BE497329A - - Google Patents

Info

Publication number
BE497329A
BE497329A BE497329DA BE497329A BE 497329 A BE497329 A BE 497329A BE 497329D A BE497329D A BE 497329DA BE 497329 A BE497329 A BE 497329A
Authority
BE
Belgium
Prior art keywords
beams
formwork
elements
chord
floor
Prior art date
Application number
Other languages
French (fr)
Publication of BE497329A publication Critical patent/BE497329A/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/50Girders, beams, or the like as supporting members for forms
    • E04G11/52Girders, beams, or the like as supporting members for forms of several units arranged one after another

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

       

   <Desc/Clms Page number 1> 
 



  POUTRES POUR COFFRAGES METALLIQUES, POUR CONSTRUCTIONS EN BETON ARME ET 
EN BETON ET HOURDIS ET PROCEDE Y   RELATIFo   Dans la construction des bâtiments ou lors de la réparation des bâtiments endommagés,  on utilise   jusqu'à présent un coffrage en bois pour l'établissement des planchers massifs. A cet effet, on dispose des planches   ou   panneaux de coffrage sur des bois équarris écartés de 70 à 80 cm environ les uns des autres et supportés par des poutres faites de bois équarris. Ces poutres sont supportées par des chandelles,le plus souvent en bois ronds, contreventées les unes par rapport aux autres par des planches pour donner à l'échafaudage la stabilité nécessaire.

   Ce bois de coffrage et d'échafau- dage s'use très rapidement, ainsi que le montre   1-'expérience,,   Un tel écha- faudage rends en outre:,, toute circulation impossible en-dessous du plancher   coffré.   



   La figure 1 est une vue avant d'un tel coffrage et échafaudage en bois. 



   Pour économiser le bois de coffrage et d'échafaudage,qui est   coû-   teux et difficile à se procurer, on a déjà essayé de remplacer le coffrage et l'échafaudage en bois par un coffrage métallique, mais on n'a pas   encore,   jusqu'à présent, trouvé pour cela un coffrage métallique qui convienne.Les coffrages métalliques connus ont une grande hauteur constructive, ils sont lourds et peu maniables et ne fournissent pas non plus de face inférieure lisse pour le plancher. 



   L'invention a pour but de réaliser un coffrage métallique composé de pièces métalliques légères et maniables faciles à monter et à démonter, pouvant être rehaussées en vue de la compensation de la flèche inévitable se produisant lors de   Inapplication   de la charge, convenant   à   la réalisation de voûtes et, en outre, suffisamment rigides dans le sens latéral pour recueillir les forces horizontales qui se produisent éventuellement lors de l'établisse= ment des planchers, Ce coffrage métallique doit,en outre,être meilleur mar- ché que le coffrage en bois en usage jusqu'à présent, il doit conférer au plan- cher une face inférieure aussi lisse que possible et ne pas gêner la circula- 

 <Desc/Clms Page number 2> 

   tion   en-dessous du coffrage du plancher. 



   L'invention résoud ce problème à l'aide d'éléments de poutre courts, bas et légers, se joignant bout à bout dans la membrure supérieure et assem- blés dans la membrure inférieure à l'aide de tendeurs, en forme de poutres en treillis à membrures parallèles, pouvant être assemblées en poutres métalli- ques de coffrage franchissant l'espace compris entre les murs   d'appui.   



   Il est avantageux de donner aux différents éléments de poutre une longueur telle qu'ils puissent être disposés suivant un réseau. On peut alors, avec,par exemple, trois éléments de poutres ayant les longueurs de série de   0,625m,   0,9375m et 1,25m, franchir toutes les portées de 1,25m et davantage dont les dimensions ont été calculées d'après le module de réseau de 0,3125- soit le quart de 1,25   -. On   pourrait encore franchir toutes les portées de   1,00m   et au-dessus, supérieures, chacune, de 10cm à la précédente, avec les longueurs de série de   0,50m,     0,60m   et 0,70m. 



   Les éléments de poutre exécutés sous la forme de poutres en treil- lis à membrures parallèles permettent d'économiser de la matière et d'obtenir un poids aussi réduit que possible. 



   La figure 2 est une vue en long représentant schématiquement un exemple d'exécution de la poutre de coffrage conforme à l'invention, avec la construction exécutée sur cette poutre pour le plancher. Ses deux pièces d' extrémité et d'appui y sont désignées par 1 et les pièces médianes par 2. 



   La figure 3 représente une vue en bout de poutres de coffrage dis- . posées parallèlement pour planchers en béton armé avec les pierres de hourdis mises en place, les poutres de'coffrage étant disposées à une distance les unes des autres égale à celle qui sépare les axes de deux pierres de hourdis voisines. 



   La figure   4   représente la poutre de coffrage lors de son démon- tage. 



   L'élément de poutre conforme à la présente invention, exécuté à la façon d'une poutre en treillis, est représenté aux figures 5 à 7 suivant une vue en long, une vue en coupe transversale et une vue en bout. Sa mem- brure supérieure 3 est exécutée avec avantage sous la forme d'une tôle   cin-   trée en U, comme le montrent les figures 5 à 7, ou bien on utilise, à cet ef- fet, un profilé léger similaire du commerce. La membrure inférieure 4 est cons- tituée avec avantage par un tube. La membrure supérieure et la membrure in- férieure sont reliées, suivant la forme de la membrure supérieurepar une ou deux ondulations en fil d'acier rond ou en tube 5, fixées en place par soudure, et qui constituent les barres diagonales de la poutre en treillis. 



   A leurs extrémités, les éléments de poutre ont une forme telle que, dans la membrure supérieure, ils se rencontrent bout à bout suivant une surface de grande étendue et que leurs surfaces de contact bout à bout soient mainte- nues assemblées par des boulons 6, comme le montre la figure ll, ou bien par une pince de fermeture 7 pouvant être passée par dessus le joint par glisse- ment, comme le montrent les figures   14   à   17,   suivant une vue en coupe trans- versale, une vue de côté et une vue en plan. La figure 14 est une vue en cou- pe transversale d'une pince de fermeture mise en place,la figure 15 est une coupe en long de la pince non mise en place.

   Lorsque c'est nécessaire, on exécute les surfaces ou portées de jonction bout à bout de la membrure supé- rieure pour poutres de coffrage, dont la hauteur peut être fortement augmentée, à la façon d'une articulation comme le montrent les figures 18 et 19, quand il s'agit de poutres de coffrage non soutenues dans lesquelles il ne peut pas se produire, dans la membrure comprimée, d'efforts de traction ou tension considérables. De cette façon, on évite qu'en cas de surhaussement important les éléments de la poutre baillent dans la membrure supérieure. La membrure inférieure est maintenue assemblée par un tendeur 8, comme il en est représen- té différentes formes d'exécution sur les figures 11 à 13 et lla à 13a. 



   Pour le montage de la poutre de coffrage, il faut les moyens de fixation prévus dans la membrure supérieure, comme par exemple, les boulons 

 <Desc/Clms Page number 3> 

 6 précités (figures   11   et 18) et la pince 7 pouvant être passée par dessus par glissement (figures 11a, 14 à 17 et 19), pour empêcher le baillement des éléments de poutre. Ils agissent aussi, après-leur montage et leur mise en place, en sens contraire des efforts horizontaux et transversaux qui se produisent éventuellement, et qui agissent lors de   l'application   des char- ges de la construction.

   Pour permettre un décoffrage aisé, on dispose avan- tageusement les organes de fixation de la membrure supérieure, de telle sorte qu'après le durcissement du plancher ils ne soient pas exposés à des tensions appréciables, 
On maintient avec avantage les surfaces'de contact bout à bout de la membrure supérieure relativement larges par rapport à la superficie de la section   normale   et déterminée statiquement. Les forces   à   transmettre   n'agis-   sent alors que faiblement sur la matière aux endroits des joints bout à bout et les tensions maxima à prévoir restent de loin inférieures aux contraintes admissibles. 



   Les tendeurs de la membrure inférieure comportent bien entendu, un filetage à pas à gauche et à pas à droite. A l'aide de ces tendeurs, on aligne la poutre après l'assemblage des éléments de poutre des extrémités et du milieu, et on règle le surhaussement à la valeur voulue,On exécute avec avantage sous la forme d'une articulation au moins un tendeur de cha- que poutre de coffrage et,de préférences, celui du joint bout à bout du mi- lieu, comme le montrent, par exemple, les figures 12 et 13.  Coci   permet alors., après la réalisation du plancher, le démontage de la poutre de coffrage, com- me cela est représenté schématiquement sur la figure 4.

   Le tendeur est exécu-   té,   dans l'exemple d'exécution des figures 12 et   13,  à la façon d'une   articu-     lation,   et il se compose de deux demi-tiges 9 et 10.La   demi-tige   9 comporte deux yeux latéraux Il entre lesquels on fait glisser   l'oeil   unique 12 de 1?autre demi-tige 10.

   A travers tous les yeux qui, à cet effet;, ont même diamètre intérieur, on fait passer une broche   13   qui se termine en   cône..   Le tendeur constitue-donc,  à     l'état   d'assemblage, une demi-articulation.Sa bro- che peut facilement être retirée après que le tendeur a été détendue Pour re- cevoir ce dispositif tendeur, on utilise selon la figure   11   des éléments de tube avec filetage 14 qui sont fixés aux extrémités de la membrure inférieure. 



   Au lieu des tendeurs semblables à une articulation, on peut aussi utiliser les tendeurs rigides habituels,,qui doivent alors être fixés aux mem- brures inférieures d'une manière articuléeLes tendeurs à vis fixés d'une manière   articulée   aux extrémités de la membrure inférieure sont   représen-   tés schématiquement sur les figures 11a, 12a et 13a. 



   Les poutres de coffrage selon   l'invention   sont très étroites par rapport à leur longueur. Elles n'auraient donc pas suffisamment de rigidité dans le sens latéral dans le cas de grandes portées et elles   n'absorberaient   pas les efforts horizontaux qui se produisent toujours lors de l'établissement des planchers. Dans-ce but, on pourrait,, il est vrai, donner une résistance suffisante aux poutres, ou les monter de façon qu'elles aient une   liaison     la-   térale, ce qui permettrait d'obtenir un effet de répartition de la charge dans le sens transversal.

   Mais, dans ce cas, les poutres deviendraient trop fortes et trop   lourdes.   Elles ne pourraient alors plus être montées aisément et commdément, De même, dans le montage avec des liaisons latérales, il se produirait des difficultés lors du coffrage  mais   surtout lors du décoffrage. 



   On évite ces difficultés avec les poutres de coffrage légères con- formes à l'invention,qui se laissent monter également avec une rigidité   laté-   rale suffisantes quand on utilise, à cette   occasion,   un système de barres dis-   posées transversalement, ou transversalement et en diagonale, pour le raidissement mutuels La figure 24 est une vue en plan de poutres de coffrage solide-   ment liées les unes aux autres dans le sens latéral, par des barres   transver-   sales et diagonales 15 et 16, ces poutres de coffrage se composant d'éléments d'extrémité 1 et intermédiaires 2.

   Pour leur fixation,, il a été monté par sou- dure sur les éléments de poutre des tôles 17 qui comportent des ouvertures des- tinées à recevoir des boulons de fixation, comme le montrent les figures 5 à 10 et 20 à 22. Les figures 20 à 23 sont, respectivement,une vue de côté, une 

 <Desc/Clms Page number 4> 

 vue en plan et une vue en bout des barres transversales et diagonales. Les barres de raidissement ne gênent en aucune façon le coffrage ni le décoffrage. 



  On peut sans inconvénient les retirer peu après le montage et l'établissement du plancher, donc avant même le durcissement du béton. 



   On utilise avec avantage comme appuis pour les poutres de coffra- ge, comme le montrent les figures 2 et   4,   les éléments de la   construction   destinés à servir d'appuis pour le plancher. Dans ce but, l'élément d'ex- trémité 1 (figure 2) est muni, dans la membrure supérieure, d'une forte pla- que de pression 18 dont les dimensions sont calculées de façon qu'elle re- cueille en toute sécurité les forces concentrées en ce point. En-dessous de la plaque de pression, la membrure inférieure est raccourcie. Les figures 8 à 10 représentent une telle pièce de pression par une vue de côté et une vue en bout, ainsi que par une vue de côté partielle, à échelle plus grande. Entre le mur servant d'appui et l'extrémité de la membrure inférieure, il subsiste donc un intervalle après le montage de la poutre.

   Il permet d'abaisser   commo-   dément les moitiés de poutre après déserrage du tendeur articulé. Quand on continue à abaisser l'élément de poutre davantage, l'extrémité de la membru- re inférieure appuie contre la face de la maçonnerie.. L'effort de traction produit alors dans la membrure supérieure par   1-'effet   de levier achève de ti- rer hors de son logement la plaque de pression coincée entre le plancher et la magonnerie, après quelle a déjà été considérablement desserrée par le mou- vement d'abaissemnt. Les moitiés de poutre peuvent alors être montées ail- leurs ou être démontées en leurs éléments. Ceci est particulièrement avanta- geux pour le transport d'un chantier à un autre et pour la mise en magasin. 



  Il va de soi qu'avant la coulée du béton on dispose au-dessus de la plaque de pression 18 de la membrure supérieure un matelas souple, constitué, par   exem-   ple, par un petit ballon de papier comprimé, pour que la plaque de pression ait suffisamment de jeu lors de l'abaissement de la poutre. 



   Comme appuis pour les poutres de coffrage, on peut également uti- liser des éléments mobiles de soutien ou bien des consoles fixées dans le mur. 



   La figure 3 représente un exemple d'exécution des poutres de cof- frage selon l'invention pour la réalisation de planchers mixtes en béton armé et hourdis de céramique. Les poutres forment, dans ce cas, ce qu'on appelle un coffrage à bandes et elles sont placées à la même distance les unes des autres que les hourdis creux formant coffrage, de sorte que les hourdis creux trouvent un appui suffisant par leurs rebords de la base et par une partie de la dalle inférieure. 



   Il est avantageux de donner aux poutres de coffrage des dimensions telles que leur longueur entre appuis ne dépasse pas 5 mètres. Car, dans ce cas, on peut se contenter d'une hauteur d'environ   24   centimètres. Dans le cas d'une longueur de 1 mètre, les éléments de poutre ont chacun un poids de 10,5 kg, Pour des portées supérieures à 5 mètres, on utilise des supports in- termédiaires sur lesquels on fait prendre appui les extrémités libres.des   poutrese   Ces appuis isolés ne gênent pas la circulation en-dessous du plancher coffré. Pour faire l'économie d-appuis intermédiaires, on pourrait également disposer sur des appuis des poutres de coffrage portant le plancher. 



   Les différences inférieures à la dimension de la grille ou du ré- seau peuvent être compensées par des longueurs de série intercalées ou par des éléments intermédiaires spéciaux comportant des parties pouvant coulis- ser et, par conséquent, être adaptées à toute valeur des longueurs. 



   La membrure supérieure de la poutre de coffrage selon l'invention servant à la confection des planchers en béton armé et hourdis en céramique est un peu plus large que la nervure de béton armé qui se forme par la cou- lée du béton entre les éléments du hourdis, pour que les rebords de la base des éléments du hourdis ne se brisent pas. 



   Pour les planchers nervurés, comme ils sont représentés en coupe schématique dans la figure 25, on peut se contenter d'une membrure supérieure plus étroite de la poutre de coffrage. On utilise, à cet effet, avec avanta- 

 <Desc/Clms Page number 5> 

 ge les éléments de poutre représentés par une vue en long, une vue en coupe et une vue en bout dans les figures 26 à 28. Dans ces poutres en treillis, les barres obliques sont constituées simplement par un serpentin tubulaire fixé par soudure à la membrure supérieure et à la membrure inférieure de la poutre. La membrure supérieure est formée, dans ce cas, de deux cornières. 



  Elle peut être plus étroite que la membrure supérieure des poutres de cof- frage pour planchers en béton et hourdis en céramique, parce qu'on dispose sur elle des tôles et des dalles en béton armé servant d'éléments de coffra- ge pour le plancher. Ces dalles de béton deviennent ensuite des éléments de la   construction,   après la coulée du béton. Et pour ces éléments de coffra- ge, on n'a pas besoin des larges surfaces pour les membrures supérieures, comme elles sont nécessaires dans les poutres de coffrage qui servent d'ap- puis pour les hourdis en réfractaire formant coffrage dans les planchers de béton armé et comportant de tels hourdis. 



   Les poutres de coffrage selon   12' invention   conviennent également pour le coffrage des poutres   principales   et secondaires. Dans ce bute on les munit de parois latérales selon les figures 29 à 31 qui représentent ces poutres par une vue en long, une vue en coupe transversale et une vue en bout.

   Dans ces figures, la paroi latérale, exécutée en tôle qui forme cof- frage est désignée par 190 20, désigne les ouvertures pour la fixation des équerres   dappui   représentées dans les figures 32 à 35,   quon   boulonne contre la face en bout d'une telle poutre de coffrage, ainsi que les ouvertures pour la fixation des éléments les uns par rapport aux autreso 
La figure 32 est une vue en long de ces poutres de coffrage avec équerre d'appui 21 fixée par boulons et prenant appui sur le mur portant le plancher.

   La figure 33 représente l'équerre d'appui vue   d'en   haut, la figu- re 34 la représente vue de l'avant et la figure 35 sa coupe   longitudinale.   La figure 36 représente l'évidement qu'on a laissé dans le mur pour l'appui d' une poutre en béton armé à couler en un seul bloc.Ce grand évidement com- porte à sa base encore deux petits évidements latéraux 22 pour les équerres d'appui qui doivent être rapportées à gauche et à droite, représentées dans les figures 32 à   35,   et qui portent les deux éléments latéraux de coffrage verticaux représentés dans les figures 29 à 320 
On recouvre, évidemment, les   coffrageslatéraux.,   à leurs extrémi- tés inférieures, avec des tôles pour former le coffrage   complet   pour la pou- tre en béton armé à couler.

   Dans ce bute il est prévu dans les tôles latéra- les 19 des ouvertures pour y faire passer des barres de support. Ces barres de support ne sont pas représentées spécialement sur la figure. Elles por- tent les tôles au fond du coffrage. Le coffrage pour un plancher à poutres apparentes principales et secondaires se   fabrique,   conformément à la figure 25,de la manière suivante 
On dispose les poutres de coffrage 23 assemblées, destinées à la poutre principale, sur les éléments portants de la construction et on les soutient par des supports 24,  lorsque   c'est nécessaire. Les poutres de coffra- ge 23 sont représentées dans la moitié de droite de la figure 25 par une vue en long qui donne une coupe immédiatement avant la poutre principale du plan- cher à poutres apparentes.

   Perpendiculairement à ces poutres, on dispose sur leurs membrures supérieures et sur les parois latérales,parallèles entre elles, les poutres de coffrage 25 pour les poutres secondaires du plancher, ou bien on les fixe en un emplacement approprié différent des éléments de cof- frage des poutres principales qui doivent, à cet effet, être munies de dispo- sitifs de fixation appropriés.Ensuite, on dispose sur les membrures   supérieu-   res des poutres de coffrage principales 23, parallèlement au coffrage des poutres principales du plancher, les poutres de coffrage pour les dalles du plancher comprises entre les poutres secondaires de ce dernier, comme le mon- tre la moitié de gauche de la figure 25 qui représente une coupe du plancher entre deux poutres principales. 



   Aux emplacements où se sépare ou bien où   commence   une poutre prin- cipale ou secondaire on assemble avantageusement, selon les figures 37 et   38,   les poutres de coffrage pour la paroi latérale d'une poutre principale du plan- 

 <Desc/Clms Page number 6> 

 chero La membrure supérieure est reliée en ce point à une équerre 26 sur la largeur de la poutre principale ou secondaire qui se détache. Elle reste après le démontage comme élément perdu du coffrage dans la poutre principale ou se- condaire ayant durci, à l'emplacement de cette dérivation.

   En-dessous, la pa- roi latérale de la poutre principale est franchie par les tôles 27 et, le cas échéant aussi par les tôles 28, de même que la zone tendue de la poutre de   cof-   frage l'est par un court élément de tube qui comporte de chaque côté un pas de vis pour recevoir les tendeurs à vis. La figure 37 représente la vue avant, et la figure 38 une coupe horizontale de remplacement où les poutres de cof- frage latéral se rencontrent en bout pour le raccordement   d'un   coffrage de poutre secondaire. 



   La figure 39 représente   Inexécution   d'un élément de   coffrage   avec dérivation pour poutre secondaire au-dessus du coffrage pour une colonne ou un pilier en béton arméo Ce coffrage   sertg   en même temps, d'appui pour le cof- frage des poutres. 



   Afin de rendre la poutre de coffrage aussi légère que possible, la membrure supérieure, tout en ayant-un poids réduit au   minimum.,   doit offrir une résistance suffisante au flambage et au bossellement. Ceci peut être réalisé en munissant cette membrure   d'une   ou de plusieurs rigoles parallèles et   jux-   taposées 290 Celles-ci peuvent aussi être décalées les unes par rapport aux autres et présentent des intervalles appropriés dans le sens de la longueur, afin de sauvegarder la rigidité transversale de la poutre. L'écartement des rigoles est utilement choisi, d'après un calcul statique, de façon que la matière soit pleinement utilisée et que la zone entre les rigoles offre la résistance requise au bossellement. 



   La figure   40   ci-jointe montre en plan une membrure supérieure mu- nie de rigoles 29 ;la figure 41 est une coupe transversale de cette membrure. 



   Les poutres de coffrage peuvent aussi servir au coffrage de cais- sons de plafond limité par des poutres en I. A cette fin, les poutres de cof- ±rage montées sur les poutres en I sont munies d'éléments d'extrémité régla- bles, en forme de béquilles, représentés dans les figures   42   et 43 en éléva- tion latérale et   frontale,   par lesquelles la membrure supérieure 3 de la pou- tre de coffrage   5' appuie   sur la membrure inférieure des poutres en I. 



   La longueur de   l'élément   d'extrémité   ad j oint   à la membrure supé- rieure 3 est variable, afin de compenser de légères différences dans les cais- sons, lesquelles peuvent se présenter éventuellement après assemblage des élé- ments de la poutre. La béquille 30 est à inclinaison variable et présente un bec ajustable 31 par lequel elle s'appuie sur la membrure inférieure de la pou- tre en   I.   La membrure supérieure de la béquille présente des forages 32 desti- nés à recevoir les vis pour la fixation du bec. La membrure inférieure des pou- tres de coffrage est réunie au boulon fixé   à   la manière   d'une   articulation et qui est reliée par un barreau à la membrure supérieure de   Isolement     d'extrémi-   té.



   <Desc / Clms Page number 1>
 



  BEAMS FOR METAL FORMWORK, FOR REINFORCED CONCRETE CONSTRUCTIONS AND
IN CONCRETE AND HURDIS AND RELATED PROCESS In the construction of buildings or during the repair of damaged buildings, wooden formwork has been used up to now for the establishment of solid floors. For this purpose, we have planks or shuttering panels on squared timber spaced approximately 70 to 80 cm from each other and supported by beams made of squared timber. These beams are supported by candles, most often made of round timber, braced relative to each other by boards to give the scaffolding the necessary stability.

   This formwork and scaffolding timber wears out very quickly, as experience has shown. Such a scaffolding furthermore makes: ,, all traffic impossible under the coffered floor.



   Figure 1 is a front view of such a formwork and wooden scaffolding.



   In order to save formwork and scaffolding timber, which is expensive and difficult to obtain, attempts have already been made to replace the wooden formwork and scaffolding with metal shuttering, but we have not yet, until Now, a suitable metal formwork has been found for this. Known metal forms have a great constructive height, are heavy and unwieldy and do not provide a smooth underside for the floor either.



   The object of the invention is to produce a metal formwork composed of light and handy metal parts easy to assemble and disassemble, which can be heightened with a view to compensating for the inevitable deflection occurring during the inapplication of the load, suitable for the realization. vaults and, moreover, sufficiently rigid in the lateral direction to absorb the horizontal forces which may occur during the laying of floors, This metal formwork must, moreover, be cheaper than the wooden formwork in use until now, it must give the floor as smooth an underside as possible and not interfere with circulation.

 <Desc / Clms Page number 2>

   tion below the floor formwork.



   The invention solves this problem by using short, low and light beam elements which are joined end to end in the upper chord and assembled in the lower chord using turnbuckles, in the form of beams. Lattice with parallel members, which can be assembled into metal formwork beams crossing the space between the supporting walls.



   It is advantageous to give the various beam elements a length such that they can be arranged in a network. It is then possible, with, for example, three beam elements having the series lengths of 0.625m, 0.9375m and 1.25m, all the spans of 1.25m and more whose dimensions have been calculated according to the network module of 0.3125- or a quarter of 1.25 -. We could still cross all spans of 1.00m and above, each greater than 10cm to the previous one, with the standard lengths of 0.50m, 0.60m and 0.70m.



   The beam elements executed in the form of lattice girders with parallel chords save material and achieve as little weight as possible.



   Figure 2 is a longitudinal view schematically showing an exemplary embodiment of the formwork beam according to the invention, with the construction performed on this beam for the floor. Its two end and support pieces are designated by 1 and the middle pieces by 2.



   Figure 3 shows an end view of formwork beams dis-. laid parallel for reinforced concrete floors with the slab stones in place, the shuttering beams being arranged at a distance from each other equal to that which separates the axes of two neighboring slab stones.



   FIG. 4 represents the formwork beam during its dismantling.



   The beam element according to the present invention, constructed in the manner of a truss beam, is shown in Figures 5 to 7 in a longitudinal view, a cross-sectional view and an end view. Its upper member 3 is advantageously made in the form of a U-shaped sheet metal, as shown in Figures 5 to 7, or a similar lightweight commercial profile is used for this purpose. The lower chord 4 is advantageously constituted by a tube. The top chord and the bottom chord are connected, depending on the shape of the top chord, by one or two corrugations of round steel wire or tube 5, fixed in place by welding, and which constitute the diagonal bars of the beam. trellis.



   At their ends, the beam elements have a shape such that, in the upper chord, they meet end to end over a large area and that their end-to-end contact surfaces are held together by bolts 6, as shown in figure 11, or by a closing clamp 7 which can be passed over the seal by sliding, as shown in figures 14 to 17, in a cross-sectional view, a side view and a plan view. Figure 14 is a cross-sectional view of a closing clip in place, Figure 15 is a sectional view of the clip not in place.

   When necessary, the junction surfaces or spans of the top chord for formwork beams, the height of which can be greatly increased, are made end-to-end in the manner of a joint as shown in figures 18 and 19, in the case of unsupported shuttering beams in which no considerable tensile or tension forces can occur in the compressed member. In this way, it is avoided that in the event of significant raising the elements of the beam yawning in the upper chord. The lower chord is held together by a tensioner 8, as different embodiments thereof are shown in Figures 11 to 13 and 11a to 13a.



   For mounting the shuttering beam, the fixing means provided in the upper chord are required, such as for example bolts

 <Desc / Clms Page number 3>

 6 above (Figures 11 and 18) and the clamp 7 can be passed over by sliding (Figures 11a, 14 to 17 and 19), to prevent the yawning of the beam elements. They also act, after their assembly and their installation, in the opposite direction of the horizontal and transverse forces which may occur, and which act during the application of the loads of the construction.

   To allow easy stripping, the upper chord fasteners are advantageously arranged so that after the floor has hardened they are not exposed to appreciable stresses,
The butt contact surfaces of the top chord are advantageously maintained relatively large compared to the area of the normal and statically determined section. The forces to be transmitted then act only weakly on the material at the places of the butt joints and the maximum tensions to be expected remain far below the admissible stresses.



   The lower chord turnbuckles naturally have a left-hand and right-hand thread. With the help of these tensioners, the beam is aligned after the assembly of the beam elements of the ends and the middle, and the heightening is adjusted to the desired value.We carry out with advantage in the form of a joint at least one tensioner of each formwork beam and, preferably, that of the butt joint in the middle, as shown, for example, in Figures 12 and 13. Coci then allows., after the completion of the floor, the dismantling of the shuttering beam, as shown schematically in figure 4.

   The tensioner is executed, in the exemplary embodiment of FIGS. 12 and 13, in the manner of an articulation, and it consists of two half-rods 9 and 10. The half-rod 9 comprises two side eyes II between which one slides the single eye 12 of the other half-rod 10.

   A pin 13 which ends in a cone is passed through all the eyes which, for this purpose ;, have the same internal diameter. The tensioner therefore constitutes, in the assembled state, a half-joint. spindle can easily be removed after the tensioner has been relaxed. In order to accommodate this tensioning device, according to figure 11, threaded tube members 14 are used which are fixed to the ends of the lower chord.



   Instead of the hinge-like turnbuckles, the usual rigid turnbuckles can also be used, which must then be attached to the lower limbs in a hinged fashion. Screw turnbuckles attached in a hinged fashion to the ends of the lower chord are schematically shown in Figures 11a, 12a and 13a.



   The formwork beams according to the invention are very narrow compared to their length. They would therefore not have sufficient rigidity in the lateral direction in the case of large spans and they would not absorb the horizontal forces which always occur when laying the floors. For this purpose, it is true, one could, it is true, give a sufficient resistance to the beams, or mount them so that they have a lateral connection, which would make it possible to obtain an effect of distribution of the load in the transverse direction.

   But, in this case, the beams would become too strong and too heavy. They could then no longer be mounted easily and conveniently. Likewise, in the assembly with lateral links, difficulties would arise during the formwork but especially during the stripping.



   These difficulties are avoided with the light formwork beams according to the invention, which can also be mounted with sufficient lateral rigidity when using, on this occasion, a system of bars arranged transversely, or transversely and diagonally, for mutual stiffening Figure 24 is a plan view of shuttering beams firmly connected to each other in the lateral direction, by transverse and diagonal bars 15 and 16, these shuttering beams consisting of end elements 1 and intermediate 2.

   For their fixing, it was mounted by welding on the beam elements of the sheets 17 which have openings intended to receive fixing bolts, as shown in Figures 5 to 10 and 20 to 22. Figures 20 to 23 are, respectively, a side view, a

 <Desc / Clms Page number 4>

 plan view and end view of crossbars and diagonal bars. The stiffening bars do not in any way interfere with the formwork or the stripping.



  They can easily be removed shortly after assembly and laying of the floor, so even before the concrete has hardened.



   As supports for the shuttering beams, as shown in Figures 2 and 4, the structural elements intended to serve as supports for the floor are advantageously used. For this purpose, the end element 1 (figure 2) is provided in the upper chord with a strong pressure plate 18, the dimensions of which are calculated in such a way that it collects completely. security forces concentrated at this point. Below the pressure plate, the bottom chord is shortened. Figures 8 to 10 show such a pressure piece in a side view and an end view, as well as in a partial side view, on a larger scale. Between the wall serving as support and the end of the lower chord, there is therefore a gap after the assembly of the beam.

   It allows the beam halves to be lowered conveniently after loosening the articulated tensioner. As one continues to lower the beam member further, the end of the lower chord presses against the face of the masonry. The tensile force then produced in the upper chord by the leverage is completed. Pull the pressure plate wedged between the floor and the doorframe out of its housing, after which it has already been loosened considerably by the lowering movement. The beam halves can then be mounted elsewhere or be dismantled into their parts. This is particularly advantageous for transport from one site to another and for storage.



  It goes without saying that before the concrete is poured, a flexible mat is placed above the pressure plate 18 of the upper chord, consisting, for example, of a small ball of compressed paper, so that the pressure plate. pressure has sufficient clearance when lowering the beam.



   As supports for the shuttering beams, it is also possible to use movable supporting elements or brackets fixed in the wall.



   FIG. 3 represents an exemplary embodiment of the formwork beams according to the invention for the production of mixed floors in reinforced concrete and ceramic slabs. The beams form, in this case, what is called a strip formwork and they are placed at the same distance from each other as the hollow slabs forming the formwork, so that the hollow slabs find sufficient support by their edges of the base and part of the lower slab.



   It is advantageous to give the formwork beams dimensions such that their length between supports does not exceed 5 meters. Because, in this case, we can be satisfied with a height of about 24 centimeters. In the case of a length of 1 meter, the beam elements each have a weight of 10.5 kg. For spans greater than 5 meters, intermediate supports are used on which the free ends are supported. beams These insulated supports do not impede traffic below the box floor. To save on intermediate supports, one could also have shuttering beams carrying the floor on the supports.



   Differences smaller than the dimension of the grid or network can be compensated for by interposed series lengths or by special intermediate elements having slidable parts and therefore be adapted to any value of the lengths.



   The upper chord of the shuttering beam according to the invention used for making reinforced concrete floors and ceramic slabs is a little wider than the reinforced concrete rib which is formed by the concrete pouring between the elements of the concrete. slabs, so that the edges of the base of the slab elements do not break.



   For ribbed floors, as they are shown in schematic section in Figure 25, one can be satisfied with a narrower top chord of the shuttering beam. We use, for this purpose, with advantage

 <Desc / Clms Page number 5>

 ge the beam elements represented by a longitudinal view, a sectional view and an end view in Figures 26 to 28. In these lattice girders, the slant bars are formed simply by a tubular coil fixed by welding to the chord top and bottom chord of the beam. The upper chord is formed, in this case, of two angles.



  It can be narrower than the top chord of formwork beams for concrete floors and ceramic slabs, because it has reinforced concrete sheets and slabs on it that serve as formwork elements for the floor. . These concrete slabs then become elements of the construction, after the concrete has been poured. And for these formwork elements, we do not need the large surfaces for the upper chords, as they are necessary in the formwork beams which serve as a support for the refractory slabs forming formwork in the floors of reinforced concrete and comprising such slabs.



   The formwork beams according to the invention are also suitable for the formwork of the main and secondary beams. In this abutment they are provided with side walls according to Figures 29 to 31 which represent these beams by a longitudinal view, a cross-sectional view and an end view.

   In these figures, the side wall, made of sheet metal which forms a casing, is designated 190 20, designates the openings for fixing the support brackets shown in figures 32 to 35, which are bolted against the end face of such a shuttering beam, as well as the openings for fixing the elements to each other
Figure 32 is a longitudinal view of these formwork beams with support bracket 21 fixed by bolts and resting on the wall carrying the floor.

   Figure 33 shows the support bracket viewed from above, figure 34 shows it seen from the front and Figure 35 its longitudinal section. Figure 36 shows the recess left in the wall for the support of a reinforced concrete beam to be poured in a single block. This large recess has at its base two more small side recesses 22 for them. support brackets which must be attached to the left and to the right, shown in figures 32 to 35, and which carry the two lateral vertical formwork elements shown in figures 29 to 320
The lateral formwork, of course, at their lower ends, is covered with sheets to form the complete formwork for the reinforced concrete beam to be poured.

   In this abutment, openings are provided in the side plates 19 for passing support bars through them. These support bars are not specially shown in the figure. They carry the sheets to the bottom of the formwork. The formwork for a floor with main and secondary exposed beams is produced, according to figure 25, as follows
The assembled formwork beams 23, intended for the main beam, are placed on the supporting elements of the construction and are supported by supports 24, when necessary. The box beams 23 are shown in the right half of Figure 25 by a longitudinal view which gives a section immediately before the main beam of the exposed beam floor.

   Perpendicular to these beams, the shuttering beams 25 for the secondary beams of the floor are placed on their upper chords and on the side walls, parallel to each other, or they are fixed in a suitable location different from the formwork elements of the floor. main beams which, for this purpose, must be fitted with suitable fixing devices. Then, the main formwork beams 23 are placed on the upper chords, parallel to the formwork of the main floor beams, the formwork beams for the slabs of the floor included between the secondary beams of the latter, as shown in the left half of Figure 25 which shows a section of the floor between two main beams.



   At the locations where a main or secondary beam separates or begins, the formwork beams for the side wall of a main beam of the plan are advantageously assembled, according to Figures 37 and 38.

 <Desc / Clms Page number 6>

 chero The upper chord is connected at this point to a bracket 26 across the width of the main or secondary beam which is detached. It remains after dismantling as a lost part of the formwork in the main or secondary beam having hardened, at the location of this bypass.

   Below, the side wall of the main beam is crossed by the sheets 27 and, if necessary also by the sheets 28, just as the tensioned area of the form beam is crossed by a short element. tube which has a screw thread on each side to receive the screw tensioners. Figure 37 is the front view, and Figure 38 is an alternate horizontal section where the side form beams meet at the end for the connection of a secondary beam formwork.



   Figure 39 shows the execution of a formwork element with a branch for a secondary beam above the formwork for a column or a reinforced concrete pillar. This formwork is set at the same time as a support for the formwork of the beams.



   In order to make the shuttering beam as light as possible, the top chord, while having minimal weight, must provide sufficient resistance to buckling and denting. This can be achieved by providing this chord with one or more parallel and juxtaposed channels 290 These can also be offset from one another and have appropriate intervals in the length direction, in order to safeguard the transverse rigidity of the beam. The channel spacing is usefully chosen, based on a static calculation, so that the material is fully utilized and the area between the channels provides the required dent resistance.



   The attached figure 40 shows in plan a top chord fitted with channels 29, figure 41 is a cross section of this chord.



   The shuttering beams can also be used for the shuttering of ceiling boxes limited by I-beams. For this purpose, the formwork beams mounted on the I-beams are provided with adjustable end elements. , in the form of crutches, shown in figures 42 and 43 in side and front elevation, by which the upper chord 3 of the shuttering beam 5 'bears on the lower chord of the I-beams.



   The length of the end element joined to the top chord 3 is variable, in order to compensate for slight differences in the boxes, which may possibly arise after assembly of the elements of the beam. The crutch 30 is of variable inclination and has an adjustable spout 31 by which it rests on the lower chord of the I-beam. The upper chord of the crutch has holes 32 intended to receive the screws for the spout fixing. The lower chord of the formwork beams is joined to the bolt fixed in the manner of a hinge and which is connected by a bar to the upper chord of the end insulation.


    

Claims (1)

RESUME. ABSTRACT. L'invention concerne : 1 ) Une poutre de coffrage composée d'éléments pouvant être assem- blés, franchissant une certaine portée, remarquable, notamment, par les carac- téristiques suivantes considérées séparément ou en combinaison a) Les membrures supérieures des éléments se rencontrent bout à bout, et sont assemblées par des éléments de fixation réglables qui se trou- vent dans la membrure inférieure. b) L'assemblage de la membrure inférieure se fait à l'aide d'un tringlage ou de dispositifs semblables à des tendeurs ou à la fois dun trin- glage et de tels dispositifs. The invention relates to: 1) A shuttering beam made up of elements that can be assembled, crossing a certain span, remarkable, in particular, by the following characteristics considered separately or in combination a) The upper chords of the elements meet end to end, and are assembled by adjustable fasteners located in the lower chord. b) The bottom chord is assembled using a linkage or devices similar to tensioners or both a linkage and such devices. c) Les membrures supérieures des éléments rajoutés bout à bout sont raccordées les unes aux autres par des éléments de fixation dans le sens de la poutre, <Desc/Clms Page number 7> d) Les moyens de fixation pour les éléments de la membrure supé- rieure à rajouter bout à bout sont disposés de telle sorte qu'ils ne soient pas exposés à des tensions appréciables lors du décoffrage après durcissement du plancher. e) La poutre de coffrage a la forme d'une poutre en treillis à trois dimensions. f) La membrure supérieure de la poutre de coffrage est formée d'u- ne tôle en U et est entretoisée, sur ses bords,par des tubes ou fers ronds à tracé ondulé par rapport à la membrure inférieure formée d'un tube ou au- tre profilé en acier. c) The upper chords of the elements added end to end are connected to each other by fixing elements in the direction of the beam, <Desc / Clms Page number 7> d) The fixing means for the elements of the top chord to be added end to end are arranged so that they are not exposed to appreciable tensions during the stripping after hardening of the floor. e) The shuttering beam is in the form of a three-dimensional lattice beam. f) The upper chord of the shuttering beam is formed from a U-shaped sheet and is braced at its edges by tubes or round bars with a corrugated pattern in relation to the lower chord formed by a tube or - be profiled in steel. g) La membrure supérieure de la poutre de coffrage est reliée à la membrure inférieure uniquement par un ou plusieurs fers ronds de tracé on- dulé ou serpentins tubulaires de section voulue. h) Les faces en bout des éléments individuels qui se rencontrent bout à bout ont une forme telle que la poutre puisse être surhaussée ou cin- trée. i) La face en bout des éléments de la poutre de coffrage est exécu- tée sous la forme d'un élément dune demi-articulation. - j) Un tendeur au moins est exécuté sous la forme d'une demi-arti- culation ou est articulé aux membrures inférieures. g) The upper chord of the formwork beam is connected to the lower chord only by one or more corrugated tracing round bars or tubular coils of the desired section. h) The end faces of the individual elements which meet end to end have a shape such that the beam can be raised or bent. i) The end face of the elements of the shuttering beam is executed as a half-joint element. - j) At least one turnbuckle is made in the form of a half-joint or is articulated to the lower chords. k) Du côté du mur,les éléments d'extrémité sont plus courts,, en- dessous de la membrure compriméeque cette dernière, 1) Ses appuis situés du côté du mur ont une forme telle que les éléments d'extrémité de la poutre puissent être abaissés à la façon d'une ar- ticulation après le durcissement de la masse de béton. m) La poutre de coffrage est exécutée sous la forme d'un coffrage latéral pour poutres en béton armé, n) On utilise des- équerres latérales comme éléments de raccorde- ment pour les poutres de coffrage. k) On the wall side, the end elements are shorter,, below the compressed member than the latter, 1) Its supports located on the wall side have a shape such that the end elements of the beam can be lowered like a hinge after the concrete mass has hardened. m) The shuttering beam is designed as a side shuttering for reinforced concrete beams, n) Lateral brackets are used as connecting elements for the shuttering beams. (1) La membrure supérieure est munie d'une ou de plusieurs rigoles orientées parallèlement dans le sens longitudinal de la poutre. p) Les rigoles sont interrompues par des intervalles appropriés dans leur sens longitudinal. q) Les rigoles sont décalées les unes par rapport aux autres. r) La matière constitutive de la membrure supérieure est pleine- ment utilisée diaprés un calcul statique, et l'écartement entre les rigoles est choisi tel que la matière entre les rigoles offre une résistance suffi- sante contre le bossellement. (1) The top chord is provided with one or more channels oriented parallel in the longitudinal direction of the beam. p) The channels are interrupted by appropriate intervals in their longitudinal direction. q) The channels are offset from each other. r) The material of the top chord is fully utilized according to a static calculation, and the spacing between the channels is chosen such that the material between the channels offers sufficient resistance against denting. 2 ) Un élément d'extrémité pour poutres de coffrage selon l . re- marquable, notamment, par les caractéristiques suivantes considérées séparé- ment ou en combinaison : a) L'élément d'extrémité présente la forme d'une béquille appe- lée à s'appuyer sur la membrure inférieure de poutres en Io b) La membrure supérieure présente une longueur variable. c) L'angle d'inclinaison de la béquille est variableo d) La béquille est munie d'un bec,notamment réglableo e) Un boulon formant pivot d'articulation est prévu pour raccorder la membrure inférieure de la poutre de coffrage à Isolément d'extrémité. 2) An end element for formwork beams according to l. remarkable, in particular, by the following characteristics considered separately or in combination: a) The end element has the form of a leg which rests on the lower chord of Io beams b) The top chord has a variable length. c) The angle of inclination of the crutch is variable o d) The crutch is fitted with a spout, in particular adjustable e) A bolt forming an articulation pivot is provided to connect the lower chord of the formwork beam to Insulation d 'end. 3 ) Un procédé pour rétablissement de coffrages de plancher à l' aide de poutres selon 1q , remarquable, notamment, par les caractéristiques suivantes considérées séparément ou en combinaison : a) Les poutres de coffrage sont raidies uniquement par des barres <Desc/Clms Page number 8> transversales, ou à la fois par des barres transversales et des barres diago- nales raccordées aux poutres de coffrage. b) Pour les planchers massifs, on utilise les poutres de coffrage pour 1-'établissement du coffrage du plancher. c) Les poutres de coffrage sont disposées sur des murs portants, sur des supports ou des consoles fixées aux murs. d) On dresse ou on surhausse le coffrage dans la zone tendue des poutres de coffrage, à l'aide du dispositif tendeur. 3) A process for re-establishing floor formwork using beams according to 1q, remarkable, in particular, for the following characteristics considered separately or in combination: a) The formwork beams are stiffened only by bars <Desc / Clms Page number 8> transverse, or both by transverse bars and diagonal bars connected to the formwork beams. b) For solid floors, formwork beams are used for the establishment of the floor formwork. c) The formwork beams are arranged on bearing walls, on supports or consoles fixed to the walls. d) The formwork is erected or raised in the tensioned area of the formwork beams, using the tensioning device. e) Le coffrage pour le plancher se pose, sous la forme d'éléments de hourdis céramiques, éventuellement creux., sur les poutres de coffrage, à la suite de quoi on coule le béton par dessus, f) Dans le cas, particulièrement, de planchers nervurés, les pou- tres de coffrage latéral pour les poutres secondaires du plancher sont dispo- sées avec leurs membrures supérieures sur les poutres de coffrage latéral des poutres principales du plancher. g) Les poutres de coffrage du plancher sont disposées avec leurs membrures supérieures ou inférieures, ou à la fois les deux, sur les poutres de coffrage latéral ou sont fixées autrement contre ces dernières ou sur elles. e) The formwork for the floor is placed, in the form of ceramic slab elements, possibly hollow., on the formwork beams, following which the concrete is poured over, f) In the case, particularly, In ribbed floors, the side formwork beams for the secondary floor beams are arranged with their upper chords on the side formwork beams of the main floor beams. g) Floor form beams are arranged with their top or bottom chords, or both, on the side form beams or otherwise secured against or on them. h) Dans la membrure supérieure des poutres de coffrage latéral, on prévoit, aux emplacements de rencontre bout à bout de poutres transversa- les ou de piliers, ou à la fois de poutres et de piliers, des éléments de coffrage qui restent dans le plancher après le durcissement du béton. i) Les coffrages ou éléments de coffrage sont métalliques. en annexe 11 dessins. h) In the upper chord of the side formwork beams, there are provided, at the end-to-end meeting places of transverse beams or pillars, or both beams and pillars, formwork elements which remain in the floor after the concrete has hardened. i) Formwork or formwork elements are metallic. in appendix 11 drawings.
BE497329D BE497329A (en)

Publications (1)

Publication Number Publication Date
BE497329A true BE497329A (en)

Family

ID=140326

Family Applications (1)

Application Number Title Priority Date Filing Date
BE497329D BE497329A (en)

Country Status (1)

Country Link
BE (1) BE497329A (en)

Similar Documents

Publication Publication Date Title
EP1101871B1 (en) Steel bridge deck and method for the construction of a bridge with such a deck
FR2481248A1 (en) LIGHTWEIGHT AND RESISTANT ARROW ELEMENTS FOR TELESCOPIC CRANE ARROW AND CRANE ARROW SHAPED OF SUCH ELEMENTS
KR101993602B1 (en) Steel girder formwork structure and reinforcement structure of steel girder parent part
WO2016189476A1 (en) Construction of the prefabricated column and beam type
WO2005012644A1 (en) Modular metal bridge and method for production thereof
BE497329A (en)
EP1065316B1 (en) Composite steel-concrete bridge- or walk way structure, especially bridge with double composite beams under the deck
BE1017376A5 (en) METAL JOINT FOR EXPANSION BETWEEN CONCRETE SLABS.
FR2880370A1 (en) Antiseismic, anticyclonic and heat insulating wall mounting method for building, involves placing trellis, channel bar and lattice stanchion in space between two rows of panels and filling concrete in space until to height of rows
FR2656020A1 (en) ASSEMBLY BY EMBOITEMENT OF TWO Z-RIGHT SECTION PROFILES, ESPECIALLY FOR MAKING A FAILURE, A SMOOTH OR A FLOOR SUPPORT.
FR2734287A1 (en) Concrete road bridge without steel structure
JP5841786B2 (en) Steel concrete composite slab construction panel and steel concrete composite slab
FR2515310A1 (en) Hollow composite steel and concrete beam - has V=shaped recess in each end receiving joint ring and mortise slots for attaching orthogonal bars
BE479715A (en)
BE413281A (en)
FR2752430A1 (en) Movable coffering for concrete bridge
EP2761090B1 (en) Metal bridge span and method for the modular construction of such a span
OA18497A (en) Construction type prefabricated posts and beams.
BE505566A (en)
FR2882074A1 (en) Wooden framed structure for building, has wooden columns fixed on metallic lower and wooden upper wall plates, and bituminized cardboard overlapping with footing on both sides, where lower plate is fixed on upper plates through screws
BE882905A (en) REMOVABLE VIADUCT WITH MIXED STEEL-CONCRETE STRUCTURE.
BE521410A (en)
FR2474556A1 (en) Road surfacing for bridge - has removable plates resting on transverse support beams made up of hinged girders
CH95338A (en) Beam for the construction of reinforced concrete floors.
BE470531A (en)