CN106160219B - The monitoring method of remote forced monitoring system for transformer station switching operation - Google Patents

The monitoring method of remote forced monitoring system for transformer station switching operation Download PDF

Info

Publication number
CN106160219B
CN106160219B CN201610555553.2A CN201610555553A CN106160219B CN 106160219 B CN106160219 B CN 106160219B CN 201610555553 A CN201610555553 A CN 201610555553A CN 106160219 B CN106160219 B CN 106160219B
Authority
CN
China
Prior art keywords
substation
guardian
computer key
passed
monitoring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610555553.2A
Other languages
Chinese (zh)
Other versions
CN106160219A (en
Inventor
王修庞
曾历
王晓红
徐恩甫
李中渊
王东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority to CN201610555553.2A priority Critical patent/CN106160219B/en
Publication of CN106160219A publication Critical patent/CN106160219A/en
Application granted granted Critical
Publication of CN106160219B publication Critical patent/CN106160219B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J13/0013
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/126Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wireless data transmission

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Selective Calling Equipment (AREA)

Abstract

The invention discloses a kind of monitoring methods of remote forced monitoring system for transformer station switching operation, it makes out an invoice by simulation preview in substation, the sequence of operation of operation order is passed in computer key, according to the nominal value format display operation ticket of standard in the client computer of substation;After personnel to device context to be operated, it sends short messages on computer key and notifies care provider, care provider carries out authorization to the computer key at scene by radio communication in the client of substation, after the solution lock key of operating personnel receives the unlock instruction that substation guardian sends out, live unlocking operation could be carried out to current operating procedure, operating result is passed back substation automatically after the completion of operation, the guardian of substation is waited for confirm;After guardian's confirmation is errorless, next step operational order is sent, the execute-in-place talent can carry out next step operation, so recycle, until whole operation ticket terminates;After the completion of operation, the operating result of computer key is passed in system as storage of history data P, to ensure that every single stepping of execute-in-place people is all carried out in the case where centralized control center guardian authorizes monitoring.

