CN109784681A - Power engineering project investment management system - Google Patents
Power engineering project investment management system Download PDFInfo
- Publication number
- CN109784681A CN109784681A CN201811608179.3A CN201811608179A CN109784681A CN 109784681 A CN109784681 A CN 109784681A CN 201811608179 A CN201811608179 A CN 201811608179A CN 109784681 A CN109784681 A CN 109784681A
- Authority
- CN
- China
- Prior art keywords
- project
- management
- investment
- engineering
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to a kind of power engineering project investment management systems, belong to informationization technology field, and the system is made of DMS framework platform layer, basic data layer, service application layer, statistical analysis layer.System includes management system standard module, stores technical document relevant to project investment, provides essential information support;Project investment management module, each phase data information of stored items information, project and associated documents carry out comprehensive, total factor tracing control to engineering construction;Report center module covers all kinds of reports of Engineering Project;System management module, basis instrument and daily maintenance for system.System carries out control analysis, tracking instruction to engineering construction overall process data information; realize resource-sharing; promote engineering project Standardization Construction, fine-grained management, large-scale development; working efficiency and quality are improved, to realize that the maximizing the benefits of project full lifetime, enhancing enterprise core competence provide effective technical support.
Description
Technical field
Present invention relates particularly to a kind of power engineering project investment management systems.
Background technique
Project management is a subdiscipline of management, and definitions refers in project activity with special
Knowledge, technical ability, tool and method enable project under limited resources qualifications, realization or demand and phase more than setting
The process of prestige.
Power generation project construction investment volume is big, technology-intensive, the construction period is long, the investment data information scale of construction is big, type is many and diverse,
Level is numerous, and generation current project is building, runing similar production factors of each stage institute's form of expression, project volume in each stage
It is the disunities such as code, title and content, lack of standardization, cause data capture working difficult point big, inefficient.It therefore, is project construction
The management method and technical standard that offer system is advanced, specification is applicable are most important.
Summary of the invention
In order to solve the above technical problems, being realized the object of the present invention is to provide a kind of power engineering project Whole Course Management
Control analysis, tracking instruction are carried out to engineering construction overall process data information, realize resource-sharing, promotes engineering project standard
Change construction, fine-grained management, large-scale development, improve working efficiency and quality, for realization project full lifetime maximizing the benefits,
Enhance enterprise core competence and effective technical support is provided.
Power engineering project investment management system of the present invention, comprising:
Management system standard module provides project construction for storing technical document relevant to project investment management
Essential information is supported, is working stamndard resources bank needed for management of investment.The management system standard includes: state's laws, row
Include in industry specification, group's system, professional quota store, project consulting management working stamndard, domestic and international investing tip and system
It is completed and is building all items information, document approvals and daily management etc..
Project investment management module, in system some build/construction information of consulting item, each stage control of investment,
The business tines such as program financial management, project materials purchasing, project work of consultation.By system automatic collection and receive, identification
Separate sources data, establish group's grade data interaction bus, and the standardization of every business realizing and personalization are freely interacted and answered
With.
The project construction information, essential information, bidding sector division including project in construction, check and approve reply, vivid progress and
The unified management of each unit of taking part in building and information inquiry sufficiently reflect project construction characteristic element, close regulator system, construction management, group
Knit structure etc..
Each stage control of investment module covers the estimation of project construction feasibility study, estimation per design, bid price, executes budgetary estimate, closes
With key contents such as management, scheduled fun control, Closing Check, project conclusion calculation, Cost Indexes;System breaks through semi-structured and non-
Structuring (WORD table, drawing, pdf document etc.) data and mass data puzzlement, improve the value density of data, realization pair
The depth of total evidence is excavated and the application of more high-level.There is provided system specifications for each stage control of investment of project construction, profession can
The fine-grained management of retrospect.
Program financial management: periodically being uploaded by WORD or EXCEL report file, is grasped project construction in time and is built peace work
Journey, first for material and equipment purchasing fund planning and actually accomplish comparative analysis;Inquire tracking project assets, cash flow, receivable
Funds on account, capital budget and construction investment complete financial statement, to ensure engineering construction capital supply, more effective controlled investment wind
Danger.
Engineering material supply: mainly there is first for equipment and materials goods and materials arrival account table, go out storage statistics, financial settlement statistics
Deng three Xiang Guanli.By content described in EXCEL template report, equipment and materials title, specification, time, transport, neck are accurately reflected
With tens item data information such as, clearing, for ensure key goods and materials required for project construction buying, using, check and write off and expense control
System provides information-based means, greatly improves working efficiency.
Project work of consultation: specification consultation service standard shows vocational work content, practicability and strong operability, has
Effect instructs professional work, management innovation best practices.Cover work of consultation plan, work log, work contact list, meeting discipline
It wants, stamping record, transmitting-receiving lists of documents and work of consultation investigation table of satisfaction degree, drawing are borrowed, engineering calculation plan and completion, work
Journey amount calculated description summarizes, change in the work visa commission record, clearing Outcome Document three-level audit more than ten professional works such as archive
Standard and system.Pass through the biography to the multiple types data information such as WORD document, Microsoft Excel, drawing, pdf document, picture
It is defeated to capture, show application, it realizes that the online execution of professional work, process audit, risk control, achievement is promoted, is that project is seeked advice from
The high quality that works completes the support of offer system.
Report center module, application management system standard form, each business module data in integration system are each according to system
Class Outcome Document carries out each stage, the comparative analysis of each element, confirmation risk factors and expense, realizes trend of investment control.Institute
Stating report center includes program estimation budgetary estimate, contract account, projects amount, scheduled fun payment, Office Of Contract Settlements book, fund planning
With 11 kinds of single reports such as completion, financial statement, materials storage;And there are feasibility study estimation and estimation per design, estimation per design and execution
Budgetary estimate executes company and lump sum, lump sum and cost mark post, expense dynamically track, group's projects construction period economic indicator
6 types such as comparison compare report generation unit.
It is Whole Process Control project construction risk, evaluation construction project valence by embodying a concentrated reflection of project investment management achievement
Value, experience for reference are learned the lesson, power-assisted subsequent project science decision provides important, system, reliable big data information
Resource.
System management module constructs system application environment based on cloud computing framework, provides Saas application clothes in Iaas platform
Business, system use diversification security strategy, using the secured fashion of the diversification such as code key, unified certification, des encryption transmission, really
Protect the safe and reliable of user identity authentication, shared service and user data.
System automatic collection and reception, identification separate sources data, and data are arranged, clean, be associated with, are calculated,
High-volume database is formed, and opening interface is provided, reserves related service system docking.
It realizes system management base setting and daily maintenance, the information includes organization, role-security, business word
Allusion quotation, System menu, operation log etc..
