CN109505609B - Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack - Google Patents

Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack Download PDF

Info

Publication number
CN109505609B
CN109505609B CN201811392723.5A CN201811392723A CN109505609B CN 109505609 B CN109505609 B CN 109505609B CN 201811392723 A CN201811392723 A CN 201811392723A CN 109505609 B CN109505609 B CN 109505609B
Authority
CN
China
Prior art keywords
steel
support
vertical steel
permanent vertical
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811392723.5A
Other languages
Chinese (zh)
Other versions
CN109505609A (en
Inventor
王成
王旭
王硕
胡浩方
刘俊奇
李鋆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Fourth Highway Engineering Co Ltd
CCCC Construction Group Co Ltd
Original Assignee
CCCC Fourth Highway Engineering Co Ltd
CCCC Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Fourth Highway Engineering Co Ltd, CCCC Construction Group Co Ltd filed Critical CCCC Fourth Highway Engineering Co Ltd
Priority to CN201811392723.5A priority Critical patent/CN109505609B/en
Publication of CN109505609A publication Critical patent/CN109505609A/en
Application granted granted Critical
Publication of CN109505609B publication Critical patent/CN109505609B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/28Longitudinal struts, i.e. longitudinal connections between adjoining arches

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a bracket-free construction method of a shallow-buried underground excavation urban underground comprehensive pipe gallery and the comprehensive pipe gallery, wherein the method comprises the following steps: determining the number and positions of small pilot tunnels excavated step by step according to the number and positions of cabins designed by the pipe gallery; constructing an initial support after each excavation and footage of the small pilot tunnel is completed, arranging a permanent vertical steel support at the superposition position of the excavation boundary and the vertical intermediate wall, and respectively connecting the upper end and the lower end of the permanent vertical steel support with a grid steel frame or a steel arch in the initial support of the small pilot tunnel; and after the primary support of the small pilot tunnel is completed, a secondary lining is applied, permanent vertical steel supports are complementarily configured according to design requirements, a threaded reinforcing steel mesh is arranged between adjacent permanent vertical steel supports, the threaded reinforcing steel mesh is connected with the permanent vertical steel supports, the permanent vertical steel supports are used as a framework to pour the concrete of the intermediate wall, so that a reinforced concrete intermediate wall is formed, and then the reinforced concrete intermediate wall, the primary support and the secondary lining form a pipe gallery structure. The invention improves the structural strength of the middle partition wall while avoiding dismantling the steel support.

Description

Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a bracket-free construction method of a shallow-buried underground excavation urban underground comprehensive pipe rack and the comprehensive pipe rack.
Background
The urban underground utility tunnel is an emerging infrastructure construction block in recent years, and the urban underground utility tunnel intensively lays and manages various municipal pipelines, thereby improving the management efficiency. Because the pipe gallery is generally shallow in burial depth and large in section, when the shallow burial and underground excavation method is adopted, the pipe gallery is divided into a plurality of small pilot tunnels for excavation, and temporary supports are erected at the same time. Before the second lining is applied, the temporary support is removed. The temporary support is mounted and dismounted, so that the cost is increased, engineering machinery cannot be adopted due to the limitation of the temporary support, and the excavation progress is severely restricted.
Disclosure of Invention
The invention aims to provide a bracket-free construction method of a shallow-buried underground excavation urban underground comprehensive pipe gallery and the comprehensive pipe gallery, which avoid frequent installation and disassembly of temporary brackets, reduce construction cost and improve construction progress.
The invention provides a bracket-free construction method of a shallow underground excavation urban underground comprehensive pipe gallery, which comprises the following steps:
step 1, determining the number and positions of small pilot tunnels excavated step by step according to the number and positions of cabins designed by a pipe gallery;
step 2, constructing an initial support after each excavation and footage of the small pilot tunnel is completed, arranging a permanent vertical steel support at the superposition position of the excavation boundary and the vertical intermediate wall to form a vertical temporary construction support, and respectively connecting the upper end and the lower end of the permanent vertical steel support with a grid steel frame or a steel arch in the initial support of the small pilot tunnel;
and 3, performing secondary lining after the primary support of the small pilot tunnel is completed, supplementing and configuring permanent vertical steel supports according to design requirements, arranging a twisted steel mesh between adjacent permanent vertical steel supports, connecting the twisted steel mesh with the permanent vertical steel supports, pouring the permanent vertical steel supports as a framework into the middle partition wall concrete to form a reinforced concrete middle partition wall, and further forming a pipe gallery structure with the primary support and the secondary lining.
Further, the number of permanent vertical steel supports is determined according to the magnitude of the vertical load.
Further, the permanent vertical steel support adopts H-shaped steel or double angle steel.
The invention also provides a shallow underground excavation urban underground comprehensive pipe gallery, which comprises a plurality of small pilot holes excavated step by step, wherein a plurality of permanent vertical steel supports are arranged at the superposition positions of the excavation boundaries of the small pilot holes and the vertical intermediate wall, and the upper and lower ends of the permanent vertical steel supports are respectively connected with a grid steel frame or a steel arch in the primary support of the small pilot holes;
a thread steel bar net is arranged between the adjacent permanent vertical steel supports, the thread steel bar net is connected with the permanent vertical steel supports, the permanent vertical steel supports are used as frameworks for casting concrete, a reinforced concrete intermediate wall is formed, and the reinforced concrete intermediate wall, the primary support and the secondary lining form a pipe gallery structure.
Further, the number of permanent vertical steel supports is determined according to the magnitude of the vertical load.
Further, the permanent vertical steel support adopts H-shaped steel or double angle steel.
By means of the scheme, the shoveless construction method of the underground comprehensive pipe rack in the shallow-buried underground excavation city and the comprehensive pipe rack, the construction load is borne by the permanent vertical steel support arranged on the intermediate wall, the temporary support is achieved, the secondary lining concrete is directly poured into the intermediate wall when the secondary lining concrete is to be poured, and the structural strength of the intermediate wall is improved while the steel support is prevented from being removed.
The foregoing description is only an overview of the present invention, and is intended to provide a better understanding of the present invention, as it is embodied in the following description, with reference to the preferred embodiments of the present invention and the accompanying drawings.
Drawings
FIG. 1 is a first construction state diagram of a shallow underground excavation urban underground utility tunnel according to an embodiment of the present invention;
FIG. 2 is a second construction state diagram of a shallow underground excavation urban utility tunnel according to an embodiment of the present invention;
FIG. 3 is a schematic diagram of a fully constructed shallow underground excavation urban underground utility tunnel in accordance with an embodiment of the present invention.
Reference numerals in the drawings:
1-pilot hole in advance; 2-a backward guide hole; 3-primary support; 4-permanent vertical steel support; 5-secondary lining.
Detailed Description
The following describes in further detail the embodiments of the present invention with reference to the drawings and examples. The following examples are illustrative of the invention and are not intended to limit the scope of the invention.
The embodiment provides a bracket-free construction method of a shallow-buried underground excavation urban underground comprehensive pipe gallery, which comprises the following steps:
and step 1, determining the number and positions of small pilot tunnels excavated step by step according to the number and positions of cabins designed by the pipe gallery. For example, a double-deck pipe gallery excavates with two small pilot holes, a three-deck pipe gallery excavates with three small pilot holes, and the boundary of each small pilot hole coincides with the intermediate wall after the pipe gallery is completed.
And 2, constructing an initial support after the small pilot tunnel is excavated and footed each time, arranging a permanent vertical steel support at the superposition position of the excavation boundary and the vertical intermediate wall to form a vertical temporary construction support, and connecting the upper end and the lower end of the permanent vertical steel support with a grid steel frame or a steel arch in the initial support of the small pilot tunnel respectively so as to bear construction load.
And 3, performing secondary lining after the primary support of the small pilot tunnel is completed, supplementing and configuring permanent vertical steel supports according to design requirements, arranging a twisted steel mesh between adjacent permanent vertical steel supports, connecting the twisted steel mesh with the permanent vertical steel supports, pouring the permanent vertical steel supports as a framework into the middle wall concrete (without dismantling the steel supports), forming a reinforced concrete middle wall, and further forming a pipe gallery structure with the primary support and the secondary lining.
By the support-free construction method for the shallow underground excavation urban underground comprehensive pipe gallery, the work of installing, dismantling, transporting outwards and the like of a temporary support in the existing construction method is completely avoided while the safety of pipe gallery excavation is ensured, engineering materials are saved, meanwhile, labor cost is reduced, excavation circulation time is shortened, and construction progress is accelerated.
In this embodiment, the number of permanent vertical steel supports (erected per excavation cycle) is determined according to the magnitude of the vertical load.
In this embodiment, the permanent vertical steel support is H-section steel or double angle steel.
The embodiment also provides a shallow underground excavation urban underground comprehensive pipe gallery, which comprises a plurality of small pilot holes excavated step by step, wherein a plurality of permanent vertical steel supports are arranged at the superposition positions of the excavation boundaries of the small pilot holes and the vertical intermediate wall, and the upper ends and the lower ends of the permanent vertical steel supports are respectively connected with a grid steel frame or a steel arch in the primary support of the small pilot holes;
a thread steel bar net is arranged between the adjacent permanent vertical steel supports, the thread steel bar net is connected with the permanent vertical steel supports, the permanent vertical steel supports are used as frameworks for casting concrete, a reinforced concrete intermediate wall is formed, and the reinforced concrete intermediate wall, the primary support and the secondary lining form a pipe gallery structure.
Through this shallow underground excavation urban underground utility tunnel, when guaranteeing the piping lane excavation safety, avoided the installation of interim support in the current utility tunnel completely, demolishd and outward fortune scheduling work, reduced the labour cost when practicing thrift engineering material to shortened excavation cycle time, accelerated the construction progress, simultaneously, improved the structural strength of median wall.
In this embodiment, the number of permanent vertical steel supports (erected per excavation cycle) is determined according to the magnitude of the vertical load.
In this embodiment, the permanent vertical steel support is H-section steel or double angle steel.
Referring to fig. 1 to 3, the construction method will be described below by taking a double deck pipe gallery as an example, and the construction steps of the double deck pipe gallery include:
(1) According to the arrangement of the pipe gallery cabins, the whole excavation section is divided into two parts, two pilot tunnels are excavated step by step, and the size and the position of each pilot tunnel are consistent with the positions of the cabins.
(2) The pilot tunnel 1 is excavated, after the excavation footage is completed each time, an initial support 3 is constructed, a permanent vertical steel support 4 is erected to form a vertical temporary construction support for bearing vertical load in the construction process, the permanent vertical steel support 4 is required to be ensured to be vertical, and the vertical axis of the permanent vertical steel support is coincident with the axis of the intermediate wall.
(3) And excavating the backward pilot tunnel 2, constructing an initial support 3 after each circulation footage is completed, and erecting a permanent vertical steel support 4 to form a vertical temporary construction support.
(4) And after the pilot tunnel is tunneled for a sufficient distance, pouring the concrete of the secondary lining 5, and pouring the concrete on the permanent vertical steel support 4 (section steel) of the intermediate wall to form the reinforced concrete intermediate wall.
Through the construction method, the whole section of the pipe gallery is divided into corresponding small pilot tunnel excavation according to cabin arrangement, and permanent vertical steel supports are arranged at the intermediate wall after each cycle of excavation is completed. When the secondary lining is poured, the permanent vertical steel support is directly poured into concrete as an intermediate wall framework to be used as a part of the intermediate wall structure. The structural strength of the middle partition wall is improved while the steel support is prevented from being dismantled.
The above description is only of the preferred embodiments of the present invention and is not intended to limit the present invention, and it should be noted that it is possible for those skilled in the art to make several improvements and modifications without departing from the technical principle of the present invention, and these improvements and modifications should also be regarded as the protection scope of the present invention.

Claims (6)

1. The bracket-free construction method of the shallow underground excavation urban underground comprehensive pipe gallery is characterized by comprising the following steps of:
step 1, determining the number and positions of small pilot tunnels excavated step by step according to the number and positions of cabins designed by a pipe gallery;
step 2, constructing an initial support after each excavation and footage of the small pilot tunnel is completed, arranging a permanent vertical steel support at the superposition position of the excavation boundary and the vertical intermediate wall to form a vertical temporary construction support, and connecting the upper end and the lower end of the permanent vertical steel support with a grid steel frame or a steel arch in the initial support of the small pilot tunnel respectively;
and 3, performing secondary lining after the primary support of the small pilot tunnel is completed, supplementing and configuring permanent vertical steel supports according to design requirements, arranging a twisted steel mesh between adjacent permanent vertical steel supports, connecting the twisted steel mesh with the permanent vertical steel supports, pouring the permanent vertical steel supports as a framework into the middle partition wall concrete to form a reinforced concrete middle partition wall, and further forming a pipe gallery structure with the primary support and the secondary lining.
2. The bracket-free construction method of the shallow underground excavation urban underground utility tunnel of claim 1, wherein the number of permanent vertical steel supports is determined according to the magnitude of vertical load.
3. The bracket-free construction method of the shallow underground excavation urban underground utility tunnel of claim 1, wherein the permanent vertical steel support is H-shaped steel or double-angle steel.
4. The utility model provides a shallow underground excavation urban underground utility tunnel which is characterized in that the utility tunnel comprises a plurality of small pilot tunnels excavated step by step, a plurality of permanent vertical steel supports are arranged at the superposition position of the excavation boundary of the small pilot tunnels and a vertical intermediate wall, and the upper end and the lower end of each permanent vertical steel support are respectively connected with a grid steel frame or a steel arch in the primary support of the small pilot tunnels;
a screw thread reinforcing steel mesh is arranged between the adjacent permanent vertical steel supports, the screw thread reinforcing steel mesh is connected with the permanent vertical steel supports, the permanent vertical steel supports are used as frameworks for casting concrete to form reinforced concrete intermediate walls, and the reinforced concrete intermediate walls, the primary supports and the secondary lining form a pipe gallery structure.
5. The shallow-buried underground excavation urban utility tunnel of claim 4, wherein the number of permanent vertical steel supports is determined based on the magnitude of the vertical load.
6. The shallow-buried underground excavation urban utility tunnel of claim 4, wherein the permanent vertical steel support is H-section steel or double angle steel.
CN201811392723.5A 2018-11-21 2018-11-21 Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack Active CN109505609B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811392723.5A CN109505609B (en) 2018-11-21 2018-11-21 Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811392723.5A CN109505609B (en) 2018-11-21 2018-11-21 Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack

Publications (2)

Publication Number Publication Date
CN109505609A CN109505609A (en) 2019-03-22
CN109505609B true CN109505609B (en) 2023-11-14

Family

ID=65749513

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811392723.5A Active CN109505609B (en) 2018-11-21 2018-11-21 Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack

Country Status (1)

Country Link
CN (1) CN109505609B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617079A (en) * 2019-10-28 2019-12-27 中铁二院工程集团有限责任公司 Shield comprehensive pipe gallery pipeline installation shed frame system
CN110714791A (en) * 2019-10-29 2020-01-21 中国十七冶集团有限公司 Method for shallow-buried and underground-excavated two-lining waterproof rapid construction in comprehensive pipe gallery engineering
CN111188640B (en) * 2020-01-16 2021-08-31 中国十七冶集团有限公司 Underground pipe gallery shallow-buried underground tunnel waterproof plate installation trolley and construction method thereof
CN111828051B (en) * 2020-07-28 2022-04-15 中建七局安装工程有限公司 Construction method of two-lining middle partition wall injection tunnel with support
CN112065451B (en) * 2020-09-14 2022-06-28 中国建筑第八工程局有限公司 Underground excavation method for underground passage
CN113339000A (en) * 2021-06-03 2021-09-03 上海市城市建设设计研究总院(集团)有限公司 Cable steel pipe shell trenchless supporting structure with intermediate wall and construction method

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4402358A1 (en) * 1994-01-27 1995-08-03 Quante Heinrich Berg Ing Stacking pot pillar for mining supports
JP2003160944A (en) * 2001-11-26 2003-06-06 Hokukon Co Ltd Construction method for precast concrete reservoir
CN101666232A (en) * 2009-09-27 2010-03-10 中铁四局集团有限公司 Construction method for six-part excavation of super-large section tunnel
CN101749031A (en) * 2009-12-24 2010-06-23 北京交通大学 Compound grouting reinforcement method for subsea tunnel going through water-rich sand stratum
CN102650212A (en) * 2012-05-04 2012-08-29 中国十七冶集团有限公司 Construction method for protecting partition wall in double-arch tunnel through temporary support of middle pilot tunnel
CN102704939A (en) * 2012-06-26 2012-10-03 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section
CN103835728A (en) * 2012-11-27 2014-06-04 五冶集团上海有限公司 Method for pouring concrete into mid-board arch crown of multi-arch tunnel
CN105370288A (en) * 2015-10-28 2016-03-02 北京市市政工程设计研究总院有限公司 Construction method of shallow-buried large-span tunnels
CN106088147A (en) * 2016-08-01 2016-11-09 中建五局第三建设有限公司 Hollow wallboard mixed prefabricated assembly type comprehensive pipe gallery and construction method thereof
CN106836273A (en) * 2017-01-13 2017-06-13 沈阳建筑大学 A kind of pair of arch Urban Underground Complex and its tunneling method of construction
CN107130968A (en) * 2017-07-11 2017-09-05 北京市政建设集团有限责任公司 A kind of tunnel construction mid-board
CN107401411A (en) * 2017-07-11 2017-11-28 中交隧道工程局有限公司 Step excavation construction method is strengthened in a kind of interim perpendicular support for being applied to IV grade of country rock Shallow depth bored tunnel
CN107725064A (en) * 2017-11-22 2018-02-23 北京市政建设集团有限责任公司 Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method
CN108166989A (en) * 2018-01-31 2018-06-15 中铁二十局集团轨道交通工程有限公司 The asymmetric twin-arch tunnel interval wall construction method of water rich strata " OC " shape
CN108180025A (en) * 2018-01-31 2018-06-19 中铁二十局集团轨道交通工程有限公司 A kind of circular cross section tunnel lining construction method three times
CN208749354U (en) * 2018-11-21 2019-04-16 中交第四公路工程局有限公司 Shallow buried covered excavation Urban Underground pipe gallery

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967050B (en) * 2014-01-29 2015-05-20 广州机施建设集团有限公司 Construction system of subway station

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4402358A1 (en) * 1994-01-27 1995-08-03 Quante Heinrich Berg Ing Stacking pot pillar for mining supports
JP2003160944A (en) * 2001-11-26 2003-06-06 Hokukon Co Ltd Construction method for precast concrete reservoir
CN101666232A (en) * 2009-09-27 2010-03-10 中铁四局集团有限公司 Construction method for six-part excavation of super-large section tunnel
CN101749031A (en) * 2009-12-24 2010-06-23 北京交通大学 Compound grouting reinforcement method for subsea tunnel going through water-rich sand stratum
CN102650212A (en) * 2012-05-04 2012-08-29 中国十七冶集团有限公司 Construction method for protecting partition wall in double-arch tunnel through temporary support of middle pilot tunnel
CN102704939A (en) * 2012-06-26 2012-10-03 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section
CN103835728A (en) * 2012-11-27 2014-06-04 五冶集团上海有限公司 Method for pouring concrete into mid-board arch crown of multi-arch tunnel
CN105370288A (en) * 2015-10-28 2016-03-02 北京市市政工程设计研究总院有限公司 Construction method of shallow-buried large-span tunnels
CN106088147A (en) * 2016-08-01 2016-11-09 中建五局第三建设有限公司 Hollow wallboard mixed prefabricated assembly type comprehensive pipe gallery and construction method thereof
CN106836273A (en) * 2017-01-13 2017-06-13 沈阳建筑大学 A kind of pair of arch Urban Underground Complex and its tunneling method of construction
CN107130968A (en) * 2017-07-11 2017-09-05 北京市政建设集团有限责任公司 A kind of tunnel construction mid-board
CN107401411A (en) * 2017-07-11 2017-11-28 中交隧道工程局有限公司 Step excavation construction method is strengthened in a kind of interim perpendicular support for being applied to IV grade of country rock Shallow depth bored tunnel
CN107725064A (en) * 2017-11-22 2018-02-23 北京市政建设集团有限责任公司 Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method
CN108166989A (en) * 2018-01-31 2018-06-15 中铁二十局集团轨道交通工程有限公司 The asymmetric twin-arch tunnel interval wall construction method of water rich strata " OC " shape
CN108180025A (en) * 2018-01-31 2018-06-19 中铁二十局集团轨道交通工程有限公司 A kind of circular cross section tunnel lining construction method three times
CN208749354U (en) * 2018-11-21 2019-04-16 中交第四公路工程局有限公司 Shallow buried covered excavation Urban Underground pipe gallery

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
大跨平顶直墙暗挖通道二次衬砌技术探析;田海波;;隧道建设(第03期);全文 *
浅埋暗挖施工技术在地铁工程中的应用;李誉;;广东科技(第06期);全文 *
监控量测在姚村坦隧道施工险情预报中的应用;郑卫华;程振华;柳伟;;交通科技与经济(第03期);全文 *
邻地铁的建筑深基坑中隔墙支撑换撑及墙体拆除施工技术;费巍;张德标;王成焱;;建筑施工(第12期);全文 *

Also Published As

Publication number Publication date
CN109505609A (en) 2019-03-22

Similar Documents

Publication Publication Date Title
CN109505609B (en) Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack
CN109723085B (en) Deep foundation pit division construction rib wall support replacing structure and construction method thereof
CN105256812B (en) Foundation ditch prefabricated assembled concrete supporting construction and its construction method
CN210086295U (en) Compound assembled underground structure
CN111365017B (en) Construction method of underground intercommunication tunnel
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
CN104032744A (en) Support replacing construction method in group pit project
CN105525753A (en) Method and structure for simultaneously constructing constructional column and main body structure
CN103628572A (en) Project beam-column joint for reverse building method
CN104328789A (en) Overhanging type support changing construction method for reinforced concrete horizontal inner support
CN108343450B (en) Novel pipe curtain method working well reinforcing structure and reinforcing method
CN105370038A (en) Jointing method of construction joint of reinforced concrete shear wall body
CN110985042A (en) Urban comprehensive pipe gallery and underground shallow-buried underground tunnel combined supporting system and process
CN113464145A (en) Excavation construction method for weak surrounding rock large-section tunnel
CN111778990A (en) Permanent-temporary combined assembly type inner support system and construction method
CN204715764U (en) The structure that a kind of constructional column and agent structure are constructed simultaneously
CN106351235A (en) Assembled type four-combined-round-steel-pipe concrete inner support structure and manufacturing method
CN108756932B (en) Tunnel construction method comprising supporting structure
CN115125995B (en) Construction method for entrance and exit ring frames of assembled station
CN115467690A (en) Shallow-buried large-span underground excavation subway station new structure system and construction method thereof
CN112682048B (en) Replacement reinforcement construction method for small clear distance up-span existing tunnel of newly-built tunnel
CN211368733U (en) Prefabricated assembled concrete pipe props structure
CN212054734U (en) A template that is used for quick lining cutting of city portal tunnel
CN212506301U (en) Support system in combination assembled forever
CN205134326U (en) Prefabricated assembled concrete bearing structure of foundation ditch

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No.114, Jiaodaokou South Street, Dongcheng District, Beijing, 100007

Applicant after: CCCC Construction Group Co.,Ltd.

Applicant after: CCCC FOURTH HIGHWAY ENGINEERING Co.,Ltd.

Address before: 100022 27th floor, building a, Jindi center, 91 Jianguo Road, Chaoyang District, Beijing

Applicant before: CCCC FOURTH HIGHWAY ENGINEERING Co.,Ltd.

Applicant before: CCCC FOURTH HIGHWAY FIRST ENGINEERING FIRMS CO.,LTD.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant