CN104166894B - Power plant's schedule voice declaration method and system - Google Patents

Power plant's schedule voice declaration method and system Download PDF

Info

Publication number
CN104166894B
CN104166894B CN201410351712.8A CN201410351712A CN104166894B CN 104166894 B CN104166894 B CN 104166894B CN 201410351712 A CN201410351712 A CN 201410351712A CN 104166894 B CN104166894 B CN 104166894B
Authority
CN
China
Prior art keywords
power plant
power
field data
barring condition
voice
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410351712.8A
Other languages
Chinese (zh)
Other versions
CN104166894A (en
Inventor
娄亮
董林
王强
王文刚
于立涛
罗鲁东
吴文涛
汤元超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610081826.4A priority Critical patent/CN105629935B/en
Priority to CN201410351712.8A priority patent/CN104166894B/en
Publication of CN104166894A publication Critical patent/CN104166894A/en
Application granted granted Critical
Publication of CN104166894B publication Critical patent/CN104166894B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of power plant's schedule voice declaration method and system, said method comprising the steps of: step 1, the access request of reception user, and checking Customs Assigned Number and login password are followed by access customer;Step 2, voice message user input power plant's field data;Step 3, judge whether described power plant field data meets the barring condition of setting, do not meet barring condition then voice message user and return step 2 and re-enter power plant's field data;The power plant's field data meeting barring condition is confirmed or returns step 2 to re-enter power plant's field data by step 4, voice message user;Step 5, by above-mentioned through user confirm power plant's field data store.A kind of power plant schedule voice declaration method of the present invention and system solve the technical problem that field data is declared by power plant that prior art cannot realize not having corporate intranet to cover accurately and in time.

Description

Power plant's schedule voice declaration method and system
Technical field
The present invention relates to power scheduling technical field, particularly relate to power plant's schedule voice declaration method and be System.
Background technology
State Grid Corporation of China's 2010 " two Conferences " is upper proposes " three collection five are big " (human resources, wealth Business, material intensive management, huge construction program, greatly construction, big operation, big production, big marketing system are built If)." adjust, join, control integration ", as the important embodiment of " running greatly ", is current national grid A kind of Regulation pattern carried out energetically in system.Integration management and running embody emphatically intelligence Electrical network efficient, it relates to standardization and specialized management, lean and the indexing pipe of control centre The longitudinal direction interconnection of reason and control centre, is that control centre externally provides types of functionality and data, services Window.
" adjust, join, control integration " relates to two class business, i.e. to the properly functioning control of electrical network and right The emergency processing of accident improves control room to power system operating mode, equipment running status, a power supply Plan, and electrical network overall process, the control ability of specialty comprehensive, complete;Improve to anomalous weather, The disposal ability of the accidents such as external force destruction, system fluctuation.
" adjust, join, control integration " system achieves the centralization of management and running height, simultaneously to from Dynamicization system proposes new requirement.Along with the deep propelling of " running greatly " System Construction, in order to protect Card new system runs well, and needs to improve the informatization platform of electrical network.Part little thermoelectricity (little fire Electricity typically refers to 50,000 kilowatts and following thermoelectricity is main oil burning boiler and generating set) enterprise because Enterprise's existing network condition limits and is not carried out the covering of Intranet, it is impossible to by inner-mesh network number Report time factually.
It is thus desirable to set up the information system of a set of intelligence, to realize the little timely Shen of thermoelectricity field data Report, promotes regulation and control operation level, and then improves power grid security and stability.Traditional information system is not User misoperation during preventing little thermoelectricity field data from declaring, thus cause related data to declare not Accurately, these inaccurate data store in database, need by manual type carry out examination & verification and Amendment, wastes time and energy, affects power plant's traffic control efficiency.
Summary of the invention
To this end, in the technical problem to be solved is that prior art cannot realize not having enterprise Field data is declared by power plant that net covers accurately and in time, thus proposes a kind of power plant schedule voice Declaration method and system solve this problem.
For solve above-mentioned technical problem, the present invention by the following technical solutions:
A kind of power plant schedule voice declaration method, comprises the following steps: step 1, the access of reception user Request, checking Customs Assigned Number and login password are followed by access customer;Step 2, voice message user input electricity Factory's field data;Step 3, judge whether described power plant field data meets the barring condition of setting, no Meet barring condition then voice message user to return step 2 and re-enter power plant's field data;Step 4, The power plant's field data meeting barring condition is confirmed or returns step 2 weight by voice message user Newly inputted power plant field data;Step 5, by above-mentioned through user confirm power plant's field data deposit Storage.
As the further improvement of power plant's schedule voice declaration method of the present invention, described power plant scene number According to including: power minimum load, power maximum load, start power capacity, generated energy and online electricity Amount.
As the further improvement of power plant's schedule voice declaration method of the present invention, described barring condition For: electricity volume generated energy, and power minimum load < power maximum load start power appearance Amount, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As the further improvement of power plant's schedule voice declaration method of the present invention, described barring condition For: 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As the further improvement of power plant's schedule voice declaration method of the present invention, described barring condition For: electricity volume generated energy.
As the further improvement of power plant's schedule voice declaration method of the present invention, described barring condition For: power minimum load < power maximum load start power capacity.
As the further improvement of power plant's schedule voice declaration method of the present invention, after step 5 also Comprise the following steps: power plant's field data of storage is audited.
As the further improvement of power plant's schedule voice declaration method of the present invention, also by the electricity after examination & verification Factory's field data reports higher level's thread.
As the further improvement of power plant's schedule voice declaration method of the present invention, after step 5 also Comprise the following steps: power plant's field data of storage is collected displaying.
Based on same inventive concept, the present invention also proposes a kind of power plant schedule voice declaration system, bag Include: user's access unit, for receiving the access request of user, checking Customs Assigned Number and login password It is followed by access customer;Input block, inputs power plant's field data for voice message user;Locking list Unit, for judging whether described power plant field data meets the barring condition of setting, does not meets locking bar Part then voice message user returns input block and re-enters power plant's field data;Confirmation unit, is used for The power plant's field data meeting barring condition is confirmed or returns input block by voice message user Re-enter power plant's field data;Memory cell, for by on-the-spot for the above-mentioned power plant through user's confirmation Data store.
As the further improvement of power plant's schedule voice declaration system of the present invention, described power plant scene number According to including: power minimum load, power maximum load, start power capacity, generated energy and online electricity Amount.
As the further improvement of power plant's schedule voice declaration system of the present invention, described barring condition For: power minimum load < power maximum load start power capacity.
As the further improvement of power plant's schedule voice declaration system of the present invention, described barring condition For: 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As the further improvement of power plant's schedule voice declaration system of the present invention, described barring condition For: electricity volume generated energy.
As the further improvement of power plant's schedule voice declaration system of the present invention, described barring condition For: electricity volume generated energy, and, power minimum load < power maximum load start power Capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As the further improvement of power plant's schedule voice declaration system of the present invention, also include that examination & verification is single Unit, for auditing power plant's field data of storage.
As the further improvement of power plant's schedule voice declaration system of the present invention, also include reporting list Unit, for reporting higher level's thread by the power plant's field data after examination & verification.
As the further improvement of power plant's schedule voice declaration system of the present invention, also include cover sheet Unit, for collecting displaying to power plant's field data of storage.
The technique scheme of the present invention has the advantage that compared to existing technology
1, a kind of power plant schedule voice declaration method of the present invention and system, owing to comprising the following steps: Step 1, the access request of reception user, checking Customs Assigned Number and login password are followed by access customer;Step 2, voice message user inputs power plant's field data;Step 3, whether judge described power plant field data Meeting the barring condition of setting, not meeting barring condition then voice message user, to return step 2 the most defeated Enter power plant's field data;The power plant's field data meeting barring condition is entered by step 4, voice message user Row confirms or returns step 2 to re-enter power plant's field data;Step 5, by above-mentioned true through user The power plant's field data recognized stores.The barring condition set is possible to prevent little thermoelectricity field data Shen User misoperation during report, it is ensured that data declaration is accurate, it is to avoid inaccurate data store data In storehouse, thus improve power plant's traffic control efficiency.
2, a kind of power plant schedule voice declaration method of the present invention and system, described power plant field data bag Include: power minimum load, power maximum load, start power capacity, generated energy and electricity volume, Described barring condition is: electricity volume generated energy, and power minimum load < power maximum load Start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times powers are the highest negative Lotus.So can be prevented effectively from during power plant's field data is declared, the electricity volume of appearance generating Amount, power minimum load >=power maximum load, power minimum load >=start power capacity, power Maximum load > start data declaration person's maloperation such as power capacity and data unit mistake cause obvious Mistake.Data error rate is reduced to less than 5.12% by 21.33%.Meanwhile, on-the-spot when the power plant of input Data meet 2.4 times power minimum load < generated energy < 2.4 times power maximum load barring conditions simultaneously Time, other are not that the data error rate that artificial origin causes is significantly reduced, and such as, check meter at the scene Time the wrong data that causes due to reasons such as electric instruments significantly reduce.By long-time statistical observation, Data error rate is 0, achieves unexpected technique effect.
Accompanying drawing explanation
In order to make present disclosure be more likely to be clearly understood, below according to the concrete reality of the present invention Executing example and combine accompanying drawing, the present invention is further detailed explanation, wherein
Fig. 1 is a kind of power plant schedule voice declaration method schematic diagram of the embodiment of the present invention 1;
Fig. 2 is a kind of small coal power plants schedule voice declaration method flow chart of the embodiment of the present invention 2.
Detailed description of the invention
Embodiment 1
Fig. 1 shows a kind of power plant schedule voice declaration method of the embodiment of the present invention, including following step Rapid:
Step 1, access user.Receive the access request of user, after checking Customs Assigned Number and login password Access user.
Step 2, input power plant field data.Power plant's field data is inputted by voice message user.Institute State power plant's field data to include: power minimum load, power maximum load, start power capacity, send out Electricity and electricity volume.
Step 3, judge whether data meet barring condition.Judge whether described power plant field data meets The barring condition set, described barring condition is: electricity volume generated energy, and power is minimum negative Lotus < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.Meet barring condition and then perform step 4;Do not meet barring condition then voice Prompting user returns step 2 and re-enters power plant's field data.
So can be prevented effectively from during power plant's field data is declared, the electricity volume of appearance generating Amount, power minimum load >=power maximum load, power minimum load >=start power capacity, power Maximum load > start data declaration person's maloperation such as power capacity and data unit mistake cause obvious Mistake.Data error rate is reduced to less than 5.12% by 21.33%.Meanwhile, on-the-spot when the power plant of input Data meet 2.4 times power minimum load < generated energy < 2.4 times power maximum load barring conditions simultaneously Time, other are not that the data error rate that artificial origin causes is significantly reduced, and such as, check meter at the scene Time the wrong data that causes due to reasons such as electric instruments significantly reduce.By long-time statistical observation, Data error rate is 0, achieves unexpected technique effect.
As other embodiment, described barring condition is: power minimum load < power is the highest negative Lotus start power capacity.
As other embodiment, described barring condition is: 2.4 times power minimum load < generated energy < 2.4 times power maximum load.
As other embodiment, described barring condition is: electricity volume generated energy.
Step 4, confirmation data.The power plant's field data meeting barring condition is carried out by voice message user Confirm, confirm then to carry out step 5;Re-enter, return step 2 and re-enter power plant's field data.
Step 5, storage power plant field data.The above-mentioned power plant's field data confirmed through user is carried out Storage.
As the preferred embodiment of a kind of power plant schedule voice declaration method of the embodiment of the present invention, Step 5 is the most further comprising the steps of: audit power plant's field data of storage, and will examination & verification After power plant field data report higher level's thread.
As the preferred embodiment of a kind of power plant schedule voice declaration method of the embodiment of the present invention, Step 5 is the most further comprising the steps of: power plant's field data of storage is collected displaying.
Embodiment 2
Fig. 2 shows a kind of small coal power plants schedule voice declaration method of the embodiment of the present invention.
First, the data declaration person of small coal power plants dials and declares telephone number, and voice message after connection is " joyous Meet the little thermoelectricity Data-phone declaration system of use, Customs Assigned Number please be input, terminate with # key ".Example As, data declaration person inputs Customs Assigned Number " 001# ", if this numbering does not exists, and voice message " you do not exist by the Customs Assigned Number of input, please re-enter Customs Assigned Number, terminate with # key ", if Numbering exists then voice message further " please input login password, terminate with # key ".Such as, number Login password " * * * * * * # " is inputted according to the person of declaring, if code error, voice message " Password Input Mistake, please re-enter, terminate with # key ", if Password Input is correct, then login successfully.
After logining successfully, voice message " declaration data please by 1, exits, please hang up ", data Shen After person's of report input " 1 ", voice message " please input generated energy, terminate with # key ", such as data The person of declaring inputs " 1036.28 ".
Judge whether the generated energy of input meets the barring condition of setting: electricity volume generated energy, and And power minimum load < power maximum load start power capacity, and 2.4 times powers are minimum negative Lotus < generated energy < 2.4 times power maximum load.If do not met, then voice message " I'm sorry, you Input wrong!Please re-enter ", data declaration person returns and re-enters generated energy.
If met, then further voice message " your typing is: 1036.28, confirms, please by 1, re-enter, please by 2 ", if to input generated energy incorrect for data declaration person, then return by 2 Return, re-enter;If it is correct that data declaration person inputs generated energy, then confirm by 1.Data The person of declaring is by after 1, and voice message " please input electricity volume, terminate with # key ", such as data Shen The person of report inputs " 964.14 ".
