CN102587658A - Construction method of variable curved-surface steel-concrete tubular structure - Google Patents

Construction method of variable curved-surface steel-concrete tubular structure Download PDF

Info

Publication number
CN102587658A
CN102587658A CN2012100621046A CN201210062104A CN102587658A CN 102587658 A CN102587658 A CN 102587658A CN 2012100621046 A CN2012100621046 A CN 2012100621046A CN 201210062104 A CN201210062104 A CN 201210062104A CN 102587658 A CN102587658 A CN 102587658A
Authority
CN
China
Prior art keywords
surface steel
changeable
tubular construction
curved surface
concrete tubular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100621046A
Other languages
Chinese (zh)
Inventor
陈勇辉
林忠和
戈祥林
陶暑生
黄贵
于天成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN2012100621046A priority Critical patent/CN102587658A/en
Publication of CN102587658A publication Critical patent/CN102587658A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a construction method of a variable curved-surface steel-concrete tubular structure, which includes the steps: establishing a building information model; subjecting the building information model to data processing to obtain space coordinate data of positioning forms of the tubular structure; performing construction layout according to the space coordinate data and fabricating the positioning forms; installing and reinforcing the positioning forms; and performing casting. By the construction method, construction of the variable curved-surface steel-concrete tubular structure is achieved, the solid sensory artistic effect of the variable curved-surface steel-concrete tubular structure is guaranteed, cost is low, and facade streamline is highly continuous in variation.

Description

Changeable abnormal curved surface steel reinforced concrete tubular construction job practices
Technical field
The present invention relates to a kind of building structure construction method, refer to a kind of changeable abnormal curved surface steel reinforced concrete tubular construction job practices especially.
Background technology
Changeable abnormal curved surface tubular construction occurs under construction, because changeable abnormal curved surface tubular construction is complicated, outward appearance is unusual, cylindrical shell from bottom to top as the irregular cone of a handstand; Shape is not planning and development, distortion from bottom to top; Construction technology is quite complicated, particularly shaped steel, reinforcing bar moulding, Template Location, blanking, assembly unit; The choosing and installing of medial and lateral mould material; The design of falsework and enforcement, the cylindrical shell internal mold is set up and is removed under the situation of little space, and the selection of concrete blanking height and vibrating method all need be abandoned conventional thinking.Therefore the artistic effect of changeable special-shaped barrel entity sense organ is necessary to propose a kind of new job practices for changeable abnormal curved surface cylindrical shell construction if general conventional reinforcing bar moulding, formwork erection and the concrete pouring construction method of employing can't be constructed out.
Summary of the invention
The objective of the invention is to overcome the defective of prior art; And a kind of changeable abnormal curved surface steel reinforced concrete tubular construction job practices is provided; This method has realized the construction of changeable abnormal curved surface steel reinforced concrete tubular construction; Guaranteed the artistic effect of the entity sense organ of changeable abnormal curved surface steel reinforced concrete tubular construction, and cost is low, the continuity of the streamlined variation of facade is strong.
The technical scheme that realizes above-mentioned purpose is:
A kind of changeable abnormal curved surface steel reinforced concrete tubular construction job practices of the present invention comprises the steps:
Set up BIM;
Through said BIM is carried out data, obtain the spatial data of each locating template of tubular construction;
According to said spatial data construction lofting and fabrication and processing locating template;
Install and reinforce locating template;
Build moulding.
Above-mentioned data processing step comprises:
Obtain the auditory localization cues of the horizontal profile of said each absolute altitude of BIM through application software;
Every in the central axis position of the said tubular construction of each absolute altitude at a distance from the said auditory localization cues radioactive ray of fixed angle to current absolute altitude;
Pick up whole intersection points of said auditory localization cues of each absolute altitude and said ray, and with the spatial data of adjacent said intersection point in the identical absolute altitude spatial data as said locating template both ends.
The said fixing angular dimension is 3 degree.
Above-mentioned data processing step further comprises:
Confirm the installation position data of scaffold.
Above-mentioned installation and reinforcing locating template step comprise:
Set up scaffold according to construction lofting;
Said locating template is installed;
Said locating template is carried out the inside and outside to be reinforced.
Further comprise step before reinforcing step in above-mentioned inside and outside that said locating template is carried out:
In said locating template inboard one deck 3mm optic panel is set.
Above-mentioned BIM is set up through the BIM application software.
Above-mentioned data utilizes the AutoCAD application software to carry out.
The present invention has been owing to adopted above technical scheme, makes it have following beneficial effect to be:
Every in the central axis position of the tubular construction of each absolute altitude at a distance from the auditory localization cues radioactive ray of fixed angle to current absolute altitude; And with straight Dai Qu; Make straight line connect the polygon that forms behind the intersection point and extremely level off to former location curve, solve the inside and outside circular formwork moulding difficult problem of changeable abnormal curved surface steel reinforced concrete tubular construction.Simultaneously owing to adopted many absolute altitudes; And according to the scheme of making along the height merogenesis; Make that the streamlined variation of facade of changeable abnormal curved surface steel reinforced concrete tubular construction is more smooth, solved the continuity problem of the streamlined variation of facade that runs in the changeable abnormal curved surface steel reinforced concrete tubular construction forming process.The employing of the inboard 3mm optic panel of locating template has realized eliminating the corner angle that produce between the inside and outside wall form seam of cylindrical shell.This method has realized the construction of changeable abnormal curved surface steel reinforced concrete tubular construction, has guaranteed the artistic effect of the entity sense organ of changeable abnormal curved surface steel reinforced concrete tubular construction, and cost is low, the continuity of the streamlined variation of facade is strong.
Description of drawings
Fig. 1 is the flow chart of the changeable abnormal curved surface steel reinforced concrete of the present invention tubular construction job practices;
Fig. 2 is the locating template and the 3mm optic panel mounting structure sketch map of the changeable abnormal curved surface steel reinforced concrete of the present invention tubular construction job practices.
The specific embodiment
Below in conjunction with specific embodiment the present invention is described further.
See also Fig. 1, a kind of changeable abnormal curved surface steel reinforced concrete tubular construction job practices of the present invention comprises the steps:
At first, set up BIM through the BIM application software;
Then, BIM is carried out data, obtain the spatial data of each locating template 1 of tubular construction through the AutoCAD application software;
Wherein data processing step comprises:
Obtain the auditory localization cues of the horizontal profile of each absolute altitude of BIM through AutoCAD;
Every in the central axis position of the tubular construction of each absolute altitude at a distance from the 3 auditory localization cues radioactive ray of spending to current absolute altitude;
Pick up whole intersection points of each absolute altitude auditory localization cues and ray, and with the spatial data of adjacent intersection point in the identical absolute altitude spatial data as template 1 both ends, a location.
Simultaneously, confirm the installation position data of scaffold.
Then, according to spatial data construction lofting and fabrication and processing locating template 1;
Then, set up scaffold according to construction lofting, installing and locating template 1 sees also Fig. 2, in locating template 1 inboard one deck 3mm optic panel 2 is set.Locating template 1 is carried out the inside and outside to be reinforced.The employing of locating template 1 inboard 3mm optic panel 2 has realized eliminating the corner angle that produce between the inside and outside wall form seam of cylindrical shell.
Changeable abnormal curved surface steel reinforced concrete tubular construction is built moulding.
The thinking of forming space curved surface with " integration " behind the plane of higher mathematics " calculus " theoretical " differential " earlier; Make secant be substantially equal to tangent line; Curve is substantially equal to straight line, thereby with straight Dai Qu, solves nonlinear problem with linearizing method; Solve the inside and outside circular formwork moulding difficult problem of changeable abnormal curved surface steel concrete cylindrical shell, and through making the continuity problem that solves the streamlined variation of facade that runs in the concrete tube structure forming process along the height merogenesis.Use clamping plate cheap, that be convenient to cutting stock to make " special-shaped barrel " structure level section locating template 1 and inside and outside template, reduce production costs.
Every in the central axis position of the tubular construction of each absolute altitude at a distance from the auditory localization cues radioactive ray of fixed angle to current absolute altitude; And with straight Dai Qu; Make straight line connect the polygon that forms behind the intersection point and extremely level off to former location curve, solve the inside and outside circular formwork moulding difficult problem of changeable abnormal curved surface steel reinforced concrete tubular construction.Simultaneously owing to adopted many absolute altitudes; And according to the scheme of making along the height merogenesis; Make that the streamlined variation of facade of changeable abnormal curved surface steel reinforced concrete tubular construction is more smooth, solved the continuity problem of the streamlined variation of facade that runs in the changeable abnormal curved surface steel reinforced concrete tubular construction forming process.This method has realized the construction of changeable abnormal curved surface steel reinforced concrete tubular construction, has guaranteed the artistic effect of the entity sense organ of changeable abnormal curved surface steel reinforced concrete tubular construction, and cost is low, the continuity of the streamlined variation of facade is strong.
More than combine accompanying drawing embodiment that the present invention is specified, those skilled in the art can make the many variations example to the present invention according to above-mentioned explanation.Thereby some details among the embodiment should not constitute qualification of the present invention, and the scope that the present invention will define with appended claims is as protection scope of the present invention.

Claims (8)

1. a changeable abnormal curved surface steel reinforced concrete tubular construction job practices is characterized in that, comprises the steps:
Set up BIM;
Through said BIM is carried out data, obtain the spatial data of each locating template of tubular construction;
According to said spatial data construction lofting and fabrication and processing locating template;
Install and reinforce locating template;
Build moulding.
2. changeable abnormal curved surface steel reinforced concrete tubular construction job practices according to claim 1 is characterized in that said data processing step comprises:
Obtain the auditory localization cues of the horizontal profile of said each absolute altitude of BIM through application software;
Every in the central axis position of the said tubular construction of each absolute altitude at a distance from the said auditory localization cues radioactive ray of fixed angle to current absolute altitude;
Pick up whole intersection points of said auditory localization cues of each absolute altitude and said ray, and with the spatial data of adjacent said intersection point in the identical absolute altitude spatial data as said locating template both ends.
3. changeable abnormal curved surface steel reinforced concrete tubular construction job practices according to claim 2 is characterized in that, said fixed angle size is 3 degree.
4. according to claim 2 or 3 described changeable abnormal curved surface steel reinforced concrete tubular construction job practicess, it is characterized in that said data processing step further comprises:
Confirm the installation position data of scaffold.
5. changeable abnormal curved surface steel reinforced concrete tubular construction job practices according to claim 4 is characterized in that, said installation and reinforcing locating template step comprise:
Set up scaffold according to construction lofting;
Said locating template is installed;
Said locating template is carried out the inside and outside to be reinforced.
6. changeable abnormal curved surface steel reinforced concrete tubular construction job practices according to claim 5 is characterized in that, further comprises step before reinforcing step in said inside and outside that said locating template is carried out:
In said locating template inboard one deck 3mm optic panel is set.
7. changeable abnormal curved surface steel reinforced concrete tubular construction job practices according to claim 5 is characterized in that, said BIM is set up through the BIM application software.
8. changeable abnormal curved surface steel reinforced concrete tubular construction job practices according to claim 5 is characterized in that said data utilizes the AutoCAD application software to carry out.
CN2012100621046A 2012-03-09 2012-03-09 Construction method of variable curved-surface steel-concrete tubular structure Pending CN102587658A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100621046A CN102587658A (en) 2012-03-09 2012-03-09 Construction method of variable curved-surface steel-concrete tubular structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100621046A CN102587658A (en) 2012-03-09 2012-03-09 Construction method of variable curved-surface steel-concrete tubular structure

Publications (1)

Publication Number Publication Date
CN102587658A true CN102587658A (en) 2012-07-18

Family

ID=46476842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100621046A Pending CN102587658A (en) 2012-03-09 2012-03-09 Construction method of variable curved-surface steel-concrete tubular structure

Country Status (1)

Country Link
CN (1) CN102587658A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943565A (en) * 2012-11-30 2013-02-27 中国建筑第八工程局有限公司 Construction method of large-sized arc-shaped wall
CN103195247A (en) * 2013-04-19 2013-07-10 江苏省华建建设股份有限公司 Saddle-shaped hyperboloidal concrete slab construction method
CN103949860A (en) * 2014-04-30 2014-07-30 中国十九冶集团有限公司 Method for processing single-node-space multi-opening flange of tower
CN104120827A (en) * 2014-07-23 2014-10-29 浙江省一建建设集团有限公司 Ship rail type bare concrete wallboard and construction method thereof
CN104196012A (en) * 2014-08-28 2014-12-10 广州市第二建筑工程有限公司 Karst cave processing method based on BIM
CN106245906A (en) * 2016-08-30 2016-12-21 中国葛洲坝集团三峡建设工程有限公司 The auxiliary abnormal formwork design of a kind of threedimensional model and the method installed
CN106285028A (en) * 2015-05-28 2017-01-04 中国二十冶集团有限公司 Reinforcement of factory building construction method in long-span heavy type crane girder based on BIM technology dismounting
CN107451350A (en) * 2017-07-26 2017-12-08 中交公局第二工程有限公司 One kind is based on BIM modeling technique space three-dimensional abnormity bridge abutment moulding plate construction methods
CN107724299A (en) * 2017-09-29 2018-02-23 上海宝冶集团有限公司 A kind of manufacture method of hyperboloid anticollision barrier
CN107842192A (en) * 2017-11-23 2018-03-27 安徽同济建设集团有限责任公司 A kind of making of the outer builder's jack closed cover of architectural engineering and installation method
CN108363860A (en) * 2018-02-07 2018-08-03 中交公局第二工程有限公司 A kind of 3-D abnormal bridge formwork assembly setting out method based on BIM technology
CN108416162A (en) * 2018-03-23 2018-08-17 中国十七冶集团有限公司 A kind of construction method of the spiral formula reinforced concrete structure based on BIM
CN112131650A (en) * 2020-09-28 2020-12-25 中船黄埔文冲船舶有限公司 Construction method of curved surface structure
CN114673386A (en) * 2022-05-07 2022-06-28 广州茏腾园林景观设计有限公司 Construction method of hyperboloid special-shaped water drop waterscape and water drop waterscape system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007239223A (en) * 2006-03-06 2007-09-20 Shimizu Corp Construction planning system and construction planning program
CN101109227A (en) * 2007-09-05 2008-01-23 中国建筑第七工程局 Construction method of single-stride large cantilever double-pre-stress concrete steel concrete crossbeam
CN101136259A (en) * 2007-09-27 2008-03-05 中国核工业第二三建设公司 Modularize building method for nuclear reactor of nuclear plant
JP2008276591A (en) * 2007-05-01 2008-11-13 Shimizu Corp Building information processing system and building information processing method
CN101761134A (en) * 2009-12-31 2010-06-30 浙江中成建工集团有限公司 Construction technology of spatial variable curved surface reinforced concrete irregular barrel group structure
CN102345377A (en) * 2011-07-15 2012-02-08 广州市第三建筑工程有限公司 Method for making spatial multi-curved-surface as-cast finish concrete stay in place formwork by using plywood

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007239223A (en) * 2006-03-06 2007-09-20 Shimizu Corp Construction planning system and construction planning program
JP2008276591A (en) * 2007-05-01 2008-11-13 Shimizu Corp Building information processing system and building information processing method
CN101109227A (en) * 2007-09-05 2008-01-23 中国建筑第七工程局 Construction method of single-stride large cantilever double-pre-stress concrete steel concrete crossbeam
CN101136259A (en) * 2007-09-27 2008-03-05 中国核工业第二三建设公司 Modularize building method for nuclear reactor of nuclear plant
CN101761134A (en) * 2009-12-31 2010-06-30 浙江中成建工集团有限公司 Construction technology of spatial variable curved surface reinforced concrete irregular barrel group structure
CN102345377A (en) * 2011-07-15 2012-02-08 广州市第三建筑工程有限公司 Method for making spatial multi-curved-surface as-cast finish concrete stay in place formwork by using plywood

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943565A (en) * 2012-11-30 2013-02-27 中国建筑第八工程局有限公司 Construction method of large-sized arc-shaped wall
CN103195247A (en) * 2013-04-19 2013-07-10 江苏省华建建设股份有限公司 Saddle-shaped hyperboloidal concrete slab construction method
CN103949860A (en) * 2014-04-30 2014-07-30 中国十九冶集团有限公司 Method for processing single-node-space multi-opening flange of tower
CN104120827A (en) * 2014-07-23 2014-10-29 浙江省一建建设集团有限公司 Ship rail type bare concrete wallboard and construction method thereof
CN104196012A (en) * 2014-08-28 2014-12-10 广州市第二建筑工程有限公司 Karst cave processing method based on BIM
CN106285028A (en) * 2015-05-28 2017-01-04 中国二十冶集团有限公司 Reinforcement of factory building construction method in long-span heavy type crane girder based on BIM technology dismounting
CN106245906A (en) * 2016-08-30 2016-12-21 中国葛洲坝集团三峡建设工程有限公司 The auxiliary abnormal formwork design of a kind of threedimensional model and the method installed
CN107451350B (en) * 2017-07-26 2021-01-22 中交一公局第二工程有限公司 Spatial three-dimensional special-shaped bridge pier template construction method based on BIM modeling technology
CN107451350A (en) * 2017-07-26 2017-12-08 中交公局第二工程有限公司 One kind is based on BIM modeling technique space three-dimensional abnormity bridge abutment moulding plate construction methods
CN107724299A (en) * 2017-09-29 2018-02-23 上海宝冶集团有限公司 A kind of manufacture method of hyperboloid anticollision barrier
CN107842192A (en) * 2017-11-23 2018-03-27 安徽同济建设集团有限责任公司 A kind of making of the outer builder's jack closed cover of architectural engineering and installation method
CN108363860A (en) * 2018-02-07 2018-08-03 中交公局第二工程有限公司 A kind of 3-D abnormal bridge formwork assembly setting out method based on BIM technology
CN108416162A (en) * 2018-03-23 2018-08-17 中国十七冶集团有限公司 A kind of construction method of the spiral formula reinforced concrete structure based on BIM
CN112131650A (en) * 2020-09-28 2020-12-25 中船黄埔文冲船舶有限公司 Construction method of curved surface structure
CN112131650B (en) * 2020-09-28 2024-05-14 中船黄埔文冲船舶有限公司 Construction method of curved surface structure
CN114673386A (en) * 2022-05-07 2022-06-28 广州茏腾园林景观设计有限公司 Construction method of hyperboloid special-shaped water drop waterscape and water drop waterscape system
CN114673386B (en) * 2022-05-07 2024-02-13 广州茏腾园林景观设计有限公司 Hyperboloid special-shaped drop waterscape construction method and drop waterscape system

Similar Documents

Publication Publication Date Title
CN102587658A (en) Construction method of variable curved-surface steel-concrete tubular structure
CN103612323B (en) A kind of concrete member mould and application thereof
CN106284976A (en) A kind of aluminum alloy mould plate based on Revit joins mould method
CN104631684A (en) Single-layer latticed shell steel structure roof system based on concrete building and assembling method of single-layer latticed shell steel structure roof system based on concrete building
CN109505609B (en) Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack
CN203213585U (en) Scaffold tool for pouring concrete slab provided with saddle-shaped double curved surfaces
CN103255918A (en) Concrete double-curved-surface thin shell cylinder construction method
CN103290967A (en) Multi-ribbed hollow composite floor slab and manufacturing method thereof
CN103195247B (en) Saddle-shaped hyperboloidal concrete slab construction method
CN105625719A (en) Tensile sheet structure aluminum alloy formwork early-dismantling system and construction method thereof
CN103306463B (en) Metal liner concrete air channel construction method
CN105544887A (en) Upturned roof-ridge cornice of Tang style simulation building and construction method thereof
CN110685434B (en) Cast-in-situ multi-curved surface double-layer oblique-crossing concrete grid structure formwork system and construction method
CN102205480A (en) Method for manufacturing spatial curved surface spiral box type component
CN214531887U (en) Template reinforcing system for arc-shaped wall
CN104929295A (en) Seamless steel tube construction method for double-curvature arc-shaped roof
CN102744774B (en) Prefabricated small box girder adjustable template for curved bridge
CN104196246A (en) Partial-evacuation in-site lifting construction method for multidirectional stress structure of continuous truss
CN110284706B (en) Construction method of internal mold support system for ultra-large wind tunnel diffusion section
CN115600277A (en) Method for binding reinforcing steel bars in bridge cable tower anchoring area based on software secondary development technology
CN203878718U (en) Joint structure of cover plate of trench and pipe trench
CN104389348B (en) A kind of installation method with covering arch structure
CN204098487U (en) Gear-like curved wall pilaster template
CN103510703B (en) Method for constructing concrete arch columns with variable cross-sections
CN203271118U (en) Double-curved-surface thin-shell-barrel reinforcing bar formwork

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120718