CN104532757A - Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower - Google Patents

Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower Download PDF

Info

Publication number
CN104532757A
CN104532757A CN201410775593.9A CN201410775593A CN104532757A CN 104532757 A CN104532757 A CN 104532757A CN 201410775593 A CN201410775593 A CN 201410775593A CN 104532757 A CN104532757 A CN 104532757A
Authority
CN
China
Prior art keywords
vertical transfer
steel arch
arch tower
steel
transfer frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410775593.9A
Other languages
Chinese (zh)
Inventor
肖明钊
韩德章
王向阳
黄祥国
程华强
范杰
高云
杜新德
张哲�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN BRANCH TYLIN INTERNATIONAL ENGINEERING CONSULTING (CHINA) Co Ltd
WUHAN BRIDGE ENGINEERING Co Ltd
WUHAN OPTICAL VALLEY CONSTRUCTION
WUHAN WUQIAO TRANSPORTATION EQUIPMENT TECHNOLOGY Co Ltd
Wuhan University of Technology WUT
Wuhan Municipal Construction Group Co Ltd
China Railway Heavy Machinery Co Ltd
Original Assignee
WUHAN BRANCH TYLIN INTERNATIONAL ENGINEERING CONSULTING (CHINA) Co Ltd
WUHAN BRIDGE ENGINEERING Co Ltd
WUHAN OPTICAL VALLEY CONSTRUCTION
WUHAN WUQIAO TRANSPORTATION EQUIPMENT TECHNOLOGY Co Ltd
Wuhan University of Technology WUT
Wuhan Municipal Construction Group Co Ltd
China Railway Heavy Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN BRANCH TYLIN INTERNATIONAL ENGINEERING CONSULTING (CHINA) Co Ltd, WUHAN BRIDGE ENGINEERING Co Ltd, WUHAN OPTICAL VALLEY CONSTRUCTION, WUHAN WUQIAO TRANSPORTATION EQUIPMENT TECHNOLOGY Co Ltd, Wuhan University of Technology WUT, Wuhan Municipal Construction Group Co Ltd, China Railway Heavy Machinery Co Ltd filed Critical WUHAN BRANCH TYLIN INTERNATIONAL ENGINEERING CONSULTING (CHINA) Co Ltd
Priority to CN201410775593.9A priority Critical patent/CN104532757A/en
Publication of CN104532757A publication Critical patent/CN104532757A/en
Priority to CN201520301191.5U priority patent/CN204589825U/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a bridge construction device, specifically to a bi-directional traction vertical rotation construction device for a cable-stayed bridge steel arch tower. The bi-directional traction vertical rotation construction device for the cable-stayed bridge steel arch tower comprises a vertical rotation hinge, a skid-resistant support base, a steel arch tower assembly moulding bed, a vertical rotation frame assembly moulding bed, a vertical rotation frame, a vertical rotation frame hinge base, a front pull cable, a rear pull cable, a balance cable, and a stable cable; the skid-resistant support base is located on the bottom of a steel box girder; the steel arch tower assembly moulding bed is consist of multiple lattice steel columns; the vertical rotation frame assembly moulding bed is installed on the steel box girder; one end of the front pull cable is installed on the front pull cable anchoring point of the steel arch tower, and the other end of the front pull cable is hinged with the ear plate of the front end of the vertical rotation frame; one end of the rear pull cable is installed on the ear plate of the rear end of the vertical rotation frame, and the other end of the rear pull cable is hinged with the rear pull cable anchoring point of the steel box girder; and one end of the balance cable is hinged with the balance cable anchoring point of the steel arch tower, and the other end of the balance cable is hinged with the balance cable anchoring point of the steel box girder. The device is capable of achieving the goal of safely constructing, improving the project quality, shortening the construction period, and saving the construction cost.

Description

Cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment
Technical field
The present invention relates to a kind of bridge construction device, the device of particularly a kind of vertical transfer construction of the cable stayed bridge steel arch tower for large scale, large weight, facet rigidity, little angle of inclination.
Background technology
Because steel arch pylon cable-stayed bridge has aesthetic property, its design is also more and more extensive with application.But due to the restriction of special Mechanical Builds and construction condition, the installation of steel arch tower possibly cannot adopt conventional hanging method to construct.Generally first steel arch tower is carried out assembled at bridge floor, design station of then turning.The conventional method of turning has two kinds: one utilizes perpendicular the carrying of pylon to turn, and another kind utilizes triangle to erect to pull to turn.The forming accuracy of steel arch tower can both be controlled well during vertical transfer construction; Most steel arch tower structure can be welded on ground before construction, be convenient to on-the-spot welding and quality examination; Avoid work high above the ground, also reduce investment simultaneously.But vertical transfer construction also exists the shortcoming that construction load is comparatively large, risk is larger, and risk increases along with the reduction at the increase of cable stayed bridge steel arch Sopwith staff cun, weight and plane stiffness, angle of inclination.
Summary of the invention
The object of the invention is to: provide a kind of cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment, this device reaches construction safety, improves the object of workmanship, reduction of erection time, saving construction cost.
The technical solution used in the present invention is such: a kind of cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment, it is characterized in that comprising vertical transfer hinge 4, antiskid bearing 9, the assembled moulding bed of steel arch tower 10, the assembled moulding bed 11 of vertical transfer frame, vertical transfer frame 12, vertical transfer frame free bearing 13, fore stay 14, backstay 18, tail rope 21, steadying line 25;
Vertical transfer hinge 4 cuts with scissors lower free bearing 5 by vertical transfer and the upper free bearing 6 of vertical transfer hinge forms, and the lower free bearing 5 of vertical transfer hinge is fixed on the steel arch tower arch springing embedded section in pier shaft agent structure 3; It is hinged that free bearing 6 is cut with scissors in the lower free bearing 5 of vertical transfer hinge and vertical transfer; The upper free bearing 6 of vertical transfer hinge is fixed on the arch springing sections of steel arch tower 1;
Antiskid bearing 9 is positioned at the bottom surface of steel box-girder 2, antiskid bearing 9 and the pre-embedded steel slab close contact in pier shaft agent structure 3;
The assembled moulding bed of steel arch tower 10 is made up of multiple laced of battened compression member, and multiple laced of battened compression member is arranged on the front portion of steel box-girder 2, the line of the upper end formation of multiple laced of battened compression member and steel box-girder 2 degree angle into θ angle, and a highest laced of battened compression member is away from vertical transfer hinge 4;
The assembled moulding bed 11 of vertical transfer frame is set up on steel box-girder 2, and the assembled moulding bed 11 of vertical transfer frame is positioned at the front portion of steel box-girder 2; The bottom of vertical transfer frame 12 is hinged with the vertical transfer frame free bearing 13 be arranged on steel arch tower 1 arch springing sections; The upper end of vertical transfer frame 12 is shelved on the upper end of the assembled moulding bed 11 of vertical transfer frame;
One end of fore stay 14 is arranged on the steel arch tower fore stay anchor point 16 on steel arch tower 1 by anchor connector 15 before fore stay, the other end of fore stay 14 is hinged with the vertical transfer frame front end otic placode on vertical transfer frame 12 by anchor link element after fore stay 17; One end of backstay 18 is installed on the vertical transfer frame rear end otic placode on vertical transfer frame 12 by anchor connector 19 before backstay, the other end of backstay 18 is hinged by the steel box-girder backstay anchor point 8 in backstay hydraulic jack and connector 20 and steel box-girder 2 thereof;
One end of tail rope 21 is hinged with the steel arch tower tail rope anchor point 23 on steel arch tower 1 by anchor connector after tail rope 22, and the other end of tail rope 21 is hinged by the steel box-girder tail rope anchor point 7 in tail rope hydraulic jack and connector 24 and steel box-girder 2 thereof;
Steadying line 25 is arranged on the steel arch tower steadying line anchor point 27 of steel arch tower 1 by steadying line connector 26.
Described multiple laced of battened compression member is 3-20.
Described angle is 10-30 degree.
When the top of vertical transfer frame 12 is shelved on the assembled moulding bed 11 of vertical transfer frame, 12 one-tenth 45 degree, vertical transfer frame.
Owing to taking such scheme, the invention has the beneficial effects as follows:
1, adopt the assembled stretching force that can reduce in vertical transfer process in vertical transfer system backstay assembled relative to level in θ degree angle, alleviate the weight of vertical transfer supplementary structure, increase the safety of vertical transfer process.
2, antiskid bearing can resist the horizontal drag force of backstay to steel box-girder, the relative bridge pier of steel box-girder in arch tower vertical transfer process is avoided to slide, making steel arch tower, steel box-girder and vertical transfer device form a self equilibrium systems, ensureing vertical transfer safety, without the need to arranging special backstay grappling.
3, tail rope can ensure that in vertical transfer process, Suo Li remains at more than safety cable power, avoids strand tapered anchorage pine anchor, ensures the stability of vertical transfer system.If do not arrange tail rope, steel arch tower center of gravity in vertical transfer process will constantly move forward, and particularly the vertical transfer system center of gravity of little angle of inclination arch tower probably exceeds vertical transfer hinge vertical plane, causes entirety to topple to lead.
4, the architectural characteristic of domes determines that it can produce larger root bending moment in junction, end under gravity, and excessive root bending moment will affect the safety of structure of the main hinge of vertical transfer and increase the rotary resistance of main hinge.Prestressing force steadying line is set and can balances root bending moment, reduce rotary resistance, reduce vertical transfer risk.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment of the present invention (vertical transfer structure assembled and hanging cable).
Fig. 2 is the initial station figure of vertical transfer of the present invention.
Fig. 3 is the final station figure of vertical transfer of the present invention.
Fig. 4 is tail rope of the present invention and steadying line schematic diagram.
Fig. 5 is the schematic diagram of antiskid bearing of the present invention.
Fig. 6 is that Fig. 5 is along A-A line view.
Fig. 7 is that Fig. 5 is along B-B line view.
Mark in figure: 1 is steel arch tower; 2 is steel box-girder; 3 is pier shaft agent structure; 4 is vertical transfer hinge; 5 is the lower free bearing of vertical transfer hinge; 6 is the upper free bearing of vertical transfer hinge; 7 is steel box-girder tail rope anchor point; 8 is steel box-girder backstay anchor point; 9 is antiskid bearing; 10 is the assembled moulding bed of steel arch tower; 11 is the assembled moulding bed of vertical transfer frame; 12 is vertical transfer frame; 13 is vertical transfer frame free bearing; 14 is fore stay; 15 is anchor connector before fore stay; 16 is steel arch tower fore stay anchor point; 17 is anchor connector after fore stay; 18 is backstay; 19 is anchor connector before backstay; 20 is backstay hydraulic jack and connector thereof; 21 is tail rope; 22 is anchor connector after tail rope; 23 is steel arch tower tail rope anchor point; 24 is tail rope hydraulic jack and connector thereof; 25 is steadying line; 26 is steadying line connector; 27 is steel arch tower steadying line anchor point.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is described in detail.
Embodiment:
As shown in figs. 1-7, a kind of cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment, comprises vertical transfer hinge 4, antiskid bearing 9, the assembled moulding bed of steel arch tower 10, the assembled moulding bed 11 of vertical transfer frame, vertical transfer frame 12, vertical transfer frame free bearing 13, fore stay 14, backstay 18, tail rope 21, steadying line 25;
Vertical transfer hinge 4 cuts with scissors lower free bearing 5 by vertical transfer and the upper free bearing 6 of vertical transfer hinge forms, on the steel arch tower arch springing embedded section of the lower free bearing of vertical transfer hinge 5 fixing (as welded) in pier shaft agent structure 3; It is hinged that free bearing 6 is cut with scissors in the lower free bearing 5 of vertical transfer hinge and vertical transfer; At the arch springing sections of steel arch tower 1, (steel arch tower 1 has 2 arch springing sections to the upper free bearing of vertical transfer hinge 6 fixing (as welding), and each arch springing sections installs a upper free bearing 6 of vertical transfer hinge; Vertical transfer hinge 4 has 2);
Antiskid bearing 9 is positioned at the bottom surface of steel box-girder 2, antiskid bearing 9 and the pre-embedded steel slab close contact in pier shaft agent structure 3;
The assembled moulding bed of steel arch tower 10 is made up of multiple laced of battened compression member that (described multiple laced of battened compression member is 3-20, the present embodiment adopts 16), multiple laced of battened compression member is arranged on the front portion (left part in Fig. 1) of steel box-girder 1, the line of the upper end formation of multiple laced of battened compression member and steel box-girder 1(bridge floor) (described angle is 10-30 degree to degree angle into θ angle, the present embodiment adopts 15 degree), a highest laced of battened compression member is away from vertical transfer hinge 4;
The assembled moulding bed 11 of vertical transfer frame is set up at steel box-girder 2(bridge floor) on, the assembled moulding bed 11 of vertical transfer frame is positioned at the front portion of steel box-girder 2; The bottom of vertical transfer frame 12 is hinged with the vertical transfer frame free bearing 13 be arranged on steel arch tower 1 arch springing sections; The upper end of vertical transfer frame 12 is shelved on the upper end (when the top of vertical transfer frame 12 is shelved on the assembled moulding bed 11 of vertical transfer frame, 12 one-tenth 45 degree, vertical transfer frame) of the assembled moulding bed of vertical transfer frame 11;
One end of fore stay 14 is arranged on the steel arch tower fore stay anchor point 16 on steel arch tower 1 by anchor connector 15 before fore stay, the other end of fore stay 14 is by anchor link element after fore stay 17 and the vertical transfer frame front end otic placode hinged (vertical transfer frame front end otic placode is positioned at the upper end of vertical transfer frame 12) on vertical transfer frame 12; One end of backstay 18 is installed on the vertical transfer frame rear end otic placode on vertical transfer frame 12 (vertical transfer frame rear end otic placode is positioned at the upper end of vertical transfer frame 12) by anchor connector 19 before backstay, the other end of backstay 18 by backstay hydraulic jack and connector 20 hinged with the steel box-girder backstay anchor point 8 on steel box-girder 2;
One end of tail rope 21 is by anchor connector after tail rope 22 and the steel arch tower tail rope anchor point 23 hinged (steel arch tower tail rope anchor point 23 is positioned at the top of steel arch tower 1) on steel arch tower 1, and the other end of tail rope 21 is by the steel box-girder tail rope anchor point 7 hinged (steel box-girder tail rope anchor point 7 is positioned at the front end of steel box-girder 2) in tail rope hydraulic jack and connector 24 and steel box-girder 2 thereof;
Steadying line 25 is arranged on the steel arch tower steadying line anchor point 27 of steel arch tower 1 by steadying line connector 26 that (2 steel arch tower steadying line anchor points 27 lay respectively at the centre position in the left and right portion of steel arch tower 1, are symmetrical arranged.Namely steadying line 25 connects symmetrically arranged two steel arch tower steadying line anchor points 27 in the middle part of steel arch tower).
A kind of cable stayed bridge steel arch tower bivector traction vertical rotating construction method, comprises following construction sequence:
1), assembling construction:
1., vertical transfer hinge is installed:
The pier shaft agent structure 3(pier shaft agent structure 3 completing steel arch tower 1 two ends is 2) construction, pier shaft agent structure 3 with the pier shaft agent structure 3 of the connecting portion of steel arch tower 1 arrange steel arch tower arch springing embedded section (namely each pier shaft agent structure 3 being arranged a steel arch tower arch springing embedded section), steel arch tower arch springing embedded section is arranged the lower free bearing 5 of vertical transfer hinge; It is 2 that the arch springing sections (steel arch tower 1 two ends) of steel arch tower 1 arranges the upper free bearing 6 of vertical transfer hinge upper free bearing 6(vertical transfer hinge), the upper free bearing 6 of vertical transfer hinge by bearing pin and vertical transfer cut with scissors lower free bearing 5 hinged (vertical transfer cut with scissors 4 cut with scissors by vertical transfer under free bearing 5 and vertical transfer cut with scissors that free bearing 6 is hinged to be formed) form the vertical transfer that steel arch tower 1 turns and cut with scissors 4;
2., steel box-girder is installed:
Complete the assembled of the steel box-girder 2 of cable stayed bridge, and at the front end of the top surface that the end face of steel box-girder 2 arranges steel box-girder tail rope anchor point 7, steel box-girder backstay anchor point 8(steel box-girder tail rope anchor point 7 is positioned at steel box-girder 2, steel box-girder backstay anchor point 8 is positioned at the end face rear end of steel box-girder 2), in the bottom surface of steel box-girder 1, antiskid bearing 9 is set, antiskid bearing 9 is arranged on two vertical transfers and cuts with scissors immediately below 4 lines, antiskid bearing 9 and the pre-embedded steel slab close contact in pier shaft agent structure 3;
3., steel arch tower is installed:
Make the assembled moulding bed 10 of steel arch tower, the assembled moulding bed of steel arch tower 10 is made up of (described multiple laced of battened compression member is 3-20, and the present embodiment adopts 16) multiple laced of battened compression member; The assembled moulding bed of steel arch tower 10 build according to steel arch tower 1 overall to put with steel box-girder 2 one-tenth θ degree projection of angle sample (described θ is 10-30, the present embodiment adopts 15 degree), release the appearance profile line of steel arch tower 1 and the center line of steel arch tower 1 when steel arch tower 1 is spent with steel box-girder 2 one-tenth θ with total powerstation, according to surveying setting-out result, the assembled moulding bed 10 of steel arch tower is installed;
On-the-spot each sections according to becoming the assembled moulding bed of steel arch tower 10 of θ degree to assemble steel arch tower 1, assembling sequence is installed from two ends (two arch springing sections) to intermediate symmetry, finally closure segment in the middle of assembling;
4., vertical transfer frame is assembled:
Steel box-girder 2 is set up the assembled moulding bed of vertical transfer frame 11, and (the assembled moulding bed of vertical transfer frame 11 is positioned at the front side (left side of Fig. 1 is front) of vertical transfer hinge 4, the assembled moulding bed 10 of arch tower is positioned at the front side of vertical transfer hinge 4), by loop wheel machine complete vertical transfer frame 12 installation (vertical transfer frame adopt fall frame 45 degree of methods install, bridge floor (steel box-girder 2) is set up 45 degree of assembled moulding beds 11 of vertical transfer frame, complete vertical transfer frame 12 by erection crane to install), the bottom of vertical transfer frame 12 is hinged with the vertical transfer frame free bearing 13 be arranged on steel arch tower 1 arch springing sections; The upper end of vertical transfer frame 12 is shelved on the upper end of the assembled moulding bed 11 of vertical transfer frame;
5., hanging cable and vertical transfer frame in place:
One end of fore stay 14 is arranged on the steel arch tower fore stay anchor point 16 on steel arch tower 1 by anchor connector 15 before fore stay, the other end of fore stay 14 is by anchor link element after fore stay 17 and the vertical transfer frame front end otic placode hinged (vertical transfer frame front end otic placode is positioned at the upper end of vertical transfer frame 12) on vertical transfer frame 12; One end of backstay 18 is installed on the vertical transfer frame rear end otic placode on vertical transfer frame 12 (vertical transfer frame rear end otic placode is positioned at the upper end of vertical transfer frame 12) by anchor connector 19 before backstay, the other end of backstay 18 by backstay hydraulic jack and connector 20 hinged with the steel box-girder backstay anchor point 8 on steel box-girder 2;
One end of tail rope 21 is by anchor connector after tail rope 22 and the steel arch tower tail rope anchor point 23 hinged (steel arch tower tail rope anchor point 23 is positioned at the top of steel arch tower 1) on steel arch tower 1, and the other end of tail rope 21 is by the steel box-girder tail rope anchor point 7 hinged (steel box-girder tail rope anchor point 7 is positioned at the front end of steel box-girder 2) in tail rope hydraulic jack and connector 24 and steel box-girder 2 thereof;
Steadying line 25 is arranged on (2 steel arch tower steadying line anchor points 27 lay respectively at the centre position in the left and right portion of steel arch tower 1, are symmetrical arranged) on the steel arch tower steadying line anchor point 27 of steel arch tower 1 by steadying line connector 26;
By backstay 18, slowly pull-up vertical transfer frame 12 is to default station, by monitoring system, progressively stretch-draw backstay 18, ensures that every root backstay is stressed close to even; Treat that the Suo Li of backstay 18 reaches 1/2 and presets Suo Lishi, stretch-draw steadying line 25 is to presetting Suo Li; Continuing stretch-draw backstay 18 makes vertical transfer frame 12 depart from the assembled moulding bed 11 of vertical transfer frame until vertical transfer frame 12 reaches design station, removes the assembled moulding bed 11 of vertical transfer frame after confirming safety;
2), rotator construction:
Traction backstay 18 entirety rises pulls steel arch tower 1, and when steel arch tower 1 has just departed from steel arch tower assembled moulding bed 10, stop stretch-draw, observe 24h, after confirming safety, stretch-draw backstay 18 plays slab arch tower continuously; When backstay 18 Suo Li be down to safety cable power (guaranteeing that strand tapered anchorage is without loose anchor risk) below time, synchronous tension tail rope 21 ensures that backstay 18 Suo Li is not less than safety cable power, continues to turn; After steel arch tower 1 is turned and put in place, incision position is welded into entirety; Remove the assembled moulding bed 10 of steel arch tower, vertical transfer hinge 4, steadying line 25 and steadying line connector 26, installation.

Claims (4)

1. a cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment, is characterized in that comprising vertical transfer hinge (4), antiskid bearing (9), the assembled moulding bed of steel arch tower (10), the assembled moulding bed of vertical transfer frame (11), vertical transfer frame (12), vertical transfer frame free bearing (13), fore stay (14), backstay (18), tail rope (21), steadying line (25);
Vertical transfer hinge (4) cuts with scissors lower free bearing (5) by vertical transfer and the upper free bearing (6) of vertical transfer hinge forms, and the lower free bearing (5) of vertical transfer hinge is fixed on the steel arch tower arch springing embedded section in pier shaft agent structure (3); It is hinged that free bearing (6) is cut with scissors in the lower free bearing (5) of vertical transfer hinge and vertical transfer; The upper free bearing (6) of vertical transfer hinge is fixed on the arch springing sections of steel arch tower (1);
Antiskid bearing (9) is positioned at the bottom surface of steel box-girder (2), antiskid bearing (9) and the pre-embedded steel slab close contact in pier shaft agent structure (3);
The assembled moulding bed of steel arch tower (10) is made up of multiple laced of battened compression member, multiple laced of battened compression member is arranged on the front portion of steel box-girder (2), the line of the upper end formation of multiple laced of battened compression member and steel box-girder (1) degree angle into θ angle, a highest laced of battened compression member is away from vertical transfer hinge (4);
The assembled moulding bed of vertical transfer frame (11) is set up on steel box-girder (2), and the assembled moulding bed of vertical transfer frame (11) is positioned at the front portion of steel box-girder (2); The bottom of vertical transfer frame (12) is hinged with the vertical transfer frame free bearing (13) be arranged on steel arch tower (1) arch springing sections; The upper end of vertical transfer frame (12) is shelved on the upper end of the assembled moulding bed of vertical transfer frame (11);
One end of fore stay (14) is arranged on steel arch tower fore stay anchor point (16) on steel arch tower (1) by anchor connector (15) before fore stay, and the other end of fore stay (14) is hinged with the vertical transfer frame front end otic placode on vertical transfer frame (12) by anchor link element (17) after fore stay; One end of backstay (18) is installed on the vertical transfer frame rear end otic placode on vertical transfer frame (12) by anchor connector (19) before backstay, and the other end of backstay (18) is hinged by the steel box-girder backstay anchor point (8) in backstay hydraulic jack and connector (20) and steel box-girder (2) thereof;
One end of tail rope (21) is hinged with steel arch tower tail rope anchor point (23) on steel arch tower (1) by anchor connector (22) after tail rope, and the other end of tail rope (21) is hinged by the steel box-girder tail rope anchor point (7) in tail rope hydraulic jack and connector (24) and steel box-girder (2) thereof;
Steadying line (25) is arranged on steel arch tower steadying line anchor point (27) of steel arch tower (1) by steadying line connector (26).
2. a kind of cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment according to claim 1, is characterized in that: described multiple laced of battened compression member is 3-20.
3. a kind of cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment according to claim 1, is characterized in that: described angle is 10-30 degree.
4. a kind of cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment according to claim 1, is characterized in that: when the top of vertical transfer frame (12) is shelved on the assembled moulding bed of vertical transfer frame (11), and vertical transfer frame (12) becomes 45 degree.
CN201410775593.9A 2014-12-15 2014-12-15 Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower Pending CN104532757A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201410775593.9A CN104532757A (en) 2014-12-15 2014-12-15 Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower
CN201520301191.5U CN204589825U (en) 2014-12-15 2015-05-08 Cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410775593.9A CN104532757A (en) 2014-12-15 2014-12-15 Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower

Publications (1)

Publication Number Publication Date
CN104532757A true CN104532757A (en) 2015-04-22

Family

ID=52848365

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201410775593.9A Pending CN104532757A (en) 2014-12-15 2014-12-15 Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower
CN201520301191.5U Active CN204589825U (en) 2014-12-15 2015-05-08 Cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201520301191.5U Active CN204589825U (en) 2014-12-15 2015-05-08 Cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment

Country Status (1)

Country Link
CN (2) CN104532757A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155416A (en) * 2015-08-04 2015-12-16 武船重型工程股份有限公司 Integral slippage and vertical rotation device for steel pylon
CN106638331A (en) * 2017-01-18 2017-05-10 中铁大桥局集团有限公司 Method for installing cable tower
CN109113183A (en) * 2018-09-28 2019-01-01 同济大学 Construction method based on large span self-contained pattern suspended-cable structure
CN114250705A (en) * 2021-11-25 2022-03-29 富赢隆基科技(广西)有限公司 Truss bridge structure construction method based on secondary vertical rotation method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371845B (en) * 2018-11-27 2020-07-14 中国核工业华兴建设有限公司 Method for lifting steel arch tower by using main tower cross beam
CN111455870B (en) * 2020-05-19 2024-06-25 中交路桥建设有限公司 Whole-width single-side combined swivel structure of steel box arch bridge and construction method
CN114561878B (en) * 2022-04-18 2023-09-05 中交路桥建设有限公司 Arch rib lateral balance swivel construction method
CN114790695B (en) * 2022-04-27 2023-04-28 中铁重工有限公司 Manufacturing method of special-shaped independent tower matched hinged steel bridge pier system cable-stayed landscape steel bridge

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155416A (en) * 2015-08-04 2015-12-16 武船重型工程股份有限公司 Integral slippage and vertical rotation device for steel pylon
CN106638331A (en) * 2017-01-18 2017-05-10 中铁大桥局集团有限公司 Method for installing cable tower
CN106638331B (en) * 2017-01-18 2019-03-22 中铁大桥局集团有限公司 A kind of installation method of tower with suspended cable
CN109113183A (en) * 2018-09-28 2019-01-01 同济大学 Construction method based on large span self-contained pattern suspended-cable structure
CN109113183B (en) * 2018-09-28 2020-07-14 同济大学 Construction method based on large-span self-forming type suspension cable structure
CN114250705A (en) * 2021-11-25 2022-03-29 富赢隆基科技(广西)有限公司 Truss bridge structure construction method based on secondary vertical rotation method

Also Published As

Publication number Publication date
CN204589825U (en) 2015-08-26

Similar Documents

Publication Publication Date Title
CN104532756B (en) Cable stayed bridge steel arch tower bivector traction vertical rotating construction method
CN204589825U (en) Cable stayed bridge steel arch tower bivector traction vertical transfer construction equipment
CN101864737B (en) Secondary vertical rotating construction method for arch rib of long-span steel arch bridge
CN108374347A (en) A kind of high-speed railway large span cable-carried arch bridge steel lagging jack buckling and hanging system construction method
CN109972517A (en) A kind of construction method of steel reinforced concrete bondbeam cable-stayed bridge main-beam
CN103938552B (en) Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier
CN103526699B (en) Method for replacing pipe bridge hanging steel ropes
CN103643637B (en) Original position construction method for lifting whole after the first vertical transfer of Long-Span Concrete Filled Steel Tubular Arch Bridges
AU782827B2 (en) Adjustable anchor bearing a civil engineering structure
CN102146660A (en) Installation methods of cross-arch-rib gantry crane and butterfly arch bridge space structure system
CN103243658B (en) The spelling method of cable stayed bridge dragging suspension basket
CN103194981A (en) System and method for bridge steel tower maritime vertical rotation construction
CN103074854A (en) Rear supporting point triangular bracket hanging basket and bridge construction method using same
CN205133081U (en) Novel hanging flower basket system
CN205188797U (en) Concrete tied arch bridge jib casts anchor and holds connection structure
CN101649604A (en) Construction bracket of 1# block of inclined pull bridge and constructing method thereof
CN105484164B (en) Spanning type bailey beam bracket and construction method thereof
CN107034791A (en) A kind of assembling method of Cantilever Casting Construction Hanging Basket
CN101705660B (en) Reaction frame prestress anchoring system and method for vertical rotating steel pipe arch on concrete bridge
CN102535348A (en) Method for tensioning stayed cables of hinged tower cable stayed bridge
CN104790301A (en) Sling converting once tensioning construction method of rope bridge system
CN203334664U (en) Ultra-long cantilever truss structure high formwork supporting system
CN104120659B (en) Descending hanging basket
CN207032062U (en) Tower with suspended cable available for Large-span Steel Box Beam construction
CN103306479A (en) Long-length overhang trusswork high form hanger system

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150422