Judge whether the electricity volume of input meets the barring condition of setting: electricity volume generated energy, And power minimum load < power maximum load start power capacity, and 2.4 times powers are minimum Load < generated energy < 2.4 times power maximum load.If do not met, then voice message " it is I'm sorry, Your input is wrong!Please re-enter ", data declaration person returns and re-enters electricity volume.
If met, then voice message further " your typing is: 964.14, confirms, please by 1, Re-enter, please by 2 ", if to input electricity volume incorrect for data declaration person, then by 2 returns, Re-enter;If it is correct that data declaration person inputs electricity volume, then confirm by 1.Data Shen After the person of report presses 1, voice message " asks input power minimum load, terminate with # key ", such as data The person of declaring inputs " 102.56 ".
Judge whether the power minimum load of input meets the barring condition of setting: electricity volume generates electricity Amount, and power minimum load < power maximum load start power capacity, and 2.4 times powers Minimum load < generated energy < 2.4 times power maximum load.If do not met, then voice message is not " to Rising, your input is wrong!Please re-enter ", it is minimum negative that power is re-entered in data declaration person's return Lotus.
If met, then voice message further " your typing is: 102.56, confirms, please by 1, Re-enter, please by 2 ", if data declaration person's input power minimum load is incorrect, then return by 2 Return, re-enter;If data declaration person's input power minimum load is correct, then carry out really by 1 Recognize.After data declaration person presses 1, voice message " is asked input power maximum load, is tied with # key Bundle ", such as data declaration person's input " 505.43 ".
Judge whether the power maximum load of input meets the barring condition of setting: electricity volume generates electricity Amount, and power minimum load < power maximum load start power capacity, and 2.4 times powers Minimum load < generated energy < 2.4 times power maximum load.If do not met, then voice message is not " to Rising, your input is wrong!Please re-enter ", it is the highest negative that power is re-entered in data declaration person's return Lotus.
If met, then voice message further " your typing is: 505.43, confirms, please by 1, Re-enter, please by 2 ", if data declaration person's input power maximum load is incorrect, then return by 2 Return, re-enter;If data declaration person's input power maximum load is correct, then carry out really by 1 Recognize.After data declaration person presses 1, voice message " please input start power capacity, tie with # key Bundle ", such as data declaration person's input " 665.64 ".
Judge whether the start power capacity of input meets the barring condition of setting: electricity volume generates electricity Amount, and power minimum load < power maximum load start power capacity, and 2.4 times powers Minimum load < generated energy < 2.4 times power maximum load.If do not met, then voice message is not " to Rising, your input is wrong!Please re-enter ", data declaration person returns and re-enters start power appearance Amount.
If met, then voice message further " your typing is: 505.43, confirms, please by 1, Re-enter, please by 2 ", if data declaration person inputs start, power capacity is incorrect, then return by 2 Return, re-enter;If data declaration person inputs start, power capacity is correct, then carry out really by 1 Recognize.
After data declaration person presses 1, enter operating database flow process, to above-mentioned true through data declaration person The small coal power plants field data recognized stores, and voice message " operates the most successful!Generated energy: 1036.28, electricity volume: 964.16, power minimum load 102.56, power maximum load: 505.43, power capacity of starting shooting: 665.64, as also needed other to service, please by 0, exits and please hang Machine ".
The side of being preferable to carry out as a kind of small coal power plants schedule voice declaration method of the embodiment of the present invention Formula, the above-mentioned small coal power plants field data of storage can be audited by dispatcher, and by after examination & verification Small coal power plants field data report higher level's thread.
The side of being preferable to carry out as a kind of small coal power plants schedule voice declaration method of the embodiment of the present invention Formula, the above-mentioned small coal power plants field data of storage can be collected displaying by dispatcher.
Embodiment 3
A kind of power plant schedule voice declaration system of the embodiment of the present invention, including user's access unit, defeated Enter unit, locking unit, confirmation unit and memory cell.
Described user's access unit is for receiving the access request of user, and checking Customs Assigned Number and login are close Code is followed by access customer.
Described input block is for inputting power plant's field data by voice message user.Described power plant is existing Field data includes: power minimum load, power maximum load, start power capacity, generated energy and on Net electricity.
Described locking unit is used for judging whether described power plant field data meets the barring condition of setting, Described barring condition is: electricity volume generated energy, and power minimum load < power maximum load Start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times powers are the highest negative Lotus.Meet barring condition and then perform step 4;Do not meet barring condition then voice message user and return step 2 re-enter power plant's field data.
As other embodiment, described barring condition is: power minimum load < power is the highest negative Lotus start power capacity.
As other embodiment, described barring condition is: 2.4 times power minimum load < generated energy < 2.4 times power maximum load.
As other embodiment, described barring condition is: electricity volume generated energy.
The power plant's field data meeting barring condition is carried out by described confirmation unit for voice message user Confirm, confirm then to carry out step 5;Re-enter, return step 2 and re-enter power plant's field data.
Described memory cell is for storing the above-mentioned power plant's field data confirmed through user.
A kind of power plant schedule voice declaration system of the embodiment of the present invention also includes auditing unit, reporting list Unit and collection unit.
Described examination & verification unit is for auditing power plant's field data of storage.
Described reporting element is for reporting higher level's thread by the power plant's field data after examination & verification.
Described collection unit is for collecting displaying to power plant's field data of storage.
As the preferred embodiment of a kind of power plant schedule voice declaration system of the embodiment of the present invention, can To develop voice server, integrated above-mentioned use in described voice server based on Dialogic sound card Family access unit, input block, locking unit, confirmation unit and memory cell.Further, Build WEB server, in described voice server integrated above-mentioned examination & verification unit, reporting element and Collection unit.Technology based on Dialogic voice exploitation voice server, and build WEB service The technology of device belongs to the art technology known technology, by combining a kind of electricity of the embodiment of the present invention The functional requirement that factory's schedule voice declaration system provides, the technical field for the art is not being paid Can implement under the conditions of going out creative work, thus repeat no more.
Obviously, above-described embodiment is only for clearly demonstrating example, and not to embodiment party The restriction of formula.For those of ordinary skill in the field, the most also may be used To make other changes in different forms.Here without also all of embodiment being given With exhaustive.And the obvious change thus extended out or variation are still in the guarantor of the invention Protect among scope.

Claims (5)

1. power plant's schedule voice declaration method, it is characterised in that comprise the following steps:
Step 1, the access request of reception user, checking Customs Assigned Number and login password are followed by access customer;
Step 2, voice message user input power plant's field data;
Step 3, judge whether described power plant field data meets the barring condition of setting, do not meet and close Bolt part then voice message user returns step 2 and re-enters power plant's field data;
Wherein, described barring condition is: electricity volume generated energy, and power minimum load < merit Rate maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads;Or
Described barring condition is: 2.4 times power minimum load < generated energy < 2.4 times powers are the highest negative Lotus;Or
Described barring condition is: electricity volume generated energy;Or
Described barring condition is: power minimum load < power maximum load start power capacity;
Step 4, voice message user carry out confirmation to the power plant's field data meeting barring condition and obtain User confirm power plant's field data, or return step 2 re-enter power plant's field data;
Step 5, by above-mentioned through user confirm power plant's field data store.
Power plant the most according to claim 1 schedule voice declaration method, it is characterised in that institute State power plant's field data to include: power minimum load, power maximum load, start power capacity, Generated energy and electricity volume.
Power plant the most according to claim 1 schedule voice declaration method, it is characterised in that Step 5 is the most further comprising the steps of: audit power plant's field data of storage.
Power plant the most according to claim 3 schedule voice declaration method, it is characterised in that also Power plant's field data after examination & verification is reported higher level's thread.
Power plant the most according to claim 4 schedule voice declaration method, it is characterised in that Step 5 is the most further comprising the steps of: power plant's field data of storage is collected displaying.
CN201410351712.8A 2014-07-23 2014-07-23 Power plant's schedule voice declaration method and system Active CN104166894B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610081826.4A CN105629935B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration system
CN201410351712.8A CN104166894B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410351712.8A CN104166894B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration method and system

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201610081826.4A Division CN105629935B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration system

Publications (2)

Publication Number Publication Date
CN104166894A CN104166894A (en) 2014-11-26
CN104166894B true CN104166894B (en) 2016-08-24

Family

ID=51910691

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610081826.4A Active CN105629935B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration system
CN201410351712.8A Active CN104166894B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration method and system

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201610081826.4A Active CN105629935B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration system

Country Status (1)

Country Link
CN (2) CN105629935B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2685328Y (en) * 2003-12-29 2005-03-16 刘临杰 Efficient combined water purifier
CN101183251A (en) * 2007-12-19 2008-05-21 田一鸣 Electrical power system safety operation intelligent monitoring device and monitoring method thereof
CN101458502A (en) * 2008-12-30 2009-06-17 湖南省电力公司湘潭电业局 Electrical power system standardized work intelligent control method and special equipment

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6393332B1 (en) * 1999-04-02 2002-05-21 American Standard Inc. Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
CN1256465A (en) * 1999-12-06 2000-06-14 欧阳永熙 Control of power output from one generator set to power network and corresponding settlement method in power market
CN1704945A (en) * 2004-06-01 2005-12-07 上海市电力公司市东供电公司 Dangerous point safety precontrol method for power network dispatch
CN1752958A (en) * 2004-09-26 2006-03-29 福建省电力试验研究院 Evaluation system of electrical network operation state and dispatch decision system
EP2685328B1 (en) * 2012-07-10 2016-10-05 Siemens Aktiengesellschaft User interface of an automation system and a method
CN103198420B (en) * 2013-03-29 2015-12-23 山东电力集团公司 Real-time interactive long-distance fee-control management system and method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2685328Y (en) * 2003-12-29 2005-03-16 刘临杰 Efficient combined water purifier
CN101183251A (en) * 2007-12-19 2008-05-21 田一鸣 Electrical power system safety operation intelligent monitoring device and monitoring method thereof
CN101458502A (en) * 2008-12-30 2009-06-17 湖南省电力公司湘潭电业局 Electrical power system standardized work intelligent control method and special equipment

Also Published As

Publication number Publication date
CN105629935B (en) 2018-03-30
CN105629935A (en) 2016-06-01
CN104166894A (en) 2014-11-26

Similar Documents

Publication Publication Date Title
Ding et al. Big-M based MIQP method for economic dispatch with disjoint prohibited zones
Rashidaee et al. A linear model for dynamic generation expansion planning considering loss of load probability
Correa-Posada et al. Security-constrained optimal power and natural-gas flow
Babaei et al. Distributionally robust distribution network configuration under random contingency
Zhao et al. Using electrical energy storage to mitigate natural gas-supply shortages
CN110765112B (en) Energy equipment data association method and system based on Internet of things identification technology
CN104915750A (en) Intelligent operation ticket management method and system for achieving integration with an EMS and an OMS
CN103578039B (en) A kind of power networks risk prewarning analysis system
CN104951524B (en) A kind of mobile platform and its application method for database O&M
Dehghani et al. Multi-stage resilience management of smart power distribution systems: A stochastic robust optimization model
Valentine Wind power politics and policy
Meng et al. Flexible operational planning framework considering multiple wind energy forecasting service providers
Palma-Behnke et al. Smart grid solutions for rural areas
CN117993789B (en) Performance management method, device, equipment and storage medium based on task decomposition
CN106446298A (en) Data management method and device based on PDM (Pulse Duration Modulation)
Zhou et al. Robustness analysis of power system dynamic process and repair strategy
CN104166894B (en) Power plant's schedule voice declaration method and system
US20110264477A1 (en) Methods and a system for use of business process management for demand response
Zhao et al. Online multi-stage decisions for robust power-grid operations under high renewable uncertainty
CN108898473A (en) A kind of project transferring method and device
Zhang et al. Electricity auctions with intermittent wind generation
CN104914813B (en) The multi-platform synchronous method of prepared auto restart model in static security analysis system
CN113191692A (en) Intelligent management system and method for power failure dispatching plan
CN109359749A (en) A kind of gridding equipment management system
CN110070339A (en) A kind of civil air defense constructions and installations data management system, method based on block chain

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant