CN113530573B - Long-probe-short-probe-grouting combined water control method based on water inflow classification - Google Patents

Long-probe-short-probe-grouting combined water control method based on water inflow classification Download PDF

Info

Publication number
CN113530573B
CN113530573B CN202110962719.3A CN202110962719A CN113530573B CN 113530573 B CN113530573 B CN 113530573B CN 202110962719 A CN202110962719 A CN 202110962719A CN 113530573 B CN113530573 B CN 113530573B
Authority
CN
China
Prior art keywords
grouting
water
roadway
water inflow
detection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110962719.3A
Other languages
Chinese (zh)
Other versions
CN113530573A (en
Inventor
谢先斌
马东峰
薛亮
方双勇
聂博伦
赵延林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Chuxiang Construction Engineering Group Co ltd
Hunan University of Science and Technology
Original Assignee
Hunan Chuxiang Construction Engineering Group Co ltd
Hunan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Chuxiang Construction Engineering Group Co ltd, Hunan University of Science and Technology filed Critical Hunan Chuxiang Construction Engineering Group Co ltd
Priority to CN202110962719.3A priority Critical patent/CN113530573B/en
Publication of CN113530573A publication Critical patent/CN113530573A/en
Application granted granted Critical
Publication of CN113530573B publication Critical patent/CN113530573B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Geophysics And Detection Of Objects (AREA)

Abstract

The invention discloses a water control method based on combination of long detection, short detection and grouting of water inflow classification, which comprises the following steps: 1) The water inflow is divided into two categories of I and II according to the water inflow of the roadway working surface: 2) Judging the class of the water inflow of the roadway working surface, and if the water inflow belongs to class I, entering step 3); if the two types belong to the II type, the step 4) is entered; 3) Grouting and tunneling roadway construction by adopting long-exploring-short-exploring water holes; 4) Grouting and tunneling the tunnel construction by adopting a long exploring water hole; 5) Grouting and reinforcing construction. The invention divides the water inflow amount into two types aiming at the water inflow condition of the roadway working surface, covers the construction method adopted by the water inflow amount of the roadway working surface from large to small, breaks through the limitation of a single construction water shutoff process, meets the urgent need of a sudden comprehensive water inflow treatment scheme in the field of roadway tunneling construction, and has the advantages of safety, reliability, short construction period, practicability and high efficiency.

Description

Long-probe-short-probe-grouting combined water control method based on water inflow classification
Technical Field
The invention relates to the technical field of mine construction, in particular to a water control method based on combination of long detection, short detection and grouting of water inflow classification.
Background
Along with the increase of the mining depth and the mining range, the stress state of the rock mass of the original rock and the nearby area is changed due to the mining activity, so that the stability of surrounding rock is influenced, the water inflow amount of a mine is increased, and the water inflow phenomenon of a roof is caused. Mine water burst seriously threatens the safety production of mine underground engineering construction. According to statistics, about 80% of major safety accidents in underground engineering construction are caused by water gushing geological disasters and improper disposal, extremely disastrous personal casualties and economic losses are brought, and water gushing accidents induced by various bad geological structures and engineering disturbance actions become bottleneck problems for restricting the development of underground engineering construction of mines.
The mine tunnel construction water is the most important factor affecting the construction progress and quality, different construction methods are adopted according to different lithology (such as wide distribution, large thickness, extremely strong water permeability and water enrichment of deep gravel pebble aquifers) and different water inflow, and due to the complexity of hydrogeological conditions and the limitations of grouting water shutoff construction technology, if tunnel tunneling construction is carried out by adopting a single water exploration mode for water inflow, the water inflow is difficult to meet the requirement of tunnel prevention and control, the water inflow water shutoff effect of construction is not obvious, the construction period is prolonged, and serious economic loss is caused, so that the water exploration water shutoff construction is carried out correctly, safely and effectively. In order to save construction cost, different construction methods are adopted according to different water inflow amounts, so that the method for preventing and controlling water in a tunneling roadway is safe, reliable, short in construction period, practical and efficient, and is a major engineering problem to be solved in mine construction.
Disclosure of Invention
In order to solve the technical problems, the invention provides a long-probe-short-probe-grouting combined water control method which is simple in construction, safe and reliable and is based on water inflow classification.
The technical scheme for solving the problems is as follows: a long-detection-short-detection-grouting combined water control method based on water inflow classification comprises the following steps:
1) The water inflow is divided into two categories of I and II according to the water inflow of the roadway working surface:
the two categories are specifically:
i: the water inflow of the roadway working surface is more than or equal to 15m 3 /h;
II: the water inflow of the roadway working surface is less than 15m 3 /h;
2) Judging the class of the water inflow of the roadway working surface, and if the water inflow belongs to class I, entering step 3); if the two types belong to the II type, the step 4) is entered;
3) Grouting and tunneling roadway construction by adopting long-exploring-short-exploring water holes;
4) And (5) adopting a long-detection water hole grouting tunneling roadway for construction.
The water control method based on the combination of long detection, short detection and grouting of water inflow classification comprises the following specific steps:
3-1) firstly chiseling bare rock on a working surface of a roadway, selecting five parts of the axial front part of the roadway, the left side wall of the roadway, the right side wall of the roadway, the top plate of the roadway and the bottom plate of the roadway by using a down-the-hole drill according to construction conditions and water gushing conditions, respectively drilling water detection holes with the length of 50m, the diameter of 120mm and the horizontal slope angle of 6 degrees, enabling the tunneling depth to be 45m, enabling the left side wall of the roadway and the right side wall of the roadway to be 20m respectively, enabling the top plate of the roadway and the bottom plate of the roadway to be 15m respectively, and reserving secondary water detection safety barriers to take values of 5m;
3-2) judging the water inflow of the working surface, if the water inflow exceeds 15m 3 And (h) plugging water by adopting a mode of water detection and grouting at the same time, so that the water inflow of the working surface is lower than 15m 3 And/h, if the water inflow after grouting is still more than 15m 3 In the time of/h, a grouting hole is additionally arranged in front of the working face until the water inflow is lower than 15m 3 /h;
3-3) tunneling by adopting short probe water, wherein the control range is 5m in front of the tunnel, the left side wall and the right side wall of the tunnel are respectively 3.0m, and the top plate and the bottom plate of the tunnel are respectively 2.5m; the length of the short water detection hole is 5m, the allowed tunneling distance is 3m, if the water inflow is less than 10m 3 And (3) continuously tunneling the tunnel during the period of/h, if the water inflow is more than 10m 3 In the process of/h, grouting holes are added on the working surface of the roadway, grouting and water shutoff are carried out until the water inflow is reduced to 10m 3 And (3) stopping grouting below/h, and recovering the tunneling construction.
