JPS6324276B2 - - Google Patents
Info
- Publication number
- JPS6324276B2 JPS6324276B2 JP56051065A JP5106581A JPS6324276B2 JP S6324276 B2 JPS6324276 B2 JP S6324276B2 JP 56051065 A JP56051065 A JP 56051065A JP 5106581 A JP5106581 A JP 5106581A JP S6324276 B2 JPS6324276 B2 JP S6324276B2
- Authority
- JP
- Japan
- Prior art keywords
- torus
- containment vessel
- construction
- reactor building
- reactor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010276 construction Methods 0.000 claims description 27
- 229910000831 Steel Inorganic materials 0.000 claims description 12
- 239000010959 steel Substances 0.000 claims description 12
- 238000009415 formwork Methods 0.000 claims description 10
- 238000000034 method Methods 0.000 claims description 9
- 238000009434 installation Methods 0.000 claims description 6
- 235000008331 Pinus X rigitaeda Nutrition 0.000 description 3
- 235000011613 Pinus brutia Nutrition 0.000 description 3
- 241000018646 Pinus brutia Species 0.000 description 3
- 230000003111 delayed effect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000000725 suspension Substances 0.000 description 2
- 101100491335 Caenorhabditis elegans mat-2 gene Proteins 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】
本発明はトーラス型原子炉格納容器を有する原
子力発電所の原子炉建屋の施工方法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing a reactor building for a nuclear power plant having a torus-type reactor containment vessel.
従来の原子炉建屋の施工方法における原子炉格
納容器の据付方法および地下壁の建設方法につい
て第1図を参照しながら説明する。第1図は原子
力発電所の原子炉建屋と原子炉格納容器との関連
を一部側面で示す断面図である。 A method of installing a reactor containment vessel and a method of constructing an underground wall in a conventional construction method of a nuclear reactor building will be explained with reference to FIG. FIG. 1 is a partially sectional side view showing the relationship between a reactor building and a reactor containment vessel of a nuclear power plant.
地盤Fを堀削して原子炉建屋1のマツトスラブ
2が完了し、地下壁3の建設用足場4を組み、地
下壁3のコンクリートを打設したのち養生完了
後、トーラス室5の清掃及び足場4の解体を行
い、タワークレーン6によつて原子炉格納容器7
のトーラス8を搬入する。その後トーラス8、組
立用の足場9を設置するが、トーラス8と地下壁
3との間隔は、建屋の構造上約600〜700mm程度と
非常に狭く、通常設置される足場を設置するのが
不可能なため、パイプ等により簡易な足場を組
み、トーラス8の組立を行つている。そして、原
子炉格納容器7の外面塗装を行い、シールド壁1
0及び原子炉建屋1の建設工事を実施し原子炉建
屋を完成させるのである。 After excavating the ground F and completing the pine slab 2 of the reactor building 1, constructing scaffolding 4 for the construction of the underground wall 3, and pouring concrete for the underground wall 3, and after completion of curing, cleaning of the torus room 5 and scaffolding. 4 was dismantled, and the reactor containment vessel 7 was dismantled by tower crane 6.
Torus 8 will be brought in. After that, the torus 8 and the scaffolding 9 for assembly are installed, but the distance between the torus 8 and the underground wall 3 is very narrow, about 600 to 700 mm, due to the structure of the building, so it is impossible to install the scaffolding that is normally installed. As it is possible, torus 8 is being assembled using simple scaffolding made of pipes, etc. Then, the outer surface of the reactor containment vessel 7 is painted, and the shield wall 1 is painted.
0 and reactor building 1 to complete the reactor building.
しかしながら上記従来の原子炉格納容器7およ
び地下壁3の施工方法は次の様な欠点があつた。 However, the conventional method of constructing the reactor containment vessel 7 and underground wall 3 has the following drawbacks.
すなわち、原子炉建屋1の地下壁3が完成した
後に原子炉格納容器7のトーラス8を搬入する手
順のためトーラス8の組立開始時期が極めて遅く
なり、したがつて原子炉格納容器組立のクリチカ
ルパスとなつている。また壁があるため機械側の
搬入及び作業が非常に規制をうける。さらにトー
ラス8と地下壁3との間隔が狭くて並行作業が困
難であり、機械側及び建築側工事が各々手待ち工
事となり、工事量の標準化が極めて困難となる。
さらには、足場を建築側または機械側と組替る必
要があり、かつパイプ足場であるため安全上も問
題があつた。この結果、地下壁3の施工及び格納
容器のトーラス8の据付組立が、原子力発電所の
全体建設期間におけるクリチカルパスとなり、原
子炉建屋全体の建設工期が長期におよぶ最大の原
因となつている。 In other words, due to the procedure of transporting the torus 8 of the reactor containment vessel 7 after the basement wall 3 of the reactor building 1 is completed, the time to start assembling the torus 8 is extremely delayed, and therefore the critical path for reactor containment vessel assembly is delayed. It is becoming. In addition, due to the walls, there are severe restrictions on bringing in and working on machinery. Furthermore, the distance between the torus 8 and the underground wall 3 is narrow, making it difficult to carry out parallel work, and the mechanical and construction work must be completed separately, making it extremely difficult to standardize the amount of work.
Furthermore, it was necessary to replace the scaffolding with the building side or the machinery side, and since it was a pipe scaffolding, there were also safety issues. As a result, the construction of the underground wall 3 and the installation and assembly of the torus 8 of the containment vessel become critical paths in the overall construction period of the nuclear power plant, and are the biggest reason for the long construction period of the entire reactor building.
本発明は、以上の事情に鑑みてなされたもので
その目的とするところは、工期の大巾短縮と工数
の低減及び標準化作業上の安全性向上および能率
の向上を図つた原子炉格納容器トーラス8を地下
壁3における原子炉建屋の施工方法を提供するこ
とにある。 The present invention has been made in view of the above circumstances, and its purpose is to provide a reactor containment vessel torus that significantly shortens the construction period, reduces the number of man-hours, and improves the safety and efficiency of standardization work. 8 is to provide a method of constructing a nuclear reactor building in an underground wall 3.
すなわち、本発明は、トーラス型原子炉格納容
器7の組立工事を原子炉建屋地下壁3の建設工事
と無関係に組立を開始して、さらに原子炉格納容
器7とトーラス8組立作業とは並行作業で原子炉
建屋地下壁3及び天井11の建設作業を実施しよ
うとする原子炉建屋の施工方法である。 That is, the present invention starts the assembly work of the torus-type reactor containment vessel 7 independently of the construction work of the reactor building basement wall 3, and furthermore, the assembly work of the reactor containment vessel 7 and the torus 8 is performed in parallel. This is a construction method for a reactor building in which the construction work of the underground wall 3 and ceiling 11 of the reactor building is to be carried out.
以下第2図および第3図を参照して本発明の一
実施例を説明する。 An embodiment of the present invention will be described below with reference to FIGS. 2 and 3.
第2図は本発明において使用するトーラス8と
地下壁3用の鉄骨型枠形状を示す断面図である。
第3図に示したように、先ず原子炉建屋1のマツ
トスラブ2完了後、タワークレーン6により第2
図のように予め工場及び現場の地上組立場でトー
ラス8と地下壁3の鉄骨型枠12、鉄骨型枠支持
材13及びトーラス上部床鉄骨デツキプレート1
1を一体化にしたトーラス8をマツト2上に吊り
込みを行なう。吊り込みが完了したならば、トー
ラス8の据付および組立を開始するとともにトー
ラス室5側に鉄骨型枠12の設定が終つている地
下壁3の施工を並行作業により行なう。地下壁3
の建設が完了したならば、引き続き鉄骨デツキプ
レート11が設定されているトーラス室上部の施
工を行なう。トーラス8及び原子炉格納容器7の
据付が完了したならば全体漏洩試験を実施して、
外面塗装完了後、シールド壁10の施工を開始し
て原子炉建屋1を完成させる。 FIG. 2 is a sectional view showing the shape of the torus 8 and the steel formwork for the underground wall 3 used in the present invention.
As shown in Fig. 3, first, after the pine slab 2 of the reactor building 1 is completed, the tower crane 6
As shown in the figure, the torus 8, the steel frame formwork 12 of the underground wall 3, the steel frame support material 13, and the torus upper floor steel deck plate 1 are prepared in advance at the above-ground assembly site in the factory and on-site.
A torus 8 which is integrated with 1 is hung onto a mat 2. Once the lifting is completed, the installation and assembly of the torus 8 is started, and the construction of the underground wall 3, on which the steel formwork 12 has already been set, is carried out in parallel on the torus room 5 side. basement wall 3
After the construction of the torus room is completed, the construction of the upper part of the torus room where the steel deck plate 11 is installed will be continued. After the installation of torus 8 and reactor containment vessel 7 is completed, a total leakage test is conducted.
After the exterior painting is completed, construction of the shield wall 10 is started and the reactor building 1 is completed.
以上の説明の様に、本発明による原子炉格納容
器およびトーラスの据付による原子炉建屋の施工
方法によれば、原子炉建屋マツトスラブのコンク
リート打設養生後、すぐにトーラスの搬入および
組立、地下壁の建設工事に入いることが出来る。
また機械側、建築側の建設工事とが並行作業を行
えるため、トーラス型原子炉格納容器を有する原
子力発電所の建設工程のクリチカルパスとなつて
いる地下壁とトーラス組立工期が短縮されること
から、原子力発電所の全体工期の大巾な短縮が出
来る。さらにトーラスの搬入は、地下壁・天井の
鉄骨型枠、鉄骨型枠支持材ともに一体化で同時に
吊り込むため、大巾に作業性の向上を図ることが
出来る。 As explained above, according to the method of constructing a reactor building by installing a reactor containment vessel and a torus according to the present invention, immediately after the concrete pouring and curing of the pine slab of the reactor building, the torus is transported and assembled, and the underground wall construction work can begin.
In addition, since the construction work on the machinery side and the building side can be carried out in parallel, the construction period for assembling the underground walls and torus, which is a critical path in the construction process of a nuclear power plant with a torus-type reactor containment vessel, can be shortened. , it is possible to significantly shorten the overall construction period of a nuclear power plant. Furthermore, when transporting the torus, the steel formwork for underground walls and ceilings, as well as the steel formwork support materials, are integrated and suspended at the same time, greatly improving work efficiency.
またさらに、従来用いられていたトーラス室の
側面を形成する地下壁のトーラス室に面する側の
型枠を組立てる建設用足場及びトーラスの組立用
の足場を設定することがなくなり、安全性の向上
及び上述した足場の組立、解体作業に費す工期を
短縮させることができる。 Furthermore, it is no longer necessary to set up construction scaffolding for assembling the formwork on the side of the basement wall facing the torus room that forms the side of the torus room, which was conventionally used, and scaffolding for assembling the torus, improving safety. Also, the time required for assembling and dismantling the scaffolding described above can be shortened.
なお、本発明において、吊り込みが行なわれた
各々のトーラスの組立に足場が用いられ、さらに
はこの組立作業と並行に行なわれる地下壁のコン
クリート打設時にトーラス室と対向する位置に足
場が用いられる。しかしながらこれらの作業に用
いられる足場はトーラスの吊り込み後であるた
め、工期に規制を与えるものではなく、本発明の
作用効果には影響がない。 In addition, in the present invention, scaffolding is used to assemble each suspended torus, and furthermore, scaffolding is used at a position facing the torus room during concrete pouring of the basement wall, which is performed in parallel with this assembly work. It will be done. However, since the scaffolding used for these works is used after the torus has been suspended, the construction period is not restricted and the effects of the present invention are not affected.
これらの種々の効果の総合により原子力発電所
建設工期の大巾な短縮と建設費用の節約は著しい
ものであることは、容易に理解出来る。 It is easy to understand that the combination of these various effects will significantly shorten the construction period of a nuclear power plant and save construction costs.
以上本発明はその具体的実施例について説明し
たが、本発明はこれら特定の実施例に限定される
ものでなく本発明の精神を逸脱しないで幾多の応
用例および変形例がなし得ることは勿論である。 Although the present invention has been described above with reference to specific embodiments, the present invention is not limited to these specific embodiments, and it goes without saying that numerous applications and modifications can be made without departing from the spirit of the invention. It is.
第1図は従来の原子炉建屋の施工方法における
格納容器(トーラス型)のトーラス部分の吊り込
み及び据付状況を一部側面で示す断面図、第2図
は本発明において使用する鉄骨型枠を取付けたト
ーラスの側面図、第3図は本発明による原子炉建
屋の施工方法の一実施例を説明するための格納容
器のトーラス部の吊り込み及び据付状況を一部側
面で示す断面図である。
1……原子炉建屋、2……原子炉建屋マツト、
3……原子炉建屋地下壁、4……建設用足場、5
……原子炉建屋トーラス室、6……タワークレー
ン、7……原子炉格納容器、8……原子炉格納容
器トーラス、9……原子炉格納容器組立用足場、
10……原子炉建屋シールド壁、11……原子炉
建屋トーラス天井、12……鉄骨型枠、13……
鉄骨型枠支持材。
Figure 1 is a cross-sectional view partially showing the suspension and installation of the torus part of the containment vessel (torus type) in the conventional construction method for a reactor building, and Figure 2 shows the steel formwork used in the present invention. FIG. 3 is a side view of the installed torus, and FIG. 3 is a cross-sectional view partially showing a side view of the suspension and installation of the torus portion of the containment vessel for explaining one embodiment of the method of constructing a reactor building according to the present invention. . 1...Reactor building, 2...Reactor building Matsuto,
3... Reactor building underground wall, 4... Construction scaffolding, 5
...Reactor building torus room, 6...Tower crane, 7...Reactor containment vessel, 8...Reactor containment vessel torus, 9...Scaffolding for reactor containment vessel assembly,
10... Reactor building shield wall, 11... Reactor building torus ceiling, 12... Steel formwork, 13...
Steel formwork support.
Claims (1)
力発電所における原子炉建屋の施工方法におい
て、トーラスを収容するトーラス室の側面を形成
する地下壁の鉄骨型枠をトーラスに取り付けると
ともに該トーラスの据付組立と地下壁の建設工事
を並行して行うことを特徴とする原子炉建屋の施
工方法。1. In the construction method of a nuclear reactor building in a nuclear power plant where a torus-type reactor containment vessel is installed, the steel formwork of the underground wall that forms the side surface of the torus chamber that accommodates the torus is attached to the torus, and the installation and assembly of the torus is carried out. A method of constructing a nuclear reactor building, which is characterized by carrying out construction work of underground walls and basement walls in parallel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP56051065A JPS57165792A (en) | 1981-04-07 | 1981-04-07 | Method of constructing nuclear reactor building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP56051065A JPS57165792A (en) | 1981-04-07 | 1981-04-07 | Method of constructing nuclear reactor building |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS57165792A JPS57165792A (en) | 1982-10-12 |
JPS6324276B2 true JPS6324276B2 (en) | 1988-05-19 |
Family
ID=12876391
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP56051065A Granted JPS57165792A (en) | 1981-04-07 | 1981-04-07 | Method of constructing nuclear reactor building |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS57165792A (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6117986A (en) * | 1984-07-05 | 1986-01-25 | 株式会社東芝 | Method of installing housing vessel for nuclear reactor and divided unit used for said installation |
JPS62233789A (en) * | 1986-04-04 | 1987-10-14 | 株式会社東芝 | Method of building nuclear power plant |
-
1981
- 1981-04-07 JP JP56051065A patent/JPS57165792A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS57165792A (en) | 1982-10-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS6324276B2 (en) | ||
CN210067447U (en) | Assembled lintel | |
JPH0996036A (en) | Structure of wall material or floor material for construction | |
KR102679042B1 (en) | PC half-slab construction method for quick construction of precast concrete apartment house | |
JPS6331076B2 (en) | ||
KR20010097524A (en) | Hybrid precast concrete structure and the method of the same | |
JPS63272690A (en) | Construction of lining tank | |
JPS6326215B2 (en) | ||
JPH06341179A (en) | Spandrel construction method | |
JPH03158519A (en) | Direct finishing method by inner-casting of cast-in-place concrete pile | |
KR920004493B1 (en) | Panel for heating system | |
JPS6355572B2 (en) | ||
JPS6318155B2 (en) | ||
JP3009298B2 (en) | Method of manufacturing PCa slab | |
JPH08177068A (en) | Construction of underground structure | |
JPS6131258B2 (en) | ||
JP2004061443A (en) | Building of nuclear power plant and method for constructing it | |
JPS6246758Y2 (en) | ||
JPH0471478B2 (en) | ||
JPS6338674B2 (en) | ||
JP2531045B2 (en) | Construction method for reinforced concrete structure | |
JPH0519959B2 (en) | ||
JPH0790972A (en) | Construction of building and lightweight floor slab | |
JPH0151951B2 (en) | ||
JPH09256457A (en) | Building assembly method |