JPS5520816A - Foundation construction method - Google Patents
Foundation construction methodInfo
- Publication number
- JPS5520816A JPS5520816A JP9327478A JP9327478A JPS5520816A JP S5520816 A JPS5520816 A JP S5520816A JP 9327478 A JP9327478 A JP 9327478A JP 9327478 A JP9327478 A JP 9327478A JP S5520816 A JPS5520816 A JP S5520816A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- frame
- steel
- guide frame
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
PURPOSE: To provide a method which enables the driving of steel piles at such a high accuracy to assemble thereof prior to the setting up of the guide frame affording a high water stopping effect while the withdrawal of the frame eliminates trouble-some underwater cutting.
CONSTITUTION: Steel pipes or steel pipe sheet piles are connected together to ensure water stoppage matching the shape of a foundation 6 to be erected beforehand. At the same time, a guide frame 1 in which a cut section is arranged at the portion there-inside corresponding to the lower end of the steel pipe is carried to and set up at an erection point. Running through the steel pipes of the steel pipe pile 5 smaller in the diameter than the steel pipe 2 is driven into the ground. Subsequently, water in the frame is drained and a joint reinforcement is projected at the portion where the steel pipe pile 5 is exposed from the cut of the frame 1. With the casting of the concrete, a foundation 6 is built. Thereafter, the guide frame is with-drawn to remove.
COPYRIGHT: (C)1980,JPO&Japio
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9327478A JPS5520816A (en) | 1978-07-31 | 1978-07-31 | Foundation construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9327478A JPS5520816A (en) | 1978-07-31 | 1978-07-31 | Foundation construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS5520816A true JPS5520816A (en) | 1980-02-14 |
Family
ID=14077856
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9327478A Pending JPS5520816A (en) | 1978-07-31 | 1978-07-31 | Foundation construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5520816A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS579426U (en) * | 1980-06-13 | 1982-01-18 | ||
JPS59129940U (en) * | 1983-02-22 | 1984-08-31 | 新日本製鐵株式会社 | Steel pipe cell structure |
CN104594368A (en) * | 2015-01-28 | 2015-05-06 | 泰昌建设有限公司 | Bamboo raft pile oversized cofferdam and construction method for sea reclamation by adopting same |
CN105040701A (en) * | 2015-08-28 | 2015-11-11 | 中国水利水电第七工程局有限公司 | Water spraying type distribution hopper device for lattice type steel plate pile cofferdam |
CN105951861A (en) * | 2016-06-24 | 2016-09-21 | 北京城建集团有限责任公司 | Lateral freezing bottom-making water stop structure for underground excavated foundation pit of urban sensitive area and method |
CN105951860A (en) * | 2016-06-24 | 2016-09-21 | 北京城建集团有限责任公司 | Slanting freezing bottom-making water stop structure for interior and side faces of underground excavated foundation pit and method |
CN106120827A (en) * | 2016-06-23 | 2016-11-16 | 北京城建集团有限责任公司 | Freeze to make end water-bound and method inside a kind of sensitizing range, city tunneling foundation ditch |
-
1978
- 1978-07-31 JP JP9327478A patent/JPS5520816A/en active Pending
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS579426U (en) * | 1980-06-13 | 1982-01-18 | ||
JPS59129940U (en) * | 1983-02-22 | 1984-08-31 | 新日本製鐵株式会社 | Steel pipe cell structure |
CN104594368A (en) * | 2015-01-28 | 2015-05-06 | 泰昌建设有限公司 | Bamboo raft pile oversized cofferdam and construction method for sea reclamation by adopting same |
CN104594368B (en) * | 2015-01-28 | 2017-01-11 | 泰昌建设有限公司 | Bamboo raft pile oversized cofferdam and construction method for sea reclamation by adopting same |
CN105040701A (en) * | 2015-08-28 | 2015-11-11 | 中国水利水电第七工程局有限公司 | Water spraying type distribution hopper device for lattice type steel plate pile cofferdam |
CN106120827A (en) * | 2016-06-23 | 2016-11-16 | 北京城建集团有限责任公司 | Freeze to make end water-bound and method inside a kind of sensitizing range, city tunneling foundation ditch |
CN105951861A (en) * | 2016-06-24 | 2016-09-21 | 北京城建集团有限责任公司 | Lateral freezing bottom-making water stop structure for underground excavated foundation pit of urban sensitive area and method |
CN105951860A (en) * | 2016-06-24 | 2016-09-21 | 北京城建集团有限责任公司 | Slanting freezing bottom-making water stop structure for interior and side faces of underground excavated foundation pit and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS5520816A (en) | Foundation construction method | |
JPS559949A (en) | Installing process for foundation pile | |
SU771252A1 (en) | Drainage arrangement | |
JPS5721623A (en) | Treatment work for top of pile | |
JPS5646031A (en) | Constructing method for pile foundation footing with erected trunk | |
JPS56139307A (en) | Execution of foundation pile | |
JPS57108326A (en) | Construction of pile foundation with underground wall | |
JPS55114715A (en) | Method for construction of steel pipe sheet pile well foundation | |
JPS57112513A (en) | Construction of foundation pile for ground improvement | |
JPS56105016A (en) | Executing method for reinforced foundation pile and reinforcing steel pipe | |
JPS5532812A (en) | Huge pole foundation practice | |
JPS51138914A (en) | Method of construction of an underground tank for liquid natural gas | |
JPS56150222A (en) | Construction of marine structure | |
JPS55161118A (en) | Pile driving method and pile | |
JPS5532809A (en) | Pile foundation practice | |
JPS56153016A (en) | Application of reinforced foundation pile | |
JPS56131716A (en) | Removal of pile | |
JPS55116922A (en) | Jointing method of continuous underground wall | |
JPS5677424A (en) | Auger screw for underground continuous wall construction | |
JPS5664019A (en) | Method and apparatus for in-situ pile driving work | |
JPS5761111A (en) | Reduction of extra-banking concrete for head of pile driven in situ | |
JPS57137518A (en) | Construction of underground wall | |
JPS55161123A (en) | Sg-reinforced piping method | |
JPS5634829A (en) | Foundation constructing method by steel plate cell | |
JPS55147475A (en) | Cutting method of steel pipe sheet pile |