CN101458502A - Electrical power system standardized work intelligent control method and special equipment - Google Patents

Electrical power system standardized work intelligent control method and special equipment Download PDF

Info

Publication number
CN101458502A
CN101458502A CNA2008102374901A CN200810237490A CN101458502A CN 101458502 A CN101458502 A CN 101458502A CN A2008102374901 A CNA2008102374901 A CN A2008102374901A CN 200810237490 A CN200810237490 A CN 200810237490A CN 101458502 A CN101458502 A CN 101458502A
Authority
CN
China
Prior art keywords
module
power system
electrical power
mobile phone
voice suggestion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008102374901A
Other languages
Chinese (zh)
Inventor
邓国平
田一鸣
贺铁光
符立新
贺漫清
杨灿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Yincheng Technology Co ltd
Xiangtan Power Bureau Of Hunan Electric Power Co ltd
Original Assignee
Hunan Yincheng Technology Co ltd
Xiangtan Power Bureau Of Hunan Electric Power Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Yincheng Technology Co ltd, Xiangtan Power Bureau Of Hunan Electric Power Co ltd filed Critical Hunan Yincheng Technology Co ltd
Priority to CNA2008102374901A priority Critical patent/CN101458502A/en
Publication of CN101458502A publication Critical patent/CN101458502A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Testing And Monitoring For Control Systems (AREA)
  • Telephonic Communication Services (AREA)

Abstract

The invention discloses a standardized operation intelligent control method in power system and a special device thereof. An ordinary intelligent mobile phone integrates an image collecting unit, a standardized operation database and an expert database module that connect with a data processing analysis software respectively, information processed by the data processing analysis software connects with an audio prompt and message alarm module, and a wireless data transmission unit respectively, the wireless data transmission unit connects with a monitor host in remote control data processing center. The device disclosed by the invention has reasonable structure, good popularity, can guide, control and monitor worker accomplishing various electrical equipment operation and work according with work flow trustily, can be used as secondary device for connecting with a system host through a wireless interface. The device can be widely used in electric power plant, transformer substation, transmission and distribution line, standardized operation of local operation and construction in other industry field.

Description

Electrical power system standardized work intelligent control method and isolated plant
Technical field
The present invention relates to a kind of electrical power system standardized work intelligent control method and isolated plant.
Background technology
The present standardized work system that uses in electric system, use handheld-type intelligent device (as palm PC) replacement operation order or standardized work ticket to operate or operation mostly, this system is actually a kind of operation order of hiding operation item, promptly before finishing the next item up operation, can not show the next item down content of operation, with the operation of avoiding bypassing the immediate leadership of this mode, reach the purpose that prevents maloperation.But in the practical operation, human factor is very complicated, any situation all might take place, if follow the line of least resistance, operation do not beat yet and collude (the operation back beat collude expression operate finish), next step operation can show in the same old way, therefore, can not avoid the operation of bypassing the immediate leadership by the mode of hiding operation item, this system also can not in time correct the faulty operation that personnel's carelessness causes.If can adopt advanced intelligent apparatus, can guide, control and supervise the requirement of operation (operation) personnel according to the electric power safety working regulation, verily carry out on-the-spot standardized work, just can reach curing operation flow process and operation behaviour, reduce the security incident probability greatly, convenient work, the purpose of increasing work efficiency.
Summary of the invention
The object of the present invention is to provide a kind of electrical power system standardized work intelligent control method and control device that replaces palm PC with regular handset.
A kind of electrical power system standardized work intelligent control method of the present invention may further comprise the steps:
(1) operation order is entered into the standardized work intelligence controlling device, and carries out basic setup on request;
(2) before the operation, device carries out identification according to entry information, if meet the requirements, and open system then, voice suggestion " allows operation "; If undesirable, then voice suggestion " authentication failed, terminating operation "
(3) in the operating process, by image unit the operation of key is taken pictures, the image that the graphic processing data module is responsible for taking compresses processing and deposits mobile phone in, by the intellectual analysis processing module operating result is judged, incorrect then warning, and do not allow to carry out next step operation;
(4) voice suggestion and SMS alarm and note control module are responsible for the control between voice suggestion, warning and the mobile phone, and the issue note is informed the related personnel;
(5) the recording data processing module is responsible for the whole process recording is carried out in operating process, for the analysis operation behavior provides original foundation;
(6) normalizing operation storehouse and experts database processing module are included normalizing operation program and job procedure, and whether operation time limit standard and judgment criteria compare with it every operation calls experts database data, differentiate correct;
(7) after the whole operation task was finished, whether normalizing operation storehouse and experts database module appropriately carried out analysis and judgment to operating process and used time, provide the comprehensive evaluation conclusion.
Electrical power system standardized work intelligence controlling device of the present invention is: the integrated image unit that is connected with Data Management Analysis software respectively in logical mobile phone of a Daepori or handheld-type intelligent device, the recording unit, standardized work storehouse and experts database module, information after the Data Management Analysis software processes respectively with voice suggestion, SMS alarm, the note control module, wireless data transmission unit connects, wireless data transmission unit is connected with the monitoring host computer of remote data processing center, is provided with the graphic processing data module that is connected with image unit in the described Data Management Analysis software, normalizing operation storehouse and experts database processing module, the recording data processing module that is connected with the recording unit, they are connected with the intellectual analysis processing module respectively.
Described image unit, recording unit, voice suggestion and short message alarm module, wireless data transmission unit are the self-contained functional module of mobile phone in the prior art.
Of the present invention rational in infrastructure, versatility is good, simple and easy, the control of can assist operator verily finishing all kinds of electrical equipment operation and operation, can link to each other with other main frame as slave unit by wave point, can be widely used in power plant, transformer station, electric line and other industrial circles.
Description of drawings
Fig. 1 is that embodiment 1 constitutes unit connection block diagram;
Fig. 2 is a Data Management Analysis software module composition frame chart;
Fig. 3 is embodiment 2 operation monitoring process flow diagrams.
Embodiment
The invention will be further described below in conjunction with drawings and Examples.
Embodiment 1:
In conjunction with the accompanying drawings 1 and 2:
Present embodiment is the integrated image unit that is connected with Data Management Analysis software respectively in regular handset, the recording unit, normalizing operation storehouse and experts database module, information after the Data Management Analysis software processes is connected with SMS alarm unit and wireless data transmission unit with voice suggestion respectively, and wireless data transmission unit is connected with the monitoring host computer of remote data processing center.The camera of present embodiment image unit is installed in the back side of standardized work intelligent monitoring device, is convenient to take.
Be provided with graphic processing data module, the standardization that is connected with image unit in the Data Management Analysis software of present embodiment
Operation storehouse and experts database processing module, the recording data processing module that is connected with the unit of recording, they respectively with intellectual analysis
Processing module connects.
Embodiment 2:
With the grid switching operation is the intelligent monitor method that example illustrates this device:
At first, operation order is entered in the accurate equalization intelligence controlling device, and carries out basic setup on request, as key operation, standard operating procedure (SOP), standard time spent etc.
Before the operation, the training of telling somebody what one's real intentions are, the typing standardized work intelligent monitoring device of taking pictures mutually, device carries out identification according to entry information, if meet the requirements, open system then, voice suggestion " allows operation "; If undesirable, then voice suggestion " authentication failed, terminating operation ".The automatic blocking system does not allow operation.On personnel's problem, carried out effectively checking on.
In the operating process, by image unit the operation of key is taken pictures, the image that the graphic processing data module is responsible for taking compresses to handle and deposits mobile phone in, and by the intellectual analysis processing module operating result is judged, incorrect then warning, and do not allow to carry out next step operation; The note that voice suggestion and note release module are responsible for providing prompting, warn and need be issued etc.; The recording data processing module is responsible for the whole process recording is carried out in operating process, for the analysis operation behavior provides original foundation; Normalizing operation storehouse and experts database are included normalizing operation program and job procedure, operation time limit standard and judgment criteria, every operation task and each step operating result, can both call the experts database data compares with it, whether correctly differentiate, the whole operation task is finished, and whether system can also appropriately carry out analysis and judgment to operating process and used time, provides the comprehensive evaluation conclusion.

Claims (4)

1. an electrical power system standardized work intelligent control method is characterized in that, may further comprise the steps:
(1) operation order is entered into the standardized work intelligence controlling device, and carries out basic setup on request;
(2) before the operation, device carries out identification according to entry information, if meet the requirements, and open system then, voice suggestion " allows operation "; If undesirable, then voice suggestion " authentication failed, terminating operation "
(3) in the operating process, by image unit the operation of key is taken pictures, the image that the graphic processing data module is responsible for taking compresses processing and deposits mobile phone in, by the intellectual analysis processing module operating result is judged, incorrect then warning, and do not allow to carry out next step operation;
(4) voice suggestion and SMS alarm and note control module are responsible for the control between voice suggestion, warning and the mobile phone, and the issue note is informed the related personnel;
(5) the recording data processing module is responsible for the whole process recording is carried out in operating process, for the analysis operation behavior provides original foundation;
(6) normalizing operation storehouse and experts database processing module are included normalizing operation program and job procedure, and whether operation time limit standard and judgment criteria compare with it every operation calls experts database data, differentiate correct;
(7) after the whole operation task was finished, whether normalizing operation storehouse and experts database module appropriately carried out analysis and judgment to operating process and used time, provide the comprehensive evaluation conclusion.
2. the isolated plant of an electrical power system standardized work Based Intelligent Control, it is characterized in that, the integrated image unit that is connected with Data Management Analysis software respectively in logical mobile phone of a Daepori or handheld-type intelligent device, the recording unit, standardized work storehouse and experts database module, information after the Data Management Analysis software processes respectively with voice suggestion, SMS alarm, the note control module, wireless data transmission unit connects, wireless data transmission unit is connected with the monitoring host computer of remote data processing center, is provided with the graphic processing data module that is connected with image unit in the described Data Management Analysis software, normalizing operation storehouse and experts database processing module, the recording data processing module that is connected with the recording unit, they are connected with the intellectual analysis processing module respectively.
3. electrical power system safety operation intelligent control isolated plant according to claim 2 is characterized in that described image unit, recording unit, voice suggestion and short message alarm module are the self-contained functional module of mobile phone in the prior art.
4. electrical power system safety operation intelligent control isolated plant according to claim 2 is characterized in that described wireless data transmission unit is the original data transmission module of mobile phone.
CNA2008102374901A 2008-12-30 2008-12-30 Electrical power system standardized work intelligent control method and special equipment Pending CN101458502A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008102374901A CN101458502A (en) 2008-12-30 2008-12-30 Electrical power system standardized work intelligent control method and special equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008102374901A CN101458502A (en) 2008-12-30 2008-12-30 Electrical power system standardized work intelligent control method and special equipment

Publications (1)

Publication Number Publication Date
CN101458502A true CN101458502A (en) 2009-06-17

Family

ID=40769425

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008102374901A Pending CN101458502A (en) 2008-12-30 2008-12-30 Electrical power system standardized work intelligent control method and special equipment

Country Status (1)

Country Link
CN (1) CN101458502A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103164998A (en) * 2011-12-14 2013-06-19 中国广东核电集团有限公司 Training device and training method for monitoring operation
CN103559658A (en) * 2013-11-21 2014-02-05 国家电网公司 Electronic type operation order auditing system
CN104035404A (en) * 2014-05-30 2014-09-10 邢涛 Development method for operation order real-time state monitoring
CN104166894A (en) * 2014-07-23 2014-11-26 国网山东省电力公司青岛供电公司 Power plant scheduling voice reporting method and system
CN104656619A (en) * 2015-01-20 2015-05-27 国家电网公司 Electric field work instruction integrated-control system
CN104808516A (en) * 2014-01-28 2015-07-29 宁夏京能宁东发电有限责任公司 Electrical equipment operation control method and device
CN105279591A (en) * 2014-07-01 2016-01-27 上海日趋信息技术有限公司 Man-machine interactive system supporting one-man process operation instruction and verification
CN105278335A (en) * 2014-07-01 2016-01-27 上海日趋信息技术有限公司 Man-machine interactive method for instructing and verifying single-person process operation
CN105427402A (en) * 2015-12-18 2016-03-23 贵州南源电力科技股份有限公司 Inspection robot and method capable of monitoring maintenance and debugging process of substation equipment in real time
CN105701728A (en) * 2016-01-21 2016-06-22 国家电网公司 Hydropower construction standard application implementation method
CN107301234A (en) * 2017-06-27 2017-10-27 国网浙江省电力公司宁波供电公司 A kind of voice and word interactive system based on regulation and control atypia data
CN107368541A (en) * 2017-06-27 2017-11-21 国网浙江省电力公司宁波供电公司 A kind of parsing and proofreading method based on regulation and control atypia data
CN109471375A (en) * 2018-01-30 2019-03-15 国网浙江省电力公司湖州供电公司 A kind of electric system grid switching operation Risk Pre-control system and method
CN109782703A (en) * 2018-12-13 2019-05-21 湖南铁路科技职业技术学院 A kind of railway standardization operation control system based on intelligent glasses
CN111696223A (en) * 2020-06-04 2020-09-22 天津帕比特科技有限公司 Cloud control machine room operation monitoring method and system
CN112233267A (en) * 2020-09-02 2021-01-15 广东飞企互联科技股份有限公司 Fire fighting equipment monitoring method and system

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103164998B (en) * 2011-12-14 2015-06-03 中国广东核电集团有限公司 Training device and training method for monitoring operation
CN103164998A (en) * 2011-12-14 2013-06-19 中国广东核电集团有限公司 Training device and training method for monitoring operation
CN103559658A (en) * 2013-11-21 2014-02-05 国家电网公司 Electronic type operation order auditing system
CN103559658B (en) * 2013-11-21 2017-02-08 国家电网公司 Electronic type operation order auditing system
CN104808516A (en) * 2014-01-28 2015-07-29 宁夏京能宁东发电有限责任公司 Electrical equipment operation control method and device
CN104035404A (en) * 2014-05-30 2014-09-10 邢涛 Development method for operation order real-time state monitoring
CN105278335B (en) * 2014-07-01 2019-12-10 上海日趋信息技术有限公司 Man-machine interaction method for single-person flow operation instruction and verification
CN105279591A (en) * 2014-07-01 2016-01-27 上海日趋信息技术有限公司 Man-machine interactive system supporting one-man process operation instruction and verification
CN105278335A (en) * 2014-07-01 2016-01-27 上海日趋信息技术有限公司 Man-machine interactive method for instructing and verifying single-person process operation
CN104166894B (en) * 2014-07-23 2016-08-24 国网山东省电力公司青岛供电公司 Power plant's schedule voice declaration method and system
CN104166894A (en) * 2014-07-23 2014-11-26 国网山东省电力公司青岛供电公司 Power plant scheduling voice reporting method and system
CN104656619B (en) * 2015-01-20 2018-03-16 国家电网公司 Electric power field work instructs complex control system
CN104656619A (en) * 2015-01-20 2015-05-27 国家电网公司 Electric field work instruction integrated-control system
CN105427402A (en) * 2015-12-18 2016-03-23 贵州南源电力科技股份有限公司 Inspection robot and method capable of monitoring maintenance and debugging process of substation equipment in real time
CN105701728A (en) * 2016-01-21 2016-06-22 国家电网公司 Hydropower construction standard application implementation method
CN107301234A (en) * 2017-06-27 2017-10-27 国网浙江省电力公司宁波供电公司 A kind of voice and word interactive system based on regulation and control atypia data
CN107368541A (en) * 2017-06-27 2017-11-21 国网浙江省电力公司宁波供电公司 A kind of parsing and proofreading method based on regulation and control atypia data
CN109471375A (en) * 2018-01-30 2019-03-15 国网浙江省电力公司湖州供电公司 A kind of electric system grid switching operation Risk Pre-control system and method
CN109782703A (en) * 2018-12-13 2019-05-21 湖南铁路科技职业技术学院 A kind of railway standardization operation control system based on intelligent glasses
CN111696223A (en) * 2020-06-04 2020-09-22 天津帕比特科技有限公司 Cloud control machine room operation monitoring method and system
CN112233267A (en) * 2020-09-02 2021-01-15 广东飞企互联科技股份有限公司 Fire fighting equipment monitoring method and system

Similar Documents

Publication Publication Date Title
CN101458502A (en) Electrical power system standardized work intelligent control method and special equipment
CN100485558C (en) Electrical power system safety operation intelligent monitoring device and monitoring method thereof
CN110992509B (en) Equipment monitoring system and method for production workshop
CN103269130B (en) Method for remotely confirming remote-control operation of transformer station
CN204856196U (en) Intelligent production line process control system of bearing thing networking
CN106160219B (en) The monitoring method of remote forced monitoring system for transformer station switching operation
CN107591892B (en) Intelligent substation operation and maintenance method and system
CN103544739A (en) B/S (Browser/Server) architecture-based polling method of visual subway equipment polling management system
CN104065163A (en) Intelligent substation warning message delivering method
CN105049223A (en) Electric power communication network defect and fault processing decision-aided analysis method
CN214154147U (en) Intelligent anti-misoperation system for switching operation
CN211509189U (en) Electric power operation field supervision equipment and system
CN104966150A (en) Intelligent anti-error analysis method and system
CN105809571A (en) Intelligent monitoring method and system for outputting scheduling operation tickets
CN111062504A (en) AR technology-based intelligent power distribution station operation and maintenance system and method
CN110378803B (en) Industrial power outage and transmission C2C platform and method
CN106502219A (en) A kind of bearing Internet of Things intelligence fabrication line process control system
CN204807982U (en) Distributed environment monitoring and protection system based on cloud calculates
CN111030224A (en) Intelligent charging method, charging system, electronic device and medium
CN106059090A (en) Prompt system based on scheduling automation system and work method thereof
CN108415387A (en) A kind of safety control system and method for controlling security
CN109901471B (en) Intelligent control system of electromechanical device
CN113110243B (en) Construction operation site safety intelligent management and control platform
CN212276466U (en) Large-scale hoisting equipment system of patrolling and examining in harbour
CN112165170A (en) Intelligent sequential control method and system for substation equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20090617