Above description is only the general introduction of the present invention program, in order to better understand the technical means of the present invention, and can
It is implemented in accordance with the contents of the specification, the following is a detailed description of the preferred embodiments of the present invention and the accompanying drawings.
Detailed description of the invention
Fig. 1 power engineering project investment management system construction drawing of the present invention;
Fig. 2 power engineering project investment management system composition figure of the present invention;
The project list code pattern of Fig. 3 power engineering project investment management system of the present invention;
Bid contrul valence, the Office Of Contract Settlements, projects amount, work of Fig. 4 power engineering project investment management system of the present invention
Make the examination & approval flow charts such as connection list, meeting summary, engineering stamping record;
The Office Of Contract Settlements three-level auditing flow figure of Fig. 5 power engineering project investment management system of the present invention.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiments of the present invention will be described in further detail.Implement below
Example is not intended to limit the scope of the invention for illustrating the present invention.
Embodiment 1
The present embodiment power engineering project investment management system, the management system standard module include normative document list
Member, for safeguarding that normative document and policies and regulations that all items use, normative document are divided into: national standard, industry standard,
Group company's system;
The management system standard module further includes professional quota library unit, and " power construction engineering budgetary estimate is fixed for data source
Volume ", " power construction engineering norm for detailed estimates " (2013 editions), including quota labor, material, mechanical one-shift specific consumption data,
Corresponding quota is called for the inquiry of project quota, investment data analysis and establishes the functions such as project supplement ration.
The management system standard module further includes project investment management modular unit, is project investment management and consulting pipe
Reason provides uniform template and unified standard, including program estimation budgetary estimate, scheduled fun management, contract management, Office Of Contract Settlements, change pipe
Reason, project counseling program, construction drawing management, quantities calculation, meeting summary, working relation contact list, handling of goods and materials, plan
The templates such as finance, bill of quantities;
The management system standard module further includes domestic and international investing tip unit, for storing the domestic and international of user's input
Project investment information, including feasibility study, just set, each stage static investment of engineering construction, dynamic investment, specific investment cost.
The management system standard module further includes consulting item information unit, for safeguarding all complete and building consulting
Project essential information, including project code, project name, construction capacity, starting date, time of accomplishment, construction unit, project public affairs
The contents such as department, affiliated unit, head of the unit.
The management system standard module further includes consulting item administrative unit, and the outstanding work for work approval is reminded
And processing, the module shown in the form of pending list examination & approval in need work.
The management system standard module further includes consulting item working cell, for inquiring work log, according to user
The work log of the open different range of permission difference check permission.Wherein, responsible person can inquire and invest project personnel
Work log, project manager can inquire all personnel's work log in current project.
The management system standard module further includes that project list coding is established referring to unified power generation project coding standard
Power generation project coding scheme in management system is realized the automatically generating of coding using unduplicated genetic algorithm, is managed and automatically
Verifying, and pass through list item, budgetary estimate in standard form realization building quantity, installing engineering amount and construction project other fees
By norm, the historical datas such as project amount and basis of compilation are imported, are exported using data.Item dividing and project name are according to " firepower
Generation engineering builds budget compilation and computational rules (2013 editions) ", project code is referring to " power construction engineering bill of quantities meter
One Fossil Fueled Power Plant Project of valence specification " combine system functional requirement to be worked out.
First and second is industry type: coal-fired FM, combustion engine FR, wind-powered electricity generation FF, water power FS, solar energy FY, scene FG, underground heat
FD, tidal power generation FC, nuclear power FH;
Third and fourth position is works category: such as 01 major-minor production engineering, 02 engineering related with factory site
Five, the six are professional system: such as 01 therrmodynamic system, 02 fuel system, 03, ash disposal system;
7th is engineering classification: T represents civil engineering, A represents installation;
Eight, the nine are individual works: by taking therrmodynamic system as an example, 01 boiler controller system (installation), 01 main building ontology and being set
Standby basis (building)
Ten, the 11 are unit engineering: by taking therrmodynamic system as an example, 01 boiler body (installation), 01 main building ontology (are built
It builds)
12nd, 13 is partitioned project: by taking therrmodynamic system as an example, 01 combination installation (installation), 01 foundation structure (are built
It builds)
14th, 15, sixteen bit be subdivisional work: by taking therrmodynamic system as an example, A11 boiler steel frame install (installation), A15
Earthwork construction (building)
17th, 18,19 is sequence code.
As shown in Figure 3.
Embodiment 2
The present embodiment power engineering project investment management system, on the basis of embodiment 1, the project investment management mould
Block includes this project information unit, in which:
Project essential information is used to safeguard the essential information of current operation project, including project number, project entity, goes into operation
Date, time of accomplishment, setup state, item size, power generation type, project amount version, budgetary estimate version, item description, related official communication
Inquiry personnel etc.;
Item target phase information is for being arranged project correlation bid section information, including bid section serial number, bid section title, contract number
Deng;
Project associated documents are used to safeguard the related management file of current operation project, including document classification, filename, volume
Volume personnel, uplink time etc., and can download, preview and deletion;
Project image progress is used to safeguard the vivid progress of current operation project, including document classification, filename, human editor
Member, uplink time etc., and can download, preview and deletion;
All organizational informations are used to safeguard all unit of taking part in building's information of current operation project, including organization name, tissue
Referred to as, tissue class etc..
The project investment management module further includes each stage control of investment unit, and the unit contains power engineering and builds
If the multiple engineering phases of overall process investment document, have the estimation of engineering feasibility study, engineering design budgetary estimate, calling for tenders of project control valence,
Engineering executes budgetary estimate, engineering executes budgetary estimate (dynamic), engineering contract management, scheduled fun management, engineering contract clearing, Office Of Contract Settlements
Three-level audit, Office Of Contract Settlements document approvals, engineering lump sum (dynamic), engineering lump sum, project base stake.Wherein:
The estimation of engineering feasibility study can import data according to template and save text for importing and showing engineering feasibility study estimation information
Part;
Engineering design budgetary estimate can import data according to template and save text for importing and showing engineering design budgetary estimate information
Part;
Calling for tenders of project control valence is examined for examining bid contrul valence, establishment people's submission-project manager's first trial-service management
Core-department head's examination & approval, bid contrul valence can issue after the completion of examination & approval, approval process such as Fig. 4.
Engineering executes budgetary estimate and executes budgetary estimate information for importing and showing engineering, and data can be imported according to template style and are protected
Deposit file;
Engineering executes budgetary estimate (dynamic) for importing and showing engineering Dynamic Execution budgetary estimate information, can lead according to template style
Enter data and save file, according to project bid and engineering progress situation, normality updates building installation engineering, equipment and materials is purchased
And the progress of other expenditure is completed, and is compared with standard value, dynamic controls construction investment;
Engineering contract management is used for the relevant all contracts of maintenance engineering, is shown in the form of account, according to expense for construction
With attribute, industry preliminary budget administrative provisions and construction unit's system, installation equipment purchasing, device material, construction and installation work are pressed
Journey, Architectural Equipment, Architectural Equipment, building first can be imported for the classifications design template such as material and other fees according to template style,
Can also be by system editor, newly-increased and deletion, and bidding document, tender documents, contract and the skill for saving every part of contract can be uploaded
Situations such as art document of agreement, dynamic grasps contract signing, manufacturer, contracting system, changed content, payment progress comprehensively;
The audit of Office Of Contract Settlements three-level is for auditing Office Of Contract Settlements, when login system interface is presented Office Of Contract Settlements file, submits
Between, the authorization amount of money, applicant and time, state and operation see, then carry out three-level audit by the suggestions made after examination of operation setting, press
Professional division initiate level-one, second level, three-level auditing flow, according to upload the Outcome Documents such as WORD or EXCEL report or drawing and
Support file carries out step by step, and reflects audit item with " quality control process list " and there are problem, complete by phase mutual feedback
After three-level audit, submits business responsible person and complete to examine with " Consultation Achievements examination and approval document " content, auditing flow such as Fig. 5.
The audit of Office Of Contract Settlements document approvals works out people's submission-project manager's first trial-service management for the clearing that approve the contract
Audit-department head's examination & approval, can publish, approval process such as Fig. 4 after the completion of examination & approval.
Engineering lump sum (dynamic) is used for maintenance engineering lump sum (dynamic) information, based on contract settles accounts situation and timely updates
Engineering lump sum, dynamic controlled investment;
Engineering lump sum can import data according to template style and save text for importing and showing engineering lump sum information
Part;
Project base stake is for importing and showing project base stake information, according to group company's mark post index according to item
Mesh project setting this project base stake is used for bidding assessment, and data can be imported according to template style and save file.
The project investment management module further includes program financial management unit, for storing multiple works in table form
The financial relevant information in journey stage;Wherein:
Financial statement unit, for days financial statement data import and show, inquiry tracking project assets, cash flow,
Accounts receivable, investment performance;
Fund planning and unit is actually accomplished, for uploading and preview fund planning and actually accomplishing information, inquiry tracking
Engineering capital budget performance.
The project investment management module further includes handling of goods and materials unit, for storing multiple engineering ranks in table form
The goods and materials relevant information of section;Wherein:
Goods and materials arrival account unit is stored and is shown for days goods and materials arrival account, including contract number, contract name
Title, arrival time, equipment and materials title, figure number, specifications and models, unit, quantity, weight, supply unit, manufacturer, handover
The information such as people, handover odd numbers, recruiting unit, recipient, handover time;
Goods and materials go out to be put in storage statistic unit, go out to be put in storage statistical data storage for days goods and materials and show, including equipment and materials
Title, unit, quantity, unit price, conjunction valence, storage date, outbound quantity, receives the date, receives unit, cancelling stocks number specifications and models
The information such as amount, cancelling stocks date, cancelling stocks unit, contract number, contract title, producer, acceptance of the bid date;
Goods and materials financial settlement statistic unit, for store and display material provide financial settlement statistical information, including contract number,
The information such as contract title, equipment and materials title, unit, quantity, unit price, conjunction valence.
The project investment management module further includes project consulting management unit, establishes perfect engineering consulting system, is contained
Lid work of consultation plan, work log, work contact list, meeting summary, stamping record, transmitting-receiving lists of documents and work of consultation are full
Meaning degree application form, drawing borrow, engineering calculation plan and completion, quantities calculation book summarize, change in the work visa commission record
Deng more than ten professional work standards and system, it can be achieved that being seeked advice from online, On-the-spot Counseling service conditions is grasped in time;Its
In:
Construction drawing borrowing management unit is used for statistical updating construction drawing information, stores construction drawing and safeguards construction
Drawing borrows information, including borrow number, volume catalog number, volume title, borrower, when borrowing the time, giving back people, give back
Between, borrow the information such as quantity;
Quantities calculation plan and completion unit, draw for maintenance engineering meter and performance, reaction completion rate are completed
The information such as time, completion personnel, dynamic grasps design drawing performance, and stores quantities calculation book;
Projects amount summarizes table unit, is used for maintenance engineering amount summary information, including budgetary estimate closing in engineering name, main
Content and project amount, contract inventory coding, contract work title and project amount and each bid section drawing project amount, and complete to flow
Journey examination & approval, approval process such as Fig. 4.
Change in the work unit, commission, visa account unit, for Maintenance Design change, commission, visa account information, packet
Reference number of a document is included, file name, proposed unit, leads and send unit, the origin of an incident, sender and date of shipping, recipient and date received
Etc. information;
Change in the work, commission, visa, (pre-) the clearing book list member of leakage item, for the projects clearing such as maintenance engineering change, commission
It is (pre-) to examine the information such as inventory information, including amount declared, the supervision & assessment amount of money, the consulting authorization amount of money, foundation, and achievement can be stored
File;
Project counseling program unit, for uploading and preview engineering consulting plan information, including project each year, monthly and respectively
Plan, reflection work of consultation content, human resources, working stamndard etc. are summarized in the work of consultation in week, solve the problems, such as exist in time,
Help is provided to improve consultation service quality and efficiency;
Work log unit, for filling in personal work log information, including filling time, reporter, work today meter
It draws, action today, the information such as work plan tomorrow;
Working relation single unit, for upload and preview work contact list information, including file name, proposed unit, master
It send unit, the origin of an incident, granting department, provide the information such as people and release date, recipient and date received, and complete workflow examination and approval,
Approval process such as Fig. 4.
Meeting summary unit, for upload and preview meeting summary information, including file name, proposed unit, master send list
Position, the origin of an incident provide department, provide the information such as people and release date, recipient and date received, and completing workflow examination and approval, examine
Process such as Fig. 4.
Engineering stamping recording unit records information, including name of seal, stamping thing for upload and preview engineering stamping
By information such as, stamping quantity, user, project manager, stamping date, applicant and application times, and workflow examination and approval is completed, examined
Criticize process such as Fig. 4.
Outcome Document handover record unit, for upload and preview Outcome Document handover record information, including reference number of a document,
File name, quantity submit the information such as unit, the time of delivery, recruiting unit, receiving time;
Satisfaction investigation table unit, for storing and showing in investigation table of satisfaction degree information, including investigation table numbering, investigation
The information such as appearance, control time, score or evaluation, and the marking evaluation of consulting client can be stored and signed and stamped " customer is full
Meaning degree application form " WORD text original part, the attitude of true reflection consulting unit, ability to solve problem, skilful service degree,
Consultation report data accuracy, consultation report timeliness, data-integrity etc. situation;
Each unit of the above project consulting management file module, user can download standard form, will meet pattern rule
Data import complete consultation information storage;The history list of consultation information is shown according to the instruction of user.
Embodiment 3
The present embodiment power engineering project investment management system, on the basis of embodiment 1,2, the report center die
Block, application management system standard form, each business module data in integration system carry out each rank according to all kinds of Outcome Documents of system
Section, the comparative analysis of each element, confirmation risk factors and expense, realize trend of investment control.The report center includes project
Estimate budgetary estimate, contract account, projects amount, scheduled fun payment, Office Of Contract Settlements book, fund planning and completion, financial statement, object
11 kinds of single reports such as money keeping;And have feasibility study budgetary estimate and estimation per design comparison, estimation per design and execute budgetary estimate, execute budgetary estimate with
6 types pair such as lump sum, lump sum and cost mark post, expense dynamically track, the comparison of group's projects construction period economic indicator
Than report generation unit.
The above is only a preferred embodiment of the present invention, it is not intended to restrict the invention, it is noted that for this skill
For the those of ordinary skill in art field, without departing from the technical principles of the invention, can also make it is several improvement and
Modification, these improvements and modifications also should be regarded as protection scope of the present invention.
Claims (9)
1. a kind of power engineering project investment management system characterized by comprising
Management system standard module provides the basic of project construction for storing technical document relevant to project investment management
Informational support is working stamndard resources bank needed for management of investment;Management system standard includes: state's laws, industry standard, collection
It is completed in group's system, professional quota store, project consulting management working stamndard, domestic and international investing tip and system and building
There are project information, document approvals and daily management;
Project investment management module is that some is building/consulting item construction information, each stage control of investment, plan wealth in system
Be engaged in management, project materials purchasing, the business tines such as project work of consultation, by system automatic collection and reception, identification it is different come
Source data, establishes group's grade data interaction bus, and the standardization of every business realizing and personalization are freely interacted and applied;
The project construction information, essential information, bidding sector division, approval reply, vivid progress and each ginseng including project in construction
The unified management and information inquiry for building unit, sufficiently reflect project construction characteristic element, close regulator system, construction management, knot of tissue
Structure;
Each stage control of investment module covers the estimation of project construction feasibility study, estimation per design, bid price, executes budgetary estimate, contract pipe
The key contents such as reason, scheduled fun control, Closing Check, project conclusion calculation, Cost Index;System breaks through semi-structured and non-structural
Change data and mass data puzzlement, improve the value density of data, realizes and the depth of total evidence is excavated and more high-level
Using providing system specifications, the retrospective fine-grained management of profession for each stage control of investment of project construction;
Program financial management: periodically being uploaded by WORD or EXCEL report file, is grasped project construction in time and is built peace engineering, first
For material and equipment purchasing fund planning and actually accomplish comparative analysis;Inquire tracking project assets, cash flow, accounts receivable,
Capital budget and construction investment complete financial statement, to ensure engineering construction capital supply, more effective controlled investment risk;
Engineering material supply: first mainly is put in storage statistics, financial settlement statistics etc. three for equipment and materials goods and materials arrival account table, out
Item management, by content described in EXCEL template report, accurately reflects equipment and materials title, specification, the time, transports, receives, tying
The tens item data information such as calculate, for ensure key goods and materials required for project construction buying, using, check and write off and Payment control provides
Information-based means, greatly improve working efficiency;
Project work of consultation: specification consultation service standard shows vocational work content, practicability and strong operability, effectively refers to
Lead professional work, management innovation best practices;Cover work of consultation plan, work log, work contact list, meeting summary, use
Zhang Jilu, transmitting-receiving lists of documents and work of consultation investigation table of satisfaction degree, drawing borrow, engineering calculation plan and completion, project amount
More than ten professional work standards and the systems such as calculated description summarizes, change in the work visa commission record, by WORD document,
The transmission of the multiple types data information such as Microsoft Excel, drawing, pdf document, picture captures, shows application, realizes professional work
Online execution, process audit, risk control, achievement are promoted, and provide system support for the completion of project work of consultation high quality;
Report center module, application management system standard form, each business module data in integration system, according to system it is all kinds of at
Fruit file carries out each stage, the comparative analysis of each element, confirmation risk factors and expense, realizes trend of investment control;The report
Table center include program estimation budgetary estimate, contract account, projects amount, scheduled fun payment, Office Of Contract Settlements book, fund planning with it is complete
At 11 kinds of single reports such as, financial statement, materials storages;And have feasibility study estimation with estimation per design, estimation per design and execute budgetary estimate,
Execute budgetary estimate and lump sum, lump sum and cost mark post, expense dynamically track, the comparison of group's projects construction period economic indicator etc.
6 types compare report generation unit;It is Whole Process Control project construction wind by embodying a concentrated reflection of project investment management achievement
Danger, evaluation construction project value, experience for reference learn the lesson, power-assisted subsequent project science decision provide it is important, system,
Reliable big data information resources;
System management module constructs system application environment based on cloud computing framework, provides Saas application service in Iaas platform, is
System uses diversification security strategy, using the secured fashion of the diversification such as code key, unified certification, des encryption transmission, it is ensured that user
Authentication, shared service and user data it is safe and reliable;
System automatic collection and reception, identification separate sources data, and data are arranged, clean, be associated with, are calculated, it is formed
High-volume database, and opening interface is provided, reserve related service system docking;
Realize that system management base setting and daily maintenance, the information include organization, role-security, business dictionary, are
System menu and operation log.
2. power engineering project investment management system according to claim 1, which is characterized in that management system standard module
Project list coding unit establishes power generation project coding scheme in management system referring to unified power generation project coding standard, utilizes
Unduplicated genetic algorithm realizes automatically generating, manage and verifying automatically for coding, and realizes architectural engineering by standard form
The historical datas such as list item, quota of budgetary estimate, project amount and basis of compilation in amount, installing engineering amount and construction project other fees
It imports, exported using data, laid the foundation for management of investment data classification set, bidding assessment.
3. power engineering project investment management system according to claim 1, which is characterized in that each stage control of investment mould
The budgetary estimate dynamic of block controls, and according to industry standard, Unified coding system, solidification template, normality updates building installation engineering, equipment
Material is purchased and the progress of other expenditure is completed, and is compared with standard value, and analyzing influence factor formulates satisfactory after correcting, guarantees item
Mesh investment is controllably controlled again, realizes set objective.
4. power engineering project investment management system according to claim 1, which is characterized in that each stage control of investment mould
The contract management of block is the important evidence of engineering construction stage management of investment, and this system is according to engineering construction cost attribute, industry
Preliminary budget administrative provisions and construction unit's system, by installation equipment purchasing, device material, building installation engineering, Architectural Equipment,
First is built for the classifications design template such as material and other fees, is uploaded by template downloading, contract inputting, statistics, realization is being built
All contract system management of project, and dynamic is grasped comprehensively by master file (bidding document, contract text, technical protocol)
Situations such as contract signing, manufacturer, contracting system, changed content, payment progress is engineering construction progress, quality, cost pipe
Reason provides reliable support.
5. power engineering project investment management system according to claim 1, which is characterized in that each stage control of investment mould
The scheduled fun management of block, as the key link of engineering construction investment process control, system is according to Practical Project Payment control mesh
Mark chooses contract title, number, time inquiring rest in build Project contract each monthly and total the output value, contractor unit, item
The information such as mesh manager, and the master file by uploading WORD or EXCEL report can specifically reflect each unit of taking part in building to building peace work
Journey part-to-item project amount, change attestation, commission and the corresponding expense auditing of measure project are as a result, be project progress, quality, cost
Control provides robust techniques and supports.
6. power engineering project investment management system according to claim 1, which is characterized in that each stage control of investment mould
The Office Of Contract Settlements three-level of block is audited, and for the key link of consultation quality control, system passes through using message queue as technological means
The data bus technology that XML, serializing, stream compress realizes auditing flow design and the storage of each class formation and unstructured data
It deposits and transmits.
Office Of Contract Settlements file, submission time, the authorization amount of money, applicant and time, state and operation is presented in login system interface, then
Three-level audit is carried out by the suggestions made after examination of operation setting, initiates level-one, second level, three-level auditing flow by professional division, according to
It uploads the Outcome Documents such as WORD or EXCEL report or drawing and support file carries out step by step, and is anti-with " quality control process list "
It reflects audit item and there are problem, after phase mutual feedback completes three-level audit, submit business responsible person and with " Consultation Achievements are examined
Criticize single " content completion examination & approval.
7. power engineering project investment management system according to claim 1, which is characterized in that each stage control of investment mould
The quantities calculation of project work of consultation involved by block is consultation service element task.Its feature needs the super large scale of construction non-structural
The text of chemical industry journey drawing data is imported, stores and is exported, and by login system drawing information interface, dynamic grasps design drawing
Performance, and importing storage design drawing is master file, formulates and meets the work that the payment of engineering construction progress and clearing need
Journey meter, which is calculated, to be drawn;
Login system project amount summarizes, and can reflect building installation engineering bill of quantities coding, budgetary estimate comprehensively by substrate interface
Closing in engineering name, main contents and project amount, contract inventory coding, contract work title and project amount and each bid section figure
Paper project amount etc. provides important references for Optimization Plan, Office Of Contract Settlements, bidding assessment, cost Control, consultation quality management
Foundation.
8. power engineering project investment management system according to claim 1, which is characterized in that each stage control of investment mould
Project work of consultation plan involved by block, as the directive document of consultation service work, system passes through project counseling program window
Mouthful, downloading or preview project each year, monthly and the work of consultation in each week summarize plan, reflection work of consultation content, manpower money
Source, working stamndard etc. solve the problems, such as exist in time, provide help to improve consultation service quality and efficiency.
9. power engineering project investment management system according to claim 1, which is characterized in that each stage control of investment mould
The investigation of project satisfaction with AIDS counseling involved by block, system is by importing the marking evaluation of consulting client and signed and stamped " customer
Investigation table of satisfaction degree " WORD text original part, attitude, ability to solve problem, the skilful service journey of true reflection consulting unit
Degree, consultation report data accuracy, consultation report timeliness, data-integrity etc. situation are engineering consultation unit's developings
Market, the important references for improving operation ability and sustainable development.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811608179.3A CN109784681A (en) | 2018-12-26 | 2018-12-26 | Power engineering project investment management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811608179.3A CN109784681A (en) | 2018-12-26 | 2018-12-26 | Power engineering project investment management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109784681A true CN109784681A (en) | 2019-05-21 |
Family
ID=66497791
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811608179.3A Pending CN109784681A (en) | 2018-12-26 | 2018-12-26 | Power engineering project investment management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109784681A (en) |
Cited By (54)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109858751A (en) * | 2018-12-26 | 2019-06-07 | 中国大唐集团科学技术研究院有限公司 | Power engineering Evaluating Projects System |
CN110232288A (en) * | 2019-06-25 | 2019-09-13 | 重庆市地理信息中心 | Geographic information data complex encryption system |
CN110503386A (en) * | 2019-07-23 | 2019-11-26 | 国网河北能源技术服务有限公司 | A kind of data processing system for market-oriented project |
CN110599072A (en) * | 2019-10-10 | 2019-12-20 | 贵州百胜工程建设咨询有限公司 | BIM-based investment cost control method |
CN110705837A (en) * | 2019-09-11 | 2020-01-17 | 中国三峡建设管理有限公司 | Visual engineering construction management system and construction method thereof |
CN110910092A (en) * | 2019-11-21 | 2020-03-24 | 四川高路交通信息工程有限公司 | Highway construction information management platform |
CN110991985A (en) * | 2019-11-11 | 2020-04-10 | 国网浙江武义县供电有限公司 | Project progress data processing method |
CN110991990A (en) * | 2019-11-25 | 2020-04-10 | 四川华通建设工程造价管理有限责任公司 | Engineering project cost management system |
CN111061789A (en) * | 2019-12-10 | 2020-04-24 | 国家电网有限公司 | Smart power grids capital construction information management system |
CN111191965A (en) * | 2020-02-10 | 2020-05-22 | 重庆图强工程技术咨询有限公司 | Overall process engineering consultation service evaluation system |
CN111260327A (en) * | 2020-01-16 | 2020-06-09 | 深圳市艾泰克工程咨询监理有限公司 | Project construction cooperation management and control platform based on cloud service |
CN111274774A (en) * | 2020-01-19 | 2020-06-12 | 叶志 | Industrial building engineering full-process automatic management system |
CN111311206A (en) * | 2020-05-11 | 2020-06-19 | 温州开晨科技有限公司 | Construction project ternary space relationship construction method, system and medium |
CN111367939A (en) * | 2020-03-04 | 2020-07-03 | 昆明海巍科技有限公司 | System and method for compiling and managing highway engineering project account and computer |
CN111429007A (en) * | 2020-03-25 | 2020-07-17 | 陕西合友网络科技有限公司 | Building project supervision system and supervision method |
CN111553664A (en) * | 2020-05-11 | 2020-08-18 | 重庆金美通信有限责任公司 | Method for realizing intelligent management of design and production of communication equipment based on 5G technology |
CN111553643A (en) * | 2020-05-18 | 2020-08-18 | 国网河北省电力有限公司物资分公司 | Material purchasing plan and supply chain management system |
CN111738538A (en) * | 2020-01-06 | 2020-10-02 | 业达建设管理有限公司 | Engineering project management system, management method, APP and storage medium |
CN111767247A (en) * | 2020-06-28 | 2020-10-13 | 杭州远大档案技术有限公司 | File specification and synchronous forming control platform for real-time supervision of engineering data |
CN111813745A (en) * | 2020-07-27 | 2020-10-23 | 中交路桥北方工程有限公司 | System, device and method for civil construction technology and standard query |
CN111898280A (en) * | 2020-08-12 | 2020-11-06 | 于思平 | Engineering quantity calculation system and method |
CN112000724A (en) * | 2020-08-27 | 2020-11-27 | 四川公路桥梁建设集团有限公司 | Highway engineering collaborative computation amount information management system based on custom formula |
CN112001680A (en) * | 2020-08-27 | 2020-11-27 | 四川公路桥梁建设集团有限公司 | BIM-based highway engineering management system |
CN112085481A (en) * | 2020-09-22 | 2020-12-15 | 国网山东省电力公司烟台供电公司 | Whole-process tracking system for electric power engineering project management |
CN112184068A (en) * | 2020-10-27 | 2021-01-05 | 陕西交建云数据科技有限公司 | ERP-based road engineering project information cooperation method |
CN112508417A (en) * | 2020-12-11 | 2021-03-16 | 民航中南机场设计研究院(广州)有限公司 | Civil aviation professional engineering general contract project management system based on BIM technology |
CN112561240A (en) * | 2020-11-25 | 2021-03-26 | 青岛国信建设投资有限公司 | Construction project contractor performance credit evaluation method and system |
CN112734563A (en) * | 2021-01-11 | 2021-04-30 | 上海瀚之友信息技术服务有限公司 | Data management method and system based on fund flow |
CN112785271A (en) * | 2021-01-26 | 2021-05-11 | 宝钢工程技术集团有限公司 | Method for managing cash flow of engineering project in full cycle |
CN112862341A (en) * | 2021-02-25 | 2021-05-28 | 中铁一局集团有限公司 | Project cost management system |
CN113033172A (en) * | 2021-04-01 | 2021-06-25 | 国网江苏省电力有限公司南通供电分公司 | Construction cost calculating and comparing system based on digital audit |
CN113095631A (en) * | 2021-03-22 | 2021-07-09 | 同望科技股份有限公司 | Engineering enterprise group basic data control platform based on componentization |
CN113112233A (en) * | 2021-04-16 | 2021-07-13 | 西安热工研究院有限公司 | BIM-based intelligent management method and platform for full life cycle of wind power project |
CN113220634A (en) * | 2021-05-08 | 2021-08-06 | 河南固川市政园林工程有限公司 | Information management device and electronic equipment of engineering visa file |
CN113240403A (en) * | 2021-06-10 | 2021-08-10 | 周明升 | Engineering construction project management system and method based on multi-source data |
CN113435687A (en) * | 2021-05-12 | 2021-09-24 | 中核工程咨询有限公司 | Nuclear power supervision analysis system based on big data |
CN113435743A (en) * | 2021-06-25 | 2021-09-24 | 北方实验室(沈阳)股份有限公司 | Information-based engineering overall process data resource sharing system |
CN113450083A (en) * | 2021-07-12 | 2021-09-28 | 华航环境发展有限公司 | Construction project management system |
CN113592414A (en) * | 2020-12-04 | 2021-11-02 | 上海汇招信息技术有限公司 | File authority control method |
CN113656505A (en) * | 2021-08-24 | 2021-11-16 | 生特瑞(上海)工程顾问股份有限公司 | Digitalization of distributed project management system and method for synchronizing data thereof |
CN113743911A (en) * | 2021-09-16 | 2021-12-03 | 中国电建集团成都勘测设计研究院有限公司 | Project total contract project cost management method based on information system |
CN113743716A (en) * | 2021-07-26 | 2021-12-03 | 南方电网深圳数字电网研究院有限公司 | Project investment assessment method, system and storage medium |
CN114004603A (en) * | 2021-11-16 | 2022-02-01 | 南方电网能源发展研究院有限责任公司 | Automatic statistical method and device for fixed asset investment and computer equipment |
CN114049103A (en) * | 2022-01-11 | 2022-02-15 | 国网北京市电力公司 | Power grid infrastructure project management and control method, system, equipment and medium |
CN114792226A (en) * | 2022-04-13 | 2022-07-26 | 刘博� | Electronic standing book management method and system for project material review |
CN115114604A (en) * | 2022-07-26 | 2022-09-27 | 如皋市规划建筑设计院有限公司 | Internet-based building design dynamic process management system |
CN115147083A (en) * | 2022-07-15 | 2022-10-04 | 国网四川省电力公司经济技术研究院 | Power transmission and transformation project overall-process cost evaluation system with information level interactive management |
CN115249192A (en) * | 2022-07-19 | 2022-10-28 | 广东省投资和信用中心(广东省发展和改革事务中心) | Investment project management system, method and equipment |
CN116258467A (en) * | 2023-05-16 | 2023-06-13 | 济南荣耀合创电力科技有限公司 | Electric power construction management and control system |
CN116452158A (en) * | 2023-06-19 | 2023-07-18 | 博思数采科技发展有限公司 | Method, device, equipment and medium for managing index of random extraction of suppliers |
CN116663848A (en) * | 2023-06-28 | 2023-08-29 | 雅安紫木工程咨询有限公司 | Multi-terminal full-flow engineering resource interaction management system and method |
CN116797105A (en) * | 2023-08-22 | 2023-09-22 | 中建西南咨询顾问有限公司 | Price index statistical method and system based on engineering standardized coding |
CN116823191A (en) * | 2023-08-29 | 2023-09-29 | 中亿丰数字科技集团有限公司 | Intelligent construction engineering management platform based on EMPC mode |
CN117217676A (en) * | 2023-08-01 | 2023-12-12 | 山东黄河河务局工程建设中心 | Intelligent management system and method for engineering construction project |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2808449A1 (en) * | 2011-09-11 | 2013-03-11 | Element Industrial Solutions Inc. | Method and system for managing construction projects |
CN107437154A (en) * | 2017-08-15 | 2017-12-05 | 安徽婧文科技有限公司 | Project management information processing system based on computer technology |
-
2018
- 2018-12-26 CN CN201811608179.3A patent/CN109784681A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2808449A1 (en) * | 2011-09-11 | 2013-03-11 | Element Industrial Solutions Inc. | Method and system for managing construction projects |
CN107437154A (en) * | 2017-08-15 | 2017-12-05 | 安徽婧文科技有限公司 | Project management information processing system based on computer technology |
Non-Patent Citations (6)
Title |
---|
全国注册咨询工程师(投资)职业资格考试用书编写组: "《工程咨询概论》", 30 November 2012, 哈尔滨工程大学出版社 * |
刘本良: "工程项目投资管理和信息化研究", 《中国优秀硕士学位论文全文数据库 信息科技辑》 * |
宋伟香: "《工程项目管理》", 30 June 2015, 西安交通大学出版社 * |
宋志利: "电力工程工程项目管理信息***的设计与实现", 《中国优秀硕士学位论文全文数据库 信息科技辑》 * |
赵豪迈: "《数字档案集中管理研究》", 30 June 2016, 陕西师范大学出版社 * |
马利: "《中医药卫生经济学》", 31 August 2018, 中国中医药出版社 * |
Cited By (66)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109858751A (en) * | 2018-12-26 | 2019-06-07 | 中国大唐集团科学技术研究院有限公司 | Power engineering Evaluating Projects System |
CN110232288A (en) * | 2019-06-25 | 2019-09-13 | 重庆市地理信息中心 | Geographic information data complex encryption system |
CN110503386A (en) * | 2019-07-23 | 2019-11-26 | 国网河北能源技术服务有限公司 | A kind of data processing system for market-oriented project |
CN110705837A (en) * | 2019-09-11 | 2020-01-17 | 中国三峡建设管理有限公司 | Visual engineering construction management system and construction method thereof |
CN110599072A (en) * | 2019-10-10 | 2019-12-20 | 贵州百胜工程建设咨询有限公司 | BIM-based investment cost control method |
CN110991985A (en) * | 2019-11-11 | 2020-04-10 | 国网浙江武义县供电有限公司 | Project progress data processing method |
CN110910092A (en) * | 2019-11-21 | 2020-03-24 | 四川高路交通信息工程有限公司 | Highway construction information management platform |
CN110991990A (en) * | 2019-11-25 | 2020-04-10 | 四川华通建设工程造价管理有限责任公司 | Engineering project cost management system |
CN111061789A (en) * | 2019-12-10 | 2020-04-24 | 国家电网有限公司 | Smart power grids capital construction information management system |
CN111738538A (en) * | 2020-01-06 | 2020-10-02 | 业达建设管理有限公司 | Engineering project management system, management method, APP and storage medium |
CN111260327A (en) * | 2020-01-16 | 2020-06-09 | 深圳市艾泰克工程咨询监理有限公司 | Project construction cooperation management and control platform based on cloud service |
CN111274774A (en) * | 2020-01-19 | 2020-06-12 | 叶志 | Industrial building engineering full-process automatic management system |
CN111191965A (en) * | 2020-02-10 | 2020-05-22 | 重庆图强工程技术咨询有限公司 | Overall process engineering consultation service evaluation system |
CN111367939A (en) * | 2020-03-04 | 2020-07-03 | 昆明海巍科技有限公司 | System and method for compiling and managing highway engineering project account and computer |
CN111367939B (en) * | 2020-03-04 | 2023-08-22 | 昆明海巍科技有限公司 | Highway engineering project account compiling and managing system, method and computer |
CN111429007A (en) * | 2020-03-25 | 2020-07-17 | 陕西合友网络科技有限公司 | Building project supervision system and supervision method |
CN111553664A (en) * | 2020-05-11 | 2020-08-18 | 重庆金美通信有限责任公司 | Method for realizing intelligent management of design and production of communication equipment based on 5G technology |
CN111311206B (en) * | 2020-05-11 | 2020-09-18 | 温州开晨科技有限公司 | Construction project ternary space relationship construction method, system and medium |
CN111311206A (en) * | 2020-05-11 | 2020-06-19 | 温州开晨科技有限公司 | Construction project ternary space relationship construction method, system and medium |
CN111553664B (en) * | 2020-05-11 | 2022-10-14 | 重庆金美通信有限责任公司 | System for realizing intelligent management of communication equipment design and production based on 5G technology |
CN111553643A (en) * | 2020-05-18 | 2020-08-18 | 国网河北省电力有限公司物资分公司 | Material purchasing plan and supply chain management system |
CN111767247A (en) * | 2020-06-28 | 2020-10-13 | 杭州远大档案技术有限公司 | File specification and synchronous forming control platform for real-time supervision of engineering data |
CN111813745A (en) * | 2020-07-27 | 2020-10-23 | 中交路桥北方工程有限公司 | System, device and method for civil construction technology and standard query |
CN111813745B (en) * | 2020-07-27 | 2024-06-04 | 中交路桥建设有限公司 | System, device and method for inquiring civil engineering technology and standard |
CN111898280A (en) * | 2020-08-12 | 2020-11-06 | 于思平 | Engineering quantity calculation system and method |
CN112000724A (en) * | 2020-08-27 | 2020-11-27 | 四川公路桥梁建设集团有限公司 | Highway engineering collaborative computation amount information management system based on custom formula |
CN112001680A (en) * | 2020-08-27 | 2020-11-27 | 四川公路桥梁建设集团有限公司 | BIM-based highway engineering management system |
CN112085481A (en) * | 2020-09-22 | 2020-12-15 | 国网山东省电力公司烟台供电公司 | Whole-process tracking system for electric power engineering project management |
CN112184068A (en) * | 2020-10-27 | 2021-01-05 | 陕西交建云数据科技有限公司 | ERP-based road engineering project information cooperation method |
CN112184068B (en) * | 2020-10-27 | 2024-06-11 | 陕西交建云数据科技有限公司 | Highway engineering project information collaboration method based on ERP |
CN112561240A (en) * | 2020-11-25 | 2021-03-26 | 青岛国信建设投资有限公司 | Construction project contractor performance credit evaluation method and system |
CN113592414A (en) * | 2020-12-04 | 2021-11-02 | 上海汇招信息技术有限公司 | File authority control method |
CN112508417A (en) * | 2020-12-11 | 2021-03-16 | 民航中南机场设计研究院(广州)有限公司 | Civil aviation professional engineering general contract project management system based on BIM technology |
CN112734563A (en) * | 2021-01-11 | 2021-04-30 | 上海瀚之友信息技术服务有限公司 | Data management method and system based on fund flow |
CN112785271A (en) * | 2021-01-26 | 2021-05-11 | 宝钢工程技术集团有限公司 | Method for managing cash flow of engineering project in full cycle |
CN112785271B (en) * | 2021-01-26 | 2023-01-31 | 宝钢工程技术集团有限公司 | Method for managing cash flow of engineering project in full cycle |
CN112862341A (en) * | 2021-02-25 | 2021-05-28 | 中铁一局集团有限公司 | Project cost management system |
CN113095631A (en) * | 2021-03-22 | 2021-07-09 | 同望科技股份有限公司 | Engineering enterprise group basic data control platform based on componentization |
CN113033172A (en) * | 2021-04-01 | 2021-06-25 | 国网江苏省电力有限公司南通供电分公司 | Construction cost calculating and comparing system based on digital audit |
CN113112233A (en) * | 2021-04-16 | 2021-07-13 | 西安热工研究院有限公司 | BIM-based intelligent management method and platform for full life cycle of wind power project |
CN113220634A (en) * | 2021-05-08 | 2021-08-06 | 河南固川市政园林工程有限公司 | Information management device and electronic equipment of engineering visa file |
CN113435687A (en) * | 2021-05-12 | 2021-09-24 | 中核工程咨询有限公司 | Nuclear power supervision analysis system based on big data |
CN113240403A (en) * | 2021-06-10 | 2021-08-10 | 周明升 | Engineering construction project management system and method based on multi-source data |
CN113435743B (en) * | 2021-06-25 | 2023-09-01 | 北方实验室(沈阳)股份有限公司 | Informationized engineering whole-process data resource sharing system |
CN113435743A (en) * | 2021-06-25 | 2021-09-24 | 北方实验室(沈阳)股份有限公司 | Information-based engineering overall process data resource sharing system |
CN113450083A (en) * | 2021-07-12 | 2021-09-28 | 华航环境发展有限公司 | Construction project management system |
CN113743716A (en) * | 2021-07-26 | 2021-12-03 | 南方电网深圳数字电网研究院有限公司 | Project investment assessment method, system and storage medium |
CN113656505A (en) * | 2021-08-24 | 2021-11-16 | 生特瑞(上海)工程顾问股份有限公司 | Digitalization of distributed project management system and method for synchronizing data thereof |
CN113656505B (en) * | 2021-08-24 | 2024-05-28 | 生特瑞(上海)工程顾问股份有限公司 | Digitization of distributed project management system and method for synchronizing data thereof |
CN113743911A (en) * | 2021-09-16 | 2021-12-03 | 中国电建集团成都勘测设计研究院有限公司 | Project total contract project cost management method based on information system |
CN114004603A (en) * | 2021-11-16 | 2022-02-01 | 南方电网能源发展研究院有限责任公司 | Automatic statistical method and device for fixed asset investment and computer equipment |
CN114049103A (en) * | 2022-01-11 | 2022-02-15 | 国网北京市电力公司 | Power grid infrastructure project management and control method, system, equipment and medium |
CN114792226A (en) * | 2022-04-13 | 2022-07-26 | 刘博� | Electronic standing book management method and system for project material review |
CN115147083A (en) * | 2022-07-15 | 2022-10-04 | 国网四川省电力公司经济技术研究院 | Power transmission and transformation project overall-process cost evaluation system with information level interactive management |
CN115249192A (en) * | 2022-07-19 | 2022-10-28 | 广东省投资和信用中心(广东省发展和改革事务中心) | Investment project management system, method and equipment |
CN115114604A (en) * | 2022-07-26 | 2022-09-27 | 如皋市规划建筑设计院有限公司 | Internet-based building design dynamic process management system |
CN116258467A (en) * | 2023-05-16 | 2023-06-13 | 济南荣耀合创电力科技有限公司 | Electric power construction management and control system |
CN116258467B (en) * | 2023-05-16 | 2023-08-18 | 济南荣耀合创电力科技有限公司 | Electric power construction management and control system |
CN116452158B (en) * | 2023-06-19 | 2023-10-13 | 博思数采科技发展有限公司 | Method, device, equipment and medium for managing index of random extraction of suppliers |
CN116452158A (en) * | 2023-06-19 | 2023-07-18 | 博思数采科技发展有限公司 | Method, device, equipment and medium for managing index of random extraction of suppliers |
CN116663848A (en) * | 2023-06-28 | 2023-08-29 | 雅安紫木工程咨询有限公司 | Multi-terminal full-flow engineering resource interaction management system and method |
CN117217676A (en) * | 2023-08-01 | 2023-12-12 | 山东黄河河务局工程建设中心 | Intelligent management system and method for engineering construction project |
CN116797105A (en) * | 2023-08-22 | 2023-09-22 | 中建西南咨询顾问有限公司 | Price index statistical method and system based on engineering standardized coding |
CN116797105B (en) * | 2023-08-22 | 2023-10-24 | 中建西南咨询顾问有限公司 | Price index statistical method and system based on engineering standardized coding |
CN116823191A (en) * | 2023-08-29 | 2023-09-29 | 中亿丰数字科技集团有限公司 | Intelligent construction engineering management platform based on EMPC mode |
CN116823191B (en) * | 2023-08-29 | 2023-12-01 | 中亿丰数字科技集团有限公司 | Intelligent construction engineering management platform based on EMPC mode |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109784681A (en) | Power engineering project investment management system | |
Shojaei | Exploring applications of blockchain technology in the construction industry | |
CN109816328A (en) | Power engineering Project Technical economic information system | |
CN103136626A (en) | On-line management method for engineering project | |
JP2019057160A (en) | Account managing apparatus, account managing method, and account managing program | |
Addy et al. | Data-driven sustainability: How fintech innovations are supporting green finance | |
Nezhyva et al. | Digitalization of audit in the conditions of the COVID-19 | |
CN110070334A (en) | The information processing method of project management and application | |
Strüker et al. | Blockchain in the energy sector | |
Van Chuong et al. | Robotic process automation and opportunities for Vietnamese market | |
Lee et al. | Stochastic project financing analysis system for construction | |
JP2016110610A (en) | Management support program | |
Clerkin et al. | Integrating AIS and contemporary technologies | |
Chen et al. | Knowing what is going on—a smart contract for modular construction | |
RU83639U1 (en) | INNOVATIVE ACTIVITY SYSTEM | |
Stoykova et al. | Intelligent Robotic Process Automation for Small and Medium-sized Enterprises | |
Anderson et al. | Optimal management of wind energy with storage: Structural implications for policy and market design | |
Misra et al. | Role of blockchain technology integration for green bonds issuance with sustainability aspect | |
Verbivska et al. | Taxation strategy for small businesses in the context of digitalization | |
Sullivan et al. | Comparative analysis of three proposed federal renewable electricity standards | |
Rooholelm et al. | Project Penalty Cost Management, Based on Activity Sensitivity Analysis (BASA) | |
WO2013091131A1 (en) | Knowledge capital quantization long-acting excitation mechanism management system | |
Olugbemi | Examining the legal compatibility and regulation of distributed ledger technology in facilitating decentralized energy in Nigeria | |
Halas | Blockchain technology as a part of distribution system operators’ platform business model | |
Tossavainen | Project procurement’s requirements for enterprise recourse planning system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190521 |