JP7080648B2 - How to erection the bridge girder - Google Patents

How to erection the bridge girder Download PDF

Info

Publication number
JP7080648B2
JP7080648B2 JP2018005215A JP2018005215A JP7080648B2 JP 7080648 B2 JP7080648 B2 JP 7080648B2 JP 2018005215 A JP2018005215 A JP 2018005215A JP 2018005215 A JP2018005215 A JP 2018005215A JP 7080648 B2 JP7080648 B2 JP 7080648B2
Authority
JP
Japan
Prior art keywords
bridge girder
erection
pca
bridge
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018005215A
Other languages
Japanese (ja)
Other versions
JP2019124051A (en
Inventor
明夫 正司
幸治 齋藤
一徳 川端
智法 中原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Oriental Shiraishi Corp
Original Assignee
Oriental Shiraishi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Oriental Shiraishi Corp filed Critical Oriental Shiraishi Corp
Priority to JP2018005215A priority Critical patent/JP7080648B2/en
Publication of JP2019124051A publication Critical patent/JP2019124051A/en
Application granted granted Critical
Publication of JP7080648B2 publication Critical patent/JP7080648B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、橋桁を橋梁の下部構造に架け渡して設置する橋桁の架設方法に関するものであり、詳しくは、橋梁の橋桁を架け替える際などに、PCa床版が仮固定された橋桁を架設するPCa床版付き橋桁の架設方法に関する。 The present invention relates to a method for erection of a bridge girder in which a bridge girder is installed over a substructure of a bridge. Regarding the method of erection of a bridge girder with a PCa deck.

従来、橋桁の架設方法において、道路や線路など下方の施設の交通規制を極力低減するために、手延機連結機構と軌条設備(水平移動機構)等を用いて橋桁を橋脚や橋台等の下部構造から送り出して架設する送り出し架設方法が知られている。 Conventionally, in the method of erection of bridge girders, in order to reduce traffic restrictions on lower facilities such as roads and railroad tracks as much as possible, the bridge girders are attached to the lower parts of piers and piers by using a hand-rolling machine connection mechanism and rail equipment (horizontal movement mechanism). A delivery erection method is known in which the structure is sent out and erected.

例えば、特許文献1には、橋桁1の架設予定地点を挟んで両側に橋脚7・8を立設し、橋桁1を送り出す側の橋脚7より後方に間隔をあけ固定ベントを立設し、固定ベント上に跨って送り出し設備13を設置し、送り出し設備13上で橋桁を後方へ順次直列に連結するとともに、先頭の橋桁1Aの先端上部に手延べ機5の基端部を連結して前方へ張り出させる一方、反対側の橋脚8より後方に間隔をあけて固定ベントを立設し、それらの固定ベント上に跨って橋桁9を後方へ直列に連結して設置し、送り出し設備13上の橋桁を台車を介して前方へ送り出して架設する桁の送り出し架設方法が開示されている(特許文献1の特許請求の範囲の請求項1、明細書の段落[0016]~[0021]、図面の図1等参照)。 For example, in Patent Document 1, bridge piers 7 and 8 are erected on both sides of the planned erection point of the bridge girder 1, and fixed vents are erected and fixed behind the pier 7 on the side where the bridge girder 1 is sent out. A delivery facility 13 is installed over the vent, and the bridge girders are sequentially connected in series backward on the delivery facility 13, and the base end portion of the hand-rolling machine 5 is connected to the upper tip of the leading bridge girder 1A to move forward. On the other hand, fixed vents are erected at intervals behind the pier 8 on the opposite side, and the bridge girders 9 are connected in series to the rear over those fixed vents and installed on the delivery facility 13. Disclosed is a method of sending out and erection of a girder by sending out a bridge girder forward via a trolley (claim 1, claims of claims 1, paragraphs [0016] to [0021] of the specification, in the drawing. See Fig. 1 etc.).

しかし、特許文献1に記載の従来の桁の送り出し架設方法では、橋桁の架設終了後に、コンクリート床版の設置や、壁高欄の設置などを行う後作業が残っていた。このため、これらの後作業が完了するまで、新設の際には開通までの期間や、架け替えの際には通行止めのトータル的な期間が長くなるという問題があった。 However, in the conventional girder sending-out erection method described in Patent Document 1, after the erection of the bridge girder is completed, the work after installing the concrete deck and the wall balustrade remains. For this reason, there is a problem that the period until the opening of the new building and the total period of the road closure at the time of replacement become long until these post-work are completed.

また、特許文献2には、橋桁2上に仮設したレール1上を走行する車輪付き運搬台車12と、その前進方向にスライドするスライド梁11を用いて、床版4をスライド梁11で吊り下げた状態で、スライド梁11を運搬台車1でレール1上を走行させて所定位置の橋桁2上に床版4を架設する橋梁床版の架設方法が開示されている(特許文献2の特許請求の範囲の請求項1、明細書の段落[0027]~[0039]、図面の図1等参照)。 Further, in Patent Document 2, the deck 4 is suspended by the slide beam 11 by using the carrier with wheels 12 running on the rail 1 temporarily provided on the bridge girder 2 and the slide beam 11 sliding in the forward direction thereof. Disclosed is a method of erection of a bridge deck in which a slide beam 11 is driven on a rail 1 by a carrier 1 and a deck 4 is erected on a bridge girder 2 at a predetermined position in this state (Patent Request of Patent Document 2). 1. Of the scope of the above, paragraphs [0027] to [0039] of the specification, FIG. 1 of the drawing, etc.).

しかし、特許文献2に記載の橋梁床版の架設方法は、床版の架設方法であり、橋桁を架け渡したり、取り替えたりする場合に適用できるものではなかった。このため、橋桁の架設工事や取替工事に伴う前述の後作業を含めてトータル的な交通規制期間の短縮を達成するという問題は解決できていなかった。 However, the method of erection of the bridge deck described in Patent Document 2 is a method of erection of the deck, and cannot be applied when the bridge girder is bridged or replaced. For this reason, the problem of shortening the total traffic regulation period, including the above-mentioned post-work associated with bridge girder erection work and replacement work, could not be solved.

特開2006-28733号公報Japanese Unexamined Patent Publication No. 2006-28833 特開2015-169029号公報JP-A-2015-169029

そこで、本発明は、前述した問題に鑑みて案出されたものであり、その目的とするところは、交通規制を伴う桁架設後の後作業の作業時間を短縮することができる橋桁の架設方法を提供することにある。 Therefore, the present invention has been devised in view of the above-mentioned problems, and an object thereof is a method for erection of a bridge girder that can shorten the work time of post-work after erection of a girder accompanied by traffic regulation. Is to provide.

請求項1に係る橋桁の架設方法は、橋桁を橋梁の下部構造から送り出して架設する橋桁の架設方法であって、送り出す橋桁を地組する橋桁地組工程を行い、当該橋桁地組工程では、地組した橋桁上にPCa床版を非合成状態で仮固定することを特徴とする。 The bridge girder erection method according to claim 1 is a bridge girder erection method in which the bridge girder is sent out from the substructure of the bridge and erected. The feature is that the PCa deck is temporarily fixed on the bridge girder that has been grounded in a non-synthetic state.

請求項2に係る橋桁の架設方法は、請求項1に記載の橋桁の架設方法において、橋桁地組工程では、仮固定した前記PCa床版にPCa壁高欄をさらに仮固定することを特徴とする。 The method for erection of a bridge girder according to claim 2 is characterized in that, in the method for erection of a bridge girder according to claim 1, in the bridge girder ground assembly process, a PCa wall balustrade is further temporarily fixed to the temporarily fixed PCa deck. ..

請求項に係る橋桁の架設方法は、請求項1又は2に記載の橋桁の架設方法において、前記PCa床版の仮固定は、上部にねじ溝が切削加工されたねじ付きスタッドに高ナットを介してボルトを延長し、このボルトに螺合するナットで鋼製プレートを緊結することにより仮固定していることを特徴とする。 The method for erection of the bridge girder according to claim 3 is the method for erection of the bridge girder according to claim 1 or 2 . The bolt is extended through the bolt, and the steel plate is temporarily fixed by tightening the steel plate with a nut screwed to the bolt.

請求項に係る橋桁の架設方法は、請求項に記載の橋桁の架設方法において、前記PCa床版と前記橋桁を接合する経時硬化材を打設する前に、前記ボルトを取り外すことによって高ナットの被り厚さを確保することを特徴とする。 The method for erection of the bridge girder according to claim 4 is the method for erection of the bridge girder according to claim 3 , wherein the bolt is removed before placing the time-curing material for joining the PCa deck and the bridge girder. It is characterized by ensuring the covering thickness of the nut.

請求項に係る橋桁の架設方法は、請求項2に記載の橋桁の架設方法において、前記PCa壁高欄の仮固定では、前記PCa床版の外側へ前記PCa壁高欄が転倒しないように止め付ける転倒防止材を設置することを特徴とする。 The method for erection of the bridge girder according to claim 5 is the method for erection of the bridge girder according to claim 2, in which the PCa wall column is temporarily fixed to the outside of the PCa deck so that the PCa wall column does not fall. It is characterized by installing a fall prevention material.

請求項1~に係る発明によれば、コンクリート床版の設置や壁高欄の設置などを行う橋桁設置後の後作業において、揚重機で各床版を吊り上げて何度も旋回するなどの時間のかかる作業を他の作業と同時並行で行うことができる。このため、交通規制を伴う作業の作業時間を短縮することができる。 According to the inventions according to claims 1 to 5 , in the post-work after the bridge girder installation such as the installation of concrete decks and the installation of wall balustrades, the time required to lift each deck with a lifting machine and turn it many times. This work can be done in parallel with other work. Therefore, it is possible to shorten the work time of the work involving traffic regulation.

特に、請求項2に係る発明によれば、揚重機で各壁高欄を吊り上げて何度も旋回するなどの時間のかかる作業を他の作業と同時並行で行うことができる。このため、交通規制を伴う作業の作業時間をさらに短縮することができる。 In particular, according to the second aspect of the present invention, it is possible to perform time-consuming work such as lifting each wall balustrade with a lifting machine and turning it many times in parallel with other work. Therefore, the work time of the work involving traffic regulation can be further shortened.

特に、請求項に係る発明によれば、PCa床版の仮固定が、容易且つ確実に行うことができる。このため、作業時間が短縮されるだけでなく、橋桁の架設作業を安全に行うことができる。 In particular, according to the invention of claim 3 , temporary fixing of the PCa deck can be easily and surely performed. Therefore, not only the work time is shortened, but also the bridge girder erection work can be performed safely.

特に、請求項に係る発明によれば、仮固定を解除して経時硬化材を打設する作業が容易に短時間で行うことができる。また、必要な被り厚さを確実に確保することができる。 In particular, according to the invention of claim 4 , the work of releasing the temporary fixing and placing the time-curing material can be easily performed in a short time. In addition, the required cover thickness can be reliably secured.

特に、請求項に係る発明によれば、転倒防止材によりPCa壁高欄がPCa床版の外側へ転倒するおそれを完全に払拭することができ、極めて安全である。 In particular, according to the invention of claim 5 , the fall prevention material can completely eliminate the possibility that the PCa wall balustrade will fall to the outside of the PCa deck, which is extremely safe.

本発明の実施形態に係る橋桁の架設方法の第1ステップを示す工程説明図である。It is a process explanatory drawing which shows the 1st step of the bridge girder erection method which concerns on embodiment of this invention. 新設の橋桁を示す側面図である。It is a side view which shows the new bridge girder. 同上の新設の橋桁上に仮固定されたPCa床版とPCa壁高欄の接合部分を示す部分拡大図である。It is a partial enlarged view which shows the joint part of the PCa floor slab and the PCa wall balustrade temporarily fixed on the newly constructed bridge girder of the same above. 同上の新設の橋桁上に仮固定されたPCa床版とPCa壁高欄を示す平面図である。It is a plan view which shows the PCa floor slab and the PCa wall balustrade temporarily fixed on the newly constructed bridge girder of the same above. 図4の橋軸直角方向に沿ったA-A線断面図である。4 is a cross-sectional view taken along the line AA along the direction perpendicular to the bridge axis of FIG. 図4の橋軸方向に沿ったB-B線断面図である。It is a cross-sectional view taken along the line BB along the bridge axis direction of FIG. 本発明の実施形態に係る橋桁の架設方法の第2ステップを示す工程説明図である。It is a process explanatory drawing which shows the 2nd step of the bridge girder erection method which concerns on embodiment of this invention. 同上の橋桁の架設方法の第3ステップを示す工程説明図である。It is a process explanatory drawing which shows the 3rd step of the erection method of the bridge girder of the same above. 同上の橋桁の架設方法の第4ステップを示す工程説明図である。It is a process explanatory diagram which shows the 4th step of the erection method of the bridge girder of the same above. 同上の橋桁の架設方法の第5ステップを示す工程説明図である。It is a process explanatory drawing which shows the 5th step of the erection method of the bridge girder of the same above. 同上の橋桁の架設方法の第6ステップを示す工程説明図である。It is a process explanatory drawing which shows the 6th step of the erection method of the bridge girder of the same above. 同上の橋桁の架設方法の第7ステップを示す工程説明図である。It is a process explanatory drawing which shows the 7th step of the erection method of the bridge girder of the same above. 同上の橋桁の架設方法の第8ステップを示す工程説明図である。It is a process explanatory drawing which shows the 8th step of the erection method of the bridge girder of the same above. 図6の高ナットをねじ付きスタッドにねじ込んで下降させる工程を示す工程説明図である。It is a process explanatory view which shows the process of screwing a high nut of FIG. 6 into a threaded stud and lowering it.

以下、本発明に係る橋桁の架設方法を実施するための一実施形態について、図面を参照しながら詳細に説明する。 Hereinafter, an embodiment for implementing the bridge girder erection method according to the present invention will be described in detail with reference to the drawings.

図1~図14を用いて、本発明の実施形態に係る橋桁の架設方法について説明する。第1下部構造K1~第4下部構造K4の3径間(3支間)に架け渡された鋼桁の橋を床版及び高欄も橋桁ごと一緒に架け替えて新しい橋桁を架設する場合を例示して説明する。図1は、本発明の実施形態に係る橋桁の架設方法の第1ステップを示す工程説明図である。 A method of erection of a bridge girder according to an embodiment of the present invention will be described with reference to FIGS. 1 to 14. An example is an example in which a steel girder bridge spanning three spans (three spans) of the first substructure K1 to the fourth substructure K4 is replaced together with the deck and the balustrade together with the bridge girder to construct a new bridge girder. I will explain. FIG. 1 is a process explanatory view showing a first step of a bridge girder erection method according to an embodiment of the present invention.

<第1ステップ>
(第1径間既設桁撤去工程)
先ず、本実施形態に係る橋桁の架設方法では、図1に示すように、第1ステップとして、第1径間D1に架け渡された既設の橋桁EGを撤去する第1径間既設桁撤去工程を行う。
<First step>
(Process for removing the existing girder of the first span)
First, in the bridge girder erection method according to the present embodiment, as shown in FIG. 1, as a first step, the first span existing girder removal step of removing the existing bridge girder EG bridged over the first span D1. I do.

具体的には、第1下部構造(橋台)K1と第2下部構造(橋脚)K2との間に架け渡された既設の橋桁EGを揚重機である移動式の油圧クレーンCLで吊り上げて、搬出車であるトレーラーTL等を用いて搬出撤去する。撤去作業の時間を短縮するためには、例えば、大型クレーンである300t級の自走式の油圧クレーンCL(オールテレーンクレーン)を用いて、第1径間D1に架け渡された既設の橋桁EG全体を一括して吊上げ撤去することが好ましい。 Specifically, the existing bridge girder EG bridged between the first substructure (abutment) K1 and the second substructure (pier) K2 is lifted by a mobile hydraulic crane CL, which is a lifting machine, and carried out. Carry out and remove using a trailer TL or the like that is a car. In order to shorten the time for removal work, for example, a 300t class self-propelled hydraulic crane CL (all terrain crane), which is a large crane, is used to cover the entire existing bridge girder EG spanned over the first span D1. It is preferable to lift and remove all at once.

(送出し設備組立工程)
また、本実施形態に係る橋桁の架設方法では、第1ステップとして、第1径間既設桁撤去工程と同時並行で、送出し設備SMを組み立てる送出し設備組立工程を行う。
(Sending equipment assembly process)
Further, in the bridge girder erection method according to the present embodiment, as the first step, a delivery equipment assembly process for assembling the transmission equipment SM is performed in parallel with the first span existing girder removal step.

具体的には、仮設の軌条桁TGを設置し、この軌条桁TGに新設の橋桁1を送り出す際のレールとなる軌条設備(図示せず)を組み立てる。そして、この軌条設備上を新設の橋桁1がスライド自在となるように、台車設備DCや送出し装置SDを設置する。なお、軌条桁TG、台車設備DC、送出し装置SD、軌条設備等の前述の送り出し架設方法において新設の橋桁1を送り出す設備を総称して送出し設備SMと指称している。 Specifically, a temporary rail girder TG is installed, and rail equipment (not shown) that serves as a rail for sending out the new bridge girder 1 to this rail girder TG is assembled. Then, a bogie equipment DC and a delivery device SD are installed so that the newly installed bridge girder 1 can slide freely on this rail equipment. The equipment that sends out the newly installed bridge girder 1 in the above-mentioned delivery erection method such as the rail girder TG, the bogie equipment DC, the delivery device SD, and the rail equipment is collectively referred to as the transmission equipment SM.

(第1回橋桁地組工程)
そして、本実施形態に係る橋桁の架設方法の第1ステップでは、送出し設備組立工程で組み立てた送出し設備SMの上に、送り出す新設の橋桁1を地組する第1回橋桁地組工程を行う。
(1st bridge girder ground assembly process)
Then, in the first step of the bridge girder erection method according to the present embodiment, the first bridge girder ground assembly process in which the new bridge girder 1 to be sent is grounded on the delivery equipment SM assembled in the delivery equipment assembly process is performed. conduct.

図2は、新設の橋桁1を示す側面図であり、図3は、その新設の橋桁1上に仮固定されたPCa床版2とPCa壁高欄3の接合部分を示す部分拡大図である。また、図4は、PCa床版2とPCa壁高欄3を示す平面図である。図5は、図4の橋軸直角方向に沿ったA-A線断面図、図6は、図4の橋軸方向に沿ったB-B線断面図である。 FIG. 2 is a side view showing the newly installed bridge girder 1, and FIG. 3 is a partially enlarged view showing a joint portion between the PCa floor slab 2 temporarily fixed on the newly installed bridge girder 1 and the PCa wall railing column 3. Further, FIG. 4 is a plan view showing the PCa floor slab 2 and the PCa wall height column 3. 5 is a cross-sectional view taken along the line AA along the direction perpendicular to the bridge axis of FIG. 4, and FIG. 6 is a cross-sectional view taken along the line BB along the direction of the bridge axis of FIG.

図2、図3に示すように、この第1回橋桁地組工程では、地組した新設の橋桁1上にPCa床版2とPCa壁高欄3を仮固定する。ここで、仮固定とは、PCa床版2と新設の橋桁1とを合成するコッター部分やPCa床版2同士を接合する間詰部にモルタルやグラウトなどの経時硬化材を打設して一体化せずに、経時硬化材未施工の非合成状態で固定することを指している。 As shown in FIGS. 2 and 3, in this first bridge girder groundworking process, the PCa deck 2 and the PCa wall railing 3 are temporarily fixed on the newly constructed bridge girder 1. Here, temporary fixing is integrated by placing a time-curing material such as mortar or grout in the cotter part that synthesizes the PCa floor slab 2 and the newly installed bridge girder 1 and the intercalation part that joins the PCa floor slabs 2 to each other. It refers to fixing in a non-synthetic state where the aged hardening material has not been applied, without turning it into a material.

なお、PCa床版2は、予め工場等で打設されて硬化して既に所望の強度が発現したプレキャスト鉄筋コンクリート製の床版であり、図示しないPC鋼材が埋設されてプレテンション方式でプレストレスが付与されたPC床版(プレストレストコンクリート床版)である。PCa壁高欄3も、同様に、所望の強度が発現したプレキャスト鉄筋コンクリート製の壁高欄である。 The PCa floor slab 2 is a precast reinforced concrete floor slab that has already been cast in a factory or the like and hardened to already exhibit the desired strength. It is a given PC floor slab (prestressed concrete floor slab). Similarly, the PCa wall balustrade 3 is a wall balustrade made of precast reinforced concrete that exhibits desired strength.

そして、本実施形態に係るPCa床版2は、図3に示すように、PCa床版2,2間の間詰部に突出する継手鉄筋2aが配筋され、この間詰部に所定時間経過後に硬化する経時硬化材である接合モルタルが打設されて硬化することで一体化させるタイプのPCa床版である。この継手鉄筋2aの先端には、円筒状の鋼材2bがカシメ止められている。 Then, in the PCa floor slab 2 according to the present embodiment, as shown in FIG. 3, joint reinforcing bars 2a protruding from the interstitial portion between the PCa floor slabs 2 and 2 are arranged, and after a predetermined time elapses in the interstitial portion. It is a type of PCa floor slab in which a bonded mortar, which is a time-curing material that cures, is cast and cured to integrate it. A cylindrical steel material 2b is crimped to the tip of the joint reinforcing bar 2a.

第1回橋桁地組工程では、図4、図5に示すように、鋼桁からなる複数条(図示形態では4条)の新設の橋桁1を1径間に架け渡すのに必要な本数、橋軸方向Xに沿ってボルト接合して組み立てる。なお、図2に示すように、新設の橋桁1の送出し方向先端には、先端を軽量化するとともに、仮受TKからの反力を得るために手延機連結構TMが取り付けられる。 In the first bridge girder groundwork process, as shown in FIGS. 4 and 5, the number of new bridge girders 1 made of steel girders (4 in the figure) required to bridge one span. Assemble by bolting along the bridge axis direction X. As shown in FIG. 2, a hand-rolling machine connection structure TM is attached to the tip of the newly installed bridge girder 1 in the delivery direction in order to reduce the weight of the tip and obtain a reaction force from the temporary receiving TK.

本工程におけるPCa床版2の新設の橋桁1への仮固定は、図4に示すように、PCa床版2に形成された桁との合成用の8個のコッター21~28のうち半数を用いて行う。橋軸方向Xにおいても、橋軸直角方向Yにおいても、PCa床版2のいずれか一方のコッター及び床版端部が拘束されていないフリーの状態とすることにより、後述の送出しの際に、PCa床版2に曲げ応力やせん断応力が伝達されないようにするためである。 As shown in FIG. 4, the temporary fixing of the PCa deck 2 to the newly installed bridge girder 1 in this process uses half of the eight cotters 21 to 28 for synthesizing with the girder formed on the PCa deck 2. Do using. In both the bridge axis direction X and the bridge axis perpendicular direction Y, the cotter of either one of the PCa deck 2 and the end of the deck are set to a free state in which they are not constrained, so that they can be sent out later. This is to prevent bending stress and shear stress from being transmitted to the PCa deck 2.

図4に示すように、図示形態では、コッター21,24,26,27において、新設の橋桁1にPCa床版2を仮固定している。図5は、仮固定している部分を表すため、コッター22,23を透視してコッター26,27部分を破線で表している。 As shown in FIG. 4, in the illustrated embodiment, the PCa deck 2 is temporarily fixed to the newly installed bridge girder 1 in the cotters 21, 24, 26, 27. In FIG. 5, in order to show the temporarily fixed portion, the cotters 22 and 23 are seen through and the cotters 26 and 27 portions are represented by broken lines.

なお、コッター21とコッター26、コッター27とコッター24というように互い違いに固定するのは、PCa床版2が新設の橋桁1のフランジ上を水平方向にズレることを防止するためである。 The cotter 21 and the cotter 26, and the cotter 27 and the cotter 24 are fixed alternately in order to prevent the PCa deck 2 from shifting horizontally on the flange of the newly installed bridge girder 1.

通常、合成用のコッター21~28には、2本の頭付スタッド10が新設の橋桁1の上フランジ上に溶植されて接合される。しかし、図4~図6に示すように、PCa床版2を新設の橋桁1へ仮固定するために、本工程では、2本の頭付スタッド10の他、上部にねじ溝が切削加工されたねじ付きスタッド11を溶植する。そして、高ナット12を介してねじ付きスタッド11の上方に全ネジボルト13を延長し、この全ネジボルト13に螺合するナット14でコッター21,24,26,27の上面に架け渡した矩形の鋼製プレート15を緊結してPCa床版2を新設の橋桁1へ仮固定する。 Usually, two headed studs 10 are welded and joined to the cotters 21 to 28 for synthesis on the upper flange of the newly installed bridge girder 1. However, as shown in FIGS. 4 to 6, in order to temporarily fix the PCa deck 2 to the newly installed bridge girder 1, in this step, in addition to the two headed studs 10, a thread groove is machined on the upper part. The stud 11 with a screw is welded. Then, the all-screw bolt 13 is extended above the threaded stud 11 via the high nut 12, and the rectangular steel spanned over the upper surface of the cotter 21, 24, 26, 27 with the nut 14 screwed into the all-screw bolt 13. The steel plate 15 is tightly tied and the PCa deck 2 is temporarily fixed to the new bridge girder 1.

その上、本橋桁地組工程では、図4、図5に示すように、PCa床版2の地覆部2c上にPCa壁高欄3を仮固定する。PCa壁高欄3のPCa床版2への仮固定は、PCa壁高欄3の底面に開口する固定孔30へ地覆部2cに立設された鋼棒31を嵌め込む。そして、転倒防止材としてPCa床版2とPCa壁高欄3にアンカー止めされた鋼製ワイヤ32で地覆部2cの外側へPCa壁高欄3が転倒しないように止め付ける。 Further, in the main bridge girder ground assembly process, as shown in FIGS. 4 and 5, the PCa wall railing column 3 is temporarily fixed on the ground covering portion 2c of the PCa deck 2. For temporary fixing of the PCa wall balustrade 3 to the PCa floor slab 2, a steel rod 31 erected in the ground covering portion 2c is fitted into a fixing hole 30 opened at the bottom surface of the PCa wall balustrade 3. Then, as a fall prevention material, the PCa floor slab 2 and the steel wire 32 anchored to the PCa wall balustrade 3 are fastened to the outside of the ground covering portion 2c so that the PCa wall balustrade 3 does not fall.

なお、鋼棒31の両端には、円筒状の鋼材33がカシメ止められている。また、PCa壁高欄3の固定孔30の周囲及び地覆部2cの鋼棒31の周囲には、スパイラル筋34が配筋されている。鋼棒31へ作用する曲げモーメントにより、周辺のコンクリートに働く割裂引張応力へ対抗するためである。 Cylindrical steel materials 33 are crimped to both ends of the steel rod 31. Further, spiral bars 34 are arranged around the fixing hole 30 of the PCa wall balustrade 3 and around the steel rod 31 of the ground covering portion 2c. This is because the bending moment acting on the steel rod 31 counteracts the split tensile stress acting on the surrounding concrete.

<第2ステップ>
図7は、本発明の実施形態に係る橋桁の架設方法の第2ステップを示す工程説明図である。
<Second step>
FIG. 7 is a process explanatory view showing a second step of the bridge girder erection method according to the embodiment of the present invention.

(第2径間既設桁撤去工程)
次に、本実施形態に係る橋桁の架設方法では、図7に示すように、第2ステップとして、第2径間D2に架け渡された既設の橋桁EGを撤去する第2径間既設桁撤去工程を行う。具体的な撤去方法は、前述の第1径間既設桁撤去工程と同様である。
(Process for removing the existing girder of the second span)
Next, in the bridge girder erection method according to the present embodiment, as shown in FIG. 7, as a second step, the existing bridge girder EG bridged over the second span D2 is removed. Perform the process. The specific removal method is the same as the above-mentioned step of removing the existing girder of the first span.

(下降設備及び仮受組立工程)
また、本実施形態に係る橋桁の架設方法では、第2ステップとして、第2径間既設桁撤去工程と同時並行で、新設の橋桁1を下降させる下降設備DM及び仮受TKを組み立てる下降設備及び仮受組立工程を行う。
(Descent equipment and temporary receiving assembly process)
Further, in the method of erection of the bridge girder according to the present embodiment, as the second step, the lowering equipment DM for lowering the newly installed bridge girder 1 and the lowering equipment for assembling the temporary receiving TK and the lowering equipment for assembling the temporary receiving TK in parallel with the step of removing the existing girder of the second span. Perform the temporary receiving assembly process.

具体的には、第1下部構造K1である橋台の上に下降設備DMを組み立てるとともに、第2下部構造K2である橋脚の上に手延機連結構TMを支持する仮受TKを組み立てる。 Specifically, the descending equipment DM is assembled on the abutment which is the first substructure K1, and the temporary receiving TK which supports the hand-rolling machine connecting structure TM is assembled on the pier which is the second substructure K2.

(第1回送出し工程)
そして、送出し設備SMを用いて、第1回橋桁地組工程で組み立てた新設の橋桁1を第2下部構造K2へ向け第1径間D1へゆっくりと送り出す。このとき、軌条桁TG上を台車設備DCを用いて新設の橋桁1をスライド移動させて行き、第2下部構造K2上に組み立てた仮受TKに手延機連結構TMが到達するまで送り出す。
(1st sending process)
Then, using the delivery equipment SM, the newly installed bridge girder 1 assembled in the first bridge girder ground assembly process is slowly sent out to the first span D1 toward the second substructure K2. At this time, the newly installed bridge girder 1 is slid and moved on the rail girder TG using the bogie equipment DC, and is sent out until the hand-rolling machine connection structure TM reaches the temporary receiving TK assembled on the second substructure K2.

<第3ステップ>
図8は、本発明の実施形態に係る橋桁の架設方法の第3ステップを示す工程説明図である。
<Third step>
FIG. 8 is a process explanatory view showing a third step of the bridge girder erection method according to the embodiment of the present invention.

本発明の実施形態に係る橋桁の架設方法の第3ステップでは、送出し設備SMの上において、新設の橋桁1の1径間分の橋桁を増設する第2回橋桁地組工程を行う。前述の第1回橋桁地組工程と同様に、新たに増設した新設の橋桁1上にPCa床版2とPCa壁高欄3を仮固定する。 In the third step of the method of erection of the bridge girder according to the embodiment of the present invention, the second bridge girder groundwork step of adding the bridge girder for one span of the newly installed bridge girder 1 is performed on the delivery equipment SM. Similar to the first bridge girder ground assembly process described above, the PCa deck 2 and the PCa wall railing 3 are temporarily fixed on the newly added bridge girder 1.

<第4ステップ>
図9は、本発明の実施形態に係る橋桁の架設方法の第4ステップを示す工程説明図である。
<4th step>
FIG. 9 is a process explanatory view showing the fourth step of the method of erection of the bridge girder according to the embodiment of the present invention.

(第3径間既設桁撤去工程)
次に、本実施形態に係る橋桁の架設方法では、図9に示すように、第4ステップとして、第3径間D3に架け渡された既設の橋桁EGを撤去する第3径間既設桁撤去工程を行う。具体的な撤去方法は、前述の第2径間既設桁撤去工程と同様である。
(Process for removing the existing girder of the 3rd span)
Next, in the bridge girder erection method according to the present embodiment, as shown in FIG. 9, as a fourth step, the existing bridge girder EG bridged over the third span D3 is removed. Perform the process. The specific removal method is the same as the above-mentioned second span existing girder removal step.

(下降設備及び仮受組立工程)
また、本実施形態に係る橋桁の架設方法では、第4ステップとして、第3径間既設桁撤去工程と同時並行で、新設の橋桁1を下降させる下降設備DM及び仮受TKを組み立てる下降設備及び仮受組立工程を行う。
(Descent equipment and temporary receiving assembly process)
Further, in the method of erection of the bridge girder according to the present embodiment, as the fourth step, the lowering equipment DM for lowering the newly installed bridge girder 1 and the lowering equipment for assembling the temporary receiving TK and the lowering equipment for assembling the temporary receiving TK in parallel with the step of removing the existing girder of the third span. Perform the temporary receiving assembly process.

具体的には、第2下部構造K2である橋脚の上に下降設備DMを組み立てるとともに、第3下部構造K3である橋脚の上に手延機連結構TMを支持する仮受TKを組み立てる。 Specifically, the descending equipment DM is assembled on the pier which is the second substructure K2, and the temporary receiving TK which supports the hand-rolling machine connection structure TM is assembled on the pier which is the third substructure K3.

(第2回送出し工程)
そして、送出し設備SMを用いて、第2回橋桁地組工程で組み立てた新設の橋桁1を第3下部構造K3へ向け第2径間D2へゆっくりと送り出す。このとき、軌条桁TG上を台車設備DCを用いて新設の橋桁1をスライド移動させて行き、第3下部構造K3上に組み立てた仮受TKに手延機連結構TMが到達するまで送り出す。
(2nd sending process)
Then, using the delivery equipment SM, the newly installed bridge girder 1 assembled in the second bridge girder ground assembly process is slowly sent out to the second span D2 toward the third substructure K3. At this time, the newly installed bridge girder 1 is slid and moved on the rail girder TG using the bogie equipment DC, and is sent out until the hand-rolling machine connection structure TM reaches the temporary receiving TK assembled on the third substructure K3.

<第5ステップ>
図10は、本発明の実施形態に係る橋桁の架設方法の第5ステップを示す工程説明図である。
<Fifth step>
FIG. 10 is a process explanatory view showing a fifth step of the bridge girder erection method according to the embodiment of the present invention.

本発明の実施形態に係る橋桁の架設方法の第5ステップでは、送出し設備SMの上において、新設の橋桁1の1径間分の橋桁を増設する第3回橋桁地組工程を行う。前述の第1回、第2回橋桁地組工程と同様に、新たに増設した新設の橋桁1上にPCa床版2とPCa壁高欄3を仮固定する。 In the fifth step of the method of erection of the bridge girder according to the embodiment of the present invention, the third bridge girder groundwork step of adding the bridge girder for one span of the newly installed bridge girder 1 is performed on the delivery equipment SM. The PCa floor slab 2 and the PCa wall balustrade 3 are temporarily fixed on the newly added bridge girder 1 in the same manner as in the first and second bridge girder ground assembly processes described above.

<第6ステップ>
図11は、本発明の実施形態に係る橋桁の架設方法の第6ステップを示す工程説明図である。
<6th step>
FIG. 11 is a process explanatory view showing the sixth step of the method of erection of the bridge girder according to the embodiment of the present invention.

(下降設備及び仮受組立工程)
本実施形態に係る橋桁の架設方法では、第6ステップとして、第3径間において、新設の橋桁1を下降させる下降設備DM及び仮受TKを組み立てる下降設備及び仮受組立工程を行う。
(Descent equipment and temporary receiving assembly process)
In the method of erection of the bridge girder according to the present embodiment, as the sixth step, the lowering equipment DM for lowering the newly installed bridge girder 1 and the lowering equipment for assembling the temporary receiving TK and the temporary receiving assembling process are performed in the third span.

具体的には、第3下部構造K3である橋脚の上に下降設備DMを組み立てるとともに、第4下部構造K4である橋台の上に下降設備DMを組み立てる。 Specifically, the descending equipment DM is assembled on the pier which is the third substructure K3, and the descending equipment DM is assembled on the abutment which is the fourth substructure K4.

(第3回送出し工程)
そして、送出し設備SMを用いて、第3回橋桁地組工程で組み立てた新設の橋桁1を第4下部構造K4へ向け第3径間D3へゆっくりと送り出す。このとき、軌条桁TG上を台車設備DCを用いて新設の橋桁1をスライド移動させて行き、第4下部構造K4上に組み立てた下降設備DMに新設の橋桁1の先端が到達するまで送り出す。
(3rd delivery process)
Then, using the delivery equipment SM, the newly installed bridge girder 1 assembled in the third bridge girder ground assembly process is slowly sent out to the third span D3 toward the fourth substructure K4. At this time, the newly installed bridge girder 1 is slid and moved on the rail girder TG using the bogie equipment DC, and is sent out until the tip of the new bridge girder 1 reaches the descending equipment DM assembled on the fourth substructure K4.

<第7ステップ>
図12は、本発明の実施形態に係る橋桁の架設方法の第7ステップを示す工程説明図である。
<7th step>
FIG. 12 is a process explanatory view showing the seventh step of the method of erection of the bridge girder according to the embodiment of the present invention.

本実施形態に係る橋桁の架設方法では、第7ステップとして、図12に示すように、架設用仮設設備を解体する仮設設備解体工程を行う。 In the method of erection of the bridge girder according to the present embodiment, as a seventh step, as shown in FIG. 12, a temporary equipment dismantling step of dismantling the temporary equipment for erection is performed.

具体的には、移動式の油圧クレーンCLを用いて、新設の橋桁1の先端に取り付けた手延機連結構TMを解体撤去するとともに、別の油圧クレーンCLを用いて、送出し設備SMを解体撤去する。 Specifically, a mobile hydraulic crane CL is used to dismantle and remove the hand-rolling machine connection structure TM attached to the tip of the newly installed bridge girder 1, and another hydraulic crane CL is used to dismantle the delivery equipment SM. Dismantle and remove.

<第8ステップ>
図13は、本発明の実施形態に係る橋桁の架設方法の第8ステップを示す工程説明図である。
<8th step>
FIG. 13 is a process explanatory view showing the eighth step of the bridge girder erection method according to the embodiment of the present invention.

(橋桁下降工程)
本実施形態に係る橋桁の架設方法では、第8ステップとして、図13に示すように、下降設備DMを用いて、新設の橋桁1を下降させて所定の高さへ据え付ける橋桁下降工程を行う。
(Bridge girder descent process)
In the method of erection of the bridge girder according to the present embodiment, as the eighth step, as shown in FIG. 13, a bridge girder lowering step of lowering the newly installed bridge girder 1 and installing it at a predetermined height is performed by using the lowering equipment DM.

図14は、図6の高ナットをねじ付きスタッドにねじ込んで下降させる工程を示す工程説明図である。図14に示すように、橋桁下降工程後に、全ネジボルト13を高ナット12から取り外して、仮固定を解除する。そして、所定の被り厚さが確保できるまで高ナット12をねじ付きスタッド11にねじ込んで下降させる。その後、各コッターに経時硬化材である接合モルタルを打設してPCa床版2と新設の橋桁1とを一体化させる。 FIG. 14 is a process explanatory view showing a process of screwing the high nut of FIG. 6 into the threaded stud and lowering the nut. As shown in FIG. 14, after the bridge girder lowering step, all the screw bolts 13 are removed from the high nut 12 to release the temporary fixing. Then, the high nut 12 is screwed into the threaded stud 11 and lowered until a predetermined cover thickness can be secured. After that, a bonded mortar, which is a time-curing material, is placed in each cotter to integrate the PCa deck 2 and the newly installed bridge girder 1.

なお、必要数の頭付スタッド10に加えて、ねじ付きスタッド11を溶植する場合を例示して説明したが、ねじ付きスタッド11に高ナット12が螺着されていることで、頭付スタッド10と同様の合成効果が期待できる。このため、必要数の頭付スタッド10の1本をねじ付きスタッド11に代替することで、スタッドの本数を増やすことなくPCa床版2の仮固定を実現することができる。 In addition to the required number of headed studs 10, the case where the threaded studs 11 are welded has been described as an example. However, since the high nut 12 is screwed to the threaded studs 11, the headed studs 11 are screwed together. The same synthetic effect as 10 can be expected. Therefore, by substituting one of the required number of headed studs 10 with the screwed stud 11, it is possible to temporarily fix the PCa deck 2 without increasing the number of studs.

その他、伸縮装置等を取り付け、本実施形態に係る橋桁の架設方法である橋桁のである橋桁の架け替え工事が完了する。 In addition, a telescopic device or the like is attached, and the replacement work of the bridge girder, which is the bridge girder erection method according to the present embodiment, is completed.

以上説明した本実施形態に係る橋桁の架設方法によれば、PCa床版2の設置やPCa壁高欄3の設置などを行う橋桁1の設置後の後作業において、油圧クレーンCLで各床版を吊り上げて何度も旋回するなどの時間のかかる作業を既設の橋桁の撤去作業と同時並行で行うことができる。このため、交通規制を伴う作業の作業時間を短縮することができる。 According to the bridge girder erection method according to the present embodiment described above, in the post-installation work after the installation of the bridge girder 1 for installing the PCa floor slab 2 and the PCa wall railing 3, each floor slab is installed by the hydraulic crane CL. Time-consuming work such as lifting and turning many times can be performed in parallel with the work of removing the existing bridge girder. Therefore, it is possible to shorten the work time of the work involving traffic regulation.

また、本実施形態に係る橋桁の架設方法によれば、新設の橋桁1を送り出す際に、PCa床版2に曲げ応力やせん断応力が伝達されにくく、ひびが入るなどのPCa床版2が損傷するおそれが低減される。 Further, according to the bridge girder erection method according to the present embodiment, when the newly installed bridge girder 1 is sent out, bending stress and shear stress are difficult to be transmitted to the PCa deck 2, and the PCa deck 2 is damaged due to cracks and the like. The risk of shearing is reduced.

その上、本実施形態に係る橋桁の架設方法によれば、仮固定を解除して経時硬化材を打設する作業が容易に短時間で行うことができる。また、必要な被り厚さを確実に確保することができる。 Moreover, according to the method of erection of the bridge girder according to the present embodiment, the work of releasing the temporary fixing and placing the time-curing material can be easily performed in a short time. In addition, the required cover thickness can be reliably secured.

それに加え、本実施形態に係る橋桁の架設方法によれば、転倒防止材である鋼製ワイヤ32によりPCa壁高欄3がPCa床版2の外側へ転倒するおそれを完全に払拭することができ、極めて安全である。 In addition, according to the method of erection of the bridge girder according to the present embodiment, the possibility that the PCa wall railing 3 falls to the outside of the PCa deck 2 can be completely eliminated by the steel wire 32 which is a fall prevention material. Extremely safe.

以上、本実施形態に係る橋桁の架設方法について詳細に説明したが、前述した又は図示した実施形態は、いずれも本発明を実施するにあたって具体化した一実施形態を示したものに過ぎない。よって、これらによって本発明の技術的範囲が限定的に解釈されてはならないものである。 Although the method of erection of the bridge girder according to the present embodiment has been described in detail above, all of the above-mentioned or illustrated embodiments merely show one embodiment embodied in carrying out the present invention. Therefore, the technical scope of the present invention should not be construed in a limited manner by these.

1:新設の橋桁(橋桁)
EG:既設の橋桁
10:頭付スタッド(スタッド)
11:ねじ付きスタッド(スタッド)
12:高ナット(ナット)
13:全ネジボルト(ボルト)
2:PCa床版(床版)
2a:継手鉄筋
2b:円筒状の鋼材
2c:地覆部
21~28:コッター
3:PCa壁高欄(壁高欄)
30:固定孔
31:鋼棒
32:鋼製ワイヤ(転倒防止材)
33:円筒状の鋼材
34:スパイラル筋
K1:第1下部構造
K2:第2下部構造
K3:第3下部構造
K4:第4下部構造
D1:第1径間
D2:第2径間
D3:第3径間
SM:送出し設備
SD:送出し装置(送出し設備)
TG:軌条桁(送出し設備)
DC:台車設備
DM:下降設備
TK:仮受
TM:手延機連結構
CL:油圧クレーン(揚重機)
TL:トレーラー(搬出車)
X:橋軸方法
Y:橋軸直角方向
1: New bridge girder (bridge girder)
EG: Existing bridge girder 10: Stud with head (stud)
11: Stud with screw (stud)
12: High nut (nut)
13: All screw bolts (bolts)
2: PCa floor slab (floor slab)
2a: Joint reinforcing bar 2b: Cylindrical steel material 2c: Ground covering portion 21 to 28: Cotter 3: PCa wall balustrade (wall balustrade)
30: Fixing hole 31: Steel rod 32: Steel wire (fall prevention material)
33: Cylindrical steel material 34: Spiral bar K1: 1st substructure K2: 2nd substructure K3: 3rd substructure K4: 4th substructure D1: 1st span D2: 2nd span D3: 3rd Span SM: Sending equipment SD: Sending device (sending equipment)
TG: Rail girder (delivery equipment)
DC: Bogie equipment DM: Lowering equipment TK: Temporary receiving TM: Hand-rolling machine connection structure CL: Hydraulic crane (lifting machine)
TL: Trailer (carrying out vehicle)
X: Bridge axis method Y: Bridge axis perpendicular direction

Claims (5)

橋桁を橋梁の下部構造から送り出して架設する橋桁の架設方法であって、
送り出す橋桁を地組する橋桁地組工程を行い、当該橋桁地組工程では、地組した橋桁上にPCa床版を非合成状態で仮固定すること
を特徴とする橋桁の架設方法。
It is a method of erection of a bridge girder that is erected by sending out the bridge girder from the substructure of the bridge.
A bridge girder erection method characterized in that a bridge girder groundwork process is performed to ground the bridge girder to be sent out, and the PCa deck is temporarily fixed on the grounded bridge girder in a non-synthetic state.
前記橋桁地組工程では、仮固定した前記PCa床版にPCa壁高欄をさらに仮固定すること
を特徴とする請求項1に記載の橋桁の架設方法。
The method for erection of a bridge girder according to claim 1, wherein in the bridge girder ground assembly process, a PCa wall balustrade is further temporarily fixed to the temporarily fixed PCa floor slab.
前記PCa床版の仮固定は、上部にねじ溝が切削加工されたねじ付きスタッドに高ナットを介してボルトを延長し、このボルトに螺合するナットで鋼製プレートを緊結することにより仮固定していること
を特徴とする請求項1又は2に記載の橋桁の架設方法。
Temporary fixing of the PCa deck is performed by extending a bolt to a threaded stud with a threaded groove on the upper part via a high nut and fastening a steel plate with a nut screwed to this bolt. The method for erection of a bridge girder according to claim 1 or 2 , wherein the bridge girder is erected.
前記PCa床版と前記橋桁を接合する経時硬化材を打設する前に、前記ボルトを取り外すことによって高ナットの被り厚さを確保すること
を特徴とする請求項に記載の橋桁の架設方法。
The method for erection of a bridge girder according to claim 3 , wherein a high nut covering thickness is secured by removing the bolt before placing a time-curing material for joining the PCa deck and the bridge girder. ..
前記PCa壁高欄の仮固定では、前記PCa床版の外側へ前記PCa壁高欄が転倒しないように止め付ける転倒防止材を設置すること
を特徴とする請求項2に記載の橋桁の架設方法。
The method for erection of a bridge girder according to claim 2, wherein in the temporary fixing of the PCa wall balustrade, a fall prevention material for fixing the PCa wall balustrade so as not to fall is installed on the outside of the PCa floor slab.
JP2018005215A 2018-01-16 2018-01-16 How to erection the bridge girder Active JP7080648B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018005215A JP7080648B2 (en) 2018-01-16 2018-01-16 How to erection the bridge girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018005215A JP7080648B2 (en) 2018-01-16 2018-01-16 How to erection the bridge girder

Publications (2)

Publication Number Publication Date
JP2019124051A JP2019124051A (en) 2019-07-25
JP7080648B2 true JP7080648B2 (en) 2022-06-06

Family

ID=67398163

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018005215A Active JP7080648B2 (en) 2018-01-16 2018-01-16 How to erection the bridge girder

Country Status (1)

Country Link
JP (1) JP7080648B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7451391B2 (en) 2020-12-22 2024-03-18 三井住友建設株式会社 Bridge girder replacement method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001164513A (en) 1999-12-06 2001-06-19 Kajima Corp Joint structure of section division type precast segment
JP2005023684A (en) 2003-07-04 2005-01-27 Sumitomo Mitsui Construction Co Ltd Erection method for bridge
JP2005163410A (en) 2003-12-03 2005-06-23 Public Works Research Institute Thrust construction method
JP2017002559A (en) 2015-06-10 2017-01-05 西日本高速道路株式会社 Concrete slab joint method, concrete slab replacement method, concrete slab joint structure, and precast concrete slab
JP2017008671A (en) 2015-06-25 2017-01-12 三井住友建設株式会社 Precast bridge component

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3450054B2 (en) * 1994-06-17 2003-09-22 石川島建材工業株式会社 Installation method of floor slab on bridge girder and slab cradle
JPH101915A (en) * 1996-06-18 1998-01-06 Takiron Co Ltd Buried form for filler concrete and filling method employing this

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001164513A (en) 1999-12-06 2001-06-19 Kajima Corp Joint structure of section division type precast segment
JP2005023684A (en) 2003-07-04 2005-01-27 Sumitomo Mitsui Construction Co Ltd Erection method for bridge
JP2005163410A (en) 2003-12-03 2005-06-23 Public Works Research Institute Thrust construction method
JP2017002559A (en) 2015-06-10 2017-01-05 西日本高速道路株式会社 Concrete slab joint method, concrete slab replacement method, concrete slab joint structure, and precast concrete slab
JP2017008671A (en) 2015-06-25 2017-01-12 三井住友建設株式会社 Precast bridge component

Also Published As

Publication number Publication date
JP2019124051A (en) 2019-07-25

Similar Documents

Publication Publication Date Title
CN110886237B (en) Arch bridge construction method
JP6316665B2 (en) Composite structure of steel girder and precast slab and its construction method
JP4059909B2 (en) Composite panel structure and panel bridge structure and construction method of continuous composite girder bridge
KR100820299B1 (en) Temporary structure and precast concrete beam of pylon setting method using the bracket
JP6097965B2 (en) Construction method of concrete precast slab for bridge
JP5331924B1 (en) SPC bridge construction method
JP6180376B2 (en) Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method
JP2014177766A (en) Method for constructing concrete precast floor slab for bridge
CN105484151A (en) Structure for enhancing connection among prefabricated concrete segments and construction method thereof
CN108589507B (en) Full-assembled precast concrete beam bridge superstructure and construction method thereof
JP7080648B2 (en) How to erection the bridge girder
JP6374353B2 (en) How to build a bridge
KR101734118B1 (en) Method for construction of prestressed steel-concrete composite rahmen bridge
JP2018021403A (en) Floor slab replacement method for steel composite girder, and pc floor slab
JP3737475B2 (en) Box girder bridge structure and construction method
CN110904854B (en) Arch bridge construction method adapting to removal progress
KR200431821Y1 (en) The Method of Construction for Continuous Bridge made by Prestressed Concrete I-Shape Girder
JP3877995B2 (en) How to build a string string bridge
CN104453228A (en) Construction method of large-span super-large-section steel plate wall beam
JP2006112086A (en) Structure of bridge and method for rebuilding bridge
JP7134133B2 (en) Bridge railing construction method
JP2017172144A (en) Junction structure and junction method between road floor slab and pca wall balustrade
KR200267736Y1 (en) Structures of concrete girder and steel crossbeam in concrete girder bridge
JP6053087B1 (en) Steel composite girder floor slab replacement method
KR20020059960A (en) Precasted Concrete using a Fiber Reinforced Concrete and method for construction

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201117

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211015

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211207

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220111

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220524

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220525

R150 Certificate of patent or registration of utility model

Ref document number: 7080648

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150