括盘窑、砌筑下一组砌块、以次类推直至合门;
(5).拆除侧面支撑,包括拆除侧面支撑、浇筑刚玉浇注层、勾缝。
2.权利要求1所述的一种回转窑内衬侧面支撑砌块列砌筑方法,其特征在所述侧面支撑由立杆、顶杆、旋转扣件、微调和木跳板组成;立杆竖直满焊立在窑壳上;立杆平行于砌块列,每隔6米一端焊在窑壳上;顶杆通过旋转扣件与立杆连接,一端与微调连接;在砌块侧面安放木跳板,调整微调,使顶杆通过木跳板顶紧砌块列。
3.权利要求2所述的一种回转窑内衬侧面支撑砌块列砌筑方法,其特征在于所述侧面支撑的立杆为长约60公分的Φ48脚手钢管,顶杆为长约80公分的Φ48脚手钢管。
4.权利要求1所述的一种回转窑内衬侧面支撑砌块列砌筑方法,其特征在于所述砌块每组长度为垂直高度1.5m所对应的弦切窑壳弧长。
CN201110375423.8A 2011-11-23 2011-11-23 一种回转窑内衬侧面支撑砌块列砌筑方法 Active CN102425941B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110375423.8A CN102425941B (zh) 2011-11-23 2011-11-23 一种回转窑内衬侧面支撑砌块列砌筑方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110375423.8A CN102425941B (zh) 2011-11-23 2011-11-23 一种回转窑内衬侧面支撑砌块列砌筑方法

Publications (2)

Publication Number Publication Date
CN102425941A true CN102425941A (zh) 2012-04-25
CN102425941B CN102425941B (zh) 2014-02-12

Family

ID=45959947

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110375423.8A Active CN102425941B (zh) 2011-11-23 2011-11-23 一种回转窑内衬侧面支撑砌块列砌筑方法

Country Status (1)

Country Link
CN (1) CN102425941B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102980391A (zh) * 2012-12-19 2013-03-20 中冶长天国际工程有限责任公司 一种烧嘴前端耐热层的施工方法
CN102997674A (zh) * 2012-12-27 2013-03-27 中冶长天国际工程有限责任公司 一种回转窑内衬隔热层的施工方法
CN103557695A (zh) * 2013-11-06 2014-02-05 长沙矿冶研究院有限责任公司 一种回转窑筒体内衬筑炉方法
CN104329937A (zh) * 2014-10-31 2015-02-04 章丘华明水泥有限公司 回转窑炉砌砖支撑装置
CN110470134A (zh) * 2019-07-22 2019-11-19 天津天安机电设备安装工程有限公司 一种回转窑的砌筑方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS525605A (en) * 1975-07-03 1977-01-17 Shinagawa Refract Co Ltd Inner lining construction of rotary furnaces
DE2850770A1 (de) * 1978-11-23 1980-06-04 Ssab Svenskt Stal Ab Verfahren und vorrichtung zum erneuern oder ausbessern der inneren auskleidung von eine rotationsachse aufweisenden behaeltern, wie konvertern, oefen, pfannen, insbesondere torpedopfannen
CN1712873A (zh) * 2005-07-14 2005-12-28 西安秦翔科技有限责任公司 一种工业反应炉内层工作衬浇注材料及炉衬衬砌方法
JP2006029666A (ja) * 2004-07-15 2006-02-02 Kogure Seisakusho:Kk ロータリキルン並びにロータリキルンの耐火物内張り施工法及びこれに用いる型枠
CN101140139A (zh) * 2007-09-30 2008-03-12 中国铝业股份有限公司 一种回转窑错台浇注方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS525605A (en) * 1975-07-03 1977-01-17 Shinagawa Refract Co Ltd Inner lining construction of rotary furnaces
DE2850770A1 (de) * 1978-11-23 1980-06-04 Ssab Svenskt Stal Ab Verfahren und vorrichtung zum erneuern oder ausbessern der inneren auskleidung von eine rotationsachse aufweisenden behaeltern, wie konvertern, oefen, pfannen, insbesondere torpedopfannen
JP2006029666A (ja) * 2004-07-15 2006-02-02 Kogure Seisakusho:Kk ロータリキルン並びにロータリキルンの耐火物内張り施工法及びこれに用いる型枠
CN1712873A (zh) * 2005-07-14 2005-12-28 西安秦翔科技有限责任公司 一种工业反应炉内层工作衬浇注材料及炉衬衬砌方法
CN101140139A (zh) * 2007-09-30 2008-03-12 中国铝业股份有限公司 一种回转窑错台浇注方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蒋辉: "回转窑砌筑工艺及质量控制", 《云南冶金》, vol. 34, no. 6, 31 December 2005 (2005-12-31), pages 41 - 43 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102980391A (zh) * 2012-12-19 2013-03-20 中冶长天国际工程有限责任公司 一种烧嘴前端耐热层的施工方法
CN102980391B (zh) * 2012-12-19 2014-12-17 中冶长天国际工程有限责任公司 一种烧嘴前端耐热层的施工方法
CN102997674A (zh) * 2012-12-27 2013-03-27 中冶长天国际工程有限责任公司 一种回转窑内衬隔热层的施工方法
CN102997674B (zh) * 2012-12-27 2015-01-21 中冶长天国际工程有限责任公司 一种回转窑内衬隔热层的施工方法
CN103557695A (zh) * 2013-11-06 2014-02-05 长沙矿冶研究院有限责任公司 一种回转窑筒体内衬筑炉方法
CN103557695B (zh) * 2013-11-06 2015-07-15 长沙矿冶研究院有限责任公司 一种回转窑筒体内衬筑炉方法
CN104329937A (zh) * 2014-10-31 2015-02-04 章丘华明水泥有限公司 回转窑炉砌砖支撑装置
CN110470134A (zh) * 2019-07-22 2019-11-19 天津天安机电设备安装工程有限公司 一种回转窑的砌筑方法
CN110470134B (zh) * 2019-07-22 2020-11-17 天津天安机电设备安装工程有限公司 一种回转窑的砌筑方法

Also Published As

Publication number Publication date
CN102425941B (zh) 2014-02-12

Similar Documents

Publication Publication Date Title
CN102425941A (zh) 一种回转窑内衬侧面支撑砌块列砌筑方法
CN103615884B (zh) 回转窑砌筑方法
CN100578127C (zh) 流态化焙烧炉球拱炉顶及其成形方法
CN110528390B (zh) 临近既有线狭窄空间架设t梁施工方法
CN204174222U (zh) 炼铁热风炉热风管道的修复结构及其修复模具
CN111350281B (zh) 一种核电站干保护设备环形埋件结构
CN110922071A (zh) 一种双膛石灰窑环形通道用砌砖及施工方法
CN104896194A (zh) 封闭、狭窄空间中的管道、支墩及其预埋件的安装工艺
CN111765768A (zh) 一种烧结厂烧结机点火保温炉耐材砌筑施工方法
CN104406402B (zh) 回转窑砌筑方法
CN113586060A (zh) 一种冻结普通掘进预制井壁支护的施工方法
CN209724371U (zh) 一种输水隧洞狭窄空间内衬钢管安装结构
WO2015158074A1 (zh) 一种地下供水玻璃钢夹砂管与钢管连接更换的施工方法
CN101831916B (zh) 一种大型套筒螺栓框架组合式安装的方法
CN105823329B (zh) 一种回转窑安装施工方法
CN102297595A (zh) 一种环形加热炉烧嘴砖快速更换方法
CN109505629A (zh) 一种隧洞内钢管背后回填混凝土结构及施工方法
CN110527766B (zh) 一种高炉风口带整体修补浇筑方法
CN106049972B (zh) 倒锥壳水塔水箱吊装就位***及方法
CN109338066B (zh) 卧式退火炉模块化搬迁施工方法
CN105464060A (zh) 洞内压力钢管支腿铁鞋运输施工方法
CN206859424U (zh) 一种土建施工用混凝土预埋件
CN109469498A (zh) 一种输水隧洞狭窄空间内衬钢管安装结构及其施工方法
CN114635446B (zh) 一种大型钢筒体环形基础的安装方法
CN104988945B (zh) 抽水蓄能电站机组施工方法及临时支撑结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant