CN113530573A - Long-detection-short-detection-grouting combined water prevention and control method based on water inflow classification - Google Patents

Long-detection-short-detection-grouting combined water prevention and control method based on water inflow classification Download PDF

Info

Publication number
CN113530573A
CN113530573A CN202110962719.3A CN202110962719A CN113530573A CN 113530573 A CN113530573 A CN 113530573A CN 202110962719 A CN202110962719 A CN 202110962719A CN 113530573 A CN113530573 A CN 113530573A
Authority
CN
China
Prior art keywords
water
grouting
detection
roadway
water inflow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110962719.3A
Other languages
Chinese (zh)
Other versions
CN113530573B (en
Inventor
谢先斌
马东峰
薛亮
方双勇
聂博伦
赵延林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Chuxiang Construction Engineering Group Co ltd
Hunan University of Science and Technology
Original Assignee
Hunan Chuxiang Construction Engineering Group Co ltd
Hunan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Chuxiang Construction Engineering Group Co ltd, Hunan University of Science and Technology filed Critical Hunan Chuxiang Construction Engineering Group Co ltd
Priority to CN202110962719.3A priority Critical patent/CN113530573B/en
Publication of CN113530573A publication Critical patent/CN113530573A/en
Application granted granted Critical
Publication of CN113530573B publication Critical patent/CN113530573B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Geophysics And Detection Of Objects (AREA)

Abstract

The invention discloses a long detection-short detection-grouting combined water control method based on water inflow classification, which comprises the following steps of: 1) divide into I, II two categories according to the size of the tunnel working face volume of gushing water: 2) judging the class of the water inflow amount of the roadway working surface, and if the class of the water inflow amount of the roadway working surface belongs to the class I, entering the step 3); if the test result belongs to the class II, entering the step 4); 3) adopting long-detection-short-detection water hole grouting and tunneling roadway construction; 4) adopting long-detection water hole grouting and tunneling roadway construction; 5) and (5) grouting reinforcement construction. The invention divides the water inflow amount into two types aiming at the water inflow condition of the working face of the tunnel, covers the construction method adopted by the working face of the tunnel from large to small, breaks through the limitation of a single construction water plugging process, meets the urgent need of a sudden comprehensive water inflow treatment scheme in the field of tunnel excavation construction, and has the advantages of safety, reliability, short construction period, practicability and high efficiency.

Description

Long-detection-short-detection-grouting combined water prevention and control method based on water inflow classification
Technical Field
The invention relates to the technical field of mine construction, in particular to a long-exploration-short-exploration-grouting combined water prevention and control method based on water inflow classification.
Background
Along with the increase of the mining depth and the mining range, the stress state of the original rock and the rock mass in the nearby area is changed due to the mining activity, so that the stability of the surrounding rock is affected, the water inflow of a mine is increased, and the water inflow phenomenon of a roof is caused. The water burst in the mine seriously threatens the safe production of the underground engineering construction of the mine. According to statistics, about 80% of major safety accidents in underground engineering construction are caused by water burst geological disasters and improper disposal, so that very disastrous personal casualties and economic losses are brought, and water burst accidents induced by various unfavorable geological structures and engineering disturbance functions become bottleneck problems restricting the development of underground engineering construction of mines.
Mine tunnel construction flood is the most main factor influencing construction progress and quality, different construction methods are adopted according to different lithology (such as wide distribution of deep gravel pebble aquifers, large thickness, strong water permeability and water richness) and different water inflow quantities, and due to the complexity of hydrogeological conditions and the limitation of a grouting water shutoff construction technology, if a single water exploration mode is adopted for tunnel excavation construction, the requirement of tunnel water prevention and control is difficult to meet, the construction water inflow quantity water shutoff effect is not obvious, the construction period is prolonged, and serious economic loss is caused, so that how to accurately, safely and effectively carry out water exploration water shutoff construction is extremely important. In order to save the construction cost, the construction methods adopted aiming at different water inflow amounts are different, and how to adopt a practical and efficient method for preventing and treating water in the tunneling roadway, which is safe, reliable and short in construction period is a major engineering problem to be solved in mine construction.
Disclosure of Invention
In order to solve the technical problems, the invention provides a long-detection-short-detection-grouting combined water control method based on water inflow classification, which is simple in construction, safe and reliable.
The technical scheme for solving the problems is as follows: a long detection-short detection-grouting combined water control method based on water inflow classification comprises the following steps:
1) divide into I, II two categories according to the size of the tunnel working face volume of gushing water:
the two categories are specifically:
i: the water inflow of the roadway working face is more than or equal to 15m3/h;
II: the water inflow of the roadway working surface is less than 15m3/h;
2) Judging the class of the water inflow amount of the roadway working surface, and if the class of the water inflow amount of the roadway working surface belongs to the class I, entering the step 3); if the test result belongs to the class II, entering the step 4);
3) adopting long-detection-short-detection water hole grouting and tunneling roadway construction;
4) and (5) adopting long-detection water hole grouting and tunneling roadway construction.
The water prevention and control method based on the combination of long detection, short detection and grouting based on water inflow classification comprises the following specific steps of 3):
3-1) chiseling exposed rocks on a working face of a roadway, selecting five parts of an axial front part, a left side wall, a right side wall, a top plate and a bottom plate of the roadway by using a down-the-hole drill according to construction conditions and water burst conditions, respectively drilling water detection holes with the length of 50m, the diameter of 120mm and the horizontal slope angle of 6 degrees, wherein the depth of the long-detected water detection holes is 50m, the allowable excavation depth is 45m, the control range of the left side wall and the right side wall of the roadway are respectively 20m, the top plate and the bottom plate of the roadway are respectively 15m, and a secondary water detection safety barrier is reserved and has the value of 5 m;
3-2) judging the water inflow amount of the working surface, if the water inflow amount exceeds 15m3H, plugging water by adopting a mode of detecting water and grouting at the same time, so that the water inflow of a working surface is lower than 15m3H, if the water inflow after grouting is still more than 15m3When the water inflow is less than 15m, a grouting hole is additionally arranged in front of the working face until the water inflow is less than 15m3/h;
3-3) adopting short probe water to carry out roadway excavation, wherein the control range is 5m in front of the roadway, the left side wall and the right side wall of the roadway are respectively 3.0m, and the top plate and the bottom plate of the roadway are respectively 2.5 m; the length of the short-detection water detection hole is 5m, the allowable tunneling distance is 3m, and if the water inflow is less than 10m3When the water inflow is more than 10m, the roadway driving construction is continued, and if the water inflow is more than 10m3When the water per hour is over, adding grouting holes on the working surface of the roadway, grouting and water plugging are carried out until the water inflow is reduced to 10m3And stopping grouting below the/h, and recovering the tunneling construction of the roadway.
In the water prevention and control method based on the combination of long detection, short detection and grouting for water inflow classification, in the step 3-2), a manner of grouting and water shutoff is to install an orifice pipe; when the orifice pipe is installed, uniformly winding jute, installing a flange at the end part, and welding a steel pipe for connecting a grouting pipe, a high-pressure stop valve and a pressure gauge at a position 300mm away from the end part; and sealing the orifice pipe by using double slurries to perform grouting operation and water plugging.
In the above water prevention and control method based on combination of long detection, short detection and grouting of water inflow classification, in the step 3-3), the grouting and water plugging manner is as follows: and (5) installing a drill bit of the drilling machine to punch holes to 5m, installing a hole pipe, and performing grouting and water plugging.
According to the method for preventing and treating water in the tunneling roadway based on the combination of the long detection, the short detection and the grouting based on the water inflow classification, the step of grouting the tunneling roadway through the long detection water hole in the step 4) is constructed in the same way as the steps 3-1) and 3-2), and then grouting and water plugging are carried out on the long detection water hole.
In the water prevention and control method based on the combination of long detection, short detection and grouting based on water inflow classification, in the step 3) and the step 4), 425# common portland cement is used as a grouting material, the concentration of water glass is 40Be, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1: 0.5-0.8; the initial concentration of the cement paste water-cement ratio is 2: 1.
The long detection-short detection-grouting combined water prevention and control method based on water inflow classification further comprises the following steps of 5):
5-1) selecting grouting equipment, namely arranging a grouting station 5m away from a working surface, and installing a 2TGZ60/210 type high-pressure grouting pump in the grouting station;
5-2) grouting mode and grouting hole arrangement: grouting and water plugging are carried out by adopting a roadway sectional advancing type grouting mode, the length of a grouting section is 50m, virtual slag on the face of a tunnel is cleaned, guide holes and grouting holes are arranged, water detecting holes are arranged according to the crack grade and the section size, and the hole diameter is
Figure BDA0003222839470000042
The hole depth is 5 m;
5-3) selecting and arranging the number of grouting holes: 6 fan-shaped radial grouting holes are distributed at the outer edge of the roadway, and the hole spacing and the row spacing are 1.48-2.0 m;
5-4) determining the grouting material: 425# ordinary portland cement is used as a grouting material, the concentration of water glass is 40Be, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1: 0.5-0.8; the initial concentration of the cement paste water-cement ratio is 2: 1;
5-5) determining the grouting pressure: initial grouting pressure Pa=Po+(0.3~0.5)MPa,PoIs hydrostatic pressure, normal pressure Pb=Po0.5 to 0.8 MPa, final pressure Pc=2PoMPa;
5-6) slurry injection amount: roughly calculating the slurry injection amount V according to the diffusion radius and the rock fracture rate, wherein the calculation formula is as follows:
Figure BDA0003222839470000041
a-slurry consumption coefficient; r is the slurry diffusion radius; h-is the grouting section height; eta-rock fracture rate; beta-slurry fill factor; m is the calculus rate;
5-7) finishing grouting: and (4) the grouting pressure reaches the designed final pressure value, the injection amount is less than 50-60L/min, the stability is carried out for more than 20 minutes, and the grouting is finished.
The invention has the beneficial effects that: the invention divides the water inflow amount into two types aiming at the water inflow condition of the working face of the tunnel, covers the construction method adopted by the working face of the tunnel from large to small, breaks through the limitation of a single construction water plugging process, meets the urgent need of a sudden comprehensive water inflow treatment scheme in the field of tunnel excavation construction, and has the advantages of safety, reliability, short construction period, practicability and high efficiency.
Drawings
FIG. 1 is a flow chart of the present invention.
Fig. 2 is a schematic view of an upward section of a ramp of a roadway.
Fig. 3 is a sectional view of water detecting and distributing holes on an ascending section of a roadway slope ramp.
Fig. 4 is a schematic diagram of water detecting and hole distributing of an ascending section of a roadway slope ramp.
Fig. 5 is a schematic view of radial grouting of the fan-shaped holes.
In the figure: 1. the drilling method comprises the following steps of 1# drilling, 2# drilling, 3# drilling, 4# drilling, 5# drilling, 6# drilling, 7# drilling, 8 # drilling, axial front of a roadway, 9 # drilling bottom plate, 10 # drilling left side wall, 11 # drilling right side wall, 12 # drilling top plate, 13 # grouting hole, 1# grouting hole, 14 # grouting hole, 2# grouting hole, 15 # grouting hole, 3# grouting hole, 16 # grouting hole, 4# grouting hole, 17 # grouting hole, 5# grouting hole, 18 # grouting hole, 6# grouting hole.
Detailed Description
The invention is further described below with reference to the accompanying drawings and examples.
Taking roadway construction with the width of 4000mm and the height of 4270mm in a certain coal mine in Hebei as an example, as shown in figure 1, a long detection-short detection-grouting combined water prevention and control method based on water inflow classification comprises the following steps:
1) divide into I, II two categories according to the size of the tunnel working face volume of gushing water:
the two categories are specifically:
i: the water inflow of the roadway working face is more than or equal to 15m3/h;
II: the water inflow of the roadway working surface is less than 15m3/h。
2) Judging the class of the water inflow amount of the roadway working surface, and if the class of the water inflow amount of the roadway working surface belongs to the class I, entering the step 3); and if the test result belongs to the class II, entering the step 4).
3) And (3) adopting long-detection-short-detection water hole grouting and tunneling roadway construction, as shown in fig. 2, fig. 3 and fig. 4.
The step 3) comprises the following specific steps:
3-1) chiseling exposed rocks on a roadway working surface, selecting five parts of a roadway axial front 8, a roadway left side 10, a roadway right side 11, a roadway top plate 12 and a roadway bottom plate 9 by using a down-the-hole drill according to construction conditions and water burst conditions, respectively drilling water detection holes 1, 2, 3, 4, 5, 6 and 7 with the length of 50m, the diameter of 120mm and the horizontal slope angle of 6 degrees, wherein the number of the water detection holes is 7, the depth of the water detection holes for long detection is 50m, the allowable tunneling depth is 45m, the control range of the roadway left side and the roadway right side are respectively 20m, the depth of the roadway top plate and the roadway bottom plate are respectively 15m, and the value of a water detection safety barrier reserved for a time is 5 m.
3-2) judging the water inflow amount of the working surface, if the water inflow amount exceeds 15m3H, plugging water by adopting a mode of detecting water and grouting at the same time, so that the water inflow of a working surface is lower than 15m3H, if the water inflow after grouting is still more than 15m3When the water inflow is less than 15m, a grouting hole is additionally arranged in front of the working face until the water inflow is less than 15m3/h。
In the step 3-2), the manner of grouting and water plugging is to install an orifice pipe; when the orifice pipe is installed, uniformly winding jute, installing a flange at the end part, and welding a steel pipe for connecting a grouting pipe, a high-pressure stop valve and a pressure gauge at a position 300mm away from the end part; and sealing the orifice pipe by using double slurries to perform grouting operation and water plugging.
3-3) adopting short-probe water to carry out roadway excavation, wherein the control range is 5m in front of the roadway, the left side 10 and the right side 11 of the roadway are respectively 3.0m, and the top plate 12 and the bottom plate 9 of the roadway are respectively 2.5 m; the length of the short-detection water detection hole is 5m, the allowable tunneling distance is 3m, and if the water inflow is less than 10m3When the water inflow is more than 10m, the roadway driving construction is continued, and if the water inflow is more than 10m3When the water per hour is over, adding grouting holes on the working surface of the roadway, grouting and water plugging are carried out until the water inflow is reduced to 10m3And stopping grouting below the/h, and recovering the tunneling construction of the roadway.
In the step 3-3), the grouting water plugging mode is as follows: and (5) installing a drill bit of the drilling machine to punch holes to 5m, installing a hole pipe, and performing grouting and water plugging.
4) And (5) adopting long-detection water hole grouting and tunneling roadway construction.
And 4) carrying out construction in the same steps as 3-1) and 3-2) in the middle and long water detection hole grouting tunneling construction step, and then carrying out grouting and water plugging on the long water detection hole.
5) And (5) grouting reinforcement construction.
5-1) selecting grouting equipment, namely arranging a grouting station 5m away from a working surface, and installing a 2TGZ60/210 type high-pressure grouting pump in the grouting station;
5-2) grouting mode and grouting hole arrangement: grouting and water plugging are carried out by adopting a roadway sectional advancing type grouting mode, the length of a grouting section is 50m, virtual slag on the face of a tunnel is cleaned, guide holes and grouting holes are arranged, water detecting holes are arranged according to the crack grade and the section size, and the hole diameter is
Figure BDA0003222839470000072
(by using
Figure BDA0003222839470000073
Drilling by a drill bit, fixing a 1-inch pipe), and the hole depth is 5 m;
5-3) selecting and arranging the number of grouting holes: 6 fan-shaped radial grouting holes 13, 14, 15, 16, 17 and 18 are distributed at the outer edge of the roadway, and the hole spacing and the row spacing are 1.48-2.0 m;
5-4) determining the grouting material: 425# ordinary portland cement is used as a grouting material, the concentration of water glass is 40Be, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1: 0.5-0.8; the initial concentration of the cement paste water-cement ratio is 2: 1;
5-5) determining the grouting pressure: initial grouting pressure Pa=Po+(0.3~0.5)MPa,PoIs hydrostatic pressure, normal pressure Pb=Po0.5 to 0.8 MPa, final pressure Pc=2PoMPa;
5-6) slurry injection amount: roughly calculating the slurry injection amount V according to the diffusion radius and the rock fracture rate, wherein the calculation formula is as follows:
Figure BDA0003222839470000071
a-slurry consumption coefficient, 1.5; r is the diffusion radius of the slurry, and 2m is taken; h-is the grouting section height; eta-rock fracture rate; beta-slurry filling coefficient, taking 0.85; m, calculus rate, taking 0.85;
5-7) finishing grouting: and (4) the grouting pressure reaches the designed final pressure value, the injection amount is less than 50-60L/min, the stability is carried out for more than 20 minutes, and the grouting is finished.
The invention divides the water inflow amount into two types aiming at the water inflow condition of the top plate of the tunnel, covers the construction method adopted by the working surface of the tunnel from large to small water inflow amount, breaks through the limitation of single construction water plugging process, meets the urgent need of a sudden comprehensive water inflow treatment scheme in the field of tunnel excavation construction, and has the advantages of safety, reliability, short construction period, practicability and high efficiency.

Claims (7)

1. A long detection-short detection-grouting combined water control method based on water inflow classification is characterized by comprising the following steps:
1) divide into I, II two categories according to the size of the tunnel working face volume of gushing water:
the two categories are specifically:
i: the water inflow of the roadway working face is more than or equal to 15m3/h;
II: the water inflow of the roadway working surface is less than 15m3/h;
2) Judging the class of the water inflow amount of the roadway working surface, and if the class of the water inflow amount of the roadway working surface belongs to the class I, entering the step 3); if the test result belongs to the class II, entering the step 4);
3) adopting long-detection-short-detection water hole grouting and tunneling roadway construction;
4) and (5) adopting long-detection water hole grouting and tunneling roadway construction.
2. The water control method based on the combination of long detection, short detection and grouting of water inflow classification as claimed in claim 1, wherein the step 3) comprises the following specific steps:
3-1) chiseling exposed rocks on a working face of a roadway, selecting five parts of an axial front part, a left side wall, a right side wall, a top plate and a bottom plate of the roadway by using a down-the-hole drill according to construction conditions and water burst conditions, respectively drilling water detection holes with the length of 50m, the diameter of 120mm and the horizontal slope angle of 6 degrees, wherein the depth of the long-detected water detection holes is 50m, the allowable excavation depth is 45m, the control range of the left side wall and the right side wall of the roadway are respectively 20m, the top plate and the bottom plate of the roadway are respectively 15m, and a secondary water detection safety barrier is reserved and has the value of 5 m;
3-2) judging the water inflow amount of the working surface, if the water inflow amount exceeds 15m3H, plugging water by adopting a mode of detecting water and grouting at the same time, so that the water inflow of a working surface is lower than 15m3H, if the water inflow after grouting is still more than 15m3When the water inflow is less than 15m, a grouting hole is additionally arranged in front of the working face until the water inflow is less than 15m3/h;
3-3) adopting short probe water to carry out roadway excavation, wherein the control range is 5m in front of the roadway, the left side wall and the right side wall of the roadway are respectively 3.0m, and the top plate and the bottom plate of the roadway are respectively 2.5 m; the length of the short-detection water detection hole is 5m, the allowable tunneling distance is 3m, and if the water inflow is less than 10m3When the water inflow is more than 10m, the roadway driving construction is continued, and if the water inflow is more than 10m3When the water per hour is over, adding grouting holes on the working surface of the roadway, grouting and water plugging are carried out until the water inflow is reduced to 10m3And stopping grouting below the/h, and recovering the tunneling construction of the roadway.
3. The water control method based on the combination of long detection, short detection and grouting of water inflow classification as claimed in claim 2, wherein in the step 3-2), grouting and water plugging are performed by installing an orifice pipe; when the orifice pipe is installed, uniformly winding jute, installing a flange at the end part, and welding a steel pipe for connecting a grouting pipe, a high-pressure stop valve and a pressure gauge at a position 300mm away from the end part; and sealing the orifice pipe by using double slurries to perform grouting operation and water plugging.
4. The water control method based on the combination of long detection, short detection and grouting of water inflow classification as claimed in claim 2, wherein in the step 3-3), the grouting and water plugging manner is as follows: and (5) installing a drill bit of the drilling machine to punch holes to 5m, installing a hole pipe, and performing grouting and water plugging.
5. The water control method based on the combination of the long detection, the short detection and the grouting of the water inflow classification as claimed in claim 2, wherein the step of the step 4) of grouting and tunneling the long detection water hole is constructed in the same way as the steps 3-1) and 3-2), and then grouting and water plugging are carried out on the long detection water hole.
6. The method for preventing and treating water by combining long detection, short detection and grouting based on water inflow classification as claimed in claim 1, wherein in the step 3) and the step 4), 425# Portland cement is used as grouting material, the concentration of water glass is 40Be, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1: 0.5-0.8; the initial concentration of the cement paste water-cement ratio is 2: 1.
7. The water control method based on the combination of long detection, short detection and grouting of water inflow classification as claimed in claim 2, characterized by further comprising the step 5 of grouting reinforcement construction:
5-1) selecting grouting equipment, namely arranging a grouting station 5m away from a working surface, and installing a 2TGZ60/210 type high-pressure grouting pump in the grouting station;
5-2) grouting mode and grouting hole arrangement: grouting and water plugging are carried out by adopting a roadway sectional advancing type grouting mode, the length of a grouting section is 50m, virtual slag on the face of a tunnel is cleaned, guide holes and grouting holes are arranged, water detecting holes are arranged according to the crack grade and the section size, and the hole diameter is
Figure FDA0003222839460000032
The hole depth is 5 m;
5-3) selecting and arranging the number of grouting holes: 6 fan-shaped radial grouting holes are distributed at the outer edge of the roadway, and the hole spacing and the row spacing are 1.48-2.0 m;
5-4) determining the grouting material: 425# ordinary portland cement is used as a grouting material, the concentration of water glass is 40Be, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1: 0.5-0.8; the initial concentration of the cement paste water-cement ratio is 2: 1;
5-5) determining the grouting pressure: initial grouting pressure Pa=Po+(0.3~0.5)MPa,PoHydrostatic pressure, normal pressureForce Pb=Po0.5 to 0.8 MPa, final pressure Pc=2PoMPa;
5-6) slurry injection amount: roughly calculating the slurry injection amount V according to the diffusion radius and the rock fracture rate, wherein the calculation formula is as follows:
Figure FDA0003222839460000031
a-slurry consumption coefficient; r-slurry diffusion radius; h-is the grouting section height; eta-rock fracture rate; beta-slurry fill factor; m-calculus rate;
5-7) finishing grouting: and (4) the grouting pressure reaches the designed final pressure value, the injection amount is less than 50-60L/min, the stability is carried out for more than 20 minutes, and the grouting is finished.
CN202110962719.3A 2021-08-20 2021-08-20 Long-probe-short-probe-grouting combined water control method based on water inflow classification Active CN113530573B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110962719.3A CN113530573B (en) 2021-08-20 2021-08-20 Long-probe-short-probe-grouting combined water control method based on water inflow classification

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110962719.3A CN113530573B (en) 2021-08-20 2021-08-20 Long-probe-short-probe-grouting combined water control method based on water inflow classification

Publications (2)

Publication Number Publication Date
CN113530573A true CN113530573A (en) 2021-10-22
CN113530573B CN113530573B (en) 2024-01-30

Family

ID=78091323

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110962719.3A Active CN113530573B (en) 2021-08-20 2021-08-20 Long-probe-short-probe-grouting combined water control method based on water inflow classification

Country Status (1)

Country Link
CN (1) CN113530573B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1125333A1 (en) * 1982-07-05 1984-11-23 Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Горной Геомеханики И Маркшейдерского Дела Method of decreasing water inflow in mine workings in mining coal seams
CN104481560A (en) * 2014-12-09 2015-04-01 中煤第一建设有限公司 Roadway roof aquifer treatment method
CN106567714A (en) * 2016-11-09 2017-04-19 河北钢铁集团矿业有限公司 Grouting material for underground mine roadway and grouting water control method
CN108915689A (en) * 2018-07-09 2018-11-30 中南大学 A kind of water rich strata shaft excavation spy shutoff method
CN111206933A (en) * 2020-01-20 2020-05-29 西南交通大学 Tunnel construction method for traversing karst water-rich section
CN111677550A (en) * 2020-06-18 2020-09-18 陕西延长石油巴拉素煤业有限公司 Water prevention and control protection method for safe tunneling of rock roadway through water-rich coal seam section
CN112174616A (en) * 2020-08-26 2021-01-05 煤科集团沈阳研究院有限公司 Underground consolidation material and method for loose coal rock mass in small kiln damage area
CN113153367A (en) * 2021-04-13 2021-07-23 西南交通大学 Quicksand stratum reinforcing method with different water inflow amounts

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1125333A1 (en) * 1982-07-05 1984-11-23 Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Горной Геомеханики И Маркшейдерского Дела Method of decreasing water inflow in mine workings in mining coal seams
CN104481560A (en) * 2014-12-09 2015-04-01 中煤第一建设有限公司 Roadway roof aquifer treatment method
CN106567714A (en) * 2016-11-09 2017-04-19 河北钢铁集团矿业有限公司 Grouting material for underground mine roadway and grouting water control method
CN108915689A (en) * 2018-07-09 2018-11-30 中南大学 A kind of water rich strata shaft excavation spy shutoff method
CN111206933A (en) * 2020-01-20 2020-05-29 西南交通大学 Tunnel construction method for traversing karst water-rich section
CN111677550A (en) * 2020-06-18 2020-09-18 陕西延长石油巴拉素煤业有限公司 Water prevention and control protection method for safe tunneling of rock roadway through water-rich coal seam section
CN112174616A (en) * 2020-08-26 2021-01-05 煤科集团沈阳研究院有限公司 Underground consolidation material and method for loose coal rock mass in small kiln damage area
CN113153367A (en) * 2021-04-13 2021-07-23 西南交通大学 Quicksand stratum reinforcing method with different water inflow amounts

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周华玉;: "综合防治水方案在立井施工中的应用", 煤炭科技, no. 01, pages 58 *
程鹏军;: "掘进巷道探放水施工技术研究", 自动化应用, no. 06 *

Also Published As

Publication number Publication date
CN113530573B (en) 2024-01-30

Similar Documents

Publication Publication Date Title
CN102797465B (en) Underground ultra-thin virtual protection layer hydraulic coal mining method
CN102705005B (en) Technology for plugging water bursting in mine by directional diversion grouting
CN111042831A (en) Grouting reinforcement transformation method for coal seam floor limestone confined aquifer
CN109209293A (en) A kind of crossdrift takes off projecting coal bed comprehensive outburst control construction method
CN110863833B (en) Tunneling parameter control process of tunnel shield tunneling starting end boulder area shield tunneling machine
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN111764863B (en) Method for blocking water gushing of high-pressure drilling hole in underground fault fracture zone
CN111075478A (en) Pre-grouting reinforcement process for ground construction of broken belt of excavation working face structure
CN107816365A (en) A kind of quick-fried pumping integration anti-burst method of coal seam drilling
CN114837663A (en) Construction method for improving recovery rate of fault waterproof coal pillar through ground pre-grouting
CN108374662A (en) The conduction method of artesian water tomography is crossed in a kind of tunnel
CN115263304A (en) Active intelligent regulation and control method for water level of mineral-bearing aquifer in coal-uranium coordinated mining area
CN113217043A (en) Efficient and rapid plugging method and construction method for water source with water inrush fault water guide zone
CN106968664A (en) A kind of floor undulation destruction band deep drilling water filling detection method
CN106968706A (en) A kind of method that hydraulic slotted liner technique eliminates coal and gas prominent in heading driving
CN113530573B (en) Long-probe-short-probe-grouting combined water control method based on water inflow classification
CN113217044B (en) Upward and oblique scattering type grouting water plugging method for deep large fault tunnel
CN109268060A (en) One kind is based on the quick-fried note integrated regional anti-burst method of strong and weak strong structure
CN210105807U (en) Outburst prevention and blowout prevention combined water control device for mine advanced water exploration orifice
CN111894672B (en) Method for advanced treatment of roof separation water damage of stope by adopting ground drainage drilling
CN115467639A (en) Water interception and emission reduction method for directionally exploring and blocking ground
Kaskiw et al. Backfilling at IMC Canada K-2 potash mine
CN115354987B (en) Mine water inrush treatment method
CN220621952U (en) Mining overburden composite curtain for improving overburden separation layer grouting effect
CN114837608B (en) Method for reconstructing mining overburden rock water barrier by multi-section graded grouting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant