CN111206933A - Tunnel construction method for traversing karst water-rich section - Google Patents

Tunnel construction method for traversing karst water-rich section Download PDF

Info

Publication number
CN111206933A
CN111206933A CN202010068338.6A CN202010068338A CN111206933A CN 111206933 A CN111206933 A CN 111206933A CN 202010068338 A CN202010068338 A CN 202010068338A CN 111206933 A CN111206933 A CN 111206933A
Authority
CN
China
Prior art keywords
water
tunnel
hole
face
karst
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010068338.6A
Other languages
Chinese (zh)
Inventor
张志强
谭因军
陶伟明
陈昕
卿伟宸
张磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN202010068338.6A priority Critical patent/CN111206933A/en
Publication of CN111206933A publication Critical patent/CN111206933A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to a tunnel construction method for traversing a karst water-rich area, which is characterized by comprising the following steps: step 1, when tunnel construction approaches a karst water-rich area, predicting underground water development and stratum information by adopting an advanced geological prediction method; step 2, drilling a water detection hole by adopting an advanced horizontal drilling hole, and detecting the water gushing position, the water gushing amount and the water gushing pressure of the karst water-rich section through the water detection hole; step 3, excavating a tunnel face first pilot tunnel in the tunnel contour line according to the predicted water gushing position to drain water and reduce pressure, wherein the water gushing position is positioned on the side wall of the first pilot tunnel; 4, adopting a small advanced guide pipe for grouting to support the tunnel in advance to form a grouting ring for resisting water and preventing underground water from flowing into surrounding rock in front of the tunnel face; and 5, performing tunnel body excavation operation, plugging the water detection hole, and excavating the tunnel body by adopting controlled blasting. The invention can effectively reduce the risk of water inrush on the tunnel face and ensure the safety of tunnel construction.

