CN106638269B - A kind of interim arch bridge towards city race traffic jam issue - Google Patents

A kind of interim arch bridge towards city race traffic jam issue Download PDF

Info

Publication number
CN106638269B
CN106638269B CN201710076358.6A CN201710076358A CN106638269B CN 106638269 B CN106638269 B CN 106638269B CN 201710076358 A CN201710076358 A CN 201710076358A CN 106638269 B CN106638269 B CN 106638269B
Authority
CN
China
Prior art keywords
bridge
clamp plate
floor
bridge floor
interim arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710076358.6A
Other languages
Chinese (zh)
Other versions
CN106638269A (en
Inventor
郭永安
佘昊
白易初
李睿超
陈子霏
朱忆萌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Post and Telecommunication University
Original Assignee
Nanjing Post and Telecommunication University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Post and Telecommunication University filed Critical Nanjing Post and Telecommunication University
Priority to CN201710076358.6A priority Critical patent/CN106638269B/en
Publication of CN106638269A publication Critical patent/CN106638269A/en
Application granted granted Critical
Publication of CN106638269B publication Critical patent/CN106638269B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • E01D15/133Portable or sectional bridges built-up from readily separable standardised sections or elements, e.g. Bailey bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention belongs to bridge construction technology field, there is provided a kind of to be used for the interim arch bridge towards match traffic jam issue, including bridge floor, bridge railings, bridge pier and padlock;The pontic of the interim arch bridge is formed by two section bridge floor splicing fixations, and one end of the bridge floor is placed on ground, and the other end is connected to each other with another bridge floor, and two bridge floors are fixedly connected in joint with padlock;The bridge railings is fixed on the both sides of bridge floor, and can be folded to bridge floor, and the bridge floor can also be folded down storage;The padlock includes upper clamp plate, lower clamp plate and fixing bolt, in use, upper clamp plate and lower clamp plate clamp the joint of two bridge floors, is fixed together by fixing bolt;The bridge pier is retractable structure, positioned at the lower section of two bridge floor joints, supports pontic;The bridge floor is additionally provided with pressure detecting alarm in the one end for being placed on ground.The interim arch bridge is realized is normally carried out match match on the premise of daily traffic is not influenced.

Description

A kind of interim arch bridge towards city race traffic jam issue
Technical field
The invention belongs to bridge construction technology field, and in particular to one kind solves the traffic congestion caused by city race and asks The temporary bridge of topic.
Background technology
Bridge, refers generally to be erected in rivers,lakes and seas, the structures for making traffic etc. smoothly to pass through.It is modern to adapt to The transportation industry of high speed development, bridge be also extended to across mountain stream, unfavorable geology or meet other traffic needs and set up make Current more easily building.
Most of bridge usually seen at present is more bulky concrete bridge, these bridge structures are firm, load-bearing is big, It is widely used across in river, valley, and city intersection system.But sometimes, for example, temporary road Maintenance, road cleaning, road take etc. temporarily, in order to alleviate traffic problems, it is necessary to the quick and convenient structure that frugally builds a bridge, And after the road is clear, these bridges will easily be removed and can reused.In this case, temporary bridge compares concrete bridge With significant advantage.
Nowadays, as people increase the enthusiasm of sports, it is more and more to hold the situation of athletic competition in city, For example, city marathon, city bicycles match, footrace grand prix etc., these contests generally take up a large amount of urban roads, easily make Into traffic jam issue, influence the trip of people.It is to solve the problems, such as this optimal method to build temporary bridge.Although now Through there are a variety of temporary bridges, still, the temporary bridge mostly to pass through for pedestrian or non-motor vehicle, vehicle pass-through still has very much It is difficult.
The present invention provides a kind of interim arch bridge, its install convenient, convenient disassembly, and stabilized structure, uniform force, holds Gravity is big.
The content of the invention:
In order to solve the above technical problem, the present invention provides a kind of interim arch towards city race traffic jam issue Bridge, the arch bridge can realize the smoothly current of vehicle at the same time.The arch bridge is using all motor vehicle users as service object, by taking Build interim arch bridge and solve traffic problems, and pressure sensor is housed, can learn the pressure suffered by interim arch bridge, prevent interim arch bridge It is impaired, so as to avoid user from expending the excessive time on highway.The multi-part that this product is related to arch bridge is decomposed with building, arch bridge Design structure.The technical method of the present invention is as described below.
The present invention provides a kind of interim arch bridge towards city race traffic jam issue, and the interim arch bridge includes bridge Face, bridge railings, bridge pier and padlock.The pontic of the interim arch bridge is formed by two section bridge floor splicing fixations, one end of the bridge floor Ground is placed on, the other end is connected to each other with another bridge floor, and two bridge floors are fixedly connected in joint with padlock.The bridge railings The both sides of bridge floor are fixed on, and can be folded to bridge floor, the bridge floor can also be folded down storage.The padlock includes upper folder Plate, lower clamp plate and fixing bolt, in use, upper clamp plate and lower clamp plate clamp the joint of two bridge floors, pass through fixing bolt It is fixed together.The bridge pier is retractable structure, positioned at the lower section of two bridge floor joints, supports pontic.The bridge Face is additionally provided with pressure detecting alarm in the one end for being placed on ground.
Interim arch bridge of the present invention, across playing area road, can supply on the premise of not influencing playing area sportsman and passing through Passing through for vehicle, realizes while the athletic competition of host city, does not influence the unimpeded of traffic.Meanwhile pressure detecting is alarmed Device, can detect the pressure suffered by interim arch bridge, sends alarm signal when pressure exceedes the warning value of setting, forbids the car to enter It is interior, prevent Damage of arch, and then ensure the safety of human life, and prolong the service life.
Each component of the interim arch bridge uses steel construction, to ensure having enough load-bearing capacities.
In order to facilitate the splicing of bridge floor, the joint of two bridge floors of the interim arch bridge can set groove-convex block docking Structure, pushes in convex block alignment indentation in splicing, realizes that the splicing of bridge floor, then installing tache lock are fixed.Groove-convex block docking Structure can make the splicing of bridge floor closer, and the conduction of power easy to implement, can make full use of the characteristic of arch dispersion force, make Obtain the load-bearing capacity that interim arch bridge obtains bigger.
The joint of two bridge floors of the interim arch bridge can also be fixed by bolts docking structure, two bridge floor docking End, have can partly overlapping jigsaw, jigsaw is equipped with corresponding bolt hole, and installation bolt is the docking of achievable two bridge floors.
The upper clamp plate of the padlock and the both ends of lower clamp plate are equipped with bolt hole, for installing fixing bolt.In upper clamp plate and After lower clamp plate is installed to above and below bridge floor joint, by fixing bolt through upper clamp plate and the bolt hole of lower clamp plate, and Screwing bolts, can be achieved with the fixed function of padlock.Generation of two bridge floors or so or the front and rear changing of the relative positions in order to prevent, can be by upper folder Plate and lower clamp plate set concavity, and spill length is wide quite with bridge, for accommodating bridge floor joint, prevents from occurring between two bridge floors The left and right changing of the relative positions;Block-groove structure can also be set on bridge floor and the upper clamp plate contacted with bridge floor and lower clamp plate correspondence position, After padlock clamps, bridge floor will not be slided with upper clamp plate and lower clamp plate, prevent the changing of the relative positions before and after generation between two bridge floors.
The bridge pier includes multiple hollow metal cylinders being nested together and strip-shaped bracket, hollow metal cylinder Both ends are provided with multigroup jack corresponding two-by-two, and every group of jack does not interfere with each other in the horizontal direction, and the strip-shaped bracket can insert Enter jack and pass through hollow metal cylinder.Each component of the bridge pier is stored and transported in a manner of intussusception when not in use; Assembling is in use, metal cylinder is nested together according to size headtotail and is directed at corresponding jack, the metal of diameter maximum Cylinder is placed on bottom, strip-shaped bracket insertion jack then is passed through metal cylinder, so that by connected head-to-tail two Metal cylinder fixes support.After all connected head-to-tail metal cylinder installations, the assembling of bridge pier is completed.
In actual use, the interim arch bridge is by truck transport to the place for needing setting temporary bridge.Will using crane The bridge floor expansion folded up, one end of bridge floor is fixed on ground, controls its other end to be docked, during docking under every piece of pontic Fang Peiyou piece hydraulic telescopic rod supports load-carrying, which is integrally fixed on truck transporting bridge.Next will The bridge railings of folding is opened.Then portable bridge pier is assembled with bridge floor.Finally two bridge floors are consolidated using padlock It is fixed.After interim arch bridge assembling, truck leaves, and arch bridge can be tested and be worked.
The present invention has the advantages that:
1st, the interim arch bridge structure is simple, easily assembling, convenient transportation, can fast erecting complete, relieve traffic congestion in time; 2nd, arch bridge has domes, and firm in structure, bearing capacity is big, and is equipped with pressure detecting alarm, avoids overweight vehicle by making Into bridge damage;3rd, there was only a bridge pier, do not interfere with the current of track athlete and staff and vehicle.
Brief description of the drawings
Schematic diagram when Fig. 1 is two bridge floor docking in the embodiment of the present invention;
Fig. 2 is the schematic diagram used in the embodiment of the present invention after interim arch bridge assembling completely;
Fig. 3 is the structure and scheme of installation of the padlock in the embodiment of the present invention;
Fig. 4 is storage and the scheme of installation of the bridge pier in the embodiment of the present invention;
Fig. 5 is the flow chart that interim arch bridge is installed in the embodiment of the present invention;
Fig. 6 is the docking structure schematic diagram of two bridge floors in the embodiment of the present invention.
Wherein, 1- bridge floors, 11- pressure detecting alarms, 2- bridge railings, 3- bridge piers, 31- metal cylinders, 32- strip branch Frame, 33- jacks, 4- padlocks, 41- upper clamp plates, 42- lower clamp plates, 43- fixing bolts.
Embodiment
Illustrate technical scheme with reference to specific embodiments and the drawings.
Embodiment 1
As depicted in figs. 1 and 2, a kind of interim arch bridge towards city race traffic jam issue, the interim arch bridge bag Include bridge floor 1, bridge railings 2, bridge pier 3 and padlock 4.The pontic of the interim arch bridge by two section bridge floors 1 splice it is fixed formed, the bridge The one end in face 1 is placed on ground, and the other end is connected to each other with another bridge floor, and two bridge floors are fixedly connected in joint padlock 4. The bridge railings 2 is fixed on the both sides of bridge floor 1, and can be folded to bridge floor 1, and the bridge floor 1 can also be folded down storage.Institute Stating padlock 4 includes upper clamp plate 41, lower clamp plate 42 and fixing bolt 43, in use, upper clamp plate 41 and lower clamp plate 42 are by two bridge floors Joint clamp, be fixed together by fixing bolt 43.The bridge pier 3 is retractable structure, positioned at two bridge floors 1 The lower section of joint, supports pontic.The bridge floor 1 is additionally provided with pressure detecting alarm 11 in the one end for being placed on ground.
In actual use, the interim arch bridge is by truck transport to the place for needing setting temporary bridge.Will using crane The bridge floor 1 folded up is unfolded, and then controls it to be docked.Next the bridge railings 2 of folding is opened.Then by movable type Bridge pier 3 is assembled with bridge floor 1.Finally two bridge floors 1 are fixed using padlock 4.So far interim arch bridge is completed. Its installation procedure is as shown in Figure 5.
The joint of two bridge floors 1 of the interim arch bridge is fixed by bolts docking structure, and two bridge floor butt ends, have Can partly overlapping jigsaw, jigsaw is equipped with corresponding bolt hole, and installation bolt is that the docking of two bridge floors, such as Fig. 6 can be achieved It is shown.
As shown in figure 4, the bridge pier 3 includes multiple hollow metal cylinders 31 being nested together and strip-shaped bracket 32, The both ends of hollow metal cylinder 31 are provided with multigroup jack 33 corresponding two-by-two, and every group of jack 33 be not mutual in the horizontal direction Interference, the strip-shaped bracket 32 can be inserted into jack 33 and pass through hollow metal cylinder 31.The each group of the bridge pier 3 when not in use Part is stored and transported in a manner of intussusception;Assembling in use, metal cylinder 31 be nested together according to size headtotail and Corresponding jack 33 is directed at, the metal cylinder 31 of diameter maximum is placed on bottom, strip-shaped bracket 32 then is inserted into jack 33 pass through metal cylinder 31, so that connected head-to-tail two metal cylinders 31 are fixed support.Will be all connected head-to-tail After metal cylinder 31 is installed, the assembling of bridge pier 3 is completed.
As shown in figure 3, the upper clamp plate 41 of the padlock 4 and the both ends of lower clamp plate 42 are equipped with bolt hole, for installing fixation Bolt 43.After upper clamp plate 41 and lower clamp plate 42 are installed to above and below bridge floor joint, fixing bolt 43 is passed through upper The bolt hole of clamping plate 41 and lower clamp plate 42, and screwing bolts 43, can be achieved with the fixed function of padlock 4.Two bridges in order to prevent Face 1 is slided, and upper clamp plate 41 and lower clamp plate 42 is set concavity, spill length is wide quite with bridge, for accommodating bridge floor 1 Joint, prevents from sliding between two bridge floors 1.
Each component of the interim arch bridge uses steel construction, to ensure having enough load-bearing capacities.
Above-mentioned interim arch bridge assumed above the road of playing area, opposite side is crossed from playing area side of leading the way, for fortune below bridge Mobilization, race officials etc. are current, for the single vehicle pass-through of urban district common vehicle above bridge.It can be set up at same crossing More interim arch bridges, to facilitate vehicle two way.The interim arch bridge is realized while the athletic competition of host city, not shadow Ring the unimpeded of traffic.Meanwhile pressure detecting alarm 11, the pressure suffered by interim arch bridge is can detect, exceedes setting in pressure Alarm signal is sent during warning value, forbids the car to enter interior, prevents Damage of arch, and then is ensured the safety of human life, and extends and uses the longevity Life.

Claims (9)

1. a kind of interim arch bridge towards city race traffic jam issue, the interim arch bridge includes bridge floor, bridge railings, bridge pier And padlock;The pontic of the interim arch bridge is formed by two section bridge floor splicing fixations, and one end of the bridge floor is placed on ground, another End is connected to each other with another bridge floor, and two bridge floors are fixedly connected in joint with padlock;The bridge railings is fixed on the two of bridge floor Side, and can be folded to bridge floor, the bridge floor can also be folded down storage;The padlock includes upper clamp plate, lower clamp plate and consolidates Determine bolt, in use, upper clamp plate and lower clamp plate clamp the joint of two bridge floors, one is pressed abd fixed on by fixing bolt Rise;The bridge pier is retractable structure, positioned at the lower section of two bridge floor joints, supports pontic;The bridge floor is being placed on ground The one end in face is additionally provided with pressure detecting alarm.
2. interim arch bridge according to claim 1, it is characterised in that:Each component of the interim arch bridge uses steel construction.
3. interim arch bridge according to claim 1, it is characterised in that:The joint of two bridge floors of the interim arch bridge is Groove-convex block docking structure or bolt docking structure.
4. interim arch bridge according to claim 1, it is characterised in that:The upper clamp plate of the padlock and the both ends of lower clamp plate are set There is bolt hole, for installing fixing bolt.
5. interim arch bridge according to claim 1, it is characterised in that:The padlock upper clamp plate and lower clamp plate are arranged to recessed Shape, spill length is wide quite with bridge, for accommodating bridge floor joint.
6. interim arch bridge according to claim 1, it is characterised in that:In bridge floor and the upper clamp plate contacted with bridge floor and lower folder Block-groove structure is set on plate correspondence position.
7. interim arch bridge according to claim 1, it is characterised in that:The pressure detecting alarm, can detect interim arch Pressure suffered by bridge, sends alarm signal when pressure exceedes the warning value of setting, prevents Damage of arch.
8. interim arch bridge according to claim 1, it is characterised in that:The bridge pier include it is multiple be nested together it is hollow Metal cylinder and strip-shaped bracket, the both ends of hollow metal cylinder are provided with multigroup jack corresponding two-by-two, and every group of jack exists Do not interfered with each other in horizontal direction, the strip-shaped bracket can be inserted into jack and pass through hollow metal cylinder.
9. interim arch bridge according to claim 8, it is characterised in that:Each component of the bridge pier is with intussusception when not in use Mode is stored and transported;In assembling in use, metal cylinder is nested together according to size headtotail and is aligned corresponding slotting Hole, the metal cylinder of diameter maximum are placed on bottom, and strip-shaped bracket insertion jack then is passed through metal cylinder, so that Connected head-to-tail two metal cylinders are fixed and are supported;After all connected head-to-tail metal cylinder installations, bridge pier is completed Assembling.
CN201710076358.6A 2017-02-13 2017-02-13 A kind of interim arch bridge towards city race traffic jam issue Active CN106638269B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710076358.6A CN106638269B (en) 2017-02-13 2017-02-13 A kind of interim arch bridge towards city race traffic jam issue

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710076358.6A CN106638269B (en) 2017-02-13 2017-02-13 A kind of interim arch bridge towards city race traffic jam issue

Publications (2)

Publication Number Publication Date
CN106638269A CN106638269A (en) 2017-05-10
CN106638269B true CN106638269B (en) 2018-05-04

Family

ID=58845714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710076358.6A Active CN106638269B (en) 2017-02-13 2017-02-13 A kind of interim arch bridge towards city race traffic jam issue

Country Status (1)

Country Link
CN (1) CN106638269B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107489077B (en) * 2017-08-15 2020-08-21 台州市荣创电子有限公司 Man-vehicle integrated time-sharing overpass
CN112431110B (en) * 2020-10-16 2022-03-11 杨同伟 Temporary viaduct for road repair road section passing

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1072979A (en) * 1992-12-04 1993-06-09 乔海兵 Movable detachable highway cross-over bridge
CN2258193Y (en) * 1996-12-03 1997-07-23 乌日 Combined vehicle type overpass
JPH1088518A (en) * 1996-09-13 1998-04-07 Yasuhiro Niizawa High level part of overbridge and over-road bridge
KR20060061030A (en) * 2004-12-01 2006-06-07 주식회사 선영 An curving arch-bridge
CN202131562U (en) * 2011-07-11 2012-02-01 王金 Vehicle-mounted building block emergency overpass
CN103758024A (en) * 2014-01-15 2014-04-30 云南昆钢钢结构有限公司 Quick assembling and disassembling steel-structure pedestrian overpass
CN204401393U (en) * 2014-12-12 2015-06-17 刘华强 Portable dismantled and assembled road interim road and bridge
CN206521686U (en) * 2017-02-13 2017-09-26 南京邮电大学 A kind of interim arch bridge towards city race traffic jam issue

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1072979A (en) * 1992-12-04 1993-06-09 乔海兵 Movable detachable highway cross-over bridge
JPH1088518A (en) * 1996-09-13 1998-04-07 Yasuhiro Niizawa High level part of overbridge and over-road bridge
CN2258193Y (en) * 1996-12-03 1997-07-23 乌日 Combined vehicle type overpass
KR20060061030A (en) * 2004-12-01 2006-06-07 주식회사 선영 An curving arch-bridge
CN202131562U (en) * 2011-07-11 2012-02-01 王金 Vehicle-mounted building block emergency overpass
CN103758024A (en) * 2014-01-15 2014-04-30 云南昆钢钢结构有限公司 Quick assembling and disassembling steel-structure pedestrian overpass
CN204401393U (en) * 2014-12-12 2015-06-17 刘华强 Portable dismantled and assembled road interim road and bridge
CN206521686U (en) * 2017-02-13 2017-09-26 南京邮电大学 A kind of interim arch bridge towards city race traffic jam issue

Also Published As

Publication number Publication date
CN106638269A (en) 2017-05-10

Similar Documents

Publication Publication Date Title
CN101078198B (en) Steel box beam erection method for self-anchored suspension bridge
CN106351132B (en) A kind of bridge using corrugated sheet steel connector spells wide construction and its construction method
CN106638269B (en) A kind of interim arch bridge towards city race traffic jam issue
CN104018426B (en) A kind of steel truss girder installation method
CN206521686U (en) A kind of interim arch bridge towards city race traffic jam issue
CN107956202B (en) Safe and stable crescent bridge and mounting process thereof
CN206298836U (en) A kind of bridge of use Z bar plate connector spells construction wide
CN108166377B (en) A kind of folding combined temporary bridge device
CN203684060U (en) Temporary steel-frame bridge
CN204551224U (en) Emergent shunting portable bridge
CN204570533U (en) The dumpable type isolated column of a kind of safety
CN104313993B (en) A kind of highway bridge and construction method thereof
CN205843552U (en) A kind of in rigid frame bridge across the system for monitoring displacement closing up incremental launching construction
CN206219998U (en) A kind of bridge of use corrugated sheet steel connector spells construction wide
CN102535507B (en) Combined tower base
CN111472256B (en) Foldable intelligent bridge
CN111794079B (en) Temporary bridge capable of passing through vehicles based on bridge construction
CN210219244U (en) Vibration detection sensor rack for building pillar
CN112411306A (en) Emergent hole ware of filling up of road that town road was used
CN210529489U (en) Bridge overhauls device
CN201351262Y (en) Light self-balancing assembly car platform bridge
CN2312243Y (en) Quick assemblage overcross bridge for highway
CN207047681U (en) Bridge assembly
CN105178188B (en) Triangular frame supporting formwork
CN212670254U (en) Reusable temporary bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Guo Yongan

Inventor after: She Hao

Inventor after: Bai Yichu

Inventor after: Li Ruichao

Inventor after: Chen Zifei

Inventor after: Zhu Yimeng

Inventor before: Cai Shuqi

Inventor before: Guo Yongan

Inventor before: She Hao

Inventor before: Bai Yichu

Inventor before: Zhu Hongbo

Inventor before: Yang Longxiang

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20170510

Assignee: Nanjing Chulian Information Technology Co.,Ltd.

Assignor: NANJING University OF POSTS AND TELECOMMUNICATIONS

Contract record no.: X2020980007042

Denomination of invention: A temporary arch bridge for traffic congestion in urban competition

Granted publication date: 20180504

License type: Common License

Record date: 20201023

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20170510

Assignee: Nanjing Shanyechu Agriculture and Forestry Technology Co.,Ltd.

Assignor: NANJING University OF POSTS AND TELECOMMUNICATIONS

Contract record no.: X2023980051072

Denomination of invention: A Temporary Arch Bridge for Urban Competition Traffic Congestion

Granted publication date: 20180504

License type: Common License

Record date: 20231209

EE01 Entry into force of recordation of patent licensing contract