JPS55161123A - Sg-reinforced piping method - Google Patents
Sg-reinforced piping methodInfo
- Publication number
- JPS55161123A JPS55161123A JP6929679A JP6929679A JPS55161123A JP S55161123 A JPS55161123 A JP S55161123A JP 6929679 A JP6929679 A JP 6929679A JP 6929679 A JP6929679 A JP 6929679A JP S55161123 A JPS55161123 A JP S55161123A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipes
- stratum
- supporting
- sloped ground
- injected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
PURPOSE: To prevent collapse of a sloped ground by a method wherein a grouting material is injected into steel pipes driven down to the supporting stratum of a sloped ground, thereby fixing the steel pipes to the stratum, and the steel pipes are interconnected by wire ropes, in a reinforcing method for a sloped ground.
CONSTITUTION: In a sloped ground are excavated holes piercing through the surface layer down to the supporting stratum, steel pipes are inserted or driven into the holes, and a grouting material is injected at high prssure into the steel pipes from their upper ends. The thus injected grouting material spouts from the lower ends of the steel pipes, and penetrates into the stratum to form bulbs, forming rigid supporting piles with the steel pipes as shafts. Then, the upper ends of the teel pipes of the supporting piles thus driven over the whole surface of the slope are interconnected by wire ropes 3, to construct a supporting pile group convering the slope.
COPYRIGHT: (C)1980,JPO&Japio
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6929679A JPS55161123A (en) | 1979-06-01 | 1979-06-01 | Sg-reinforced piping method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6929679A JPS55161123A (en) | 1979-06-01 | 1979-06-01 | Sg-reinforced piping method |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS55161123A true JPS55161123A (en) | 1980-12-15 |
Family
ID=13398457
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6929679A Pending JPS55161123A (en) | 1979-06-01 | 1979-06-01 | Sg-reinforced piping method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS55161123A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100451954B1 (en) * | 2001-11-03 | 2004-10-08 | 주식회사 성원안전 | Constructing method for reinforcing and protecting the slope using wire block |
-
1979
- 1979-06-01 JP JP6929679A patent/JPS55161123A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100451954B1 (en) * | 2001-11-03 | 2004-10-08 | 주식회사 성원안전 | Constructing method for reinforcing and protecting the slope using wire block |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS55161123A (en) | Sg-reinforced piping method | |
JPS56142923A (en) | Construction of foundation pile and case auger used therefor | |
JPS55119822A (en) | Method for reinforcing bearing capacity of concrete pile and reinforcing member thereof | |
JPS5721623A (en) | Treatment work for top of pile | |
JPS5673722A (en) | Withdrawing work for existing hollow pile | |
JPS5513338A (en) | Caison sinking method | |
JPS55122914A (en) | Method for early improvement of soft ground | |
JPS5664028A (en) | Sheathing construction work by antecedent support framework | |
JPS55161117A (en) | Constructing method for underground continuous wall by precast concrete member | |
JPS5595711A (en) | Forming process for underground hardened matter | |
JPS5545910A (en) | Pile pulling method | |
JPS5532809A (en) | Pile foundation practice | |
JPS5664018A (en) | Concrete pile | |
JPS5766223A (en) | Deformation reduction work for landslide protection wall | |
JPS554487A (en) | Foundation pile | |
JPS57108329A (en) | Formation of basement | |
JPS6417920A (en) | Construction of precast pile with bag | |
JPS56150222A (en) | Construction of marine structure | |
JPS56424A (en) | Reinforcing of foundation for existing building with irregular sheet pile | |
JPS55161118A (en) | Pile driving method and pile | |
JPS5781525A (en) | Construction of underground continuous wall | |
JPS5616727A (en) | Submarine anchor and method of producing the same | |
JPS56163318A (en) | Settling guider for foundation pile | |
JPS51138914A (en) | Method of construction of an underground tank for liquid natural gas | |
JPS56131716A (en) | Removal of pile |