Description

Tunnel construction method for traversing karst water-rich section
Technical Field
The invention relates to the technical field of tunnel construction, in particular to a tunnel construction method for passing through a karst water-rich area.
Background
With the rapid development of national economy and the urgent need of people for traffic development, the traffic mode mainly including highways and railways in China develops rapidly, and tunnel engineering built in karst water-rich areas with extremely complex terrain and geology is increasing day by day. Underground water existing in the stratum is one of important factors causing tunnel construction risks and construction accidents. At present, a plurality of engineering examples show that underground water in mountains in karst areas often has higher water pressure, if proper drainage and depressurization measures cannot be found in time in tunnel construction, mud burst and water burst are easily generated on the tunnel face, the tunnel structure is damaged and the construction period is delayed, and buried construction equipment and field constructors are destroyed to cause huge casualties and economic losses. How to effectively prevent the tunnel face of the tunnel in the karst water-rich stratum from gushing and bursting water has important practical significance for reducing construction risks and guaranteeing life and property safety of people.
The invention patent CN109578007A discloses a construction method for excavating and draining a tunnel passing through a high-angle back-flushing water-rich sand-rich fault, wherein a roundabout pilot tunnel and a high-position water drain tunnel are arranged on the same side of a main tunnel of the constructed tunnel, and the existing underground water is drained through the high-position water drain tunnel. The Chinese patent invention CN110630325A discloses a water drainage method for long distance tunnels by utilizing horizontal directional drilling, which has good water drainage effect on tunnels with large daily water inflow and the length of the to-be-excavated segment reaching more than 800 m, but needs 3 water retaining walls, has complex process, is not suitable for residential areas or plant areas and the like below an outlet and has great limitation. In the two inventions, drainage is carried out by building a drainage tunnel, the tunnel main tunnel cannot be fully utilized, and the investment cost is obviously increased.
The invention discloses a tunnel construction method for penetrating a karst water-rich stratum, which is mainly applied to tunnel penetration karst water-rich stratum face stability control and excavation construction. When the drainage and pressure reduction of the karst water-rich stratum are carried out, the water burst on the tunnel face can be effectively prevented, the water quantity in front of the tunnel face can be monitored, the construction time is determined, and the method has the advantages of reasonable design, safety in construction, ecological environment friendliness and the like, and is suitable for stability control and construction of the tunnel face of the water-rich stratum tunnel.
Disclosure of Invention
The invention aims to provide a tunnel construction method for passing through a karst water-rich area, which can effectively reduce the risk of water inrush on the tunnel face and ensure the safety of tunnel construction.
Therefore, the invention adopts the following technical scheme:
a tunnel construction method for passing through a karst water-rich area comprises the following steps:
step 1, when tunnel construction approaches a karst water-rich area, predicting underground water development and stratum information by adopting an advanced geological prediction method;
step 2, drilling a water detection hole by adopting an advanced horizontal drilling hole, and detecting the water gushing position, the water gushing amount and the water gushing pressure of the karst water-rich section through the water detection hole;
step 3, excavating a tunnel face first pilot hole in the tunnel contour line for draining and depressurizing according to the predicted water burst position, wherein the first pilot hole is located in the area where the drilled hole with the maximum water drainage amount is located;
4, adopting a small advanced guide pipe for grouting to support the tunnel in advance to form a grouting ring for resisting water and preventing underground water from flowing into surrounding rock in front of the tunnel face;
and 5, performing tunnel body excavation operation, plugging the water detection hole, and excavating the tunnel body by adopting controlled blasting.
Further, after the step 5, the method further comprises the following steps:
and 6, dynamically monitoring surrounding rock convergence and tunnel vault settlement by adopting a monitoring and measuring means, guiding a construction site, and optimizing and adjusting construction measures in time.
Preferably, a monitoring point is arranged in each 2-time circulation, the frequency of measurement is 2-4 times per day, surrounding rock convergence and tunnel vault settlement are dynamically monitored, and the circulation is the circulation footage of the blasting excavation of the tunnel body.
Preferably, in step 1, a TSP203 geological detector is used for detecting the surrounding rock in the range of 100-200 m in front of the tunnel face.
Preferably, in step 2, the tunnel face is divided into five regions with equal areas, 5 advanced horizontal water detection holes are drilled on the tunnel face, 2 shallow holes are arranged on the upper row, and 3 deep holes are arranged on the lower row, and the depth of the deep holes is greater than that of the shallow holes.
Preferably, the diameter of the shallow hole is 50mm, the longitudinal outward inserting angle of the drilling hole is 10-12 degrees, and the drilling depth is 30-50 m; the diameter of the deep hole is 101-225 mm, the longitudinal outward inserting angle of the drill hole is 2-4 degrees, and the depth of the drill hole is 120-200 m.
Preferably, the advanced pilot tunnel is located in the area where the largest drainage hole in the 3 deep holes is located, excavation is performed along the bottom surface of the tunnel, the diameter is 2-5 m, the tunneling length is 20m, and the advanced pilot tunnel is always kept 15-20 m ahead of the tunnel face in the construction process.
Preferably, the leading small guide pipes are arranged in the arch crown part of the tunnel face within 120 degrees, the diameter is 50mm, the circumferential distance is 30cm, the length is 5m, the external insertion angle is 20 degrees, the lap joint length of the small guide pipes is 1m, and the upper rock-soil body in front of the reinforced tunnel face is grouted to form a reinforced water plugging grouting ring.
Further, in step 5, the water-blocked water detecting hole is used as a blast hole.
Further, drilling shallow holes again every 30-50 m of tunnel tunneling, and predicting water inflow and water bursting pressure within the range of 30-50 m in front of the tunnel face through the water spraying distance of the water detecting holes; and (3) re-drilling a deep hole every 120-200 m after tunneling in the tunnel, judging the water burst position of the front tunnel face through the water discharge of the deep hole, and comparing the water discharge of the 3 deep holes, wherein the area where the deep hole with the maximum water discharge is the most likely water burst position.
Preferably, the blasting footage of the controlled blasting excavation hole body is 2 m.
The invention has the following beneficial effects:
firstly, geological forecast is carried out on surrounding rock in front of a tunnel face, the position of the tunnel face where water inrush possibly occurs is found out through drilling, then a small TBM (tunnel boring machine) is used for excavating the tunnel face to drain water in a pilot tunnel, the drainage pilot tunnel has large drainage quantity, the effect of draining water and reducing pressure can be rapidly achieved, and the risk of water inrush on the tunnel face during construction is effectively reduced;
after the water exploration of the drilled advanced horizontal hole is finished, the drilled hole can be subjected to water plugging treatment and used as a blast hole in blasting construction, the functions of the existing drilled hole are fully exerted, the hole is multipurpose, the construction time can be shortened, and the construction process is accelerated;
the blast vibration crack generated by the blasting construction can promote the formation of a water guide channel, increase the drainage capacity of surrounding rocks, facilitate the gathering of underground water into a leading drainage pilot pit, accelerate the drainage speed, and create a free surface for the subsequent blasting construction by excavating the leading pilot pit, thereby facilitating the blasting construction. Blasting construction and pilot tunnel excavation are carried out, which complement each other and bring out the best in each other;
the invention also discloses a tunnel main tunnel, which is used for reducing the blasting construction workload after water drainage, and directly uses the tunnel body as a water drainage channel, thereby realizing the purposes of drainage and pressure reduction in tunnel construction in a karst water-rich area, and obviously reducing the tunnel investment cost without constructing an auxiliary water drainage tunnel.
Drawings
FIG. 1 is a flow chart of the present invention;
FIG. 2 is a cross-sectional view of the tunnel face partition and the positions of water detection holes;
FIG. 3 is a longitudinal sectional view of a water detecting hole of a tunnel;
fig. 4 is a longitudinal section view of a tunnel face leading pit.
In the figure: 1-water detection shallow hole, 2-water detection deep hole, 3-advanced small conduit and 4-advanced pilot tunnel.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in further detail below with reference to the accompanying drawings.
As shown in fig. 1, the tunnel construction method for passing through the karst water-rich area disclosed by the invention comprises the following steps:
1) when tunnel construction approaches a karst water-rich section, predicting underground water development and stratum information by adopting an advanced geological prediction method; and (3) pasting and coating, wherein a TSP203 geological detector is adopted to detect the surrounding rock within the range of 100-200 m in front of the face.
2) Adopting advanced horizontal drilling, and detecting basic conditions such as water burst position, water burst amount, water burst pressure and the like of a karst water-rich section through a water detection shallow hole 1 and a deep hole 2;
3) adopting a TBM (tunnel boring machine), excavating a tunnel face first pilot tunnel 4 in a tunnel contour line according to the predicted water gushing position, and draining and depressurizing;
4) adopting a small advanced conduit 3 for grouting to support the tunnel in advance to form a grouting ring for resisting water and preventing underground water from flowing into surrounding rock in front of the tunnel face;
5) performing tunnel body excavation operation, plugging the water detection hole, and excavating the tunnel body by adopting controlled blasting, wherein the blasting footage is 2 m;
6) and a monitoring and measuring means is adopted to dynamically monitor surrounding rock convergence and tunnel vault settlement, guide a construction site and optimize and adjust construction measures in time.
Referring to fig. 2 and 3, the tunnel face of the tunnel is divided into five regions with equal areas, 5 advanced horizontal water detection holes are drilled on the tunnel face, 2 shallow holes 1 are arranged on the upper row, and 3 deep holes 2 are arranged on the lower row.
Upper row 2 shallow holes 1: the diameter is 50mm, the longitudinal outward insertion angle of the drilled hole is 10-12 degrees, the drilling depth is 30-50 m, the drilled hole is drilled again every 30-50 m of tunneling of the tunnel, the water inflow and the water bursting pressure within the range of 30-50 m in front of the tunnel face are predicted through the water spraying distance of the shallow hole 1, the small water bursting is carried out when the maximum spraying distance is less than 5m, the medium water bursting is carried out when the maximum spraying distance is 5-12 m, and the large water bursting is carried out when the maximum spraying distance is more than 12 m.
Lower row of 3 deep holes (2): the diameter is 101 ~ 225mm, and the outer angle of inserting of drilling longitudinal is 2 ~ 4, and drilling depth is 120 ~ 200m, and every tunnel is tunneled 120 ~ 200m and is carried out the drilling again, judges the place that gushes water of preceding face through 2 displacement in the deep hole, and the follow-up drainage measure of taking of being convenient for compares 32 displacements in the deep hole, and the biggest drilling place region of displacement corresponds to and most probably takes place to gush the position of gushing water promptly.
Referring to fig. 4, the position of the leading pit 4 is located in the area where the hole with the largest water displacement is located in the 3 deep holes 2, excavation is performed along the bottom surface of the tunnel, the diameter is 2-5 m, the excavation length is 20m, and the leading pit 4 is always kept 15-20 m ahead of the tunnel face in the construction process. In order to facilitate the free drainage of the wall surface of the pilot tunnel 4, a steel support is adopted for supporting. After the first pilot hole 4 is constructed, water in the surrounding rock in front of the tunnel face is quickly discharged through the pilot hole, and when the water discharge amount in the 2 shallow holes 1 and the first pilot hole 4 is obviously reduced and tends to be stable, the subsequent steps can be carried out.
Referring to fig. 2 and 4, the advanced small ducts 3 are arranged in the arch crown part of the tunnel face within 120 degrees, the diameter is 50mm, the circumferential distance is 30cm, the length is 5m, the external insertion angle is 20 degrees, the overlapping length of the small ducts is 1m, and the upper rock-soil body in front of the tunnel face is reinforced by grouting to form a reinforcing water plugging grouting ring.
The present invention is not limited to the above embodiments, and other embodiments are possible, and various changes and modifications may be made by those skilled in the art without departing from the spirit and the essence of the present invention, and these changes and modifications should fall within the scope of the appended claims.

