CN202530383U CN2011204724273U CN201120472427U CN202530383U CN 202530383 U CN202530383 U CN 202530383U CN 2011204724273 U CN2011204724273 U CN 2011204724273U CN 201120472427 U CN201120472427 U CN 201120472427U CN 202530383 U CN202530383 U CN 202530383U
Authority
CN
China
Prior art keywords
girder
column
top rail
hanging basket
lower transverse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011204724273U
Other languages
Chinese (zh)
Inventor
罗玉生
张宁军
刘小军
张志强
吕俊团
杨红亮
李启成
张润
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 21st Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Original Assignee
China Railway 21st Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 21st Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd filed Critical China Railway 21st Bureau Group Co Ltd
Priority to CN2011204724273U priority Critical patent/CN202530383U/en
Application granted granted Critical
Publication of CN202530383U publication Critical patent/CN202530383U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a cross-existing railway bridge construction roller hanging basket, and the technical scheme thereof is that: a front supporting leg and a rear supporting leg are installed on a slideway; a main beam, a column and a diagonal draw bar constitute a triangle combination beam; a front upper beam is installed at a front end of the main beam; rear anchor poles are pre-embedded in bridge concrete; and carrying pole beams are pressed at a rear part of the main beam and are connected with the rear anchor poles. An application method comprises steps of: anchoring the slideway by the rear anchor poles; jacking up the triangle combination beam; disposing round steel rollers on the front leg; then dismounting the rear anchor poles; and pulling forwards the roller hanging basket with a chain block to allow the roller hanging basket to slip in place. As the round steel rollers are additionally arranged between the front leg and the main beam to move the center of gravity of the roller hanging basket backwards, a frictional force in the movement is reduced, a construction task of moving the hanging basket can be completed only in one and a half hours and the task of moving the hanging basket during a skylight period of train traveling on the existing railway can be fully realized, thereby ensuring the operation of the existing railway to be safe and timely.

Description

Striding railway existing line bridge construction roller bearing hangs blue
Technical field
The utility model relates to a kind of special construction apparatus of striding the railway existing line, specifically is that a kind of roller bearing of striding railway existing line bridge construction is hung indigo plant, belongs to the railway construction machine field.
Background technology
In the construction of railways process; Inevitably will run into the existing railway line of leap and construct continuously, and the normal passing train of existing line is very frequent, like Beijing-Guangzhou Railway passing 240 multiple rows every day; Average per 10 minutes through row; In order to guarantee the enforcement safety of the passing train of existing line, crossing over the existing line construction must quick, accurate, timely, orderly carrying out, and the engineering time generally confirms not have the period that EMUs pass through in morning at night; No longer than two hours, be called " skylight " time.To in the so short time, accomplish construction continuously, just construction equipment proposed higher requirement.What generally adopt at present is cradle construction; Its front leg strut of Hanging Basket is positioned under the column; Because the Hanging Basket center of gravity is forward, causes Hanging Basket front fulcrum place frictional force bigger, Hanging Basket is more time-consuming when mobile; Can not guarantee in " skylight " smooth, safe Hanging Basket is moved into place in the time also do not have a kind of desirable railway to stride the existing line construction at present and hang blue equipment.
The utility model content
Hang blue existing defective in order to overcome present construction; The utility model discloses a kind of railway existing line bridge construction roller bearing of striding and hang indigo plant, be with the reach of Hanging Basket front leg strut, and between front leg strut and girder, add three road round steel roller bearings; Move after making the Hanging Basket center of gravity, the Hanging Basket mobile security is quick.
The technical scheme of the utility model is following:
Lay two slideways, a front leg strut and a rear support leg are installed on every slideway, front leg strut is placed directly on the slideway; The rear support leg left-hand thread is respectively being installed a girder on each front leg strut with on the rear support leg on slideway, top rail after the girder middle part connection; Column is installed on the infall of girder and back top rail, and back top rail is arranged at the column below, and column is arranged on the top rail of back; Back top rail connects girder, and girder connects column, is connected with diagonal member between column and the girder; Girder, column and diagonal member are formed a triangle compound beam, top rail before the connection of girder front end, and preceding top rail is connected respectively with the back lower transverse beam with preceding lower transverse beam and back top rail; Bed die longeron and preceding lower transverse beam and back lower transverse beam are connected, are connected pre-buried anchor pole afterwards in bridge concrete with binding-beam between column and the column; Shoulder pole girder be pressed in the girder rear portion and with the back anchor pole link to each other, 3-5 root shoulder pole girder is set behind the girder, establish the 6-10 root after anchor pole it is carried out anchoring; A rear support leg is set in rear end, girder bottom and tightly cuts, 3-5 root round steel roller bearing is installed above the front leg strut and is tightly cut with girder with the slideway steel plate.
Roller bearing Hanging Basket front leg strut is moved forward; And between front leg strut and girder, add the round steel roller bearing; Move after making roller bearing Hanging Basket center of gravity, reduced the frictional force when the roller bearing Hanging Basket moves, only needed 1 hour 30 minutes can accomplish the construction task that Hanging Basket moves; Can in existing line is driven a vehicle skylight point, accomplish Hanging Basket fully and move task, reach safety and in time guaranteed the normal effect of runing of existing line.
Description of drawings
Accompanying drawing 1 is the main TV structure sketch map of the utility model;
Accompanying drawing 2 be the utility model along accompanying drawing 1A-A to the cross section structure sketch map;
Accompanying drawing 3 be the utility model along accompanying drawing 1B-B to the cross section structure sketch map.
Description of reference numerals is following:
Girder 1, column 2, diagonal member 3, preceding top rail 4, preceding lower transverse beam 5, back top rail 6, back lower transverse beam 7, bed die longeron 8, slideway 9, front leg strut 10, rear support leg 11, shoulder pole girder 12, column binding-beam 13, round steel roller bearing 14, steel suspender belt 15, back anchor pole 16.
The specific embodiment
Below in conjunction with embodiment and accompanying drawing the utility model is explained further details:
Lay two slideways 9, a front leg strut 10 and a rear support leg 11 are installed on every slideway 9, front leg strut 10 is placed directly on the slideway 9; Rear support leg 11 left-hand threads are respectively installed a girder 1, top rail 6 after the girder 1 middle part connection on each front leg strut 10 and rear support leg 11 on slideway 9; Column 2 is installed on the infall of girder 1 and back top rail 6, and column 2 is arranged on the top rail of back, and back top rail 6 connects girders 1; Girder 1 connects column 2, is connected girder 1, column 2 and triangle compound beam of diagonal member 3 compositions with diagonal member 3 between column 2 and the girder 1; Utilize bolt to connect rear support leg 11 behind the girder 1, back top rail 6 utilizes bolt to connect girder 1, and girder 1 utilizes bolt to connect column 2; Column 2 and girder 1 are connected with pin respectively with between the diagonal member 3, between the top rail 4 before girder 1 front end utilizes bolt to connect, preceding top rail 4 and preceding lower transverse beam 5 and back top rail 6 and afterwards being connected with steel suspender belt 15 respectively between the lower transverse beam 7; Be connected with bolt respectively between bed die longeron 8 and preceding lower transverse beam 5 and the back lower transverse beam 7; Be connected with pin between column 2 and the column binding-beam 13, pre-buried back anchor pole 16 in the pontic concrete, shoulder pole girder 12 are pressed in girder 1 rear portion and link to each other with back anchor pole 16; Three shoulder pole girders 12 are set behind the girder 1; If anchor pole 16 carries out anchoring to it after the six roots of sensation, a rear support leg 11 is set in rear end, girder 1 bottom and tightly cuts with slideway 9 steel plates, three round steel roller bearings 14 are installed above the front leg strut 10 and are tightly cut with girder 1.
The method for using that the utility model roller bearing is hung indigo plant is following:
A. at first use back anchor pole 16 that slideway 9 anchorings are firm; Remove the back anchor pole 16 of triangle compound beam then; At this moment the triangle compound beam by left-hand thread wheels left-hand thread on slideway 9; Prevent that the triangle compound beam from toppling, subsequently at triangle compound beam front end with jack with triangle compound beam jack-up, on front leg strut 10, place immediately ThreeRoot round steel roller bearing 14;
B. remove the back anchor system; It is reliable to guarantee that each anchoring piece connects; Under the track blockade situation, spur forward and roller bearing is hung blue slippage put in place, simultaneously preceding top rail 4, preceding lower transverse beam 5, back top rail 6, back lower transverse beam 7, bed die longeron 8 synchronization-slidings are put in place by jack;
C. slideway 9 will be laid smooth straightly, must not squint, and guarantees that the left and right sides is evenly synchronous; Left-hand thread is on slideway 9 all the time to keep the left-hand thread wheels, and girder 1 front end is wanted timely cushioning, and girder 1 rear end is established anchor and compressed; In order to avoid topple, girder 1 moves on to the shoulder pole girder of anchoring in time 12 behind the position;
D. after the reach of roller bearing Hanging Basket puts in place; In time carry out anchoring; With the absolute altitude and the axis of jack adjustment roller bearing Hanging Basket, guarantee that roller bearing Hanging Basket front and rear fulcrum is on the same horizontal plane, and the longitudinal midline of whole roller bearing Hanging Basket is overlapped with bridge axes then; Tighten back anchor connector, make the back anchor pole stressed the jack unloading.
After removing the roller bearing Hanging Basket before the anchor;, with roller bearing Hanging Basket girder jack-up 5cm front leg strut is moved to apart from next 40cm place, beam section termination with the 50t hydraulic jack, and the front leg strut stop is installed; Move after the roller bearing Hanging Basket center of gravity like this; Three round steel roller bearings are installed in safety when increase roller bearing Hanging Basket moves then at the front leg strut top, the frictional force when moving to reduce the roller bearing Hanging Basket.After finishing, the existing line Construction of continuous beam assembles striding; Carry out the roller bearing Hanging Basket and move construction task; After maincenter existing line continuous beam closure section construction finishes, the roller bearing Hanging Basket is retreated to railway existing line gauge remove outward, use in order to next Construction of continuous beam.

Claims (2)

1. striding railway existing line bridge construction roller bearing hangs blue; It is characterized in that a front leg strut (10) and a rear support leg (9) respectively are installed on two slideways (9) of laying, front leg strut (10) is placed directly on the slideway (9), and rear support leg (11) left-hand thread is on slideway (9); On each front leg strut (10) and rear support leg (11), a girder (1) is installed respectively; Top rail (6) after girder (1) the middle part connection, column (2) is installed on the infall of girder (1) and back top rail (6), and column (2) is arranged on the top rail of back; Back top rail (6) connects girder (1); Girder (1) connects column (2), is connected girder (1), column (2) and triangle compound beam of diagonal member (3) composition with diagonal member (3) between column (2) and the girder (1); Top rail (4) before girder (1) front end connection; Before top rail (4) and preceding lower transverse beam (5) and back top rail (6) with after lower transverse beam (7) be connected respectively, bed die longeron (8) and preceding lower transverse beam (5) and afterwards lower transverse beam (7) be connected, be connected with column binding-beam (13) between column (2) and the column (2); Pre-buried back anchor pole (16) in bridge concrete; Shoulder pole girder (12) be pressed in girder (1) rear portion and with the back anchor pole (16) link to each other, 3-5 root shoulder pole girder (12) is set behind the girder (1), establish the 6-10 root after anchor pole (16) it is carried out anchoring; A rear support leg (11) is set in girder (1) rear end, bottom and tightly cuts, 3-5 root round steel roller bearing (14) is installed above the front leg strut (10) and is tightly cut with girder (1) with slideway (9) steel plate.
2. the railway existing line bridge construction roller bearing of striding according to claim 1 is hung blue; It is characterized in that: utilize bolt to connect rear support leg (11) behind the girder (1); Back top rail (6) utilizes bolt to connect girder (1); Girder (1) utilizes bolt to connect column (2), and column (2) and girder (1) are connected with pin respectively with between the diagonal member (3), top rail (4) before girder (1) front end utilizes bolt to connect; Before between top rail (4) and the preceding lower transverse beam (5) and back top rail (6) and afterwards use steel suspender belt (15) to be connected respectively between the lower transverse beam (7); Be connected with bolt respectively between bed die longeron (8) and preceding lower transverse beam (5) and the back lower transverse beam (7), be connected with pin between column (2) and the column binding-beam (13), three shoulder pole girders (12) are set behind the girder (1); If anchor pole after the six roots of sensation (16) carries out anchoring to it, three round steel roller bearings (14) are installed above the front leg strut (10) and are tightly cut with girder (1).
CN2011204724273U 2011-11-24 2011-11-24 Cross-existing railway bridge construction roller hanging basket Expired - Fee Related CN202530383U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204724273U CN202530383U (en) 2011-11-24 2011-11-24 Cross-existing railway bridge construction roller hanging basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204724273U CN202530383U (en) 2011-11-24 2011-11-24 Cross-existing railway bridge construction roller hanging basket

Publications (1)

Publication Number Publication Date
CN202530383U true CN202530383U (en) 2012-11-14

Family

ID=47131577

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204724273U Expired - Fee Related CN202530383U (en) 2011-11-24 2011-11-24 Cross-existing railway bridge construction roller hanging basket

Country Status (1)

Country Link
CN (1) CN202530383U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102373673A (en) * 2011-11-24 2012-03-14 中铁二十一局集团有限公司 Bridge construction rolling shaft hanging basket across railway existing line and use method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102373673A (en) * 2011-11-24 2012-03-14 中铁二十一局集团有限公司 Bridge construction rolling shaft hanging basket across railway existing line and use method thereof

Similar Documents

Publication Publication Date Title
CN102373673A (en) Bridge construction rolling shaft hanging basket across railway existing line and use method thereof
CN202090286U (en) Traction system suitable for self-anchored type double cable plane suspension bridge
CN102979041B (en) Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway
CN102108676B (en) Arch bridge construction method for combined beam-steel arch combined system
CN203377546U (en) High speed railway spanning construction apparatus
CN102650118B (en) Construction device and method for erecting prefabricated beam by slip method
CN103938552B (en) Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier
CN102587945B (en) Hydraulic walking multi-level temporary supporting equipment for advancement of tunnel
CN102359069A (en) Existing line reinforcing method in under-crossing railway frame bridge small-included angle large-height inclined jacking construction
CN207932932U (en) A kind of twin beams slope Bridge Erector
CN201794030U (en) Continuous beam hanging basket forward movement traction device
CN102733314A (en) Walking mechanism for moving hanging basket by front clamp type jack and construction method of walking mechanism
CN102392419A (en) High and large side-span cast-in-place construction method in conjunction with bracket and counterweight
CN203393639U (en) Diamond self-anchored hanging basket for road and bridge construction
CN202148493U (en) Existing line reinforcing device in inclined jacking construction of penetrating railway frame bridge from the lower part with small incline angle and large height
CN202530383U (en) Cross-existing railway bridge construction roller hanging basket
CN110939069A (en) Construction method of suspension bridge catwalk
CN102587293A (en) System and method for cradle cantilever construction of variable-width section concrete girder
CN102926330B (en) Installation method of hanging basket suitable for bridge construction
CN109958059B (en) Large-span Bailey beam construction device for tunnel crossing karst cave
CN201738246U (en) Ground prepressing device for continuous beam hanging basket
CN103806374A (en) Assembled road steel bridge overall track erection and push system and process
CN207277171U (en) A kind of straddle-seat type single traffic rail beam girder falling telescopic device
CN102251477B (en) Traversing construction method for tie bar arch
CN202688892U (en) Special groove-erecting machine for erecting water conservancy aqueduct

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121114

Termination date: 20191124