JPS6033187A - Method of installing main engine - Google Patents
Method of installing main engineInfo
- Publication number
- JPS6033187A JPS6033187A JP58139719A JP13971983A JPS6033187A JP S6033187 A JPS6033187 A JP S6033187A JP 58139719 A JP58139719 A JP 58139719A JP 13971983 A JP13971983 A JP 13971983A JP S6033187 A JPS6033187 A JP S6033187A
- Authority
- JP
- Japan
- Prior art keywords
- main engine
- main machine
- mount
- engine
- ship
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B71/00—Designing vessels; Predicting their performance
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Vibration Prevention Devices (AREA)
Abstract
Description
【発明の詳細な説明】
船の主機械を積込む場合は主機械は総組立の状態でする
のが作業能率上からも、また主機械の陸上試運転完了の
状態のま〜を保持する意味からも最も望ましいことであ
る。しかし従来はたとえ主機械の大きさに見合う機械室
天井開口部があってもそれが主機械据付台直上にない場
合は、この据付台に主機械を直接吊り降すことができな
いので。[Detailed Description of the Invention] When loading a ship's main machinery, it is recommended to do so in a completely assembled state, both from the standpoint of work efficiency and from the standpoint of maintaining the condition of the main machinery in a state where land trial runs have been completed. is also the most desirable. However, in the past, even if there was an opening in the machine room ceiling suitable for the size of the main machine, if it was not directly above the main machine installation stand, the main machine could not be directly suspended from the installation stand.
試運転完了後の主機械を小ブロックに分解してとうる方
法を提供するものである。This provides a method for disassembling the main machine into small blocks after a trial run is completed.
本発明は主機械をまず機関室開口部からタ/クトノブ上
に吊り降して、つぎにこれを主機械据付台上まで移動す
るものであり、第1図はこの方法を船の縦断面で示す概
念図である。図で1は船体。In the present invention, the main machine is first suspended from the engine room opening onto the turret knob, and then moved to the main machine installation stand. Figure 1 shows this method in a longitudinal section of the ship. FIG. In the diagram, 1 is the hull.
2は機関室、3は機関室天井開口部、5は主機械据付台
、5′は天井開口部直下のタンクトップを主機械据付台
面と同一高さにするために同据付台面にはポールを用い
、第2図はポール10が主機械1とタンクトップの主機
械据付台5との間にそう人されている状態を示す。ポー
ル10は据付台5上のレールとなる鋼板11.主機械据
付台盤12下面に装着されるポール受は鋼板130間に
挟まれ、これら。2 is the engine room, 3 is the engine room ceiling opening, 5 is the main machine installation stand, and 5' is a pole on the installation stand surface to make the tank top directly under the ceiling opening the same height as the main machine installation stand surface. FIG. 2 shows a state in which the pole 10 is placed between the main machine 1 and the main machine mounting stand 5 on the tank top. The pole 10 is a steel plate 11 that becomes a rail on the installation stand 5. A pole holder attached to the lower surface of the main machine installation base 12 is sandwiched between steel plates 130.
鋼板11.13は主に主機械据付関係のボルト孔、ある
いはスタッドを利用して取付けられる。14はボール1
0の保持板で、これらボール10群には進水に用いられ
るものを利用することができる。第3図は鋼板11の斜
視図で、15はボール100案内部材。The steel plates 11 and 13 are mainly attached using bolt holes or studs related to the installation of the main machine. 14 is ball 1
With a holding plate of 0, those used for launching can be used for these 10 groups of balls. FIG. 3 is a perspective view of the steel plate 11, and 15 is a ball 100 guide member.
16は主機械の横ずれ防止材、第4図は主機械台盤下の
ボール受鋼板13で、17はボール脱落防止レール、1
8はチョックライナ取付用ボルト孔に入る突起である。16 is the lateral slip prevention material of the main machine, Fig. 4 is the ball receiving plate 13 under the main machine platform, 17 is the ball fall prevention rail, 1
8 is a protrusion that fits into the chock liner mounting bolt hole.
以上のようにレールとなる鋼板11上にボール1゜の群
を介して載置された主機械は、ドックまたは岸壁クレー
ンによりそらせシーズを介して所要位置に移動される。As described above, the main machine mounted on the steel plate 11 serving as the rail via a group of 1° balls is moved to a required position via a deflection sheath by a dock or quay crane.
従来は機関室天井に総組立した主機械が充分通過しうる
大きさの開口部があってもそれが主機械台上の直上にな
い場合は試運転をおえだ主機械を分解して積込んでいた
。しかし本方法によれば上記のような場合でもそのよう
な手数をかける必要もなく、また試運転完了後の主機械
の状態を何等損うことなく積込みをすることかできる。Conventionally, even if there was an opening in the ceiling of the engine room that was large enough for the fully assembled main machine to pass through, if it was not directly above the main machine platform, the main machine that had completed its trial run would be disassembled and loaded. there was. However, according to the present method, there is no need to take such trouble even in the above case, and loading can be carried out without any damage to the condition of the main machine after the trial run is completed.
第1図は本方法を船の縦断面で示す概念図、第2図は移
動用ボールのそう入状態の側面図、第3図はレールの、
第4図は主機械台下のボール受鋼板の何れも斜視図。
1 船体
2 機関室
3 同上天井開口部
5 主機械据付台
5′ 同上延長部
7、7S 7” 主機械
lOボール
11、13 ボールを受ける鋼板
】2 主機械据付台盤
出願人 三井造船株式会社
代理人 河 1)茂 夫
第2図
牙3゛図
1らFigure 1 is a conceptual diagram showing this method in a longitudinal section of a ship, Figure 2 is a side view of the moving ball in its inserted state, and Figure 3 is a diagram of the rail.
Figure 4 is a perspective view of the ball receiving plates under the main machine stand. 1 Hull 2 Engine room 3 Same as above Ceiling opening 5 Main machine installation stand 5' Same as above extension 7, 7S 7'' Main machine lO balls 11, 13 Steel plate for receiving balls] 2 Main machine installation stand Applicant Mitsui Engineering & Shipbuilding Co., Ltd. Agent Human River 1) Shigeo 2nd figure tusk 3゛Figure 1 etc.
Claims (1)
ルの群をおき、主機械側にはその据付台盤上に移動する
ようにした船の主機械の積込方法。 法に関する。[Claims] A method for loading a ship's main machinery, in which a steel plate serving as a rail is laid on top of the rails, a group of poles are placed on this, and the main machinery is moved onto an installation platform on the main machinery side. Method. Regarding the law.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP58139719A JPS6033187A (en) | 1983-07-30 | 1983-07-30 | Method of installing main engine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP58139719A JPS6033187A (en) | 1983-07-30 | 1983-07-30 | Method of installing main engine |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6033187A true JPS6033187A (en) | 1985-02-20 |
Family
ID=15251808
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP58139719A Pending JPS6033187A (en) | 1983-07-30 | 1983-07-30 | Method of installing main engine |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6033187A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100489803B1 (en) * | 2001-11-19 | 2005-05-16 | 대우조선해양 주식회사 | Method for manufacturing a main support to the turbine of ship |
DE102010040907A1 (en) * | 2010-09-16 | 2012-03-22 | Aloys Wobben | Electric motor replacement |
-
1983
- 1983-07-30 JP JP58139719A patent/JPS6033187A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100489803B1 (en) * | 2001-11-19 | 2005-05-16 | 대우조선해양 주식회사 | Method for manufacturing a main support to the turbine of ship |
DE102010040907A1 (en) * | 2010-09-16 | 2012-03-22 | Aloys Wobben | Electric motor replacement |
WO2012034938A1 (en) * | 2010-09-16 | 2012-03-22 | Wobben, Aloys | Electric motor exchange |
TWI454408B (en) * | 2010-09-16 | 2014-10-01 | Wobben Aloys | Electric motor exchange |
US9073607B2 (en) | 2010-09-16 | 2015-07-07 | Wobben Properties Gmbh | Electric motor exchange |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4765776A (en) | Convertible barge | |
DE2755518A1 (en) | DEVICE FOR WATERING TAPPING HOUSING PARTS FOR OFF-SHORE PLATFORMS | |
US3877664A (en) | Mooring device | |
JPS6033187A (en) | Method of installing main engine | |
DE2152964A1 (en) | Device and method for driving anchorages for pipelines laid on the seabed | |
JPS5664024A (en) | Placer for steel plate cell | |
DE2056069B2 (en) | Functional unit on ships for weapons, fire control or location systems | |
RU2059522C1 (en) | Device for carriage of rescue apparatus on submarine | |
RU2667407C1 (en) | Multipurpose submarine for transportation, installation, removal of cargo under water | |
USH3H (en) | Original method of drydocking ships | |
JPS59156887A (en) | Method of installing tank in ship body | |
JPH0710072A (en) | Method for carrying out crankshaft of diesel main engine in engine room of ship | |
CN210650620U (en) | Auxiliary device is used in radar maintenance | |
FR2363340A1 (en) | Fire engine particularly for technical work - has central open topped cavity for appts. containers movable by lifting device | |
SU1493742A1 (en) | Method of constructing superstructure of stationary offshore platform | |
JPS5559220A (en) | Steel plate cell driving method and apparatus | |
JPS633360Y2 (en) | ||
US3765355A (en) | Salvage system | |
JPS579928A (en) | Installation for submarine observation chamber | |
SU765106A2 (en) | Floating load-hoisting station | |
DE102020208327A1 (en) | Transport box for setting down a watercraft | |
JPH08232579A (en) | Tunnel excavating device | |
KR790001214B1 (en) | The assembling equipment of ship frame | |
JPS5457408A (en) | Constructing method for blast furnace | |
JPS57155192A (en) | Ship |