Claims (11)

1. A tunnel construction method for passing through a karst water-rich area is characterized by comprising the following steps:
step 1, when tunnel construction approaches a karst water-rich area, predicting underground water development and stratum information by adopting an advanced geological prediction method;
step 2, drilling a water detection hole by adopting an advanced horizontal drilling hole, and detecting the water gushing position, the water gushing amount and the water gushing pressure of the karst water-rich section through the water detection hole;
step 3, excavating a tunnel face first pilot hole in the tunnel contour line for draining and depressurizing according to the predicted water burst position, wherein the first pilot hole is located in the area where the drilled hole with the maximum water drainage amount is located;
4, adopting a small advanced guide pipe for grouting to support the tunnel in advance to form a grouting ring for resisting water and preventing underground water from flowing into surrounding rock in front of the tunnel face;
and 5, performing tunnel body excavation operation, plugging the water detection hole, and excavating the tunnel body by adopting controlled blasting.
2. The method of claim 1, further comprising, after step 5:
and 6, dynamically monitoring surrounding rock convergence and tunnel vault settlement by adopting a monitoring and measuring means, guiding a construction site, and optimizing and adjusting construction measures in time.
3. The method for constructing the tunnel penetrating through the karst water-rich area according to claim 2, wherein a monitoring point is arranged every 2 cycles, the measuring frequency is 2-4 times per day, surrounding rock convergence and tunnel vault settlement are dynamically monitored, and the cycle is a cyclic footage of blasting excavation of a tunnel body.
4. The method as claimed in claim 1, wherein in step 1, a TSP203 geological detector is used to detect the surrounding rock within the range of 100 m-200 m in front of the tunnel face.
5. The method as claimed in claim 1, wherein in step 2, the tunnel face is divided into five zones with equal area, 5 face advanced horizontal water detection holes are drilled, 2 shallow holes are drilled at the upper row, and 3 deep holes are drilled at the lower row, and the depth of the deep holes is greater than that of the shallow holes.
6. The tunnel construction method for passing through the karst water-rich area according to claim 5, wherein the diameter of the shallow hole is 50mm, the longitudinal outward inserting angle of the drill hole is 10-12 degrees, and the depth of the drill hole is 30-50 m; the diameter of the deep hole is 101-225 mm, the longitudinal outward inserting angle of the drill hole is 2-4 degrees, and the depth of the drill hole is 120-200 m.
7. The method for constructing the tunnel penetrating through the karst water-rich area according to claim 1, wherein the leading pilot tunnel in the step 3 is positioned in the area where the largest water displacement hole in the 3 deep holes is positioned, the tunnel is excavated along the bottom surface of the tunnel, the diameter of the leading pilot tunnel is 2-5 m, the excavation length of the leading pilot tunnel is 20m, and the leading pilot tunnel is kept 15-20 m ahead of the tunnel face of the tunnel all the time in the construction process.
8. The method according to claim 1, wherein in step 4, the leading small ducts are arranged within 120 degrees of the vault part of the tunnel face, the diameter is 50mm, the circumferential distance is 30cm, the length is 5m, the external insertion angle is 20 degrees, the overlapping length of the small ducts is 1m, and the upper rock-soil body in front of the tunnel face is grouted to form a reinforcing water plugging grouting ring.
9. The method as claimed in claim 1, wherein the water-blocked water-exploring hole is used as a blast hole in step 5.
10. The method for constructing the tunnel penetrating through the karst water-rich area according to claim 1, wherein shallow holes are drilled again every 30-50 m of tunnel excavation, and the water inflow and water inrush pressure within the range of 30-50 m in front of a tunnel face are predicted through the water spraying distance of a water detecting hole; and (3) re-drilling a deep hole every 120-200 m after tunneling in the tunnel, judging the water burst position of the front tunnel face through the water discharge of the deep hole, and comparing the water discharge of the 3 deep holes, wherein the area where the deep hole with the maximum water discharge is the most likely water burst position.
11. The method as claimed in claim 1, wherein the blasting footage of the body of the controlled blasting excavation is 2 m.
CN202010068338.6A 2020-01-20 2020-01-20 Tunnel construction method for traversing karst water-rich section Pending CN111206933A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010068338.6A CN111206933A (en) 2020-01-20 2020-01-20 Tunnel construction method for traversing karst water-rich section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010068338.6A CN111206933A (en) 2020-01-20 2020-01-20 Tunnel construction method for traversing karst water-rich section

Publications (1)

Publication Number Publication Date
CN111206933A true CN111206933A (en) 2020-05-29

Family

ID=70787447

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010068338.6A Pending CN111206933A (en) 2020-01-20 2020-01-20 Tunnel construction method for traversing karst water-rich section

Country Status (1)

Country Link
CN (1) CN111206933A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012770A (en) * 2020-07-26 2020-12-01 中铁二院工程集团有限责任公司 Underground water advanced treatment structure and construction method for ultra-deep vertical shaft of railway tunnel
CN112066830A (en) * 2020-08-27 2020-12-11 中铁三局集团广东建设工程有限公司 Method for constructing sandy slate tunnel
CN112796769A (en) * 2020-12-24 2021-05-14 中铁十八局集团第五工程有限公司 Construction method of water-rich weak surrounding rock stratum tunnel
CN113073983A (en) * 2021-05-19 2021-07-06 中国海洋大学 Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN113153309A (en) * 2021-03-09 2021-07-23 中铁工程装备集团有限公司 Tunnel construction method
CN113153307A (en) * 2020-11-26 2021-07-23 西南交通大学 Tunnel construction method suitable for water-rich fractured rock mass
CN113187512A (en) * 2021-04-27 2021-07-30 中铁建云南交通建设管理有限公司 Grouting and drainage construction method for large-scale water burst and mud outburst of karst tunnel
CN113217036A (en) * 2021-06-23 2021-08-06 中交路桥华东工程有限公司 Post-grouting construction method for tunnel structure at water burst section of fault fracture zone
CN113530573A (en) * 2021-08-20 2021-10-22 湖南楚湘建设工程集团有限公司 Long-detection-short-detection-grouting combined water prevention and control method based on water inflow classification
CN113565566A (en) * 2021-08-24 2021-10-29 中铁二院工程集团有限责任公司 Construction method for dewatering, depressurizing and stabilizing tunnel face of water-rich composite stratum
CN113833492A (en) * 2021-09-28 2021-12-24 中铁十八局集团有限公司 TBM (tunnel boring machine) tunneling settlement and water burst section treatment method for small-section water conservancy tunnel
CN115859430A (en) * 2022-12-01 2023-03-28 中铁二十三局集团有限公司 Single-track railway tunnel reinforcement design and construction method suitable for water-rich soft rock

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10169362A (en) * 1996-12-16 1998-06-23 Taisei Corp Tunnel excavation method and excavator
CN102094678A (en) * 2009-12-11 2011-06-15 张旭东 Method for identifying water-bursting risks in karst tunnels
CN102322294A (en) * 2011-05-31 2012-01-18 中铁二十局集团第一工程有限公司 Comprehensive geological prediction method for karst tunnel construction
CN102748031A (en) * 2012-06-21 2012-10-24 中铁十三局集团有限公司 Water pressure control method for use in TBM (Tunnel Boring Machine) method construction of heavy-gradient high-burial-depth water-rich stratum inclined shaft
CN104234726A (en) * 2014-08-26 2014-12-24 中国路桥工程有限责任公司 Internal dewatering and drainage construction method for tunnel passing through water-rich unconformable contact zone
CN105334548A (en) * 2015-10-20 2016-02-17 中冶交通建设集团有限公司 Geological forecasting method for tunnel construction in karst area
CN107165659A (en) * 2017-07-17 2017-09-15 中国电建集团华东勘测设计研究院有限公司 Water-bed tunnel meets shear-zone front pre-grouting construction method
CN107589471A (en) * 2017-07-13 2018-01-16 高军 A kind of Railway Tunnel Synthetic Geological Prediction Ahead of Construction method
CN109403986A (en) * 2017-08-16 2019-03-01 中铁二院工程集团有限责任公司 The synchronous enlarging of the parallel heading of TBM tunneling construction is the construction method of double line tunnel
CN109505628A (en) * 2018-12-06 2019-03-22 中铁三局集团广东建设工程有限公司 A kind of water-rich fault zone method for tunnel construction
CN109578007A (en) * 2018-11-26 2019-04-05 中铁二十局集团有限公司 Pass through that high angle is inverse to rush rich water richness sand tomography tunnel excavation and drainage and construction method
CN109751063A (en) * 2019-02-26 2019-05-14 中铁第四勘察设计院集团有限公司 A kind of large section tunnel supporting construction and its construction method
CN110185457A (en) * 2019-06-24 2019-08-30 中铁隧道局集团有限公司 A kind of flat pilot tunnel body construction method of TBM
CN110221340A (en) * 2019-07-03 2019-09-10 武汉中科岩土工程有限责任公司 A kind of set of tunneling construction method for forecasting advanced geology
CN110284890A (en) * 2019-07-16 2019-09-27 中铁五局集团第四工程有限责任公司 A kind of clast stream formation tunnel excavation construction method and structure
CN110284889A (en) * 2019-06-24 2019-09-27 中铁隧道局集团有限公司 A kind of flat pilot tunnel Enlargement excavation method of TBM
CN110630325A (en) * 2019-09-06 2019-12-31 中铁隧道集团一处有限公司 Draining method for long-distance tunnel by utilizing horizontal directional drilling

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10169362A (en) * 1996-12-16 1998-06-23 Taisei Corp Tunnel excavation method and excavator
CN102094678A (en) * 2009-12-11 2011-06-15 张旭东 Method for identifying water-bursting risks in karst tunnels
CN102322294A (en) * 2011-05-31 2012-01-18 中铁二十局集团第一工程有限公司 Comprehensive geological prediction method for karst tunnel construction
CN102748031A (en) * 2012-06-21 2012-10-24 中铁十三局集团有限公司 Water pressure control method for use in TBM (Tunnel Boring Machine) method construction of heavy-gradient high-burial-depth water-rich stratum inclined shaft
CN104234726A (en) * 2014-08-26 2014-12-24 中国路桥工程有限责任公司 Internal dewatering and drainage construction method for tunnel passing through water-rich unconformable contact zone
CN105334548A (en) * 2015-10-20 2016-02-17 中冶交通建设集团有限公司 Geological forecasting method for tunnel construction in karst area
CN107589471A (en) * 2017-07-13 2018-01-16 高军 A kind of Railway Tunnel Synthetic Geological Prediction Ahead of Construction method
CN107165659A (en) * 2017-07-17 2017-09-15 中国电建集团华东勘测设计研究院有限公司 Water-bed tunnel meets shear-zone front pre-grouting construction method
CN109403986A (en) * 2017-08-16 2019-03-01 中铁二院工程集团有限责任公司 The synchronous enlarging of the parallel heading of TBM tunneling construction is the construction method of double line tunnel
CN109578007A (en) * 2018-11-26 2019-04-05 中铁二十局集团有限公司 Pass through that high angle is inverse to rush rich water richness sand tomography tunnel excavation and drainage and construction method
CN109505628A (en) * 2018-12-06 2019-03-22 中铁三局集团广东建设工程有限公司 A kind of water-rich fault zone method for tunnel construction
CN109751063A (en) * 2019-02-26 2019-05-14 中铁第四勘察设计院集团有限公司 A kind of large section tunnel supporting construction and its construction method
CN110185457A (en) * 2019-06-24 2019-08-30 中铁隧道局集团有限公司 A kind of flat pilot tunnel body construction method of TBM
CN110284889A (en) * 2019-06-24 2019-09-27 中铁隧道局集团有限公司 A kind of flat pilot tunnel Enlargement excavation method of TBM
CN110221340A (en) * 2019-07-03 2019-09-10 武汉中科岩土工程有限责任公司 A kind of set of tunneling construction method for forecasting advanced geology
CN110284890A (en) * 2019-07-16 2019-09-27 中铁五局集团第四工程有限责任公司 A kind of clast stream formation tunnel excavation construction method and structure
CN110630325A (en) * 2019-09-06 2019-12-31 中铁隧道集团一处有限公司 Draining method for long-distance tunnel by utilizing horizontal directional drilling

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
中国公路学会隧道工程分会等: "《2004年岩溶地区隧道修筑技术专题研讨会论文集》", 31 October 2004, 人民交通出版社 *
俞养田: "《水文地质》", 30 November 1993, 冶金工业出版社 *
卿伟宸等: "特大跨度四线深埋隧道施工工法研究——以乌蒙山2号出口车站隧道为例", 《隧道建设(中英文)》 *
李薇: "《公路隧道施工安全技术》", 30 November 2014, 云南科学技术出版社 *
郭佳奇等: "岩溶区隧道突水灾害防治原则及治理对策", 《中国地质灾害与防治学报》 *
郭占月: "《高速铁路隧道施工与维护》", 31 January 2012, 西南交通大学出版社 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012770A (en) * 2020-07-26 2020-12-01 中铁二院工程集团有限责任公司 Underground water advanced treatment structure and construction method for ultra-deep vertical shaft of railway tunnel
CN112066830A (en) * 2020-08-27 2020-12-11 中铁三局集团广东建设工程有限公司 Method for constructing sandy slate tunnel
CN113153307A (en) * 2020-11-26 2021-07-23 西南交通大学 Tunnel construction method suitable for water-rich fractured rock mass
CN112796769A (en) * 2020-12-24 2021-05-14 中铁十八局集团第五工程有限公司 Construction method of water-rich weak surrounding rock stratum tunnel
CN113153309B (en) * 2021-03-09 2022-03-15 中铁工程装备集团有限公司 Tunnel construction method
CN113153309A (en) * 2021-03-09 2021-07-23 中铁工程装备集团有限公司 Tunnel construction method
CN113187512A (en) * 2021-04-27 2021-07-30 中铁建云南交通建设管理有限公司 Grouting and drainage construction method for large-scale water burst and mud outburst of karst tunnel
CN113073983B (en) * 2021-05-19 2022-02-01 中国海洋大学 Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN113073983A (en) * 2021-05-19 2021-07-06 中国海洋大学 Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN113217036A (en) * 2021-06-23 2021-08-06 中交路桥华东工程有限公司 Post-grouting construction method for tunnel structure at water burst section of fault fracture zone
CN113217036B (en) * 2021-06-23 2023-09-12 中交路桥华东工程有限公司 Post grouting construction method for fault fracture tunnel structure with water flushing section
CN113530573A (en) * 2021-08-20 2021-10-22 湖南楚湘建设工程集团有限公司 Long-detection-short-detection-grouting combined water prevention and control method based on water inflow classification
CN113530573B (en) * 2021-08-20 2024-01-30 湖南楚湘建设工程集团有限公司 Long-probe-short-probe-grouting combined water control method based on water inflow classification
CN113565566A (en) * 2021-08-24 2021-10-29 中铁二院工程集团有限责任公司 Construction method for dewatering, depressurizing and stabilizing tunnel face of water-rich composite stratum
CN113833492A (en) * 2021-09-28 2021-12-24 中铁十八局集团有限公司 TBM (tunnel boring machine) tunneling settlement and water burst section treatment method for small-section water conservancy tunnel
CN113833492B (en) * 2021-09-28 2022-12-20 中铁十八局集团有限公司 TBM (Tunnel boring machine) tunneling settlement and water burst section treatment method for small-section water conservancy tunnel
CN115859430A (en) * 2022-12-01 2023-03-28 中铁二十三局集团有限公司 Single-track railway tunnel reinforcement design and construction method suitable for water-rich soft rock
CN115859430B (en) * 2022-12-01 2024-05-07 中铁二十三局集团有限公司 Reinforced design and construction method suitable for water-rich soft rock single-track railway tunnel

Similar Documents

Publication Publication Date Title
CN111206933A (en) Tunnel construction method for traversing karst water-rich section
CN103835651B (en) A kind of single hole directional drilling local slip casting mine shaft rising boring technique
CN111140279B (en) Method for preventing and treating old empty water on thick coal seam under condition of repeated mining caused by small kiln damage to layering
CN105134219B (en) Soft rock strata freezing shaft borehole wall construction technology
CN111271064B (en) Excavation construction method for water-rich stratum tunnel stabilization tunnel face
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN109209293A (en) A kind of crossdrift takes off projecting coal bed comprehensive outburst control construction method
CN111828031B (en) Method for directionally reinforcing soft broken water-rich stratum tunnel face of open TBM tunnel
CN112343647B (en) Method for preventing and controlling self-discharging pressure-eliminating outburst-eliminating rapid tunneling gas of adjacent air tunnel
CN113073983B (en) Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
AU2023226534A1 (en) Pre-grouting treatment method for water hazards in shaft construction
CN113153307A (en) Tunnel construction method suitable for water-rich fractured rock mass
CN110067597A (en) A kind of mine angle of depression negative pressure visits the method for putting old dead zone ponding
CN210049927U (en) Connecting structure of gas extraction pipeline of lower adjacent layer of directional long drill hole with floor penetrating layer
CN113404517A (en) Construction method for mud-bursting and water-flushing of tunnel
CN113217036A (en) Post-grouting construction method for tunnel structure at water burst section of fault fracture zone
CN203475453U (en) Deeply-buried type bearing platform curtain structure of bridge
CN111119951A (en) Construction method for highway tunnel to pass through fault fracture zone water-rich cavity area
CN214464225U (en) Tunnel staggered-crossing rock stratum broken zone grouting structure
CN112780314B (en) Tunnel alternately passes through broken slip casting structure in rock stratum
CN115324123B (en) Method and system for tunnel side shift treatment
CN213016285U (en) Water treatment structure of large water mine water pump room
CN112282784B (en) Construction method for tunnel crossing underpass close to karst cave underground river
CN117248962B (en) Method for treating presbyopia water among small kiln roadway column type residual coal pillars
CN115262661B (en) Soil taking method and system for tunnel floating treatment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200529