CN104790956A - Remote control heading machine tunnel type or fully-mechanized top coal exploitation end slope coal technology - Google Patents

Remote control heading machine tunnel type or fully-mechanized top coal exploitation end slope coal technology Download PDF

Info

Publication number
CN104790956A
CN104790956A CN201510109853.3A CN201510109853A CN104790956A CN 104790956 A CN104790956 A CN 104790956A CN 201510109853 A CN201510109853 A CN 201510109853A CN 104790956 A CN104790956 A CN 104790956A
Authority
CN
China
Prior art keywords
coal
exploitation
slope
end slope
remote control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510109853.3A
Other languages
Chinese (zh)
Other versions
CN104790956B (en
Inventor
余绍泽
梁正召
尹升华
闫作厚
王立新
卫星
杨志军
肖鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510109853.3A priority Critical patent/CN104790956B/en
Publication of CN104790956A publication Critical patent/CN104790956A/en
Application granted granted Critical
Publication of CN104790956B publication Critical patent/CN104790956B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/26Methods of surface mining; Layouts therefor
    • E21C41/28Methods of surface mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/32Reclamation of surface-mined areas
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A remote control heading machine tunnel type or fully-mechanized top coal exploitation end slope coal technology is mainly used in exploitation of resources under opencast coal mine slope. A figure shown in the invention is an end slope coal exploitation mode carried out through cooperation of a tunnel type remote control heading machine tilting to an inner dumping site direction and tape transportation. An end slope coal seam exploitation technology of local occurrence is characterized in that tunnel exploitation end slope coal vertical or obliquely crossed to the slope is unexploited, a coal pillar with proper width is residual in the middle, and the shielding and supporting effect of the inner dumping site on the slope is used to rapidly exploit the end slope coal before internal discharge of the inner dumping site; an exploitation device is a composed of a remote control or line control heading machine and a tape transporter, and the remote control or line control heading machine cooperates with the tape transporter to realize unmanned exploitation; waste stones at the top of the step of the inner dumping site in the opencast coal mine are used to fill under necessary conditions; and a full mechanizing technology is adopted to exploit continuous large-occurrence end slope or non-working slope coal seam, favorable conditions of the developing transport system of the opencast coal mine are utilized, and an end slope fully mechanized exploitation system is arranged under the slops to exploit the end slope coal.

