CN1535566A - Stereo-greening method of residential quarter - Google Patents

Stereo-greening method of residential quarter Download PDF

Info

Publication number
CN1535566A
CN1535566A CNA031182380A CN03118238A CN1535566A CN 1535566 A CN1535566 A CN 1535566A CN A031182380 A CNA031182380 A CN A031182380A CN 03118238 A CN03118238 A CN 03118238A CN 1535566 A CN1535566 A CN 1535566A
Authority
CN
China
Prior art keywords
greening
vegetation
exterior wall
turf
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA031182380A
Other languages
Chinese (zh)
Other versions
CN100531558C (en
Inventor
仙 李
李仙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB031182380A priority Critical patent/CN100531558C/en
Priority to PCT/CN2003/000510 priority patent/WO2004090262A1/en
Priority to AU2003252523A priority patent/AU2003252523A1/en
Publication of CN1535566A publication Critical patent/CN1535566A/en
Application granted granted Critical
Publication of CN100531558C publication Critical patent/CN100531558C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D11/00Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings
    • E04D11/002Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings consisting of two or more layers, at least one of the layers permitting turfing of the roof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/02Dwelling houses; Buildings for temporary habitation, e.g. summer houses
    • E04H1/04Apartment houses arranged in two or more levels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/254Roof garden systems; Roof coverings with high solar reflectance
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B80/00Architectural or constructional elements improving the thermal performance of buildings
    • Y02B80/32Roof garden systems

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Cultivation Of Plants (AREA)
  • Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)

Abstract

The present invention relates to a stereoscopic greening method for residential quarter. The method includes building roof greening, greening interval space between adjacent buildings, vertical greening of wall body of building, street accessory component garbage can greening, leadscape development of highway in the residential quarter and greening dividing lines of road and railway which are connected with said residential quarter. Said invention can consume lots of domestic refuse and industrial garbage, and can beautify city and reduce pollution, etc.

Description

A kind of building sub-district method for stereo afforesting
The present invention builds the sub-district vertical planting and is meant classified garbage box monitored on space between roof, house, the adjacent house, external wall of house, the pavement, the limit separated time of highway and the greening of middle separated time and railway boundary line.
Raising day by day along with development of global economy and industrialization degree, urbanization is being quickened, highway, railway construction fly to advance by leaps and bounds especially suddenly, but what be accompanied by is that to go to pot with ecotope be cost: reduce in the greenery patches, desertization aggravation, atmospheric pollution are on the rise, global warming, greenhouse effect more and more show acute.At present the vertical planting in house only rests on balcony and roof, and highway, railway greening only rest on bank protection, and existing urban afforestation planning, roadside greening planning, the one, exist planning not advanced; The 2nd, exist execution planning not thorough, cause the greening of a lot of cities, road to lag behind the demand of the expanding economy and the ecological balance far away, will produce and be difficult to expect, unmanageable consequence, bring irreparable damage, therefore the sub-district is built in the omnibearing stereo greening, and highway, railway are extremely urgent.
Essence of the present invention is to carry out omnibearing greening to the building sub-district and with the joining highway in sub-district, railway, thereby reaches the purpose that increases green coverage, changes microclimate.Indication roof greening of the present invention is compared with existing roof greening, its greening basin has the characteristics of batch production, large-scale production, because the greening basin has been carried out the cover cap connection, thereby has formed a rain-proof layer of separating fully with roofing, not only can be heat insulation, insulation, had the function of antiseepage especially; The sky that adjacent buildings has been afforested vacant lot by slide fastener, climbing plants can increase green coverage on a large scale, reduces the injury of ultraviolet ray to human body, solves the irrational contradiction of orientation of room; The greening of exterior wall large tracts of land can reduce noise, filtered air, absorption pernicious gas, particle and ultraviolet ray, satisfies the hope that people go back to nature; On the pavement, be provided with the classified garbage box monitored of greening basin, can reduce pedestrian's fidgety mood, improve people's life grade, improve the common people's environmental consciousness; The greening of highway limit separated time, middle separated time, railway boundary line can reduce road vehicle tail gas, noise pollution, beautifies road environment, eliminates journey fatigue, particularly afforests the highway center line, also has the function that reduces the mutual interference of the relative light phase of vehicle at night.
Technical scheme of the present invention is: a kind of building sub-district method for stereo afforesting, comprise with in grid water, with fertilizer for topdressing, it is characterized in that also being included in the subdistrict architecture corresponding site following 7 kinds of architecture greening members are set: 1) be arranged on the flat roof, can prevent the greening basin of roof seepage; 2) the greening chain on connection adjacent architectural roof; 3) fill out the brick turf vegetation exterior wall of building of the heart with the turf vegetation; 4) plant the brick non-turf vegetation exterior wall of building of the heart with non-turf vegetation; 5) it is indoor to be arranged on each floor, the water leakage pipe is housed in becoming by non-vegetation exterior wall, has and protect the indoor greening basin that the hole of going along with sb. to guard him in the hole exposes green plants stem and branches and leaves outward; 6) be arranged on the pavement, it is classified garbage box monitored that top is provided with the greening of afforesting basin; 7) be arranged in the highway limit that connects with the sub-district on the separated time and the limit separated time of railway on, in the water storage tube is housed vegetation fill out heart tube.
The cover plate that the trough of belt cover plate of dash and two ends dash arranged with an end connects the seam of greening basin longshore current water direction respectively by screw on the greening basin and pad and perpendicular to the seam of current direction, the joint that the trough of belt cover plate has an end of dash and a cover plate that two ends have dash is collided and is connect, and the other end stretches in the greening basin by the cover plate seam that two ends have dash.
In be provided with collecting bowl the turf vegetation to fill out the forming hole method that heart brick and non-turf vegetation fill out the hole of topdressing, turf hole and the tree planting hole of heart brick be to use with the identical plate nail paper matrix of eyelet specification to put into stock mould, with aggregate moulding together.
Turf vegetation exterior wall and non-turf vegetation exterior wall all adopt frame structure, leave maintenance frame plate eye and safety cock on frame beam column, the beam column indoor surface is provided with sealing drip circle, and indoor glass partition closes hydrosphere, the drip loop flooring is lower than indoor flooring, and masonry mortar is a cement mortar.When building turf vegetation exterior wall by laying bricks or stones, put into collecting bowl earlier, fill and lead up collecting bowl, fill up the turf vegetation with soil again and fill out heart brick with slag or rubble or sandstone, build by laying bricks or stones finish after, digging out eye, water, is that 7--30 days paper muscle (straw or straw) clay compound whitewashes exterior wall with soak time, spary grass seeds glue paper pulp thereon again, at once cover body of wall with straw or straw, water seasoning is until germinateing into turf.When building non-turf vegetation exterior wall by laying bricks or stones, put into collecting bowl earlier, in collecting bowl, fill slag or rubble or sandstone, wait to build by laying bricks or stones finish after, dig out eyelet, the root of planting trees is implanted non-turf vegetation by the tree planting hole fills out in the heart brick, fill up soil by the hole of topdressing simultaneously, water then, covering, maintenance.
Turf vegetation exterior wall and non-turf vegetation exterior wall topdress and fill out the hole of topdressing that heart brick and non-turf vegetation fill out heart brick from the turf vegetation and add.
The present invention will be further described below in conjunction with drawings and Examples:
Fig. 1 is a roof greening of the present invention, vacant lot greening between the adjacent buildings, the greening of non-vegetation exterior wall, the greening of turf vegetation exterior wall, the greening of non-turf vegetation exterior wall, the classified garbage box monitored greening schematic diagram in pavement; Fig. 2 is the floor map of roof greening basin along drainage direction horizontal layout and the connection of seam cover plate; Fig. 3 is that the structural section of roof greening basin and the joint of seam and seam connect generalized section; Fig. 4 is that the turf vegetation is filled out shape schematic diagram and the structure section schematic diagram that heart brick, non-turf vegetation are filled out heart brick; Fig. 5 is highway limit and middle separated time and the railway boundary line greening schematic diagram that is connected with the sub-district; Fig. 6 is structure section schematic diagram and the shape generalized section that vegetation is filled out heart tube.
As shown in Figure 1, adjacent buildings is afforested in the air, in the armored concrete that pulling plug is located at parapet of roofing bears down on one, main chain (10) is the delrin zippers with pulllers of chain eye 200mm, chain link diameter 20mm, arrangement pitch is 4000mm, and the inferior chain (11) that connects thereon is chain eye 100mm, the delrin zippers with pulllers of chain link diameter 10mm, arrangement pitch is 2000mm, climbs green plants and forms a green ceiling along the primary and secondary chain.
As shown in Figure 1, the greening of non-vegetation exterior wall (13), mould system greening basin (12) along the indoor setting of exterior wall, it is of a size of length * wide * height=1000mm * 500mm * 400mm, wall thickness 3mm, in be the greening basin (12) of the thick humus soil of 400mm, get out spacing 300mm, diameter 100mm along the non-bearing exterior wall and face upward laterally wall hole, insert diameter 100mm, the antiseep of wall thickness 3mm is moulded pipe (14), pass with root, the stem of straw rope wrapping tree or rattan and to mould pipe (14), root is implanted and is moulded in the humus soil of basin (12), carry out the hole of protruding wall face 60mm again and mix doubtful fortifield village and protect.
As shown in Figure 1, afforest the greening of classified garbage box monitored (24), afforest the classified garbage box monitored length * wide * height=1200mm * 1000mm * 1200mm that is of a size of, the high 400mm of its middle and upper part greening basin puts into the high humus soil of 350mm in the greening basin, get final product plant species.
As Fig. 1, Fig. 2, shown in Figure 3, flat roof greening, on roofing be of a size of 240mm length * 240mm wide * the 120mm height, intensity is that cinder concrete building block (9), the flowing water gradient by 1%, the 250mm spacing of MU10 built bearing by laying bricks or stones, last arrangement plastics greening basin (3), its be of a size of length * wide * height=1000mm * 1000mm * 450mm and length * wide * height=1500mm * * 1000mm * 450mm, wall thickness is 3mm, filling out the thick lightweight slag (7) of 100mm in basin earlier, is 100 * 100mm with the slag of particle diameter 20mm at the thick area of tapping pipe (6) top 50mm 2The space fill in, fill out humus soil (8) again, laying and soil layer are with thick particle diameter 20mm around the basin, wide is the slag permeable layer of 50mm, branch drain and house steward are installed in the bearing gap, the joint treatment of greening basin, the seam of greening basin requires to stagger, use wall thickness 3mm, groove depth 20mm, wide 50mm, cover high 30mm's, arrange with the system of moulding trough of belt cover plate (2) the longshore current water direction of eyelet above, use wall thickness 3mm, wide 50mm, cover high 30mm, above attached eyelet mould the system cover plate (1) arrange perpendicular to current direction, with the plastic-steel screw (5) of the long 50mm in greening basin (3) with mould gasket (4) and connect with cover plate (1) and cover plate (2) by the form that is spirally connected, wherein (1) all connects for bumping with the joint of (1), and (1) connects with (2), and an end of band dash bumps on seam flowing water top with (1) and connects, about 50mm in the greening basin (3) is stretched into by the seam of (1) and (1) in the bottom, the selected plant of plantation on humus soil.