In the water control method based on the combination of long detection, short detection and grouting of water inflow classification, in the step 3-2), grouting and water shutoff are carried out by installing orifice pipes; when the orifice pipe is installed, jute is uniformly wound, a flange is installed at the end part, and a steel pipe for connecting a grouting pipe, a high-pressure cut-off valve and a pressure gauge is welded at the position 300mm away from the end part; and (3) sealing the orifice pipe by using double slurry, and plugging water in grouting operation.
The water control method based on the combination of long detection, short detection and grouting of water inflow classification comprises the following steps of: and (5) installing a drill bit of a drilling machine, punching to 5m, installing an orifice pipe, and grouting and water shutoff.
The method for preventing and controlling water in the tunneling roadway based on the combination of long detection, short detection and grouting of water inflow classification comprises the steps of 3-1) and 3-2) of construction of grouting tunneling roadway of long detection water holes in the step 4), and grouting and water shutoff of the long detection water holes.
In the method for controlling water by combining long detection and short detection and grouting based on water inflow classification, in the step 3) and the step 4), the grouting material of the grouting uses 425# Portland cement, the concentration of water glass is 40Be, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1:0.5-0.8; cement slurry water cement ratio initial concentration is 2:1.
The water control method based on the combination of long detection, short detection and grouting of water inflow classification further comprises a grouting reinforcement construction step 5):
5-1) grouting equipment selection, wherein a grouting station is arranged at a distance of 5m from a working surface, and a 2TGZ60/210 type high-pressure grouting pump is arranged in the grouting station;
5-2) grouting mode and grouting hole arrangement: grouting and water plugging are carried out by adopting a tunnel segmentation forward grouting mode, the grouting segmentation length is 50m, the virtual slag of the tunnel face is cleaned, guide grouting holes are arranged, and water detection holes and pore diameters are arranged according to the fracture grade and the section sizeThe hole depth is 5m;
5-3) selecting and arranging the number of grouting holes: 6 fan-shaped radial grouting holes are distributed at the outer edge of the roadway, and the hole spacing and the row spacing are 1.48-2.0 m;
5-4) determining grouting material: the grouting material uses 425# ordinary Portland cement, the concentration of water glass is 40Be, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1:0.5-0.8; cement slurry water cement ratio initial concentration is 2:1;
5-5) determining grouting pressure: initial grouting pressure P a =P o +(0.3~0.5)MPa,P o Is hydrostatic pressure, normal pressure P b =P o + (0.5-0.8) MPa, final pressure P c =2P o MPa;
5-6) slurry injection amount: the slurry injection quantity V is roughly calculated according to the diffusion radius and the rock fracture rate, and the calculation formula is as follows:
a-slurry consumption coefficient; r—slurry diffusion radius; h-is the height of the grouting section; η—rock fracture rate; beta-slurry filling factor; m-calculus rate;
5-7) grouting end: the grouting pressure reaches the design final pressure value, the injection quantity is less than 50-60L/min, the grouting is stable for more than 20 minutes, and the grouting is finished.
The invention has the beneficial effects that: the invention divides the water inflow amount into two types aiming at the water inflow condition of the roadway working surface, covers the construction method adopted by the water inflow amount of the roadway working surface from large to small, breaks through the limitation of a single construction water shutoff process, meets the urgent need of a sudden comprehensive water inflow treatment scheme in the field of roadway tunneling construction, and has the advantages of safety, reliability, short construction period, practicability and high efficiency.
Drawings
FIG. 1 is a flow chart of the present invention.
Fig. 2 is a schematic view of an upward section of a roadway ramp.
FIG. 3 is a cross-sectional view of a water detection and hole distribution on an ascending section of a tunnel ramp.
FIG. 4 is a schematic diagram of a water detection and hole distribution of an ascending section of a tunnel ramp.
Fig. 5 is a schematic view of radial grouting of a sector hole.
In the figure: 1. 1# drilling, 2# drilling, 3# drilling, 4# drilling, 5# drilling, 6# drilling, 7# drilling, 8 # drilling, axial forward of roadway, 9 # drilling, roadway floor, 10 # drilling, roadway left side wall, 11 # drilling, roadway right side wall, 12 # drilling, roadway roof, 13 # grouting holes, 1# grouting holes, 14 # grouting holes, 2# grouting holes, 15 # grouting holes, 3# grouting holes, 16 # grouting holes, 4# grouting holes, 17 # grouting holes, 5# grouting holes, 18 # grouting holes and 6# grouting holes.
Detailed Description
The invention is further described below with reference to the drawings and examples.
By taking the construction of a roadway with the width of 4000mm and the height of 4270mm in Hebei coal mine as an example, as shown in fig. 1, the water control method based on the combination of long detection, short detection and grouting of water inflow classification comprises the following steps:
1) The water inflow is divided into two categories of I and II according to the water inflow of the roadway working surface:
the two categories are specifically:
i: the water inflow of the roadway working surface is more than or equal to 15m 3 /h;
II: the water inflow of the roadway working surface is less than 15m 3 /h。