Description

Remote control roadway formula or mining exploitation end side coal technique
Technical field
Remote control development machine lane formula, mining exploitation end side coal technique, the exploitation of resource is covered under being mainly used in Slope of Open Pit Coal Mine, be exactly in the process of exploiting in the open, exploit the resource under Slope of Open Pit Coal Mine simultaneously, these part resource reserves are huge, there is no effective ways so far in internal dumping, arrange front extraction.
Background technology
At coal industry, resource recovery is generally on the low side, the mine of pit mining, and resource recovery only has 45%, and small-sized non-governmental well industrial and mineral only has about 15-20%.Resource recovery rate in open pit boundary is about 95%, if but the Resources calculation covered under the residual ore deposit of Opent-pit limit periphery and side slope interior, the resource recovery rate great majority of open coal mine, below 75%, have the resource of about 25% not reclaim nearly.There are 4671.4 ten thousand t shale oil fields in such as ore deposit, Fuxin in exploration context, in the boundary vertical range of opencut earth's surface, Resource/Reserves is 4664.87 ten thousand t, cover stock number 1285.5 ten thousand t under the side of limit, in pit limits, have the shale oil field of 27.6% to be covered by side slope.
Be suitable for the gentle dip of interior row or horizontal opencut especially, carry out hole In-pit dumping gradually when exploitation reaches the end, hole, end wall life period is short, reduces until disappear highly gradually, if the resource covered under extraction side slope not in time and the residual ore deposit of periphery, will cause permanent loss.
Summary of the invention
One, to locally composing the end side seam mining technique of depositing
1. utilize remote control or line traffic control development machine and adhesive tape conveyor to match and carry out holding the unmanned exploitation helping coal.In recovery process, personnel are not needed to enter, the system that operating personnel are combined by Remote and video system, operation development machine cuts up and down to coal seam, the coal of cutting and crushing and then the adhesive tape conveyor being transported to rear extension are transported in open-air pit, then are transported to outside open-air pit by outdoor truck.
2, vertical or to internal dumping oblique mode is adopted to arrange tunnel exploitation end side coal.According to stability and the engineering geological conditions of side slope, between tunnel, be installed with conventional coal column, then stay every 10-20 conventional coal column and establish a ultra-wide coal column, to prevent collapsing or the reaction of collapsing of interlock type of side slope.
3. utilize the barren rock at Waste Dump inside Open Pit Mine top to carry out filling to excavating lane, to reduce the impact on Open pit slope stability.In opencut, row's step barren rock has grain composition well, and lumpiness is little, is suitable for the feature of filling.Particularly to high seam, adopt the mode slicing and filling of successively filling from the bottom up, farthest can help coal by production end.
Two, larger end side is deposited or non working slope coal seam adopts fully mechanized mining to exploit to composing continuously
1. utilize the development haulage system of opencut, under side slope, during exploitation, just arrange that end side fully-mechnized mining system carries out holding the exploitation of side coal in the open.Carry out the laying of haulage gate, air return way and work plane in the open during exploitation in good time.In end side coal mining technological work line length at about 1000m, bury complete location at internal dumping, call in when the development haulage system of opencut can utilize to combine in good time and adopt machine exploitation.
In exploitation spatial order, exploit multiple seam, the principle followed from top to bottom is carried out.
Accompanying drawing explanation
Fig. 1 is the sectional drawing of Inner Mongol open coal mine, and this open coal mine has 2 layers of minable coal seam, and 5 coals are the superiors' coal, and average thickness is 3m; 6 coals are most high seam, and average thickness is 22m.The mean depth of this opencut is about 90m, in the open under side slope and periphery, also has a large amount of coal seams not yet to exploit utilization.
Fig. 2 is the end slope laneway formula exploitation figure to 5 coals, adopts the laneway type perpendicular to side slope step to exploit, and leaves coal column in the middle of tunnel, also needs the ultra-wide coal column establishing a 10m-20m wide every 10-20 conventional coal column.In order to ensure the safety of side slope, waste fill can also be carried out to excavating lane.
Fig. 3 is for exploiting to internal dumping direction inclination certain angle mode in end side exploitation tunnel, and can reduce the disturbance to end wall like this, exploit under the shielding of internal dumping, the safety of side slope is higher, and end slope laneway is also safer.
Fig. 4 is the mining type in thick end side coal seam, forms interior row's small stair, be divided into mining area and ore pillar two parts to facilitate on high seam by internal dumping, at mining area's layer-by-layer mining from the bottom up, adopt one deck filling one deck, waste fill layer carries out the exploitation of last layer, successively upwards carry out.
Fig. 5 is the mining mining type in continuous coal seam.Along with the propelling of opencut, carry out the digging transporting coal crossheading and air return way simultaneously, wait for that face length reaches about 1000m, refuse dump is buried end side just can to call in when length also reaches about 1000m and is comprehensively adopted machine exploitation, the coal of extraction is directly transported to the end, hole with adhesive tape, then is transported out outside hole by haulage truck.
Detailed description of the invention
When opencast mining is to descending most coal seam, namely exploitation is to the most next level, just can carry out the exploitation of holding side coal.
First will in conjunction with the production program of opencut, unified carrying out holds the exploitation of side coal to plan, then in conjunction with the engineering geological conditions of opencut and the stability state of side slope, carries out planning and designing to the exploitation of multilayer end side coal.To continuous print coal seam, adopting and combining the mode of adopting exploitation is most reasonable manner, has safety, productivity ratio is high and reclaim the large feature of coal amount, consider air return way, haulage gate laying and combine the determination etc. of time of adopting.
To locally composing the coal seam of depositing, the size of conventional coal column and permanent pillar size and the position relationship of internal dumping and the exploitation of end side be considered.Particularly to consider that the exploitation of end side can not affect the stability of open-pit slope, the normal production of opencut can not be affected, under the condition of necessity, also will consider to adopt internal dumping barren rock to carry out filling, to ensure the stability of side slope.In order to farthest reduce the impact of opposite end side slope stability, in conjunction with the shielding supporting role of internal dumping to side slope, end side exploitation tunnel adopts lays to the mode of internal dumping inclination certain angle, farthest can reduce the possibility that side slope sinks to destroying like this.
In the recovery process carrying out end wall, be maximum on the impact of side slope foot, be easy to cause partial collapse to cause the accident, therefore will carry out the aggregate measures such as disposal of dangerous rock, erection shielding steel canopy to end wall and carry out security protection.
In process of production, owing to carrying out automated mining, personnel can not enter tunnel, therefore require that equipment is before entering tunnel, will carry out meticulous maintenance overhaul to equipment, guarantee that equipment does not occur any fault in tunnel.Next to prevent when local sillar drops and pounds on adhesive tape or remote control development machine, there is powerful capstan winch to pull equipment in outside, the sillar on adhesive tape and development machine and its top is withdrawn from. reenter tunnel after cleaning out again and exploit.

Claims (1)

1. cover the recovery exploitation of coal resources or the remaining resource of periphery under being applicable to level or semi-steep open-pit slope, concrete patent right is as follows:
To locally composing the coal seam of depositing
1. utilize remote control or line traffic control development machine and adhesive tape conveyor to match and carry out holding the unmanned exploitation helping coal.
2, vertical or to internal dumping oblique mode is adopted to arrange tunnel exploitation end side coal.
3. adopt the mode of waste fill to carry out filling to excavating lane.For high seam, adopt the mode separate zone production of successively filling from the bottom up, to control stability and the sedimentation of side slope, production end side coal, reduces staying of coal column and establishes thickness to greatest extent.
The larger end side of area or non working slope coal seam is deposited to composing continuously
4, end side coal and the collaborative exploitation of opencut collaborative design, adopts side coal in mining production practice opposite end to exploit.
5, the construction of haulage gate, air return way and work plane is carried out in the open while exploiting.At workline length at about 1000m, internal dumping bury complete end side coal location, then call in combine adopt machine exploitation.
6, in exploitation spatial order, to mutil-coal seam mining, the principle followed from top to bottom carries out end side coal mining.
CN201510109853.3A 2015-03-13 2015-03-13 It is remotely controlled roadway formula exploitation end and helps coal technique Active CN104790956B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510109853.3A CN104790956B (en) 2015-03-13 2015-03-13 It is remotely controlled roadway formula exploitation end and helps coal technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510109853.3A CN104790956B (en) 2015-03-13 2015-03-13 It is remotely controlled roadway formula exploitation end and helps coal technique

Publications (2)

Publication Number Publication Date
CN104790956A true CN104790956A (en) 2015-07-22
CN104790956B CN104790956B (en) 2018-08-14

Family

ID=53556091

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510109853.3A Active CN104790956B (en) 2015-03-13 2015-03-13 It is remotely controlled roadway formula exploitation end and helps coal technique

Country Status (1)

Country Link
CN (1) CN104790956B (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106089211A (en) * 2016-08-19 2016-11-09 郑晓辉 A kind of surface mine is unmanned excavates Load System
CN106321105A (en) * 2016-09-30 2017-01-11 中国矿业大学 Paste filling method for end slope of opencut coal mine
CN106761759A (en) * 2016-12-28 2017-05-31 中国神华能源股份有限公司 A kind of coal-mining method of open coal mine
CN106869937A (en) * 2017-04-11 2017-06-20 中国神华能源股份有限公司 Discharge method in the side of opencut end
CN107313804A (en) * 2017-06-29 2017-11-03 中国矿业大学 A kind of open coal mine end side pressure coal filling fully mechanized mining recovery method
CN109026006A (en) * 2018-09-20 2018-12-18 内蒙古煤矿设计研究院有限责任公司 Exploitation open pit slope covers the new method of mineral products
CN109882179A (en) * 2019-03-29 2019-06-14 中国矿业大学 A kind of outdoor end side pressure coal filling mining design method
WO2019184257A1 (en) * 2018-03-27 2019-10-03 中煤科工能源投资有限公司 Coal mining method for rotatably mining coal on an open pit slope using fully-mechanized coal mining equipment
CN111396055A (en) * 2020-03-24 2020-07-10 中煤科工集团沈阳设计研究院有限公司 Method for arranging side coal pressing mining chamber of strip mine
WO2020192078A1 (en) * 2019-03-27 2020-10-01 中国矿业大学 Method for radial mining of opencast end slope remnant coal
CN112855162A (en) * 2021-01-29 2021-05-28 辽宁工程技术大学 Mining method for upper coal seam of composite coal seam strip mine near extraction end slope
CN114033380A (en) * 2021-10-18 2022-02-11 辽宁工程技术大学 Parallel double-working-line reverse-propulsion inclined coal seam strip mine mining method
CN114278299A (en) * 2021-11-24 2022-04-05 中煤科工集团沈阳设计研究院有限公司 Stability control method for down-dip weak layer side slope of open pit coal mine
CN114320298A (en) * 2022-01-05 2022-04-12 国家能源集团国源电力有限公司 Coal mining method
RU2775028C1 (en) * 2019-03-27 2022-06-27 Чайна Юниверсити Оф Майнинг Энд Текнолоджи Method for extraction of residual coal by radial development of longitudinal slope of quarry
CN114718575A (en) * 2022-05-10 2022-07-08 中国矿业大学 Mining, loading and transporting method for unmanned lower stope of nearly horizontal open pit coal mine

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3301599A (en) * 1964-02-27 1967-01-31 Union Carbide Corp Method of continuous open-pit mining and apparatus therefor
US4589700A (en) * 1984-02-21 1986-05-20 Standard Oil Company (Indiana) Strip-auger method of mining thin seams of hydrocarbonaceous deposits
CN101899976A (en) * 2010-07-15 2010-12-01 煤炭科学研究总院太原研究院 Continuous coal mining process method of open-pit coal mine
CN102733809A (en) * 2012-06-04 2012-10-17 闫林 Coal mining method for recovering open-pit coal mine end slope coal
CN104074521A (en) * 2014-06-20 2014-10-01 中国矿业大学 End slope coal bed remote control excavating mining method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3301599A (en) * 1964-02-27 1967-01-31 Union Carbide Corp Method of continuous open-pit mining and apparatus therefor
US4589700A (en) * 1984-02-21 1986-05-20 Standard Oil Company (Indiana) Strip-auger method of mining thin seams of hydrocarbonaceous deposits
CN101899976A (en) * 2010-07-15 2010-12-01 煤炭科学研究总院太原研究院 Continuous coal mining process method of open-pit coal mine
CN102733809A (en) * 2012-06-04 2012-10-17 闫林 Coal mining method for recovering open-pit coal mine end slope coal
CN104074521A (en) * 2014-06-20 2014-10-01 中国矿业大学 End slope coal bed remote control excavating mining method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
余绍泽等: "端帮煤长壁废石充填开采工艺研究", 《露天采矿技术》 *
***等: "安家岭露天煤矿端帮采煤方法研究", 《中国矿业大学学报》 *

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106089211A (en) * 2016-08-19 2016-11-09 郑晓辉 A kind of surface mine is unmanned excavates Load System
CN106321105A (en) * 2016-09-30 2017-01-11 中国矿业大学 Paste filling method for end slope of opencut coal mine
CN106321105B (en) * 2016-09-30 2018-11-30 中国矿业大学 A kind of open coal mine end side paste body filling method
CN106761759A (en) * 2016-12-28 2017-05-31 中国神华能源股份有限公司 A kind of coal-mining method of open coal mine
CN106761759B (en) * 2016-12-28 2019-03-22 中国神华能源股份有限公司 A kind of coal-mining method of open coal mine
CN106869937B (en) * 2017-04-11 2019-01-25 中国神华能源股份有限公司 Help interior discharge method in opencut end
CN106869937A (en) * 2017-04-11 2017-06-20 中国神华能源股份有限公司 Discharge method in the side of opencut end
CN107313804B (en) * 2017-06-29 2019-05-17 中国矿业大学 A kind of open coal mine end side pressure coal filling fully mechanized mining recovery method
CN107313804A (en) * 2017-06-29 2017-11-03 中国矿业大学 A kind of open coal mine end side pressure coal filling fully mechanized mining recovery method
WO2019184257A1 (en) * 2018-03-27 2019-10-03 中煤科工能源投资有限公司 Coal mining method for rotatably mining coal on an open pit slope using fully-mechanized coal mining equipment
CN109026006A (en) * 2018-09-20 2018-12-18 内蒙古煤矿设计研究院有限责任公司 Exploitation open pit slope covers the new method of mineral products
CN109026006B (en) * 2018-09-20 2020-07-24 内蒙古煤矿设计研究院有限责任公司 Novel method for mining open-pit mine slope covered mineral products
WO2020192078A1 (en) * 2019-03-27 2020-10-01 中国矿业大学 Method for radial mining of opencast end slope remnant coal
US11377952B2 (en) 2019-03-27 2022-07-05 China University Of Mining And Technology Method for radially mining open-pit end slope pressed coal
RU2775028C1 (en) * 2019-03-27 2022-06-27 Чайна Юниверсити Оф Майнинг Энд Текнолоджи Method for extraction of residual coal by radial development of longitudinal slope of quarry
CN109882179B (en) * 2019-03-29 2020-04-28 中国矿业大学 Open-air end slope coal-pressing filling mining design method
CN109882179A (en) * 2019-03-29 2019-06-14 中国矿业大学 A kind of outdoor end side pressure coal filling mining design method
CN111396055A (en) * 2020-03-24 2020-07-10 中煤科工集团沈阳设计研究院有限公司 Method for arranging side coal pressing mining chamber of strip mine
CN112855162A (en) * 2021-01-29 2021-05-28 辽宁工程技术大学 Mining method for upper coal seam of composite coal seam strip mine near extraction end slope
CN112855162B (en) * 2021-01-29 2023-03-21 辽宁工程技术大学 Mining method for upper coal seam of composite coal seam strip mine near extraction end slope
CN114033380A (en) * 2021-10-18 2022-02-11 辽宁工程技术大学 Parallel double-working-line reverse-propulsion inclined coal seam strip mine mining method
CN114278299A (en) * 2021-11-24 2022-04-05 中煤科工集团沈阳设计研究院有限公司 Stability control method for down-dip weak layer side slope of open pit coal mine
CN114278299B (en) * 2021-11-24 2023-11-24 中煤科工集团沈阳设计研究院有限公司 Stability control method for forward-inclined weak layer slope of open pit coal mine
CN114320298A (en) * 2022-01-05 2022-04-12 国家能源集团国源电力有限公司 Coal mining method
CN114320298B (en) * 2022-01-05 2024-03-01 国家能源集团国源电力有限公司 Coal mining method
CN114718575A (en) * 2022-05-10 2022-07-08 中国矿业大学 Mining, loading and transporting method for unmanned lower stope of nearly horizontal open pit coal mine
CN114718575B (en) * 2022-05-10 2023-05-02 中国矿业大学 Mining, transporting and transporting method for stope under unmanned condition of near-horizontal open-air coal mine

Also Published As

Publication number Publication date
CN104790956B (en) 2018-08-14

Similar Documents

Publication Publication Date Title
CN104790956B (en) It is remotely controlled roadway formula exploitation end and helps coal technique
US5782539A (en) Wall-to-wall surface mining process
CN101899976B (en) Continuous coal mining process method of open-pit coal mine
CN107387084B (en) The construction method of top depth is cut in a kind of gob side entry retaining reduction
CA2883015C (en) A system for the reduction in applied energy, improved efficiencies and reduced costs in open pit mining
CN103603665B (en) Upper dish side ore body stoping method in the scope of adopting of mine
CN103206215A (en) Precontrol top upward access cut-and-filling stopping method
CN109458181A (en) A kind of filling mining method of metallic ore across pitch full-seam mining
AU2015100066B4 (en) A System for the Reduction in Applied Energy, Improved Efficiencies and Reduced Costs in Open Pit Mining
CN109630116B (en) Mining method for inclined medium-thickness blind ore body
RU2571776C1 (en) Open development of steep ore bodies
CN107237635B (en) A kind of thick solid potassium salt mine recovery method of spy for once adopting full thickness
CN115110955A (en) Improved process for mining steeply inclined lenticular ore body by stage chamber method
CN210317355U (en) Supporting structure for fully mechanized caving face to pass through fault along coal seam extraction
RU2488693C1 (en) Method for in-line production of work at non-benching version of extraction of chambers along strike on chamber-and-pillar system
AU2014100343A4 (en) A System for the Reduction in Applied Energy, Improved Efficiencies and Reduced Costs in Open Pit Mining
Egerton Presidential address: The mechanisation of UG2 mining in the Bushveld Complex
AU2015204338A1 (en) A high wall mining method
RU2367794C1 (en) Recovery method of minerals
CN110905510A (en) Strip and block stoping method for horizontal ore pillar of metal ore body
RU2777214C1 (en) Method for mining coal seams from the sides of coal mines using underground coal mining technologies
Marepalli et al. Optimum utilization of continuous miner used for pillar extraction in bord and pillar mining method and support requirement in various roof conditions
Matsui et al. Highwall stability due to punch mining at opencut coal mines
CN110630266B (en) Method for enabling large-dip-angle fully-mechanized coal mining face to cross fault
Dao The effect of seam dip on the application of the Longwall Top Coal Caving method for inclined thick seams

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant