CN104656619B - Electric power field work instructs complex control system - Google Patents

Electric power field work instructs complex control system Download PDF

Info

Publication number
CN104656619B
CN104656619B CN201510026984.5A CN201510026984A CN104656619B CN 104656619 B CN104656619 B CN 104656619B CN 201510026984 A CN201510026984 A CN 201510026984A CN 104656619 B CN104656619 B CN 104656619B
Authority
CN
China
Prior art keywords
module
instructs
electric power
power field
field work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510026984.5A
Other languages
Chinese (zh)
Other versions
CN104656619A (en
Inventor
石永彪
王振
郝秀聪
宋小兵
马力强
程自珍
李峰
董宵燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Luliang Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Luliang Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Luliang Power Supply Co of State Grid Shanxi Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510026984.5A priority Critical patent/CN104656619B/en
Publication of CN104656619A publication Critical patent/CN104656619A/en
Application granted granted Critical
Publication of CN104656619B publication Critical patent/CN104656619B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Alarm Systems (AREA)

Abstract

Electric power field work of the present invention instructs complex control system, belongs to the technical field of electric power field work equipment;The technical problem of solution instructs terminal to provide a kind of novel electric power field operation that is lower-cost, supporting expert's task instruction;The technical scheme used for:Electric power field work instructs complex control system, including:Master control analysis module, database module, operating process instruct module, operation record module, data acquisition module, data memory module and operating right module;The master control analysis module instructs module, operation record module, data acquisition module, data memory module and operating right module to be connected with database module, operating process respectively;The operating right module instructs module to be connected with database module and operating process respectively;Suitable for power system.

Description

Electric power field work instructs complex control system
Technical field
Electric power field work of the present invention instructs complex control system, belongs to the technical field of electric power field work equipment.
Background technology
During the safety in production of electric power enterprise, can usually be related to power circuit polling operation, emergent operation process, The power businesses such as handling of goods and materials, the management of power use are, it is necessary to which operating personnel carries out execute-in-place;Yet with the technology energy of operating personnel The reason such as power deficiency, violation operation, negligence violating the regulations, it would be possible to which the accident for the power grid security that damages occurs, and not only gives The life security of operating personnel brings grave danger, and serious economic loss can be also caused to electric power enterprise;Therefore, looked forward in electric power In the substantial amounts of operation field of industry, emphasis, difficulties that safety in production is related to for some must be participated in solving by expert, so And operation field geographical position is scattered, territorial environment is complicated, when multiple operations are carried out the work simultaneously, often occur high-quality The problem of resource contention, solves, it is necessary to expend considerable time and effort, and causes can not timely and effectively solve field operation Problem.
Field operation is participated in solve the problems, such as that resource contention, expert can not be in the action, at present, frequently with in-site installation Sound, video capture device, on-site personnel is interacted with the real-time audio frequency and video of carry out of Remote personnel, or give The method that operating personnel is equipped with handheld terminal, job safety specification is downloaded by handheld terminal, to be lifted in operation process in real time Security;But both approaches hardware purchase cost is high, economy is poor, and it is required for carrying out data by network Transmission, in addition to network construction cost and operating cost are high, because site work environment is mostly mountain area or depopulated zone, network environment Badly, network connection interruption will lead to not provide real-time expert's guidance, and the safety operation to on-site personnel brings wind Danger.
The content of the invention
The present invention overcomes the shortcomings of the prior art, technical problem to be solved for provide it is a kind of it is lower-cost, The novel electric power field operation of expert's task instruction is supported to instruct terminal.
In order to solve the above-mentioned technical problem, the technical solution adopted by the present invention is:Electric power field work instructs Comprehensive Control System, including:Master control analysis module, database module, operating process instruct module, operation record module, data acquisition module, Data memory module and operating right module;
The master control analysis module instructs module, operation record module, data to adopt with database module, operating process respectively Collection module, data memory module are connected with operating right module;The operating right module respectively with database module and operation Flow instructs module to be connected;
The data acquisition module includes video acquisition module and data conversion module, and the video acquisition module passes through number It is connected according to modular converter with master control analysis module.
The operating process instructs module to include:Safety operation instructs module and standard operation to instruct module.
The data memory module includes:Audio storage module, video storage modules, word memory module and storage archives Module.
The master control analysis module is also associated with alarm module.
The present invention has the advantages that compared with prior art:The present invention can be by providing the expert of field operation Instruct, lift the coordination ability of field operation, realize that normative, security instructs, make on-site personnel in strict accordance with specification Operated, find potential safety hazard and leak in time, the security risk for avoiding non-standard operation from bringing, lift field work safe Property it is horizontal;Meanwhile and operating right can be set, further ensure the safety of operation.
Brief description of the drawings
The present invention will be further described in detail below in conjunction with the accompanying drawings.
Fig. 1 is electrical block diagram of the present invention;
In figure:1 it is master control analysis module, 2 be database module, 3 is that to instruct module, 4 be operation note mould to operating process Block, 5 be data acquisition module, 6 be data memory module, 7 be operating right module, 8 be video acquisition module, 9 be data turn Mold changing block, 10 are that to instruct module, 11 be that to instruct module, 12 be alarm module to standard operation for safety operation.
Embodiment
As shown in Figure 1:Electric power field work of the present invention instructs complex control system, including:Master control analysis module 1, data Library module 2, operating process instruct module 3, operation record module 4, data acquisition module 5, data memory module 6 and operating right Module 7;
The master control analysis module 1 instructs module 3, operation record module 4, number with database module 2, operating process respectively It is connected according to acquisition module 5, data memory module 6 with operating right module 7;The operating right module 7 respectively with database mould Block 2 instructs module 3 to be connected with operating process;
The data acquisition module 5 includes video acquisition module 8 and data conversion module 9, and the video acquisition module 8 is logical Data conversion module 9 is crossed with master control analysis module 1 to be connected.
The operating process instructs module 3 to include:Safety operation instructs module 10 and standard operation to instruct module 11.
The master control analysis module 1 is also associated with alarm module 12.
In the present invention, the operating right module 7 can set the operating right and grade of different work personnel, and can To control the operating process that different personnel can use;The safety operation is instructed to be provided with needed for on-site personnel in module 10 Safely instruction filespec Operating Guideline module 11 in provided with the standard operation policy paper needed for on-site personnel, scene When operating personnel works at the scene, the policy paper of module 3 can be instructed with operating process, realizes security, the rule of operation process Plasticity instructs;Further, the master control analysis module 1 can instruct module 3 real with data acquisition module 5 according to operating process Shi Jilu operation field operation data is contrasted, and realizes the inspection of routine work, is found potential safety hazard and leak in time, is gone out When existing operation data is not inconsistent with secure data, and on-site personnel can be reminded by alarm module 12, realized The safety standard management of operating process, the safe level of field operation is lifted, avoids engineering accident caused by violation operation.
The data memory module 6 includes:Audio storage module, video storage modules, word memory module and storage shelves Case module.To solve the problems, such as collection in worksite data compression distortion, transmission packet loss, these file datas, electric power can be used as to look forward to The auxiliary teaching material of industry safety in production, intensified safety production business different majors personnel, the professional skill and security knowledge, meaning of teams and groups Know, improve the teaching efficiency of production operation.
The present invention can be instructed by providing the expert of field operation, lifted the coordination ability of field operation, realized specification Property, security instruct, on-site personnel is operated in strict accordance with specification, find potential safety hazard and leak in time, avoid The security risk that non-standard operation is brought, lifting field work safe are horizontal;Meanwhile and operating right can be set, enter One step ensure that the safety of operation.

Claims (4)

1. electric power field work instructs complex control system, it is characterised in that:Including:Master control analysis module(1), database module (2), operating process instruct module(3), operation record module(4), data acquisition module(5), data memory module(6)And operation Authority module(7);
The master control analysis module(1)Respectively with database module(2), operating process instruct module(3), operation record module (4), data acquisition module(5), data memory module(6)With operating right module(7)It is connected;The operating right module(7) Respectively with database module(2)Module is instructed with operating process(3)It is connected;
The data acquisition module(5)Including video acquisition module(8)And data conversion module(9), the video acquisition module (8)Pass through data conversion module(9)With master control analysis module(1)It is connected.
2. electric power field work according to claim 1 instructs complex control system, it is characterised in that:The operating process Instruct module(3)Including:Module is instructed in safety operation(10)Module is instructed with standard operation(11).
3. electric power field work according to claim 1 or 2 instructs complex control system, it is characterised in that:The data Memory module(6)Including:Audio storage module, video storage modules, word memory module and storage profile module.
4. electric power field work according to claim 3 instructs complex control system, it is characterised in that:The master control analysis Module(1)It is also associated with alarm module(12).
CN201510026984.5A 2015-01-20 2015-01-20 Electric power field work instructs complex control system Active CN104656619B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510026984.5A CN104656619B (en) 2015-01-20 2015-01-20 Electric power field work instructs complex control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510026984.5A CN104656619B (en) 2015-01-20 2015-01-20 Electric power field work instructs complex control system

Publications (2)

Publication Number Publication Date
CN104656619A CN104656619A (en) 2015-05-27
CN104656619B true CN104656619B (en) 2018-03-16

Family

ID=53247880

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510026984.5A Active CN104656619B (en) 2015-01-20 2015-01-20 Electric power field work instructs complex control system

Country Status (1)

Country Link
CN (1) CN104656619B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105812750A (en) * 2016-04-27 2016-07-27 国网安徽省电力公司六安市叶集供电公司 Mobile anti-violation of regulations individual equipment in power dispatching monitoring system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101183251A (en) * 2007-12-19 2008-05-21 田一鸣 Electrical power system safety operation intelligent monitoring device and monitoring method thereof
CN101458502A (en) * 2008-12-30 2009-06-17 湖南省电力公司湘潭电业局 Electrical power system standardized work intelligent control method and special equipment
CN202948484U (en) * 2012-12-21 2013-05-22 浙江省电力公司台州电业局 Electric power transformation overhaul mobile risk control system
CN103824153A (en) * 2014-02-07 2014-05-28 深圳供电局有限公司 Mobile terminal for processing power generation field operation
CN104079878A (en) * 2014-06-27 2014-10-01 国家电网公司 Mobile audio and video expert system of electric remote operation scene
CN104239985A (en) * 2013-06-06 2014-12-24 张藤予 Intelligent electrical equipment operation management system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101183251A (en) * 2007-12-19 2008-05-21 田一鸣 Electrical power system safety operation intelligent monitoring device and monitoring method thereof
CN101458502A (en) * 2008-12-30 2009-06-17 湖南省电力公司湘潭电业局 Electrical power system standardized work intelligent control method and special equipment
CN202948484U (en) * 2012-12-21 2013-05-22 浙江省电力公司台州电业局 Electric power transformation overhaul mobile risk control system
CN104239985A (en) * 2013-06-06 2014-12-24 张藤予 Intelligent electrical equipment operation management system
CN103824153A (en) * 2014-02-07 2014-05-28 深圳供电局有限公司 Mobile terminal for processing power generation field operation
CN104079878A (en) * 2014-06-27 2014-10-01 国家电网公司 Mobile audio and video expert system of electric remote operation scene

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
基于PDA的现场作业管理***的开发;黄莹;《中国优秀硕士学位论文全文数据库信息科技辑》;20080715(第07期);第1-81页 *

Also Published As

Publication number Publication date
CN104656619A (en) 2015-05-27

Similar Documents

Publication Publication Date Title
WO2019095910A1 (en) Daily patrol working method and system in substation
CN202331693U (en) Online monitoring and sound-light expelling platform of substation security system
CN203070033U (en) PLC remote monitoring system based on Web
WO2016019748A1 (en) Mine safety management method and apparatus based on geographic information system
CN104065163A (en) Intelligent substation warning message delivering method
CN104167818A (en) Intelligent remote inspection system in linkage with GIS substation integrated automation system and method
CN104951998A (en) Strong wind early warning modeling method and strong wind early warning modeling system based on power grid GIS (geographic information system)
CN203800707U (en) Substation overhauling electric shock preventing digital stereoscopic safety deployment device
CN202257822U (en) Infrared co-irradiated detection system of transformer substation
CN105278470A (en) Regional harmful gas automatic monitoring wireless alarm interlocking control system
CN104656619B (en) Electric power field work instructs complex control system
CN113656872B (en) FM intelligent construction site operation and maintenance management and control system and method based on BIM
CN113556377B (en) Ship external field coating environment monitoring system
CN103326472A (en) Information sharing and interoperating method for intelligent electrical devices of intelligent substation operation cockpit
CN105206129A (en) Fault simulation system of nuclear fuel operation training and method thereof
CN203608291U (en) Mobile wireless video supervising device for water conservancy supervision
CN202986990U (en) Device for controlling on-the-spot explosive mixed loading vehicle in real time through video monitoring
CN202948484U (en) Electric power transformation overhaul mobile risk control system
CN106789182B (en) Detection and scoring system and implementation method of automatic evaluation device for power plant grade protection
CN202257805U (en) Remote acoustooptical alarm system for transformer station
CN104218680A (en) Real-time alarm system and communication method thereof for supervisory control and data acquisition (SCADA) system
CN204759171U (en) Overhaul operation mobile terminal monitoring device
CN207856142U (en) A kind of novel building fire protection and maintained equipment
CN204624400U (en) A kind of can the rubbish container of remote monitor and control
CN204496268U (en) A kind of digital integration remote training fault diagnosis system of production system

Legal Events

Date Code Title Description