Fill out the greening of heart brick exterior wall as Fig. 1, vegetation shown in Figure 4, vegetation is filled out heart brick exterior wall and comprises turf vegetation exterior wall (15) and non-turf vegetation exterior wall (22), used building block is respectively that cinder concrete turf vegetation is filled out heart brick (20) and the non-turf vegetation of cinder concrete is filled out heart brick (21), the method basically identical of its preparation method and cinder concrete hollow brick, the forming hole method of the lateral aperture (17) of different is brick (20) and (21), (16), (18) is for to put into the brick film earlier with paper film nail-plate, pour aggregate vibration moulding together into, the paper film is still in brick during the demoulding.The size of brick (20), (21) all be 400mm length * 240mm wide * the 180mm height, intensity is MU10, build by laying bricks or stones in the exterior wall framework, frame beam column is by spacing 1500mm, and size diameter 20mm, degree of depth 150mm stay system to prune preformed hole, and have stayed safety cock on Vierendeel girder, framework reserved closed drip loop, drip is of a size of 20mm, and wide * 30mm is dark, and the drip loop flooring is lower than indoor flooring 60mm, uses the M75 masonry of cement mortar.
When a. filling out heart brick (20) and build turf vegetation exterior wall (15) by laying bricks or stones with cinder concrete turf vegetation, put well earlier be of a size of 100mm length * 150mm wide * the 30mm height, the system of the moulding collecting bowl (19) of wall thickness 3mm, fill out the thick slag of 30mm (7), fill in mixing ratio by weight again and be 15: 1: 15 humus soil, fertilizer, clay compound (8), watering then, fully loaded degree is 95% to the natural slump, outer-wall building finishes, from top to bottom, dig out turf eyelet (16) on the brick, water exterior wall, with the important match ratio of soaking 7 days is that 1: 30 paper muscle (straw or straw) clay composite material whitewashes exterior wall, thickness 25mm, one-shot forming, spray important proportioning more thereon and be 1: 10 hinge muscle seed slurry, seed consumption 100g/m 2, cover, water, with straw or straw immediately until germinateing into turf
When b. filling out heart brick (21) and build non-turf vegetation exterior wall (22) by laying bricks or stones with the non-turf vegetation of cinder concrete, put into collecting bowl (19) earlier, fill up collecting bowl slag (7), after treating that one deck wall has been built by laying bricks or stones, dig out plant eye (18) and the eye that topdresses (17) from bottom to up, implant selected plant, pour soil (8) into by eye (17) simultaneously by eye (18), exterior wall does not whitewash, cladding system and turf vegetation exterior wall (15) basically identical.
Vegetation exterior wall beam column is decorated with exterior wall tile, and it is wide that indoor glass (23) is isolated 600mm, so that water, apply fertilizer, every floor is gone up and establish a middle water droplet water pipe on the skin brick most, eye drip of a skin brick.
As Fig. 5, shown in Figure 6, the highway that is connected with the sub-district (28) limit, the greening of middle separated time and railway (29) boundary line, water earlier and smash the wide C10 concrete cushion of 500mm, center line is not done bed course, with M75 masonry of cement mortar diameter 330mm, wall thickness 60mm, highly be respectively 1600mm, 1000mm, the cinder concrete vegetation that has a spilled water hole (27) is filled out heart tube (25) and builds sideline and center line by laying bricks or stones, when building by laying bricks or stones, put into earlier the 1200mm height respectively, 600mm, wall thickness 3mm, diameter is equal to the system of the moulding Water collecting tube (26) that vegetation is filled out heart tube (25) internal diameter, fill up Water collecting tube with slag (7), fill out humus soil (8) again, the plantation plant, every 20m establishes armored concrete folder post, grid pouring in using.
The present invention builds sub-district vertical planting engineering, advance and irritate with middle water, the fertilizer that in order to people's poultry manure is primary raw material is for topdressing, the primary raw material of each member is slag, rubble and plastics, filling soil is humus soil, these major parts can be obtained from the product of garbage disposal, thereby provide opportunity for the marketization of garbage disposal.The a lot of countries in the world are all implementing the plan of conceding the land to forestry at present, quicken the vertical planting of building sub-district, have equal strategic importance with it, and whole engineering can be provided funds to foster by government, utilizes society to go up every fund, incorporates market at last.Particularly present the commercial house cellular engineering if adopt afforestation project of the present invention, then can directly come into the market.

Claims (5)

1, a kind of building sub-district method for stereo afforesting, comprise with in grid water,, it is characterized in that also being included in the subdistrict architecture corresponding site following 7 kinds of greening members be set for topdressing with fertilizer:
1), be arranged on the flat roof, prevent the roof seepage, be located in that building block bearing (9) is gone up, tapping pipe (6) is left in the bottom, slag is equipped with in the bottom or soil (8), the edge greening basin (3) with screw (5) is equipped with on sandstone or rubble (7), top;
2) be the termination, with the pulling plug that is located on the roofing collar tie beam, mutual spacing is 500mm~5000mm, with mutual spacing be that the inferior chain (11) of 1000mm~3000mm connects, leave light shaft by spacing 10m~150m, supply climbing plants to grow, connect the greening chain (10) on adjacent buildings roof;
3), fill out the turf vegetation exterior wall (14) that heart brick (20) is built by laying bricks or stones with the turf vegetation;
4), fill out the non-turf vegetation exterior wall (22) that heart brick (21) is built by laying bricks or stones with non-turf vegetation;
5), to be arranged on each floor indoor, become by non-vegetation exterior wall (13), in water leakage sleeve pipe (14) is housed, has and protect the indoor greening basin (12) that the hole of going along with sb. to guard him in the hole exposes green plants stem and branches and leaves outward;
6), be arranged on the pavement, top be provided with the greening basin greening classified garbage box monitored (24);
7), be arranged on and build in the limit of the joining highway in sub-district (28) on the separated time and on the limit separated time of railway (29), leave spilled water hole (27), in have water storage tube (26), bottom that slag or sandstone or rubble (7), top are housed the vegetation of soil (8) is housed fills out heart tube (25);
2, according to right 1 described building sub-district method for stereo afforesting, it is characterized in that having the trough of belt cover plate (2) of dash and the cover plate (1) that there is dash at two ends to connect the seam of afforesting basin (3) longshore current water direction respectively and perpendicular to the seam of current direction by screw (5) and pad (4) with an end, an end that has dash of trough of belt cover plate (2) and the joint of cover plate (1) are collided and are connect, and the other end stretches in the greening basin (3) by the seam of (1).
3, according to right 1 described building sub-district method for stereo afforesting, be equipped with and topdress and water inlet (17), collecting bowl (19), slag or sandstone or rubble (7), clay (8) and be respectively equipped with turf hole (16) and the turf vegetation of tree planting hole (18) to fill out the forming hole method in (17) hole that heart brick (20) and non-turf vegetation fill out heart brick (21), (16) hole, (18) hole be to use with the identical paper matrix nail-plate of eyelet specification to put into stock mould, with aggregate moulding together.
4, according to right 1 described building sub-district method for stereo afforesting, it is characterized in that turf vegetation exterior wall (15) and non-turf vegetation exterior wall (22) all adopt frame structure, on frame beam column, leave maintenance frame plate eye and safety cock, the beam column indoor surface is provided with sealing drip circle, indoor glass (23) partition closes hydrosphere, the drip loop flooring is lower than indoor flooring, and masonry mortar is a cement mortar.When building turf vegetation exterior wall (14) by laying bricks or stones, put into collecting bowl (19) earlier, fill and lead up collecting bowl (19) with slag or rubble or sandstone (7), use soil (8) to fill up the turf vegetation again and fill out heart brick (20), build by laying bricks or stones finish after, dig out eye (16), water, be that 7~30 days paper muscle (straw or straw) clay compound whitewashes exterior wall with soak time, spary grass seeds glue paper pulp thereon covers body of wall with straw or straw at once again, and water seasoning is until germinateing into turf.When building non-turf vegetation exterior wall (22) by laying bricks or stones, after putting into collecting bowl (19) earlier, in collecting bowl, fill slag or rubble or sandstone (7), wait to build by laying bricks or stones finish after, dig out eyelet (18), the root of planting trees is implanted non-turf vegetation by hole (18) fill out in the heart brick (21), the while is filled soil (8) with hole (17), waters then, covering, maintenance.
5, according to right 1 described building sub-district method for stereo afforesting, (17) add to it is characterized in that topdressing turf vegetation exterior wall (15) and non-turf vegetation exterior wall (22) from the hole.
CNB031182380A 2003-04-04 2003-04-04 Tri-dimensional greening method of residential area Expired - Fee Related CN100531558C (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CNB031182380A CN100531558C (en) 2003-04-04 2003-04-04 Tri-dimensional greening method of residential area
PCT/CN2003/000510 WO2004090262A1 (en) 2003-04-04 2003-06-30 Method for planting by three dimensions________________________
AU2003252523A AU2003252523A1 (en) 2003-04-04 2003-06-30 Method for planting by three dimensions________________________

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB031182380A CN100531558C (en) 2003-04-04 2003-04-04 Tri-dimensional greening method of residential area

Publications (2)

Publication Number Publication Date
CN1535566A true CN1535566A (en) 2004-10-13
CN100531558C CN100531558C (en) 2009-08-26

Family

ID=33136791

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB031182380A Expired - Fee Related CN100531558C (en) 2003-04-04 2003-04-04 Tri-dimensional greening method of residential area

Country Status (3)

Country Link
CN (1) CN100531558C (en)
AU (1) AU2003252523A1 (en)
WO (1) WO2004090262A1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1717978B (en) * 2005-06-03 2010-04-28 南京大学 Constituting method and application of space afforestation system for buildings
WO2017028349A1 (en) * 2015-08-14 2017-02-23 陈瑞文 Improved soil graded layer structure
CN106954486A (en) * 2017-04-24 2017-07-18 曹俊 High building exterior wall vertical greening device
CN108360846A (en) * 2018-01-24 2018-08-03 河南工程学院 A kind of multifunctional ecological Landscape Architecture and its construction method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100392204C (en) * 2006-07-10 2008-06-04 郭建军 Multistory building
CN102138433A (en) * 2011-04-29 2011-08-03 上海交通大学 Mixed planting method for vertical greening plants on urban wall surface

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07279448A (en) * 1994-04-12 1995-10-27 Mitsui Constr Co Ltd Apartment house structure
CN1147051A (en) * 1995-06-26 1997-04-09 季相金 Method for construction of dwelling house capable of planting plants in great abundance
JPH11107547A (en) * 1997-09-30 1999-04-20 Moricho Corp Building using solar heat

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1717978B (en) * 2005-06-03 2010-04-28 南京大学 Constituting method and application of space afforestation system for buildings
WO2017028349A1 (en) * 2015-08-14 2017-02-23 陈瑞文 Improved soil graded layer structure
CN106954486A (en) * 2017-04-24 2017-07-18 曹俊 High building exterior wall vertical greening device
CN108360846A (en) * 2018-01-24 2018-08-03 河南工程学院 A kind of multifunctional ecological Landscape Architecture and its construction method

Also Published As

Publication number Publication date
AU2003252523A1 (en) 2004-11-01
CN100531558C (en) 2009-08-26
WO2004090262A1 (en) 2004-10-21

Similar Documents

Publication Publication Date Title
AU2004246926B2 (en) Greening system
CN105569281B (en) A kind of environmental roof greening structure and its construction method
CN106639180A (en) Rainwater collecting system for roof garden and construction method
CN1844611A (en) Pot type ecological yard and construction method thereof
CN107853008A (en) Prefabricated assembled plant walls
CN108283080A (en) It is a kind of to set pond from ecology is poured for sponge city
CN201074307Y (en) Crash-proof wall for road-bridge greening
CN106358694A (en) Method for quickly greening stony deserted mountain
CN106013624A (en) Technical method of green sponge roof modified on basis of grass planting plate
CN205623507U (en) Sunlight greenhouse who is fit for saline and alkaline land
CN108952022A (en) Inclined roof greening system
CN107881875A (en) A kind of karst ecology parking lot and its building method
CN100531558C (en) Tri-dimensional greening method of residential area
CN101548615A (en) Porous nest brick 3D green plant technology
JP2003047346A (en) Planting vessel for vegetation and method for making the same
CN205865199U (en) Roof greening plant structure
CN202090637U (en) Parking lot for city old residential areas
CN207706804U (en) Prefabricated assembled plant walls
CN202489024U (en) Cement pillar type greening shed
CN204662553U (en) A kind of cavernous body multifunctional ecological governing system
JP2008092924A (en) Construction method comprising fertilizer/soil application and watering for frame-built-type building, and building wall surface greening, utilizing highly water-retentive lath net panel
CN207608782U (en) A kind of embedding careless brick paving structure of good ecology of drainage performance
CN215669234U (en) Energy-absorbing water-guiding waterlogging-preventing structure for urban highway
CN109137657A (en) T font zero-emission Multi-layer ecological viaduct
CN110880269B (en) Water-saving garden demonstration model and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090826

Termination date: 20120404