CN206521686U CN201720127624.9U CN201720127624U CN206521686U CN 206521686 U CN206521686 U CN 206521686U CN 201720127624 U CN201720127624 U CN 201720127624U CN 206521686 U CN206521686 U CN 206521686U
Authority
CN
China
Prior art keywords
bridge
floor
interim
interim arch
bridge floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201720127624.9U
Other languages
Chinese (zh)
Inventor
蔡舒祺
郭永安
佘昊
白易初
朱洪波
杨龙祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Post and Telecommunication University
Nanjing University of Posts and Telecommunications
Original Assignee
Nanjing Post and Telecommunication University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Post and Telecommunication University filed Critical Nanjing Post and Telecommunication University
Priority to CN201720127624.9U priority Critical patent/CN206521686U/en
Application granted granted Critical
Publication of CN206521686U publication Critical patent/CN206521686U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model belongs to bridge construction technical field is used for the interim arch bridge towards match traffic jam issue, including bridge floor, bridge railings, bridge pier and padlock there is provided a kind of;The pontic of the interim arch bridge is formed by two section bridge floor splicing fixations, and one end of the bridge floor is placed on ground, and the other end is relative with another bridge floor to be connect, and two bridge floors are fixedly connected in joint with padlock;The bridge railings is fixed on the both sides of bridge floor, and can be folded to bridge floor, and the bridge floor can also be folded down storage;The padlock includes train wheel bridge, lower plate and fixing bolt, in use, train wheel bridge and lower plate clamp the joint of two bridge floors, is fixed together by fixing bolt;The bridge pier is Collapsible structure, positioned at the lower section of two bridge floor joints, supports pontic;The bridge floor is additionally provided with pressure detecting alarm in the one end for being placed on ground.The interim arch bridge is realized is normally carried out match match on the premise of daily traffic is not influenceed.

Description

A kind of interim arch bridge towards city race traffic jam issue
Technical field
The utility model belongs to bridge construction technical field, and in particular to a kind of traffic of solution caused by city race is gathered around The temporary bridge of stifled problem.
Background technology
Bridge, refers generally to be erected in rivers,lakes and seas, the structures for making traffic etc. smoothly to pass through.It is modern to adapt to The transportation industry of high speed development, bridge is also extended to across mountain stream, unfavorable geology or meets other traffic needs and erection makes Current more easily building.
Most of bridge generally seen at present is more bulky concrete bridge, and these bridge structures are firm, load-bearing big, It is widely used across in river, valley, and city intersection system.But, sometimes, for example, temporary road Maintenance, road cleaning, road take etc. temporarily, in order to alleviate traffic problems, it is necessary to the quick and convenient structure that frugally builds a bridge, And after the road is clear, these bridges will easily be removed and can reused.In this case, temporary bridge compares concrete bridge With significant advantage.
Nowadays, as people increase to the enthusiasm of sports, the situation that athletic competition is held in city is more and more, For example, city marathon, city bicycles match, footrace grand prix etc., these contests generally take up a large amount of urban roads, easily make Into traffic jam issue, influence people trip.It is the optimal method for solving this problem to build temporary bridge.Although now Through there are a variety of temporary bridges, still, mostly for pedestrian or the current temporary bridge of non-motor vehicle, vehicle pass-through still has a lot It is difficult.
The utility model provides a kind of interim arch bridge, its install convenient, convenient disassembly, and stabilized structure, stress are equal Even, bearing capacity is big.
The content of the invention:
In order to solve the above-mentioned technical problem, the utility model provides a kind of towards the interim of city race traffic jam issue Arch bridge, the arch bridge can realize the smoothly current of vehicle simultaneously.The arch bridge passes through using all motor vehicle users as service object Build interim arch bridge and solve traffic problems, and equipped with pressure sensor, the pressure suffered by interim arch bridge can be learnt, prevent interim arch Bridge is damaged, so as to avoid user from expending the excessive time on highway.The multi-part that this product is related to arch bridge is decomposed with building, arch bridge Design structure.Technical method of the present utility model is as described below.
The utility model provides a kind of interim arch bridge towards city race traffic jam issue, and the interim arch bridge includes Bridge floor, bridge railings, bridge pier and padlock.The pontic of the interim arch bridge is formed by two section bridge floor splicing fixations, and the one of the bridge floor End is placed on ground, and the other end is relative with another bridge floor to be connect, and two bridge floors are fixedly connected in joint with padlock.The bridge railing Bar is fixed on the both sides of bridge floor, and can be folded to bridge floor, and the bridge floor can also be folded down storage.The padlock includes upper Clamping plate, lower plate and fixing bolt, in use, train wheel bridge and lower plate clamp the joint of two bridge floors, pass through fixed spiral shell Bolt is fixed together.The bridge pier is Collapsible structure, positioned at the lower section of two bridge floor joints, supports pontic.It is described Bridge floor is additionally provided with pressure detecting alarm in the one end for being placed on ground.
Interim arch bridge described in the utility model can be on the premise of not influenceing playing area sportsman current, across playing area road Road, for the current of vehicle, realize while the athletic competition of host city, the unimpeded of traffic is not influenceed.Meanwhile, pressure detecting Alarm, can detect the pressure suffered by interim arch bridge, sends alarm signal when pressure exceedes the warning value of setting, forbids the car In entering, Damage of arch is prevented, and then is ensured the safety of human life, and is increased the service life.
Each component of the interim arch bridge uses steel construction, to ensure to have enough weight capacities.
Groove-projection docking can be set in the splicing of bridge floor for convenience, the joint of two bridge floors of the interim arch bridge Structure, pushes in projection alignment indentation in splicing, realizes that the splicing of bridge floor, then installing tache lock are fixed.Groove-projection docking Structure can make the splicing of bridge floor closer, and easily realize the conduction of power, can make full use of the characteristic of arch dispersion force, make Obtain interim arch bridge and obtain bigger weight capacity.
The joint of two bridge floors of the interim arch bridge can also fix docking structure, two bridge floor docking using bolt End, have can partly overlapping jigsaw, jigsaw be provided with corresponding bolt hole, installation bolt be can be achieved two bridge floors docking.
The train wheel bridge of the padlock and the two ends of lower plate are provided with bolt hole, for installing fixing bolt.In train wheel bridge and After lower plate is installed to above and below bridge floor joint, by fixing bolt through train wheel bridge and the bolt hole of lower plate, and Screwing bolts, can be achieved with the fixing function of padlock.Generation in order to prevent two bridge floors or so or the front and rear changing of the relative positions, can be by upper folder Plate and lower plate set concavity, and spill length is wide quite with bridge, for accommodating bridge floor joint, prevents generation between two bridge floors The left and right changing of the relative positions;Block-groove structure can also be set on bridge floor and the train wheel bridge and lower plate correspondence position that are contacted with bridge floor, After padlock is clamped, bridge floor will not be slided with train wheel bridge and lower plate, prevent the front and rear changing of the relative positions between two bridge floors.
The bridge pier includes multiple hollow metal cylinders being nested together and strip-shaped bracket, hollow metal cylinder Two ends are provided with multigroup jack corresponding two-by-two, and every group of jack is not interfered with each other in the horizontal direction, and the strip-shaped bracket can be inserted Enter jack and pass through hollow metal cylinder.Each component of the bridge pier is deposited and transported in the way of intussusception when not in use; Assembling is in use, metal cylinder is nested together according to size headtotail and is directed at corresponding jack, the maximum metal of diameter Cylinder is placed on bottom, strip-shaped bracket insertion jack then is passed through into metal cylinder, so that by connected head-to-tail two Metal cylinder fixes support.After all connected head-to-tail metal cylinders are installed, the assembling of bridge pier is completed.
In actual use, the interim arch bridge by truck transport to need set temporary bridge place.Will using crane The bridge floor expansion folded up, one end of bridge floor is fixed on ground, controls its other end to be docked, during docking under every piece of pontic Fang Peiyou piece hydraulically extensible bar supports load-carrying, and the hydraulically extensible bar is integrally fixed on truck transporting bridge.Next will The bridge railings of folding is opened.Then portable bridge pier and bridge floor are assembled.Finally two bridge floors are consolidated using padlock It is fixed.After interim arch bridge assembling is finished, truck leaves, and arch bridge can be tested and be worked.
The utility model has the advantages that:
1st, the interim arch bridge structure is simple, easily assembling, convenient transportation, can fast erecting complete, relieve traffic congestion in time; 2nd, arch bridge has domes, firm in structure, and bearing capacity is big, and provided with pressure detecting alarm, it is to avoid overweight vehicle is by making Into bridge damage;3rd, only one of which bridge pier, does not interfere with the current of track athlete and staff and vehicle.
Brief description of the drawings
Schematic diagram when Fig. 1 is two bridge floors docking in the utility model embodiment;
Fig. 2 is the schematic diagram used after interim arch bridge assembling is complete in the utility model embodiment;
Fig. 3 is the structure and scheme of installation of the padlock in the utility model embodiment;
Fig. 4 is storage and the scheme of installation of the bridge pier in the utility model embodiment;
Fig. 5 is the flow chart that interim arch bridge is installed in the utility model embodiment;
Fig. 6 is the docking structure schematic diagram of two bridge floors in the utility model embodiment.
Wherein, 1- bridge floors, 11- pressure detecting alarms, 2- bridge railings, 3- bridge piers, 31- metal cylinders, 32- strip branch Frame, 33- jacks, 4- padlocks, 41- train wheel bridges, 42- lower plates, 43- fixing bolts.
Embodiment
Illustrate the technical solution of the utility model with reference to specific embodiments and the drawings.
Embodiment 1
As depicted in figs. 1 and 2, a kind of interim arch bridge towards city race traffic jam issue, the interim arch bridge bag Include bridge floor 1, bridge railings 2, bridge pier 3 and padlock 4.The pontic of the interim arch bridge by two section bridge floors 1 splice it is fixed formed, the bridge The one end in face 1 is placed on ground, and the other end is relative with another bridge floor to be connect, and two bridge floors are fixedly connected in joint padlock 4. The bridge railings 2 is fixed on the both sides of bridge floor 1, and can be folded to bridge floor 1, and the bridge floor 1 can also be folded down storage.Institute Padlock 4 is stated including train wheel bridge 41, lower plate 42 and fixing bolt 43, in use, train wheel bridge 41 and lower plate 42 are by two bridge floors Joint clamp, be fixed together by fixing bolt 43.The bridge pier 3 is Collapsible structure, positioned at two bridge floors 1 The lower section of joint, supports pontic.The bridge floor 1 is additionally provided with pressure detecting alarm 11 in the one end for being placed on ground.
In actual use, the interim arch bridge by truck transport to need set temporary bridge place.Will using crane The bridge floor 1 folded up deploys, and then controls it to be docked.Next the bridge railings 2 of folding is opened.Then by movable type Bridge pier 3 is assembled with bridge floor 1.Finally two bridge floors 1 are fixed using padlock 4.So far interim arch bridge is completed. Its installation procedure is as shown in Figure 5.
The joint of two bridge floors 1 of the interim arch bridge fixes docking structure using bolt, and two bridge floor butt ends have Can partly overlapping jigsaw, jigsaw be provided with corresponding bolt hole, installation bolt be can be achieved two bridge floors docking, such as Fig. 6 It is shown.
As shown in figure 4, the bridge pier 3 includes multiple hollow metal cylinders 31 being nested together and strip-shaped bracket 32, The two ends of hollow metal cylinder 31 are provided with multigroup jack 33 corresponding two-by-two, and every group of jack 33 be not mutual in the horizontal direction Interference, the strip-shaped bracket 32 can be inserted into jack 33 and pass through hollow metal cylinder 31.The each group of the bridge pier 3 when not in use Part is deposited and transported in the way of intussusception;Assembling in use, metal cylinder 31 be nested together according to size headtotail and Corresponding jack 33 is directed at, the maximum metal cylinder 31 of diameter is placed on bottom, strip-shaped bracket 32 then is inserted into jack 33 pass through metal cylinder 31, so that connected head-to-tail two metal cylinders 31 are fixed into support.Will be all connected head-to-tail After metal cylinder 31 is installed, the assembling of bridge pier 3 is completed.
As shown in figure 3, the train wheel bridge 41 of the padlock 4 and the two ends of lower plate 42 are provided with bolt hole, for installing fixation Bolt 43.After train wheel bridge 41 and lower plate 42 are installed to above and below bridge floor joint, fixing bolt 43 is passed through upper The bolt hole of clamping plate 41 and lower plate 42, and screwing bolts 43, can be achieved with the fixing function of padlock 4.In order to prevent two bridges Face 1 is slided, and train wheel bridge 41 and lower plate 42 are set into concavity, and spill length is wide quite with bridge, for accommodating bridge floor 1 Joint, prevents from sliding between two bridge floors 1.
Each component of the interim arch bridge uses steel construction, to ensure to have enough weight capacities.
Above-mentioned interim arch bridge assumed above the road of playing area, is crossed from playing area side of leading the way below opposite side, bridge for fortune Mobilization, race officials etc. are passed through, and the single vehicle pass-through of urban district common vehicle is available for above bridge.It can be set up at same crossing Many interim arch bridges, to facilitate vehicle two way.The interim arch bridge is realized while the athletic competition of host city, not shadow Ring the unimpeded of traffic.Meanwhile, pressure detecting alarm 11 can detect the pressure suffered by interim arch bridge, exceed setting in pressure Alarm signal is sent during warning value, forbids the car to enter interior, prevents Damage of arch, and then is ensured the safety of human life, and extension uses the longevity Life.

Claims (9)

1. a kind of interim arch bridge towards city race traffic jam issue, the interim arch bridge includes bridge floor, bridge railings, bridge pier And padlock;The pontic of the interim arch bridge is formed by two section bridge floor splicing fixations, and one end of the bridge floor is placed on ground, another End is relative with another bridge floor to be connect, and two bridge floors are fixedly connected in joint with padlock;The bridge railings is fixed on the two of bridge floor Side, and can be folded to bridge floor, the bridge floor can also be folded down storage;The padlock includes train wheel bridge, lower plate and consolidated Determine bolt, in use, train wheel bridge and lower plate clamp the joint of two bridge floors, one is pressed abd fixed on by fixing bolt Rise;The bridge pier is Collapsible structure, positioned at the lower section of two bridge floor joints, supports pontic;The bridge floor is being placed on ground The one end in face is additionally provided with pressure detecting alarm.
2. interim arch bridge according to claim 1, it is characterised in that:Each component of the interim arch bridge uses steel construction.
3. interim arch bridge according to claim 1, it is characterised in that:The joint of two bridge floors of the interim arch bridge is Groove-projection docking structure or bolt docking structure.
4. interim arch bridge according to claim 1, it is characterised in that:The train wheel bridge of the padlock and the two ends of lower plate are set There is bolt hole, for installing fixing bolt.
5. interim arch bridge according to claim 1, it is characterised in that:The padlock train wheel bridge and lower plate are arranged to recessed Shape, spill length is wide quite with bridge, for accommodating bridge floor joint.
6. interim arch bridge according to claim 1, it is characterised in that:In bridge floor and the train wheel bridge contacted with bridge floor and lower folder Block-groove structure is set on plate correspondence position.
7. interim arch bridge according to claim 1, it is characterised in that:The pressure detecting alarm, can detect interim arch Pressure suffered by bridge, sends alarm signal when pressure exceedes the warning value of setting, prevents Damage of arch.
8. interim arch bridge according to claim 1, it is characterised in that:The bridge pier include it is multiple be nested together it is hollow Metal cylinder and strip-shaped bracket, the two ends of hollow metal cylinder are provided with multigroup jack corresponding two-by-two, and every group of jack exists Do not interfered with each other in horizontal direction, the strip-shaped bracket can be inserted into jack and pass through hollow metal cylinder.
9. interim arch bridge according to claim 8, it is characterised in that:Each component of the bridge pier is with intussusception when not in use Mode is deposited and transported;In assembling in use, metal cylinder is nested together according to size headtotail and is directed at corresponding slotting Hole, the maximum metal cylinder of diameter is placed on bottom, and strip-shaped bracket insertion jack then is passed through into metal cylinder, so that Connected head-to-tail two metal cylinders are fixed and supported;After all connected head-to-tail metal cylinders are installed, bridge pier is completed Assembling.
CN201720127624.9U 2017-02-13 2017-02-13 A kind of interim arch bridge towards city race traffic jam issue Withdrawn - After Issue CN206521686U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720127624.9U CN206521686U (en) 2017-02-13 2017-02-13 A kind of interim arch bridge towards city race traffic jam issue

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720127624.9U CN206521686U (en) 2017-02-13 2017-02-13 A kind of interim arch bridge towards city race traffic jam issue

Publications (1)

Publication Number Publication Date
CN206521686U true CN206521686U (en) 2017-09-26

Family

ID=59891480

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720127624.9U Withdrawn - After Issue CN206521686U (en) 2017-02-13 2017-02-13 A kind of interim arch bridge towards city race traffic jam issue

Country Status (1)

Country Link
CN (1) CN206521686U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638269A (en) * 2017-02-13 2017-05-10 南京邮电大学 Temporary arc bridge facing traffic jam problem caused by city competing
CN108824168A (en) * 2018-07-09 2018-11-16 解晓莉 A kind of bridge structure that civil small-scale quickly splices

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638269A (en) * 2017-02-13 2017-05-10 南京邮电大学 Temporary arc bridge facing traffic jam problem caused by city competing
CN106638269B (en) * 2017-02-13 2018-05-04 南京邮电大学 A kind of interim arch bridge towards city race traffic jam issue
CN108824168A (en) * 2018-07-09 2018-11-16 解晓莉 A kind of bridge structure that civil small-scale quickly splices

Similar Documents

Publication Publication Date Title
CN106351132B (en) A kind of bridge using corrugated sheet steel connector spells wide construction and its construction method
CN206521686U (en) A kind of interim arch bridge towards city race traffic jam issue
CN106638269B (en) A kind of interim arch bridge towards city race traffic jam issue
WO2023060783A1 (en) Stretchable road bridge and manufacturing and construction method therefor
CN108166377B (en) A kind of folding combined temporary bridge device
CN107905084B (en) RPC steel truss combined bridge deck and continuous beam bridge
CN203684060U (en) Temporary steel-frame bridge
CN206219998U (en) A kind of bridge of use corrugated sheet steel connector spells construction wide
CN216739203U (en) Semi-sinking self-balancing reinforced concrete shuttle-shaped double-arch assembly type overpass
CN111472256B (en) Foldable intelligent bridge
CN211498488U (en) Highway and railway dual-purpose bridge movable railway hard protection platform
CN111794079B (en) Temporary bridge capable of passing through vehicles based on bridge construction
CN2312243Y (en) Quick assemblage overcross bridge for highway
CN201351262Y (en) Light self-balancing assembly car platform bridge
CN210888318U (en) Building engineering quality detects uses interim rail guard
CN210529489U (en) Bridge overhauls device
CN210216110U (en) Box girder bridge is assembled to split type prefabricated segment of pier top crossbeam of encorbelmenting greatly
CN114016420A (en) Assembly type construction method for single pier column steel bridge
RU121262U1 (en) MOBILE SPAN STRUCTURE OF THE BRIDGE
RU75668U1 (en) Dismountable SPAN (OPTIONS)
CN105178188B (en) Triangular frame supporting formwork
CN221193011U (en) Road bridge construction support frame
CN114717961B (en) Independent-tower self-anchored suspension bridge structure without lower cross beam and construction method thereof
CN220057746U (en) High protective capability penetrating type combined guardrail
CN211228120U (en) Bent cap formwork support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Guo Yongan

Inventor after: She Hao

Inventor after: Bai Yichu

Inventor after: Li Ruichao

Inventor after: Chen Zifei

Inventor after: Zhu Yimeng

Inventor before: Cai Shuqi

Inventor before: Guo Yongan

Inventor before: She Hao

Inventor before: Bai Yichu

Inventor before: Zhu Hongbo

Inventor before: Yang Longxiang

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170926

Effective date of abandoning: 20180504