Description

The monitoring method of remote forced monitoring system for transformer station switching operation
Technical field
The invention belongs to automation of transformation substations operating technology fields, and in particular to a kind of Substation Switch Changing Operation long distance forced The monitoring method of monitor system.
Background technology
As power grid develops rapidly, substation's quantity and transformer equipment are multiplied, substation's attended mode gradually by Someone on duty is excessively unattended or few people on duty, and the pattern of single station administration is also gradually transformed into concentrator station management mode.Electricity It nets unattended collection control operation just to be changed from the management mode of " with greatly with small " to the management mode of " District integrated control ", centralized control center Also by running monitoring originally, inspection operate unification Setting pattern the pattern being arranged independently of each other for the two is altered in steps.Electrically The operation for the process that equipment is changed into another state by operation, spare, maintenance any state is known as grid switching operation.Power grid scale Increasing, the workload of grid switching operation is also increasing, and misoperation may lead to equipment breakdown, or even jeopardize electric system Safe operation.
Substation Operating remote monitoring system grows up on the basis of computer technology and network communication technology. Foreign countries are in the 1980s, domestic until just occurring Wireless microwave load video information, long-range number at the beginning of 21 century in succession The long distance monitorings means such as word video information.But these monitoring tools, it is all using having in reality only for research field More problems:
1, cost is too high:Easily each infield wants hundreds thousand of to its system, and external equipment is too many, later maintenance amount Greatly;
2, cost performance is low:The remote monitoring system of early stage, image is unstable, and video summarization face is smaller;
3, performance is single:The mandatory blocking function of grid switching operation is can not achieve, and the station of single substation can only be carried out Area's internal electronic monitoring controls construction for the big collection of current power transformation operation, and the operation of few people on duty and unattended substation has very greatly Limitation;
4, poor reliability:Some one-man work remote image monitoring systems carry out long distance monitoring by phonetic image, unstable It is fixed, it is influenced by factors such as environmental condition, moods, personnel's randomness is bigger, after failure, can not implement to supervise online Measure personnel's operational circumstances.
Invention content
It is an object of the invention to avoid above-mentioned shortcoming in the prior art, and provide a kind of Substation Switch Changing Operation There is power grid accident in grid switching operation, far in the monitoring method of the remote forced monitoring system for transformer station switching operation of real time monitoring Square guardian can terminate operation immediately, improve working security, ensure every single stepping of execute-in-place people all in centralized control center Guardian authorizes monitoring is lower to carry out, and improves working efficiency, saves production cost.
Technical solution is used by achieving the object of the present invention:A kind of remote forced monitoring system for transformer station switching operation Monitoring method, including following flow:It makes out an invoice by simulation preview in substation, the sequence of operation of operation order is passed to computer key In spoon, according to the nominal value format display operation ticket of standard in the client computer of substation;Personnel to be operated are existing to equipment After, send short messages on computer key and notify care provider, care provider substation client by radio communication to existing Computer key carry out authorization, after the solution lock key of operating personnel receives the unlock instruction that substation guardian sends out, Live unlocking operation could be carried out to current operating procedure, and operating result is passed back substation automatically after the completion of operation, is waited for The guardian of substation confirms;After guardian's confirmation is errorless, next step operational order is sent, the execute-in-place talent can carry out down Single stepping so recycles, until whole operation ticket terminates;After the completion of operation, the operating result of computer key is passed to system It is middle to be used as storage of history data P, when operation identifies code-locked, by short message by the code value or device numbering of operated equipment lockset It is sent to centralized control center, operating personnel's computer key is positioned.
The system supports single multitask monitoring, multiuser-multitasking monitoring.
The inventive belt come advantageous effect be:
1, it solves the problems, such as the one man operation of no guardian and arbitrarily operates initiation accident without guardian's permit operation people The problem of;
2, it realizes the logic blocking between different stations and station, solves interconnection and stop operational coordination and sending end between power transmission The operational coordination between receiving end;
3, the positioning function of operating personnel is realized;
4, a guardian can guard multiple operation tasks, improve working efficiency, save production cost;
5, the same guardian can effectively control power grid, particularly interconnection operation rhythm, increase regulation and control personnel couple The control ability of power grid;
6, occurs power grid accident during grid switching operation, distant place guardian can terminate operation immediately, and it is quick to increase accident Respond grasps electric grid operating situation and provides support in real time for the platform construction of regulation and control one and regulation and control personnel in future;
7, the contradiction of power grid rapid development and operating personnel's wretched insufficiency can be effectively relieved, for power grid accident in the case of few people Fast quick-recovery provide a strong guarantee.
Description of the drawings
Fig. 1 is the structure chart of the present invention.
Fig. 2 is the software flow pattern of the present invention.
Specific implementation mode
The monitoring method of the remote forced monitoring system for transformer station switching operation of the present invention, on the basis of a large number of experiments, no Disconnected summing up experience, science are implemented, scientific design, and Exact Analysis is further below by specific embodiment to obtain this system Illustrate this system.
Embodiment one
It makes out an invoice, the sequence of operation of operation order is passed in computer key, in collection is controlled by simulation preview in centralized control center According to the nominal value format display operation ticket of standard in the client computer of the heart.After personnel to device context to be operated, phone is logical Know the care provider of centralized control center, care provider centralized control center client by radio communication to the computer key at scene into Row authorization could be to current after the solution lock key of operating personnel receives the unlock instruction that centralized control center guardian sends out Operating procedure carries out live unlocking operation, and operating result is passed back centralized control center automatically after the completion of operation, waits for centralized control center Guardian confirms.After guardian's confirmation is errorless, next step operational order is sent, the execute-in-place talent can carry out next step behaviour Make, so recycles, until whole operation ticket terminates.After the completion of operation, using the operating result of computer key be passed to system in as Storage of history data P.
Embodiment two
It makes out an invoice, the sequence of operation of operation order is passed in computer key, in substation by simulation preview in substation According to the nominal value format display operation ticket of standard in client computer.After personnel to device context to be operated, in computer key On send short messages and notify care provider, care provider by radio communication carries out the computer key at scene in the client of substation Authorization could be to current operation after the solution lock key of operating personnel receives the unlock instruction that substation guardian sends out Step carries out live unlocking operation, and operating result is passed back substation automatically after the completion of operation, waits for the guardian of substation true Recognize.After guardian's confirmation is errorless, next step operational order is sent, the execute-in-place talent can carry out next step operation, so follow Ring, until whole operation ticket terminates.After the completion of operation, the operating result of computer key is passed in system and is protected as historical data It deposits.
The present invention utilizes in substation's temperature survey by c omputer, the uniqueness of RFID codes, when operation identifies code-locked, by short The code value of operated equipment lockset or device numbering are sent to centralized control center by letter, to realize that operating personnel's computer key positions Function, that is, the equipment to be operated to correctly verification, meet first checking apparatus number before being operated in grid switching operation Requirement.
System combines the real time monitoring for carrying out operation screen with substation mobile video business, and it is attached that some may be implemented Add function, does not need to additionally increase external equipment and estimated expenditure.
Centralized control center deployment wireless communication center (CDMA or GPRS), can carry out channel radio with multiple computer keys simultaneously The system of letter, centralized control center can explain and distinguish the relationship between operation order and computer key and the mandate between them is closed System.Line communicates when something goes wrong, and computer key can be detached from the monitoring of centralized control center, by password authorization, carry out independent unlock Operation.

Claims (1)

1. a kind of monitoring method of remote forced monitoring system for transformer station switching operation, it is characterised in that:Including following flow: It makes out an invoice, the sequence of operation of operation order is passed in computer key, in the client meter of substation by simulation preview in substation According to the nominal value format display operation ticket of standard in calculation machine;After personnel to device context to be operated, send short messages on computer key Care provider, care provider is notified to carry out operation to the computer key at scene by radio communication in the client of substation and award Power, after the solution lock key of operating personnel receives the unlock instruction that substation guardian sends out, could to current operating procedure into Operating result, is passed back substation automatically after the completion of operation, the guardian of substation is waited for confirm by row scene unlocking operation;Through prison After shield people's confirmation is errorless, next step operational order is sent, the execute-in-place talent can carry out next step operation, so recycle, until Whole operation ticket terminates;After the completion of operation, the operating result of computer key is passed in system as storage of history data P, is being grasped When making identification code-locked, the code value of operated equipment lockset or device numbering are sent to by centralized control center by short message, to operator Member's computer key positioning.
CN201610555553.2A 2011-09-23 2011-09-23 The monitoring method of remote forced monitoring system for transformer station switching operation Active CN106160219B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610555553.2A CN106160219B (en) 2011-09-23 2011-09-23 The monitoring method of remote forced monitoring system for transformer station switching operation

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201110285913.9A CN102340180B (en) 2011-09-23 2011-09-23 Remote forced monitoring system for transformer station switching operation
CN201610555553.2A CN106160219B (en) 2011-09-23 2011-09-23 The monitoring method of remote forced monitoring system for transformer station switching operation

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201110285913.9A Division CN102340180B (en) 2011-09-23 2011-09-23 Remote forced monitoring system for transformer station switching operation

Publications (2)

Publication Number Publication Date
CN106160219A CN106160219A (en) 2016-11-23
CN106160219B true CN106160219B (en) 2018-11-09

Family

ID=45515751

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201110285913.9A Active CN102340180B (en) 2011-09-23 2011-09-23 Remote forced monitoring system for transformer station switching operation
CN201610555553.2A Active CN106160219B (en) 2011-09-23 2011-09-23 The monitoring method of remote forced monitoring system for transformer station switching operation

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201110285913.9A Active CN102340180B (en) 2011-09-23 2011-09-23 Remote forced monitoring system for transformer station switching operation

Country Status (1)

Country Link
CN (2) CN102340180B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103632407A (en) * 2013-12-01 2014-03-12 国网河南省电力公司安阳供电公司 Handheld equipment terminal inspection system for transformer substation
CN104008465B (en) * 2014-06-17 2017-07-07 国家电网公司 Grid switching operation bill safety implemented systems
CN104392333A (en) * 2014-12-12 2015-03-04 广西电网有限责任公司 Electronic arrival reporting method based on network commanding
CN104777808B (en) * 2015-03-27 2017-07-14 国家电网公司 A kind of record and read method of power station running status debugging
CN105243717B (en) * 2015-10-30 2019-01-22 国家电网公司 Phone permitting work ticket managing and control system and method
CN106372786A (en) * 2016-08-29 2017-02-01 长园共创电力安全技术股份有限公司 "Two ticket" operation safety management and control system and method
CN107121606B (en) * 2017-04-24 2020-06-30 国网浙江省电力公司台州供电公司 Intelligent terminal for transformer substation operation and patrol
CN107069967A (en) * 2017-04-24 2017-08-18 国网浙江省电力公司台州供电公司 For the NMS between transformer station and transformer station
CN108039772B (en) * 2017-11-20 2020-07-14 神华集团有限责任公司 Method, device, medium and system for electric interval switching operation of transformer substation
CN109636138A (en) * 2018-11-23 2019-04-16 北京南凯自动化***工程有限公司 A kind of intelligent dispatching system for railway contact line power supply management
CN112531885B (en) * 2020-09-18 2023-02-17 国网浙江省电力有限公司杭州供电公司 Construction method of transformer substation switching operation on-line modeling and actual operation guidance system
CN113794754A (en) * 2021-08-25 2021-12-14 国网福建省电力有限公司 Electronic operation ticket control system and method based on mobile application

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201218916Y (en) * 2008-06-30 2009-04-08 珠海优特电力科技股份有限公司 Electric power hand-held apparatus
CN201315256Y (en) * 2008-12-03 2009-09-23 山东鲁能奥特科技有限公司 Anti-misoperation system of wireless communication microcomputer

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002233059A (en) * 2001-01-29 2002-08-16 Toshiba Corp Transformer station remote monitoring control protection system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201218916Y (en) * 2008-06-30 2009-04-08 珠海优特电力科技股份有限公司 Electric power hand-held apparatus
CN201315256Y (en) * 2008-12-03 2009-09-23 山东鲁能奥特科技有限公司 Anti-misoperation system of wireless communication microcomputer

Also Published As

Publication number Publication date
CN102340180A (en) 2012-02-01
CN106160219A (en) 2016-11-23
CN102340180B (en) 2016-07-13

Similar Documents

Publication Publication Date Title
CN106160219B (en) The monitoring method of remote forced monitoring system for transformer station switching operation
CN105449867B (en) A kind of visualized operation process monitoring anti-error system and control method
CN102521905B (en) Intelligent access control system of transformer substation and control method thereof
CN109995138B (en) Misoperation-preventive locking management system and overhauling isolation locking management method for transformer substation
CN107591892B (en) Intelligent substation operation and maintenance method and system
CN106877508A (en) A kind of grid switching operation monitor in real time anti-error system and its control method
CN109634243A (en) A kind of scheduler program operating system based on intelligent robot
CN202362855U (en) Intelligent access control system for transformer substation
CN104882967B (en) A kind of anti-error romote controlled locking system of on-pole switch and operating method
CN105098982A (en) On-pole switch control system and method
CN105098609A (en) Anti-error remote control locking system of switch and control method of system
CN214154147U (en) Intelligent anti-misoperation system for switching operation
CN112054599B (en) Wind farm safety management system and method
CN109919451A (en) Based on true power network topology analysis and security knowledge base digital electric network system and method
CN208819285U (en) Key safety management system
CN104377835A (en) Anti-misoperation intelligent terminal for power distribution
CN105281429A (en) Method for preventing maloperation in scheduling remote control
CN212627319U (en) System for wind-powered electricity generation field safety control
CN102064609B (en) 500kV unmanned transformer station-based remote control method for protective soft pressing plate
CN109272626A (en) Key safety management system and method
CN104539045A (en) Intelligent fault-analysis-prevention system and working method thereof
CN205029175U (en) Mistake remote control locking system is prevented to switch
CN112700995B (en) Power distribution room maintenance method and device
CN201117473Y (en) Computer monitoring mis-operation preventing device
CN203930936U (en) Grid switching operation supervisory system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant