JPH0424323A - Method of building underground wall having nonuniform section - Google Patents

Method of building underground wall having nonuniform section

Info

Publication number
JPH0424323A
JPH0424323A JP12530990A JP12530990A JPH0424323A JP H0424323 A JPH0424323 A JP H0424323A JP 12530990 A JP12530990 A JP 12530990A JP 12530990 A JP12530990 A JP 12530990A JP H0424323 A JPH0424323 A JP H0424323A
Authority
JP
Japan
Prior art keywords
groove
excavation
wall
side wall
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP12530990A
Other languages
Japanese (ja)
Other versions
JP2515038B2 (en
Inventor
Shinko Sato
真弘 佐藤
Masaaki Yoshizaki
正明 吉崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2125309A priority Critical patent/JP2515038B2/en
Publication of JPH0424323A publication Critical patent/JPH0424323A/en
Application granted granted Critical
Publication of JP2515038B2 publication Critical patent/JP2515038B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To excavate a groove with a small excavating force by slightly cutting one side wall of an excavated wall at a predetermined depth, repeatedly in a suitable cycle number so as to form a wider part having a predetermined width, and then by placing concrete. CONSTITUTION:A excavater 2 such as a hydrophrase machine or the like, having a cutter drum at the front end thereof, is suspendand lowered by a crane so as to excavate a groove 1. Then, after completion of excavation of a standard section part of the groove 1, one side wall of the groove 1 is cut slightly at a predetermined depth, repeatedly, so as to form a wider part 6 having a predetermined width. Further, a preassembled reinforcement cage 7 is suspended and lowered into the groove 1, and an expandable part 70 thereof is expanded and fitted in the wider part 6 so as to arrange the reinforcement. Thereafter, raw concrete 9 is placed through tremie pipes 8 to complete the construction. Accordingly, by slightly cutting one side wall of a groove which has been excavated by only one process, the excavation can be carried out by a small excavating force.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、壁面の一部が拡幅になり剛性分布を所望に
設定できる変断面地中壁の構築方法に関する。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a method of constructing a variable cross-section underground wall in which a portion of the wall surface is widened and the stiffness distribution can be set as desired.

(従来の技術) 従来、地中連続壁においては、壁面の一部を拡幅して壁
厚を増すことが行われている。これにより、剛性の向上
あるいは地中の障害つの回避を図るものであり、そうし
たいわゆる変断面地中壁の構築方法は、例えば特開平1
−310011号などの公報に見られるようにすでに公
知となっている。
(Prior Art) Conventionally, in an underground continuous wall, a part of the wall surface is widened to increase the wall thickness. This is intended to improve rigidity or avoid underground obstacles, and such a method of constructing a so-called variable cross-section underground wall is described in, for example, Japanese Patent Application Laid-Open No.
This is already known as seen in publications such as No.-310011.

(発明が解決しようとする課題) しかしながら、拡幅部位の掘削は側壁面の掘削となるこ
とから、掘削の反力を支持するガイド部材が必要となり
、大きな剛性を得るために拡幅量を大きくすると、それ
に伴い大きな(強い)ガイド部材の設置が必要となる。
(Problems to be Solved by the Invention) However, since excavation of the widened area involves excavation of the side wall surface, a guide member is required to support the reaction force of the excavation, and if the width is increased in order to obtain large rigidity, Accordingly, it becomes necessary to install a large (strong) guide member.

掘削機の駆動力も大きなものが必要となるため、作業が
煩雑かつ大型となり、コスト高となる。
Since the excavator requires a large driving force, the work becomes complicated and large, resulting in high costs.

この発明は上記のような背景に鑑みてなされたものであ
り、ガイド部材等を要せずに小さな掘削力で拡幅部位の
掘削を行える変断面地中壁の構築方法の提供をその目的
とする。
This invention has been made in view of the above background, and its purpose is to provide a method for constructing a variable cross-section underground wall that allows excavation of a widened section with a small excavation force without the need for a guide member or the like. .

(課題を解決するための手段) 上記目的を達成するため、この発明は、壁面の一部が拡
幅になる変断面地中壁の構築に際し、まず溝の掘削を行
い、この溝の所定深度部位の側壁を浅く削ると共に、こ
れを適宜繰り返して所定幅の拡幅部位になし、その後コ
ンクリートの打設を行うことを特徴とする。
(Means for Solving the Problems) In order to achieve the above object, the present invention first excavates a trench when constructing a variable section underground wall in which a part of the wall surface is widened, and a predetermined depth of the trench is constructed. It is characterized by shallowly carving the side wall of the pipe, repeating this process as necessary to create a widened part of a predetermined width, and then pouring concrete.

(作 用) 以上のような方法によれば、溝の所定深度部位の側壁を
浅く削ることをくり返すことで拡幅部位の掘削が行なえ
る。従って、たとえ大きな掘削幅を要する場合であって
も小さな掘削力で作業が行なえる。
(Function) According to the method described above, by repeatedly cutting shallowly the side wall of the trench at a predetermined depth, the widening region can be excavated. Therefore, even if a large excavation width is required, the work can be performed with a small excavation force.

(実施例) 以下、この発明の実施例を添付図面を参照しながら説明
する。
(Embodiments) Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.

第1図〜第6図は、本発明による変断面地中壁の構築方
法の好適な一実施例における各工程を順に示す断面図で
ある。なお、第1図(A)と第1図(B)とは同一工程
を示すものの切断面が互いに90度異なる断面図である
1 to 6 are cross-sectional views sequentially showing each step in a preferred embodiment of the method for constructing a variable-section underground wall according to the present invention. Note that FIG. 1(A) and FIG. 1(B) are cross-sectional views showing the same process, but the cut planes are different from each other by 90 degrees.

壁面の一部が拡幅になる変断面地中壁の構築においては
、まず溝1の掘削を行う(第1図)。すなわち、カッタ
ードラムを先端に有するハイドロフレーズ機などの掘削
機2をクレーン3等により吊降して溝1の掘削を行うが
、このとき再開発等のため旧建物の蓋体を先行しなけれ
ばならない場合には、第7図に示すように旧建物の地下
外壁4を撤去せずに残し、その地下外壁4の内側に新た
な溝1を掘削する。これにより地下外壁4を掘削時の山
止め壁として機能させることができる。また、溝1内に
は側壁の崩壊を防止するためのポリマーなどの安定液5
を充満させる。
When constructing a variable cross-section underground wall where part of the wall surface is widened, trench 1 is first excavated (Figure 1). That is, an excavator 2 such as a hydrophrase machine having a cutter drum at the tip is suspended by a crane 3 or the like to excavate a trench 1, but at this time, the lid of the old building must be removed first for redevelopment etc. If this is not possible, as shown in FIG. 7, the underground outer wall 4 of the old building is left without being removed, and a new trench 1 is excavated inside the underground outer wall 4. This allows the underground outer wall 4 to function as a retaining wall during excavation. In addition, a stabilizing liquid 5 such as a polymer is contained in the groove 1 to prevent the side wall from collapsing.
to fill up.

溝1の標準断面部分の掘削が完了した後、その溝1の所
定深度部位の側壁を浅く削ると共に(第2図)、これを
適宜くり返して所定幅の拡幅部位6になす(第3図)。
After completing the excavation of the standard cross-section portion of the groove 1, the side wall of the groove 1 at a predetermined depth is shallowly cut (Fig. 2), and this is repeated as appropriate to form a widened portion 6 of a predetermined width (Fig. 3). .

本実施例では、掘削機2の側部から適宜に伸展される変
断面用カッター20を用いて側壁の掘削を建物外方に向
って行い、拡幅部位6を形成することにしているが、他
の掘削手段によってももちろんかまわない。
In this embodiment, the side wall is excavated toward the outside of the building using the cutter 20 for variable cross-section extended from the side of the excavator 2 as appropriate to form the widened area 6. Of course, it does not matter if the excavation method is used as well.

次に予め組立てた鉄筋能7を溝1内に吊降す(第4図)
。この鉄筋能7には溝1の拡幅部位6に係合する展開部
70が備えてあり、鉄筋能7を溝1内に挿入後、伸展ワ
イヤ71を引いて展開部70を伸展し、これを拡幅部位
6に係合させて配筋を施す(第5図)。
Next, the pre-assembled reinforcing bar 7 is suspended into the groove 1 (Fig. 4)
. This reinforcing bar 7 is provided with a developing part 70 that engages with the widened part 6 of the groove 1. After inserting the reinforcing bar 7 into the groove 1, the expanding part 70 is extended by pulling the extension wire 71, and the expanding part 70 is expanded. Reinforcement is applied by engaging the widened portion 6 (Fig. 5).

この後、溝1内の鉄筋能7にトレミ管8を挿入すると共
に、このトレミ管8から生コンクリート9を脱せしく第
6図)、施工を完了する。
Thereafter, the reinforcing pipe 8 is inserted into the reinforcing bar 7 in the groove 1, and the ready-mixed concrete 9 is removed from the reinforcing pipe 8 (Fig. 6), completing the construction.

これにより、第7図および第8図に示すような変断面地
中壁10が完成になり、図中の11は止水層である。
As a result, the variable cross-section underground wall 10 as shown in FIGS. 7 and 8 is completed, and 11 in the figure is a water stop layer.

すなわち、このような方法によれば、溝1の所定深度部
位の側壁を浅く削ることをくり返すことで拡幅部位6の
掘削が行なえる。従って、くり返し行う一回の掘削では
浅く削るので小さな掘削力でも充分であり、このように
掘削力が小さいので反力も弱く、その反力を支持するた
めのガイド部材を要しない。
That is, according to such a method, the widened portion 6 can be excavated by repeatedly cutting shallowly the side wall of the groove 1 at a predetermined depth portion. Therefore, in one repeated excavation, a small excavation force is sufficient because the excavation is performed shallowly, and since the excavation force is small, the reaction force is also weak, and no guide member is required to support the reaction force.

(発明の効果) 以上、実施例で詳細に説明したように、この発明にかか
る変断面地中壁の構築方法によれば、浅く削ることをく
り返すことで拡幅部位の掘削がなる。このため掘削の反
力を支持するためのガイド部材等を要せずに小さな掘削
力で拡幅部位の掘削を行なえる。
(Effects of the Invention) As described above in detail in the embodiments, according to the method for constructing a variable cross-section underground wall according to the present invention, the widening portion can be excavated by repeatedly cutting shallowly. Therefore, the widened area can be excavated with a small excavation force without requiring a guide member or the like to support the reaction force of excavation.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第6図は本発明の一実施例における各工程を順
に示す断面図、第7図は本発明方法により施工した変断
面地中壁を示す断面図、第8図はその斜視図である。 1・・・・・・溝 6・・・・・・拡幅部位 7・・・・・・鉄筋能 9・・・・・・コンクリート 10・・・変断面地中壁 70・・・展開部 (生フンクリ ート)
Figures 1 to 6 are cross-sectional views sequentially showing each step in an embodiment of the present invention, Figure 7 is a cross-sectional view showing a variable cross-section underground wall constructed by the method of the present invention, and Figure 8 is a perspective view thereof. It is. 1... Groove 6... Widening section 7... Reinforcement capacity 9... Concrete 10... Variable section underground wall 70... Development section ( raw funcrete)

Claims (1)

【特許請求の範囲】[Claims] 壁面の一部が拡幅になる変断面地中壁の構築に際し、ま
ず溝の掘削を行い、該溝の所定深度部位の側壁を浅く削
ると共に、これを適宜繰り返して所定幅の拡幅部位にな
し、その後コンクリートの打設を行うことを特徴とする
変断面地中壁の構築方法。
When constructing a variable cross-section underground wall where a part of the wall surface is widened, first excavate a trench, then shallowly cut the side wall at a predetermined depth part of the trench, and repeat this as appropriate to make the widened part to a predetermined width. A method for constructing a variable cross-section underground wall, which comprises subsequently placing concrete.
JP2125309A 1990-05-17 1990-05-17 Construction method of underground wall with variable cross section Expired - Lifetime JP2515038B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2125309A JP2515038B2 (en) 1990-05-17 1990-05-17 Construction method of underground wall with variable cross section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2125309A JP2515038B2 (en) 1990-05-17 1990-05-17 Construction method of underground wall with variable cross section

Publications (2)

Publication Number Publication Date
JPH0424323A true JPH0424323A (en) 1992-01-28
JP2515038B2 JP2515038B2 (en) 1996-07-10

Family

ID=14906915

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2125309A Expired - Lifetime JP2515038B2 (en) 1990-05-17 1990-05-17 Construction method of underground wall with variable cross section

Country Status (1)

Country Link
JP (1) JP2515038B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04319114A (en) * 1991-04-19 1992-11-10 Kumagai Gumi Co Ltd Construction of continuous underground wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04319114A (en) * 1991-04-19 1992-11-10 Kumagai Gumi Co Ltd Construction of continuous underground wall

Also Published As

Publication number Publication date
JP2515038B2 (en) 1996-07-10

Similar Documents

Publication Publication Date Title
CN114658007A (en) Grooving reinforcing device and grooving reinforcing method for diaphragm wall
JPH0424323A (en) Method of building underground wall having nonuniform section
JPS59228529A (en) Formation of sheathing continuous wall and rotary excavator and sheathing member therefor
JPH05339936A (en) Column strip type underground continuous wall process
JP3327454B2 (en) Underground diaphragm wall method
JPH06336725A (en) Continuous underground wall construction and excavator cage and continuous underground wall thereof
JPH0424322A (en) Method of building underground wall having nonuniform section
JPS6011179B2 (en) Construction method of underground wall
JP2551506B2 (en) Construction method of arch shell in tunnel precedent
KR200434400Y1 (en) Casing for earthquake
JPS6322916A (en) Construction of continuous underground wall in artificial islet
JP2693027B2 (en) Pile head treatment method for cast-in-place concrete pile
JP2004332368A (en) Construction method of concrete foundation
JP2988564B2 (en) Construction method of underground diaphragm wall
JP2000226982A (en) Grouting reinforcing method in tunnel excavation
JP2689743B2 (en) How to build an underground structure
JP2002206239A (en) Earth retaining wall
JPS62288214A (en) Wall type bottom-expanded piling work
JP2988565B2 (en) Construction method of underground diaphragm wall
JPH0274727A (en) Construction method of underground structure
JPS6211126B2 (en)
JPS6160922A (en) Method of enlarging pile hole diameter
JPH0266220A (en) Prevention method of damage at cross-section in concrete part of cast-in-place pile
JPS60246916A (en) Method of constructing wall type underground continuous wall using delay-cured cement
JPH01165815A (en) Construction of continuous underground wall

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080430

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090430

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100430

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100430

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110430

Year of fee payment: 15

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110430

Year of fee payment: 15