- Prior art keywords
- girder
- top rail
- hanging basket
- column
- roller bearing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a bridge construction rolling shaft hanging basket across railway existing line and a use method thereof. The invention has the technical scheme that a front support leg and a rear support leg are installed on a slide way, a main beam, a vertical column and a diagonal draw bar form a triangular combination beam, an upper front cross beam is installed at the front end of the main beam, a rear anchor rod is precast in bridge concrete, and a carrying pole beam rests on the rear part of the main beam and is connected with the rear anchor rod. The use method comprises the following steps of: anchoring the slide way by using the rear anchor rod, jacking up the triangular combination beam, placing a round steel rolling shaft on the front support leg, removing the anchor rod, and pulling the rolling shaft hanging basket forward by using a chain block to slide in place. Because the center of gravity of the rolling shaft hanging basket moves backward by adding the round steel rolling shaft between the front support leg and the main beam, the friction force during movement is reduced, the construction task of moving the hanging basket can be finished within 1 h 30 min, the task of moving the hanging basket is finished at a train sunroof point on the existing line, and the effect of safely and timely ensuring the normal operation of the existing line is achieved.
Description
Technical field
The present invention relates to a kind of special construction apparatus of striding the railway existing line, specifically is that a kind of roller bearing of striding railway existing line bridge construction is hung indigo plant and method for using thereof, belongs to the railway construction machine field.
Background technology
In the construction of railways process; Inevitably will run into the existing railway line of leap and construct continuously, and the normal passing train of existing line is very frequent, like Beijing-Guangzhou Railway passing 240 multiple rows every day; Average per 10 minutes through row; In order to guarantee the enforcement safety of the passing train of existing line, crossing over the existing line construction must quick, accurate, timely, orderly carrying out, and the engineering time generally confirms not have the period that EMUs pass through in morning at night; No longer than two hours, be called " skylight " time.To in the so short time, accomplish construction continuously, just construction equipment proposed higher requirement.What generally adopt at present is cradle construction; Its front leg strut of Hanging Basket is positioned under the column; Because the Hanging Basket center of gravity is forward, causes Hanging Basket front fulcrum place frictional force bigger, Hanging Basket is more time-consuming when mobile; Can not guarantee in " skylight " smooth, safe Hanging Basket is moved into place in the time also do not have a kind of desirable railway to stride the existing line construction at present and hang blue equipment.
Summary of the invention
Hang blue existing defective in order to overcome present construction; The invention discloses a kind of railway existing line bridge construction roller bearing of striding and hang indigo plant and method for using thereof, be with the reach of Hanging Basket front leg strut, and between front leg strut and girder, add three road round steel roller bearings; Move after making the Hanging Basket center of gravity, the Hanging Basket mobile security is quick.
The technical scheme that railway of the present invention is striden existing line bridge construction ball extension indigo plant is following:
Lay two slideways, a front leg strut and a rear support leg are installed on every slideway, front leg strut is placed directly on the slideway; The rear support leg left-hand thread is respectively being installed a girder on each front leg strut with on the rear support leg on slideway, top rail after the girder middle part connection; Column is installed on the infall of girder and back top rail, and back top rail is arranged at the column below, and column is arranged on the top rail of back; Back top rail connects girder, and girder connects column, is connected with diagonal member between column and the girder; Girder, column and diagonal member are formed a triangle compound beam, top rail before the connection of girder front end, and preceding top rail is connected respectively with the back lower transverse beam with preceding lower transverse beam and back top rail; Bed die longeron and preceding lower transverse beam and back lower transverse beam are connected, are connected pre-buried anchor pole afterwards in bridge concrete with binding-beam between column and the column; Shoulder pole girder be pressed in the girder rear portion and with the back anchor pole link to each other, 3-5 root shoulder pole girder is set behind the girder, establish the 6-10 root after anchor pole it is carried out anchoring; A rear support leg is set in rear end, girder bottom and tightly cuts, 3-5 root round steel roller bearing is installed above the front leg strut and is tightly cut with girder with the slideway steel plate.
The method for using that roller bearing of the present invention is hung indigo plant is following:
A. at first use the back anchor pole that the slideway anchoring is firm; Remove the back anchor pole of triangle compound beam then; At this moment the triangle compound beam by left-hand thread wheels left-hand thread on slideway; Prevent that the triangle compound beam from toppling, subsequently at triangle compound beam front end with jack with triangle compound beam jack-up, on front leg strut, place three round steel roller bearings immediately;
B. remove the back anchor system, it is reliable to guarantee that each anchoring piece connects, and under the track blockade situation, is spurred forward by jack and roller bearing is hung blue slippage puts in place, simultaneously preceding top rail, preceding lower transverse beam, back top rail, back lower transverse beam, bed die longeron synchronization-sliding is put in place;
C. slideway will be laid smooth straightly, must not squint, and guarantees that the left and right sides is evenly synchronous, and left-hand thread is on slideway all the time to keep the left-hand thread wheels, and the girder front end is wanted timely cushioning, and main beam rear end is established anchor and compressed, in order to avoid topple, girder moves on to the shoulder pole girder of anchoring in time behind the position;
D. after the reach of roller bearing Hanging Basket puts in place; In time carry out anchoring; With the absolute altitude and the axis of jack adjustment roller bearing Hanging Basket, guarantee that roller bearing Hanging Basket front and rear fulcrum is on the same horizontal plane, and the longitudinal midline of whole roller bearing Hanging Basket is overlapped with bridge axes then; Tighten back anchor connector, make the back anchor pole stressed the jack unloading.
Roller bearing Hanging Basket front leg strut is moved forward; And between front leg strut and girder, add the round steel roller bearing; Move after making roller bearing Hanging Basket center of gravity, reduced the frictional force when the roller bearing Hanging Basket moves, only needed 1 hour 30 minutes can accomplish the construction task that Hanging Basket moves; Can in existing line is driven a vehicle skylight point, accomplish Hanging Basket fully and move task, reach safety and in time guaranteed the normal effect of runing of existing line.
Description of drawings
Accompanying drawing 1 is a main TV structure sketch map of the present invention.
Accompanying drawing 2 for the present invention along accompanying drawing 1A-A to the cross section structure sketch map.
Accompanying drawing 3 for the present invention along accompanying drawing 1B-B to the cross section structure sketch map.
Description of reference numerals is following:
The specific embodiment
Below in conjunction with embodiment and accompanying drawing the present invention is explained further details:
Lay two slideways (9), a front leg strut (10) and a rear support leg (11) are installed on every slideway (9), front leg strut (10) is placed directly on the slideway (9); Rear support leg (11) left-hand thread is respectively installed a girder (1) on each front leg strut (10) and rear support leg (11) on slideway (9), top rail (6) after girder (1) the middle part connection; Column (2) is installed on the infall of girder (1) and back top rail (6); Column (2) is arranged on the top rail of back, and back top rail (6) connects girder (1), and girder (1) connects column (2); Be connected with diagonal member (3) between column (2) and the girder (1); Girder (1), column (2) are formed a triangle compound beam with diagonal member (3), between the top rail (4) before girder (1) front end utilizes bolt to connect, preceding top rail (4) and preceding lower transverse beam (5) and after top rail (6) with after use steel suspender belt (15) respectively between the lower transverse beam (7)) be connected; Be connected with bolt respectively between bed die longeron (8) and preceding lower transverse beam (5) and the back lower transverse beam (7); Be connected with pin between column (2) and the column binding-beam (13), pre-buried back anchor pole (16) in the pontic concrete, shoulder pole girder (12) are pressed in girder (1) rear portion and link to each other with back anchor pole (16); 3 shoulder pole girders (12) are set behind the girder (1); If anchor pole after 6 (16) carries out anchoring to it, a rear support leg (11) is set in girder (1) rear end, bottom and tightly cuts with slideway (9) steel plate, 3 round steel roller bearings (14) are installed above the front leg strut (10) and are tightly cut with girder (1).
The method for using that roller bearing of the present invention is hung indigo plant is following:
A. at first use back anchor pole (16) that slideway (9) anchoring is firm; Remove the back anchor pole (16) of triangle compound beam then; At this moment the triangle compound beam by left-hand thread wheels left-hand thread on slideway (9); Prevent that the triangle compound beam from toppling, subsequently at triangle compound beam front end with jack with triangle compound beam jack-up, go up to place three round steel roller bearings (14) at front leg strut (10) immediately;
B. remove the back anchor system; It is reliable to guarantee that each anchoring piece connects; Under the track blockade situation, spur forward and roller bearing is hung blue slippage put in place, simultaneously preceding top rail (4), preceding lower transverse beam (5), back top rail (6), back lower transverse beam (7), bed die longeron (8) synchronization-sliding are put in place by jack;
C. slideway (9) will be laid smooth straightly, must not squint, and guarantees that the left and right sides is evenly synchronous; Left-hand thread is on slideway (9) all the time to keep the left-hand thread wheels, and girder (1) front end is wanted timely cushioning, and girder (1) rear end is established anchor and compressed; In order to avoid topple, girder (1) moves on to the shoulder pole girder of anchoring in time (12) behind the position;
D. after the reach of roller bearing Hanging Basket puts in place; In time carry out anchoring; With the absolute altitude and the axis of jack adjustment roller bearing Hanging Basket, guarantee that roller bearing Hanging Basket front and rear fulcrum is on the same horizontal plane, and the longitudinal midline of whole roller bearing Hanging Basket is overlapped with bridge axes then; Tighten back anchor connector, make the back anchor pole stressed the jack unloading.
After removing the roller bearing Hanging Basket before the anchor;, with roller bearing Hanging Basket girder jack-up 5cm front leg strut is moved to apart from next 40cm place, beam section termination with the 50t hydraulic jack, and the front leg strut stop is installed; Move after the roller bearing Hanging Basket center of gravity like this; Three round steel roller bearings are installed in safety when increase roller bearing Hanging Basket moves then at the front leg strut top, the frictional force when moving to reduce the roller bearing Hanging Basket.After finishing, the existing line Construction of continuous beam assembles striding; Carry out the roller bearing Hanging Basket and move construction task; After maincenter existing line continuous beam closure section construction finishes, the roller bearing Hanging Basket is retreated to railway existing line gauge remove outward, use in order to next Construction of continuous beam.
Claims (2)
1. stride railway existing line bridge construction roller bearing and hang indigo plant, it is characterized in that a front leg strut (10) and a rear support leg (9) respectively are installed on two slideways (9) of laying, front leg strut (10) is placed directly on the slideway (9); Rear support leg (11) left-hand thread is respectively installed a girder (1) on each front leg strut (10) and rear support leg (11) on slideway (9), top rail (6) after girder (1) the middle part connection; Column (2) is installed on the infall of girder (1) and back top rail (6); Column (2) is arranged on the top rail of back, and back top rail (6) connects girder (1), and girder (1) connects column (2); Be connected with diagonal member (3) between column (2) and the girder (1); Girder (1), column (2) are formed a triangle compound beam with diagonal member (3), top rail (4) before girder (1) front end connection, and preceding top rail (4) is connected respectively with back lower transverse beam (7) with preceding lower transverse beam (5) and back top rail (6); Bed die longeron (8) is connected with preceding lower transverse beam (5) and back lower transverse beam (7); Be connected with column binding-beam (13) between column (2) and the column (2), pre-buried back anchor pole (16) in bridge concrete, shoulder pole girder (12) are pressed in girder (1) rear portion and link to each other with back anchor pole (16); 3-5 root shoulder pole girder (12) is set behind the girder (1); If anchor pole behind the 6-10 root (16) carries out anchoring to it, a rear support leg (11) is set in girder (1) rear end, bottom and tightly cuts with slideway (9) steel plate, 3-5 root round steel roller bearing (14) is installed above the front leg strut (10) and is tightly cut with girder (1);
Roller bearing according to the invention is hung blue method for using, it is characterized in that:
A. at first use back anchor pole (16) that slideway (9) anchoring is firm; Remove the back anchor pole (16) of triangle compound beam then; At this moment the triangle compound beam by left-hand thread wheels left-hand thread on slideway (9); Prevent that the triangle compound beam from toppling, subsequently at triangle compound beam front end with jack with triangle compound beam jack-up, go up to place three round steel roller bearings (14) at front leg strut (10) immediately;
B. remove the back anchor system; It is reliable to guarantee that each anchoring piece connects; Under the track blockade situation, spurred forward by jack and roller bearing is hung blue slippage put in place, preceding top rail (4), preceding lower transverse beam (5), back top rail (6), back lower transverse beam (7), bed die longeron (8) synchronization-sliding put in place;
C. slideway (9) will be laid smooth straightly, must not squint, and guarantees that the left and right sides is evenly synchronous; Left-hand thread is on slideway (9) all the time to keep the left-hand thread wheels, and girder (1) front end is wanted timely cushioning, and girder (1) rear end is established anchor and compressed; In order to avoid topple, girder (1) moves on to the shoulder pole girder of anchoring in time (12) behind the position;
D. after the reach of roller bearing Hanging Basket puts in place; In time carry out anchoring; With the absolute altitude and the axis of jack adjustment roller bearing Hanging Basket, guarantee that roller bearing Hanging Basket front and rear fulcrum is on the same horizontal plane, and the longitudinal midline of whole roller bearing Hanging Basket is overlapped with bridge axes then; Tighten back anchor connector, make the back anchor pole stressed the jack unloading.
2. the railway existing line bridge construction roller bearing of striding according to claim 1 is hung blue; It is characterized in that utilizing bolt to connect rear support leg (11) behind the girder (1); Back top rail (6) utilizes bolt to connect girder (1); Girder (1) utilizes bolt to connect column (2); Column (2) and girder (1) are connected with pin respectively with between the diagonal member (3), between the top rail (4) before girder (1) front end connects with bolt, preceding top rail (4) and preceding lower transverse beam (5) and back top rail (6) and afterwards use steel suspender belt (15) respectively between the lower transverse beam (7)) be connected; Be connected with bolt respectively between bed die longeron (8) and preceding lower transverse beam (5) and the back lower transverse beam (7), be connected with pin between column (2) and the column binding-beam (13).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011103776646A CN102373673A (en) | 2011-11-24 | 2011-11-24 | Bridge construction rolling shaft hanging basket across railway existing line and use method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011103776646A CN102373673A (en) | 2011-11-24 | 2011-11-24 | Bridge construction rolling shaft hanging basket across railway existing line and use method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102373673A true CN102373673A (en) | 2012-03-14 |
Family
ID=45792850
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011103776646A Pending CN102373673A (en) | 2011-11-24 | 2011-11-24 | Bridge construction rolling shaft hanging basket across railway existing line and use method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102373673A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102758404A (en) * | 2012-07-19 | 2012-10-31 | 中铁十六局集团第一工程有限公司 | Front fulcrum hanging basket travelling device of spatial V-shaped cable-stayed bridge |
CN102926330A (en) * | 2012-11-27 | 2013-02-13 | 吴云 | Installation method of hanging basket suitable for bridge construction |
CN103088759A (en) * | 2012-12-22 | 2013-05-08 | 中国建筑第七工程局有限公司 | Prestress lower longitudinal beam bridge cast-in-cantilever construction hanging basket |
CN103850185A (en) * | 2014-02-20 | 2014-06-11 | 中交三航局第三工程有限公司 | Multi-truss type hanging basket for super-wide type bridge construction |
CN104018691A (en) * | 2014-06-17 | 2014-09-03 | 中铁城建集团第二工程有限公司 | Safety protection method for steel-structure house hoisting construction across existing lines |
CN104631343A (en) * | 2015-02-15 | 2015-05-20 | 河海大学 | Self-travelling diamond-shaped pin-connected truss-type form traveler structure and form traveler travelling and constructing method |
CN108103948A (en) * | 2017-12-25 | 2018-06-01 | 中交路桥华南工程有限公司 | Erection crane and thereafter anchor device |
JP2019078090A (en) * | 2017-10-25 | 2019-05-23 | 鹿島建設株式会社 | Overhang erection work vehicle and construction method |
CN114541273A (en) * | 2022-03-31 | 2022-05-27 | 中国建筑第四工程局有限公司 | Novel rear anchor point anchor rod setting device and construction method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03275803A (en) * | 1990-03-23 | 1991-12-06 | Kawada Kensetsu Kk | Moving construction device for high level structure |
CN2801872Y (en) * | 2005-05-27 | 2006-08-02 | 路桥集团第二公路工程局 | Moving device of hanging basket main truss front supporting point |
CN101148861A (en) * | 2007-06-06 | 2008-03-26 | 宏润建设集团股份有限公司 | Beret truss type hanging basket and assembling method thereof |
CN201169749Y (en) * | 2008-03-26 | 2008-12-24 | 中铁四局集团有限公司 | Simple-mounted pin connection triangle hanging basket |
CN201665823U (en) * | 2009-12-04 | 2010-12-08 | 中国第一冶金建设有限责任公司 | Bridge hanging basket cast-in-situ construction triangular rear anchor inverse buckling wheel enhanced type rail |
CN102174795A (en) * | 2011-03-28 | 2011-09-07 | 中铁一局集团有限公司 | Reversible suspended basket wheel type travelling system and method |
CN202530383U (en) * | 2011-11-24 | 2012-11-14 | 中铁二十一局集团有限公司 | Cross-existing railway bridge construction roller hanging basket |
-
2011
- 2011-11-24 CN CN2011103776646A patent/CN102373673A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03275803A (en) * | 1990-03-23 | 1991-12-06 | Kawada Kensetsu Kk | Moving construction device for high level structure |
CN2801872Y (en) * | 2005-05-27 | 2006-08-02 | 路桥集团第二公路工程局 | Moving device of hanging basket main truss front supporting point |
CN101148861A (en) * | 2007-06-06 | 2008-03-26 | 宏润建设集团股份有限公司 | Beret truss type hanging basket and assembling method thereof |
CN201169749Y (en) * | 2008-03-26 | 2008-12-24 | 中铁四局集团有限公司 | Simple-mounted pin connection triangle hanging basket |
CN201665823U (en) * | 2009-12-04 | 2010-12-08 | 中国第一冶金建设有限责任公司 | Bridge hanging basket cast-in-situ construction triangular rear anchor inverse buckling wheel enhanced type rail |
CN102174795A (en) * | 2011-03-28 | 2011-09-07 | 中铁一局集团有限公司 | Reversible suspended basket wheel type travelling system and method |
CN202530383U (en) * | 2011-11-24 | 2012-11-14 | 中铁二十一局集团有限公司 | Cross-existing railway bridge construction roller hanging basket |
Non-Patent Citations (1)
Title |
---|
戎伟,李建军: "《悬臂梁挂篮施工的探讨与分析》", 《建筑设计管理》 * |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102758404B (en) * | 2012-07-19 | 2014-01-08 | 中铁十六局集团第一工程有限公司 | Front fulcrum hanging basket travelling device of spatial V-shaped cable-stayed bridge |
CN102758404A (en) * | 2012-07-19 | 2012-10-31 | 中铁十六局集团第一工程有限公司 | Front fulcrum hanging basket travelling device of spatial V-shaped cable-stayed bridge |
CN102926330A (en) * | 2012-11-27 | 2013-02-13 | 吴云 | Installation method of hanging basket suitable for bridge construction |
CN103088759A (en) * | 2012-12-22 | 2013-05-08 | 中国建筑第七工程局有限公司 | Prestress lower longitudinal beam bridge cast-in-cantilever construction hanging basket |
CN103850185A (en) * | 2014-02-20 | 2014-06-11 | 中交三航局第三工程有限公司 | Multi-truss type hanging basket for super-wide type bridge construction |
CN104018691B (en) * | 2014-06-17 | 2017-01-11 | 中铁城建集团第二工程有限公司 | Safety protection method for steel-structure house hoisting construction across existing lines |
CN104018691A (en) * | 2014-06-17 | 2014-09-03 | 中铁城建集团第二工程有限公司 | Safety protection method for steel-structure house hoisting construction across existing lines |
CN104631343A (en) * | 2015-02-15 | 2015-05-20 | 河海大学 | Self-travelling diamond-shaped pin-connected truss-type form traveler structure and form traveler travelling and constructing method |
CN104631343B (en) * | 2015-02-15 | 2016-08-24 | 河海大学 | From traveling rhombus keying cradle in truss type structure and suspended basket and construction method |
JP2019078090A (en) * | 2017-10-25 | 2019-05-23 | 鹿島建設株式会社 | Overhang erection work vehicle and construction method |
CN108103948A (en) * | 2017-12-25 | 2018-06-01 | 中交路桥华南工程有限公司 | Erection crane and thereafter anchor device |
CN114319130A (en) * | 2017-12-25 | 2022-04-12 | 中交路桥华南工程有限公司 | Bridge deck crane and rear anchor device thereof |
CN114541273A (en) * | 2022-03-31 | 2022-05-27 | 中国建筑第四工程局有限公司 | Novel rear anchor point anchor rod setting device and construction method thereof |
CN114541273B (en) * | 2022-03-31 | 2024-01-30 | 中国建筑第四工程局有限公司 | Novel rear anchor bolt setting device and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102373673A (en) | Bridge construction rolling shaft hanging basket across railway existing line and use method thereof | |
CN102979041B (en) | Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway | |
CN202090286U (en) | Traction system suitable for self-anchored type double cable plane suspension bridge | |
CN102650118B (en) | Construction device and method for erecting prefabricated beam by slip method | |
CN203377546U (en) | High speed railway spanning construction apparatus | |
CN103938552B (en) | Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier | |
CN102587945B (en) | Hydraulic walking multi-level temporary supporting equipment for advancement of tunnel | |
CN103243658B (en) | The spelling method of cable stayed bridge dragging suspension basket | |
CN102359069A (en) | Existing line reinforcing method in under-crossing railway frame bridge small-included angle large-height inclined jacking construction | |
CN104060844A (en) | Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof | |
CN201794030U (en) | Hanging basket advancing traction device for continuous beams | |
CN203393639U (en) | Diamond self-anchored hanging basket for road and bridge construction | |
CN104532757A (en) | Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower | |
CN110939069A (en) | Construction method of suspension bridge catwalk | |
CN202148493U (en) | Existing line reinforcing device in inclined jacking construction of penetrating railway frame bridge from the lower part with small incline angle and large height | |
CN207987749U (en) | Ride cable-styled erection crane | |
CN202530383U (en) | Cross-existing railway bridge construction roller hanging basket | |
CN206768627U (en) | A kind of pushing tow, erecting device for bridge rotating rear support | |
CN102926330B (en) | Installation method of hanging basket suitable for bridge construction | |
CN103806374B (en) | The overall track erection supplying system of assembly type steel bridge on highway and erection push technique | |
CN202830889U (en) | Rail type slip form device | |
CN108086168A (en) | Ride cable-styled erection crane | |
CN105714691B (en) | A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method | |
CN109958059B (en) | Large-span Bailey beam construction device for tunnel crossing karst cave | |
CN102251477B (en) | Traversing construction method for tie bar arch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120314 |