2) Judging the class of the water inflow of the roadway working surface, and if the water inflow belongs to class I, entering step 3); if the data belong to the II class, the step 4) is entered.
3) And adopting long-short detection water hole grouting tunneling tunnel construction, as shown in figures 2, 3 and 4.
The specific steps of the step 3) are as follows:
3-1) firstly removing bare rocks on a working surface of a roadway, selecting five parts of the roadway, namely an axial front part 8, a roadway left side part 10, a roadway right side part 11, a roadway top plate 12 and a roadway bottom plate 9 by using a down-the-hole drill according to construction conditions and water gushing conditions, respectively drilling water detection holes 1, 2, 3, 4, 5, 6 and 7 with the length of 50m, the diameter of 120mm and the horizontal slope angle of 6 degrees, wherein the number of the water detection holes for long detection is 7, the depth of the water detection holes for long detection is 50m, the allowable tunneling depth is 45m, the control range of the roadway left side part and the roadway right side part are 20m, the roadway top plate and the roadway bottom plate are 15m, and the reserved water detection safety barrier is 5m.
3-2) judging the water inflow of the working surface, if the water inflow exceeds 15m 3 And (h) plugging water by adopting a mode of water detection and grouting at the same time, so that the water inflow of the working surface is lower than 15m 3 And/h, if the water inflow after grouting is still more than 15m 3 In the time of/h, a grouting hole is additionally arranged in front of the working face until the water inflow is lower than 15m 3 /h。
In the step 3-2), the grouting and water shutoff mode is to install orifice pipes; when the orifice pipe is installed, jute is uniformly wound, a flange is installed at the end part, and a steel pipe for connecting a grouting pipe, a high-pressure cut-off valve and a pressure gauge is welded at the position 300mm away from the end part; and (3) sealing the orifice pipe by using double slurry, and plugging water in grouting operation.
3-3) tunneling by adopting short probe water, wherein the control range is 5m in front of the tunnel, the left side wall 10 and the right side wall 11 of the tunnel are 3.0m respectively, and the top plate 12 and the bottom plate 9 of the tunnel are 2.5m respectively; the length of the short water detection hole is 5m, the allowed tunneling distance is 3m, if the water inflow is less than 10m 3 And (3) continuously tunneling the tunnel during the period of/h, if the water inflow is more than 10m 3 In the process of/h, grouting holes are added on the working surface of the roadway, grouting and water shutoff are carried out until the water inflow is reduced to 10m 3 And (3) stopping grouting below/h, and recovering the tunneling construction.
In the step 3-3), the grouting and water shutoff modes are as follows: and (5) installing a drill bit of a drilling machine, punching to 5m, installing an orifice pipe, and grouting and water shutoff.
4) And (5) adopting a long-detection water hole grouting tunneling roadway for construction.
And 4) the construction steps of grouting and tunneling the tunnel through the long detection water hole in the step 4) are the same as those in the steps 3-1) and 3-2), and grouting and water plugging are carried out on the long detection water hole.
5) Grouting and reinforcing construction.
5-1) grouting equipment selection, wherein a grouting station is arranged at a distance of 5m from a working surface, and a 2TGZ60/210 type high-pressure grouting pump is arranged in the grouting station;
5-2) grouting mode and grouting hole arrangement: grouting and water plugging are carried out by adopting a tunnel segmentation forward grouting mode, the grouting segmentation length is 50m, the virtual slag of the tunnel face is cleaned, guide grouting holes are arranged, and water detection holes and pore diameters are arranged according to the fracture grade and the section size(use->Drilling by a drill bit, fixing a 1-inch pipe), and ensuring the depth of the hole to be 5m;
5-3) selecting and arranging the number of grouting holes: 6 fan-shaped radial grouting holes are respectively 13, 14, 15, 16, 17 and 18 at the outer edge of the roadway, and the hole spacing and the row spacing are 1.48-2.0 m;
5-4) determining grouting material: the grouting material uses 425# ordinary Portland cement, the concentration of water glass is 40Be, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1:0.5-0.8; cement slurry water cement ratio initial concentration is 2:1;
5-5) determining grouting pressure: initial grouting pressure P a =P o +(0.3~0.5)MPa,P o Is hydrostatic pressure, normal pressure P b =P o + (0.5-0.8) MPa, final pressure P c =2P o MPa;
5-6) slurry injection amount: the slurry injection quantity V is roughly calculated according to the diffusion radius and the rock fracture rate, and the calculation formula is as follows:
taking 1.5 of the A-slurry consumption coefficient; r is the slurry diffusion radius, and 2m is taken; h-is the height of the grouting section; η—rock fracture rate; beta-slurry filling coefficient, taking 0.85; m-calculus rate, 0.85;
5-7) grouting end: the grouting pressure reaches the design final pressure value, the injection quantity is less than 50-60L/min, the grouting is stable for more than 20 minutes, and the grouting is finished.
The method is aimed at the water inflow condition of the tunnel roof, divides the water inflow amount into two types, covers the construction method adopted by the tunnel working face in a large-to-small range, breaks through the limitation of a single construction water shutoff process, meets the urgent need of a sudden comprehensive water inflow treatment scheme in the tunnel tunneling construction field, and has the advantages of safety, reliability, short construction period, practicability and high efficiency.

Claims (6)

1. The long-detection-short-detection-grouting combined water control method based on water inflow classification is characterized by comprising the following steps of:
1) The water inflow is divided into two categories of I and II according to the water inflow of the roadway working surface:
the two categories are specifically:
i: the water inflow of the roadway working surface is more than or equal to 15m 3 /h;
II: the water inflow of the roadway working surface is less than 15m 3 /h;
2) Judging the class of the water inflow of the roadway working surface, and if the water inflow belongs to class I, entering step 3); if the two types belong to the II type, the step 4) is entered;
3) Grouting and tunneling roadway construction by adopting long-exploring-short-exploring water holes;
the step 3) comprises the following specific steps:
3-1) firstly chiseling bare rock on a working surface of a roadway, selecting five parts of the axial front part of the roadway, the left side wall of the roadway, the right side wall of the roadway, the top plate of the roadway and the bottom plate of the roadway by using a down-the-hole drill according to construction conditions and water gushing conditions, respectively drilling water detection holes with the length of 50m, the diameter of 120mm and the horizontal slope angle of 6 degrees, enabling the tunneling depth to be 45m, enabling the left side wall of the roadway and the right side wall of the roadway to be 20m respectively, enabling the top plate of the roadway and the bottom plate of the roadway to be 15m respectively, and reserving secondary water detection safety barriers to take values of 5m;
3-2) judging the water inflow of the working surface, if the water inflow exceeds 15m 3 And (h) plugging water by adopting a mode of water detection and grouting at the same time, so that the water inflow of the working surface is lower than 15m 3 And/h, if the water inflow after grouting is still more than 15m 3 In the time of/h, a grouting hole is additionally arranged in front of the working face until the water inflow is lower than 15m 3 /h;
3-3) tunneling by adopting short probe water, wherein the control range is 5m in front of the tunnel, the left side wall and the right side wall of the tunnel are respectively 3.0m, and the top plate and the bottom plate of the tunnel are respectively 2.5m; the length of the short water detection hole is 5m, and tunneling is allowedThe distance is 3m, if the water inflow is less than 10m 3 And (3) continuously tunneling the tunnel during the period of/h, if the water inflow is more than 10m 3 In the process of/h, grouting holes are added on the working surface of the roadway, grouting and water shutoff are carried out until the water inflow is reduced to 10m 3 Stopping grouting below/h, and recovering tunneling construction;
4) And (5) adopting a long-detection water hole grouting tunneling roadway for construction.
2. The method for controlling water by combining long probe-short probe-grouting based on water inflow classification according to claim 1, wherein in the step 3-2), the grouting water shutoff mode is to install an orifice pipe; when the orifice pipe is installed, jute is uniformly wound, a flange is installed at the end part, and a steel pipe for connecting a grouting pipe, a high-pressure cut-off valve and a pressure gauge is welded at the position 300mm away from the end part; and (3) sealing the orifice pipe by using double slurry, and plugging water in grouting operation.
3. The water control method based on the combination of long probe and short probe grouting of water inflow classification as claimed in claim 1, wherein in the step 3-3), the grouting water shutoff mode is as follows: and (5) installing a drill bit of a drilling machine, punching to 5m, installing an orifice pipe, and grouting and water shutoff.
4. The water control method based on the combination of long detection, short detection and grouting of water inflow classification as claimed in claim 1, wherein the step of grouting and tunneling the tunnel through the long detection water hole in the step 4) is similar to the steps of 3-1) and 3-2), and then grouting and water shutoff are carried out on the long detection water hole.
5. The method for controlling water by combining long detection and short detection and grouting based on water inflow classification according to claim 1, wherein in the step 3) and the step 4), 425# Portland cement is used as a grouting material, 40 DEG Be is used as water glass, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1:0.5-0.8; cement slurry water cement ratio initial concentration is 2:1.
6. The water control method based on the combination of long probe and short probe grouting of water inflow classification of claim 1, further comprising a step 5) of grouting reinforcement construction:
5-1) grouting equipment selection, wherein a grouting station is arranged at a distance of 5m from a working surface, and a 2TGZ60/210 type high-pressure grouting pump is arranged in the grouting station;
5-2) grouting mode and grouting hole arrangement: grouting and water plugging are carried out by adopting a tunnel segmentation forward grouting mode, the grouting segmentation length is 50m, the virtual slag of the tunnel face is cleaned, guide grouting holes are arranged, and water detection holes and pore diameters are arranged according to the fracture grade and the section sizeThe hole depth is 5m;
5-3) selecting and arranging the number of grouting holes: 6 fan-shaped radial grouting holes are distributed at the outer edge of the roadway, and the hole spacing and the row spacing are 1.48-2.0 m;
5-4) determining grouting material: the grouting material uses 425# Portland cement, the water glass concentration is 40 Bes, and the modulus is 3.0; the volume ratio of the cement slurry to the water glass slurry is 1:0.5-0.8; cement slurry water cement ratio initial concentration is 2:1;
5-5) determining grouting pressure: initial grouting pressure P a =P o +(0.3~0.5)MPa,P o Is hydrostatic pressure, normal pressure P b =P o + (0.5-0.8) MPa, final pressure P c =2P o MPa;
5-6) slurry injection amount: the slurry injection quantity V is roughly calculated according to the diffusion radius and the rock fracture rate, and the calculation formula is as follows:
a-slurry consumption coefficient; r—slurry diffusion radius; h-is the height of the grouting section; η—rock fracture rate; beta-slurry filling factor; m-calculus rate;
5-7) grouting end: the grouting pressure reaches the design final pressure value, the injection quantity is less than 50-60L/min, the grouting is stable for more than 20 minutes, and the grouting is finished.
CN202110962719.3A 2021-08-20 2021-08-20 Long-probe-short-probe-grouting combined water control method based on water inflow classification Active CN113530573B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110962719.3A CN113530573B (en) 2021-08-20 2021-08-20 Long-probe-short-probe-grouting combined water control method based on water inflow classification

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110962719.3A CN113530573B (en) 2021-08-20 2021-08-20 Long-probe-short-probe-grouting combined water control method based on water inflow classification

Publications (2)

Publication Number Publication Date
CN113530573A CN113530573A (en) 2021-10-22
CN113530573B true CN113530573B (en) 2024-01-30

Family

ID=78091323

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110962719.3A Active CN113530573B (en) 2021-08-20 2021-08-20 Long-probe-short-probe-grouting combined water control method based on water inflow classification

Country Status (1)

Country Link
CN (1) CN113530573B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1125333A1 (en) * 1982-07-05 1984-11-23 Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Горной Геомеханики И Маркшейдерского Дела Method of decreasing water inflow in mine workings in mining coal seams
CN104481560A (en) * 2014-12-09 2015-04-01 中煤第一建设有限公司 Roadway roof aquifer treatment method
CN106567714A (en) * 2016-11-09 2017-04-19 河北钢铁集团矿业有限公司 Grouting material for underground mine roadway and grouting water control method
CN108915689A (en) * 2018-07-09 2018-11-30 中南大学 A kind of water rich strata shaft excavation spy shutoff method
CN111206933A (en) * 2020-01-20 2020-05-29 西南交通大学 Tunnel construction method for traversing karst water-rich section
CN111677550A (en) * 2020-06-18 2020-09-18 陕西延长石油巴拉素煤业有限公司 Water prevention and control protection method for safe tunneling of rock roadway through water-rich coal seam section
CN112174616A (en) * 2020-08-26 2021-01-05 煤科集团沈阳研究院有限公司 Underground consolidation material and method for loose coal rock mass in small kiln damage area
CN113153367A (en) * 2021-04-13 2021-07-23 西南交通大学 Quicksand stratum reinforcing method with different water inflow amounts

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1125333A1 (en) * 1982-07-05 1984-11-23 Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Горной Геомеханики И Маркшейдерского Дела Method of decreasing water inflow in mine workings in mining coal seams
CN104481560A (en) * 2014-12-09 2015-04-01 中煤第一建设有限公司 Roadway roof aquifer treatment method
CN106567714A (en) * 2016-11-09 2017-04-19 河北钢铁集团矿业有限公司 Grouting material for underground mine roadway and grouting water control method
CN108915689A (en) * 2018-07-09 2018-11-30 中南大学 A kind of water rich strata shaft excavation spy shutoff method
CN111206933A (en) * 2020-01-20 2020-05-29 西南交通大学 Tunnel construction method for traversing karst water-rich section
CN111677550A (en) * 2020-06-18 2020-09-18 陕西延长石油巴拉素煤业有限公司 Water prevention and control protection method for safe tunneling of rock roadway through water-rich coal seam section
CN112174616A (en) * 2020-08-26 2021-01-05 煤科集团沈阳研究院有限公司 Underground consolidation material and method for loose coal rock mass in small kiln damage area
CN113153367A (en) * 2021-04-13 2021-07-23 西南交通大学 Quicksand stratum reinforcing method with different water inflow amounts

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
掘进巷道探放水施工技术研究;程鹏军;;自动化应用(06);全文 *
综合防治水方案在立井施工中的应用;周华玉;;煤炭科技(01);第58、59页 *

Also Published As

Publication number Publication date
CN113530573A (en) 2021-10-22

Similar Documents

Publication Publication Date Title
CN102797465B (en) Underground ultra-thin virtual protection layer hydraulic coal mining method
CN107152264A (en) Coiled tubing tubular column unit and its method for arranging halogen dilatation in salt cave underground natural gas storage tank
CN111206933A (en) Tunnel construction method for traversing karst water-rich section
CN106437632B (en) A kind of old goaf gas pumping method in colliery
CN103628912A (en) Goaf management filling grouting construction method
CN110863833B (en) Tunneling parameter control process of tunnel shield tunneling starting end boulder area shield tunneling machine
CN111827878B (en) Method for quickly and accurately probing hidden water inrush channel of coal seam floor
CN111764863B (en) Method for blocking water gushing of high-pressure drilling hole in underground fault fracture zone
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN114837663A (en) Construction method for improving recovery rate of fault waterproof coal pillar through ground pre-grouting
CN108374662A (en) The conduction method of artesian water tomography is crossed in a kind of tunnel
CN115263304A (en) Active intelligent regulation and control method for water level of mineral-bearing aquifer in coal-uranium coordinated mining area
CN107313743B (en) Method for repairing weak zone of coal seam floor water-resisting layer by utilizing coal seam gas well
CN113217043A (en) Efficient and rapid plugging method and construction method for water source with water inrush fault water guide zone
CN113530573B (en) Long-probe-short-probe-grouting combined water control method based on water inflow classification
CN113217044B (en) Upward and oblique scattering type grouting water plugging method for deep large fault tunnel
CN112302718B (en) Method for protecting water resource of water-bearing stratum of coal seam roof
CN102777183B (en) Hydraulic coal mining process for bottom plate roadway
CN109268060A (en) One kind is based on the quick-fried note integrated regional anti-burst method of strong and weak strong structure
CN210105807U (en) Outburst prevention and blowout prevention combined water control device for mine advanced water exploration orifice
CN111894672B (en) Method for advanced treatment of roof separation water damage of stope by adopting ground drainage drilling
CN220929356U (en) Coal-bed gas well structure of coal mine area with near-end butt joint of well-hole
CN113586134B (en) Method for controlling gas by hole-instead-of-lane combined drainage on coal seam working face
CN115354987B (en) Mine water inrush treatment method
CN220621952U (en) Mining overburden composite curtain for improving overburden separation layer grouting effect

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant