JP5089352B2 - Sales production planning system, operation method of sales production planning system, and computer program - Google Patents

Sales production planning system, operation method of sales production planning system, and computer program Download PDF

Info

Publication number
JP5089352B2
JP5089352B2 JP2007308443A JP2007308443A JP5089352B2 JP 5089352 B2 JP5089352 B2 JP 5089352B2 JP 2007308443 A JP2007308443 A JP 2007308443A JP 2007308443 A JP2007308443 A JP 2007308443A JP 5089352 B2 JP5089352 B2 JP 5089352B2
Authority
JP
Japan
Prior art keywords
order
data
production
sales
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2007308443A
Other languages
Japanese (ja)
Other versions
JP2009134399A (en
Inventor
廣 西川
健 依藤
哲 新田
伸元 山中
良平 瀬尾
充 千田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
JFE Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp filed Critical JFE Steel Corp
Priority to JP2007308443A priority Critical patent/JP5089352B2/en
Publication of JP2009134399A publication Critical patent/JP2009134399A/en
Application granted granted Critical
Publication of JP5089352B2 publication Critical patent/JP5089352B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、素材製品を商品として製造する素材生産企業における販売生産計画システム、販売生産計画システムの動作方法及び販売生産計画システムをコンピュータにより実現するためのコンピュータプログラムに関する。 The present invention relates to a sales production planning system in a material production company that manufactures a raw material product as a product, an operation method of the sales production planning system, and a computer program for realizing the sales production planning system by a computer.

従来、共通の出発原料に対して一定の処理を施し、その処理済原料から種々な素材製品を製造していく素材生産企業(例えば、薄鋼板、表面処理鋼板、厚鋼板、条鋼、形鋼、鋼管などに代表される鉄鋼製品を製造する鉄鋼業)においては、製品が多種類にわたる上に、その製造期間も長いため、製造中や製造済の製品(鉄源)を、注文に対して、如何に最適に配分するか、といった視点で、販売計画や生産計画を作成してきた。そして、販売計画や生産計画の作成で必要となる、まだ注文を受けていない見込注文を想定する際には、想定数量を積み上げた、販売数量枠及び生産数量枠という大枠としてまとめた『枠』単位の数値を設定して行っていた。また、輸送計画は、荷揃いが完了した段階で作成されていた。   Conventionally, a raw material production company (for example, a thin steel plate, a surface-treated steel plate, a thick steel plate, a steel strip, a shape steel, etc.) that performs a certain treatment on a common starting material and produces various raw material products from the processed raw material. In the steel industry that manufactures steel products represented by steel pipes, etc., because there are many types of products and the manufacturing period is long, products that are being manufactured or manufactured (iron sources) We have created sales plans and production plans from the perspective of how to allocate optimally. Then, when assuming a prospective order that is necessary for the creation of a sales plan or production plan but has not yet received an order, the “frame” is a large frame of the sales quantity frame and the production quantity frame, which are the estimated quantities stacked. It was done by setting the unit value. In addition, the transportation plan was created when the assortment was completed.

この種の鉄鋼製品の管理として、例えば需要家の使用計画と、適正在庫量、流通部門及び需要家の在庫とに基づいて納期・製造指示日の設定を行い、注文をグルーピング納期管理を行う方法が提案されている(例えば特許文献1参照)。また、鉄鋼製品の作業計画の例として、一貫ロットコードを付与して製造ロットを編成し、各製造工程における作業計画を作成することが提案されている(例えば特許文献2)。また、生産計画の方法の例として、製品の出荷量から算出する販売価格の合計と処理量に相当する変動量の合計と処理量に相当する変動量の合計の差が最大となる月別生産計画の方法が提案されている(例えば特許文献3及び特許文献4参照)。   As a management of this kind of steel products, for example, a method for setting delivery date and production instruction date based on customer's usage plan, appropriate stock quantity, distribution department and customer's inventory, and grouping delivery date management Has been proposed (see, for example, Patent Document 1). In addition, as an example of a work plan for steel products, it has been proposed to create a work plan in each manufacturing process by assigning a consistent lot code to organize a production lot (for example, Patent Document 2). In addition, as an example of a production plan method, a monthly production plan that maximizes the difference between the total sales price calculated from the product shipment volume, the total variation amount corresponding to the processing amount, and the total variation amount corresponding to the processing amount. Has been proposed (see, for example, Patent Document 3 and Patent Document 4).

特許第2847276号公報Japanese Patent No. 2847276 特開2002−91537号公報JP 2002-91537 A 特開2006−309573号公報JP 2006-309573 A 特開2006−338110号公報JP 2006-338110 A

従来の生産計画方法においては、販売計画枠及び生産計画枠を単位として生産計画が作成されており、計画内容に注文単位の明細情報がないため、販売計画と生産計画が一貫した計画になっていないという問題点があった。このため、計画精度が低く、顧客の引取り予定のない製品を製造し、不良在庫を増加させることになるという不都合があった。特に、鉄鋼の場合には、大手需要家から鋼材の使用予定の情報を入手し販売計画を作成しているが、現在の方法では、使用予定の変動に対応し難いという問題点がある。また、輸送計画についても、荷揃いが完了した商品について個別に作成されており、荷揃予定情報と連動する仕組みとはなっていない。   In the conventional production planning method, the production plan is created by using the sales plan frame and the production plan frame as a unit, and since there is no detailed information for each order in the plan content, the sales plan and the production plan are consistent. There was no problem. For this reason, there is an inconvenience that the planning accuracy is low and a product which is not scheduled to be picked up by a customer is manufactured, resulting in an increase in defective inventory. In particular, in the case of steel, a sales plan is created by obtaining information on the planned use of steel from a major customer, but the current method has a problem that it is difficult to cope with fluctuations in the planned use. In addition, transportation plans are also created individually for products for which assortment has been completed, and are not linked to the assortment schedule information.

また、上記の特許文献1においては提案されている方法は、仕様部品毎に注文をグルーピングした上で納期管理することが提案されているが、注文をグルーピングするには過去の注文実績を分析しなければならない等、その処理が難しいという課題がある。更に、特許文献1の方法は、販売計画・生産方法については開示されておらず、納期管理の方法にとどまっている。   In addition, in the above-mentioned Patent Document 1, it is proposed to manage the delivery date after grouping orders for each specification part, but in order to group orders, the past order results are analyzed. There is a problem that the processing is difficult. Furthermore, the method of Patent Document 1 does not disclose a sales plan / production method, but only a delivery date management method.

また、上記の特許文献2において提案されている方法は、一貫ロットコードを付与するためには、注文情報を分析しなければならないという課題がある。
また、特許文献3及び特許文献4において提案されている方法は、生産計画の作成単位は品種単位であるが、注文単位を纏めた粗い単位で計画を作成すると計画精度が上がらないという課題がある。
In addition, the method proposed in Patent Document 2 has a problem that order information must be analyzed in order to assign a consistent lot code.
In addition, the methods proposed in Patent Document 3 and Patent Document 4 have a problem that the production accuracy of the production plan is a product unit, but if the plan is created in a coarse unit including the order units, the plan accuracy does not increase. .

さらに、上述の『枠』の量による販売計画や生産計画の作成を続けてきた背景には、鉄鋼の生産量(供給量)が、注文量(需要量)を上回る状況で、十分に注文に対応できるという前提のものである。しかしながら、近年においては、需給関係が逆転するような状況になって、従来の『枠』を使った計画では計画の精度が十分でなかったり、需要家からの注文量の変化に迅速に対応できないなどの問題点がでてきた。   Furthermore, the reason behind the continued creation of sales plans and production plans based on the amount of the “frame” mentioned above is that the amount of steel production (supply amount) exceeds the order amount (demand amount). It is the premise that it can respond. However, in recent years, the supply-demand relationship has been reversed, and the plan using the conventional “frame” is not accurate enough or cannot respond quickly to changes in the order quantity from the customer. The problems such as came out.

一方、『枠』でなく『注文単位』で販売計画や生産計画を作成することは、従来からもあったが、鉄鋼業などの素材生産企業は、多種類の製品、多数の需要家がいるため、多種多様の注文データ形態を存在しており、それらをそのまま適用することは困難であった。   On the other hand, creating sales plans and production plans in “order units” instead of “frames” has traditionally existed, but material production companies such as the steel industry have many types of products and many customers. For this reason, there are a wide variety of order data forms, and it is difficult to apply them as they are.

本発明は、上記の課題を解決するためになされたものであり、注文単位で販売生産計画を作成することにより、使用予定の変動に対応し易くし、且つ、計画精度を向上させることを可能にした販売生産計画システム及び販売生産計画システムの動作方法、並びにコンピュータ前記販売生産計画システムの各手段として機能させるためのコンピュータプログラムを提供することを目的とする。 The present invention has been made to solve the above-mentioned problems, and by creating a sales production plan in units of orders, it is possible to easily cope with fluctuations in the use schedule and to improve the planning accuracy. a desired operating method of sales production planning system and sales production planning system, and a computer program for causing a computer to function as each means of the sales production planning system.

発明者らは、販売計画や生産計画の作成手順や注文データの形態を解析したところ、以下のことを見出した。
1)翌月以降に注文がされるであろう見込注文は、顧客や商社などの需要家の使用予定情報に基づいて、「枠」単位で設定されているが、需要家は注文単位での使用予定情報を有している。よって、販売計画や生産計画の処理においても、需要家が有している注文単位の使用予定情報を有効に使えば、全ての需要家に対して、注文単位で、かつ、統一されたデータ形態(データ構造)で処理することが可能である。
The inventors have analyzed the sales plan and production plan creation procedure and the order data format, and found the following.
1) Expected orders that will be placed in the following month are set in units of “frames” based on the usage schedule information of customers such as customers and trading companies. Has schedule information. Therefore, in the sales plan and production plan processing, if the usage schedule information of the order unit possessed by the customer is used effectively, it is an orderly and unified data format for all the consumers. (Data structure) can be processed.

2)注文データには、同一の需要家から、長期間(例えば、5年、10年)にわたって、繰り返される注文(「リピート注文」と称す)が、注文全体の中で占める割合が比較的多い。そして、これらの注文では、納期、数量は変更されるものの、それ以外の製造仕様などの項目は変更されない。したがって、見込注文の設定の際に、数量、納期以外の確定した項目(製造仕様など)は、予め設定したデータ形式(雛型データ)として、用意しておき、需要家の使用予定に基づいて、注文単位で、数量及び納期のみを入力する仕組みとするのがよい。
そして、上記の知見に基づいて、以下に示す本発明に想到したのである。
2) In the order data, repeated orders (referred to as “repeat orders”) from the same consumer over a long period of time (for example, 5 years, 10 years) occupy a relatively large proportion of the orders. . In these orders, the delivery date and quantity are changed, but other items such as manufacturing specifications are not changed. Therefore, when setting a prospective order, items (manufacturing specifications, etc.) that have been confirmed other than the quantity and delivery date are prepared in a preset data format (model data) and based on the customer's use schedule It is recommended that only the quantity and delivery date be entered in order units.
And based on said knowledge, it came to the present invention shown below.

本発明に係る販売生産計画システムは、種々の素材製品を商品として製造する素材生産企業における販売計画及び生産計画を作成するための販売生産計画システムであって、既に受注した製品の実績注文データが格納される第1の記憶手段と、既に出荷済の過去実績データが格納されている第2の記憶手段と、リピート注文の見込注文データが格納される第3の記憶手段と、非リピート注文の見込注文データが格納される第4の記憶手段と、販売計画データが格納される第5の記憶手段と、納期及び数量を除いた製造仕様の情報が予め設定されたフォーマット・データを用いて、需要家における製品の使用予定に基づいて、納期及び数量の入力を促す表示を端末にし、該入力された納期及び数量により、前記実績注文データと同じデータ構造のリピート注文の見込注文データを作成し、前記第3の記憶手段に格納する第1の見込み注文作成手段と、需要家における製品の使用予定に基づいて、納期及び数量の入力を促す表示を端末に行い、該入力された納期、数量と、前記第1の記憶手段及び前記第2の記憶手段の少なくとも一方に格納されている、当該製品に対応するデータの製造仕様の情報とに基づいて、前記実績注文データと同じデータ構造の非リピート注文の見込注文データを作成し、前記第4の記憶手段に格納する第2の見込み注文作成手段と、前記実績注文データ、前記リピート注文の見込注文データ及び前記非リピート注文の見込注文データから販売計画データを作成し、前記第5の記憶手段に格納する販売計画データ作成手段と、所定期間における、前記販売計画データの注文の合計数量と前記注文が指定している製造ラインの製造能力とを比較する能力検証手段と、前記注文の合計数量が前記製造能力範囲になるように、前記実績注文データ、前記リピート注文の見込注文データ及び前記非リピート注文の見込注文データの少なくとも何れかの、納期及び製造通過工程のデータの少なくとも一方を変更して販売計画を調整する販売計画データ調整手段とを備え、前記各手段において注文単位で処理を行って販売計画を作成する。 Sales production planning system according to the present invention, there is provided a sales production planning system for creating a sales plan and production planning in material production company manufacturing various materials product as a product, the product of the actual order data already received orders A first storage means for storing; a second storage means for storing past performance data that has already been shipped; a third storage means for storing expected order data for repeat orders; and a non-repeat order Using fourth storage means for storing expected order data, fifth storage means for storing sales plan data, and format data in which manufacturing specification information excluding delivery date and quantity is preset, Based on the use schedule of the product in the consumer, a display for prompting the input of the delivery date and quantity is used as a terminal, and the same data structure as the actual order data by the inputted delivery date and quantity A first prospective order creation means for creating expected order data for repeat orders and storing it in the third storage means, and a display for prompting the delivery date and quantity input based on the product use schedule at the consumer on the terminal And based on the input delivery date and quantity, and information on manufacturing specifications of data corresponding to the product stored in at least one of the first storage unit and the second storage unit, Second prospective order creation means for creating expected order data for non-repeat orders having the same data structure as the actual order data and storing it in the fourth storage means; the actual order data; the expected order data for the repeat orders; the create sales plan data from the non-repeat orders expected order data, the sales plan data creation means for storing in said fifth storage means, during a predetermined period, the sales plan And ability verification means for comparing the total quantity and the order production capacity of the production lines that specify the order of over data, such that the total quantity of the order is the production capacity range, the actual order data, the and a sales plan data adjusting means for adjusting a sales plan by changing at least one of the expected order data expected order data and the non-repeat orders repeat orders, at least one of the data delivery time and manufacturing passing step, the Each unit processes each order and creates a sales plan.

本発明に係る販売生産計画システムにおいて、前記販売計画データ調整手段は、さらに、
イ)製造ラインの生産量
ロ)納期遵守率
を最適化の制約条件として、実績注文データ及び見込注文データの少なくとも一方の、納期及び製造通過工程に関するデータの少なくとも一方を変更する。
In the sales production planning system according to the present invention, the sales plan data adjustment means further includes:
B) Production line production volume b) With the delivery date compliance rate as a constraint for optimization, at least one of the actual order data and the expected order data and at least one of the data related to the delivery date and the production passing process is changed.

本発明に係る販売生産計画システム、前記販売計画データ調整手段で調整された販売計画データを入力し、該販売計画データに基づいて、生産製造プロセスの通過ラインのスケジューリングを行うことにより、各ラインの予定通過日及び時刻を決定して、生産計画を作成する生産計画作成手段を、さらに備えたものである。 The sales production planning system according to the present invention inputs the sales plan data adjusted by the sales plan data adjustment means, and schedules the passing line of the production manufacturing process based on the sales plan data, thereby each line. The production plan creation means for creating a production plan by determining the scheduled passage date and time is further provided.

本発明に係る販売生産計画システムの動作方法は、既に受注した製品の実績注文データが格納される第1の記憶手段と、既に出荷済の過去実績データが格納されている第2の記憶手段と、リピート注文の見込注文データが格納される第3の記憶手段と、非リピート注文の見込注文データが格納される第4の記憶手段と、販売計画データが格納される第5の記憶手段とを備える、種々の素材製品を商品として製造する素材生産企業における販売計画及び生産計画を作成するための販売生産計画システムの動作方法であって、
納期及び数量を除いた製造仕様の情報が予め設定されたフォーマット・データを用いて、需要家における製品の使用予定に基づいて、納期及び数量の入力を促す表示を端末にし、該入力された納期及び数量により、前記実績注文データと同じデータ構造のリピート注文の見込注文データを作成し、前記第3の記憶手段に格納する第1の見込み注文ステップと、
需要家における製品の使用予定に基づいて、納期及び数量の入力を促す表示を端末に行い、該入力された納期、数量と、前記第1の記憶手段及び前記第2の記憶手段の少なくとも一方に格納されている、当該製品に対応するデータの製造仕様の情報とに基づいて、前記実績注文データと同じデータ構造の非リピート注文の見込注文データを作成し、前記第4の記憶手段に格納する第2の見込み注文作成ステップと、
前記実績注文データ、前記リピート注文の見込注文データ及び前記非リピート注文の見込注文データから販売計画データを作成し、前記第5の記憶手段に格納する販売計画データ作成ステップと、
所定期間における、前記販売計画データの注文の合計数量と前記注文が指定している製造ラインの製造能力とを比較する能力検証ステップと、
前記注文の合計数量が前記製造能力の範囲内になるように、前記実績注文データ、前記リピート注文の見込注文データ及び前記非リピート注文の見込注文データの少なくとも何れかの、納期及び製造通過工程のデータの少なくとも一方を変更して販売計画を調整する販売計画データ調整ステップと
を実行し、
前記各ステップにおいて注文単位で処理を行って販売計画を作成する。
The operation method of the sales production planning system according to the present invention includes a first storage means for storing the actual order data of products already ordered, and a second storage means for storing past actual data that has already been shipped. Third storage means for storing expected order data for repeat orders, fourth storage means for storing expected order data for non-repeat orders, and fifth storage means for storing sales plan data A sales production planning system for creating a sales plan and a production plan in a material production company that manufactures various material products as products,
Using format data in which manufacturing specification information excluding the delivery date and quantity is set in advance, the display prompting the customer to input the delivery date and quantity based on the planned use of the product by the consumer is used as the terminal, and the inputted delivery date And a first prospective order step of creating expected order data of a repeat order having the same data structure as the actual order data according to the quantity and storing the data in the third storage means;
A display prompting the terminal to input the delivery date and quantity is performed on the terminal based on the use schedule of the product in the consumer, and the inputted delivery date and quantity are displayed on at least one of the first storage means and the second storage means. Based on the stored manufacturing specification information of the data corresponding to the product, non-repeat order prospective order data having the same data structure as the actual order data is created and stored in the fourth storage means. A second potential order creation step;
A sales plan data creating step of creating sales plan data from the actual order data, the expected order data of the repeat order and the expected order data of the non-repeat order, and storing in the fifth storage means;
A capability verification step of comparing a total quantity of orders in the sales plan data with a manufacturing capacity of a production line specified by the orders in a predetermined period;
The delivery date and the production passing process of at least one of the actual order data, the expected order data of the repeat order, and the expected order data of the non-repeat order so that the total quantity of the order falls within the range of the manufacturing capacity A sales plan data adjustment step that adjusts the sales plan by changing at least one of the data;
Run
In each step, a sales plan is created by performing processing in units of orders.

本発明に係る販売生産計画システムの動作方法は、前記販売計画データ調整ステップで調整された販売計画データを入力し、該販売計画データに基づいて、生産製造プロセスの通過ラインのスケジューリングを行うことにより、各ラインの予定通過日及び時刻を決定して、生産計画を作成する生産計画作成ステップを、さらに備えたものである。 The operation method of the sales production planning system according to the present invention includes inputting the sales plan data adjusted in the sales plan data adjustment step , and scheduling the passing line of the production manufacturing process based on the sales plan data. The method further includes a production plan creation step of determining a scheduled passage date and time of each line and creating a production plan.

本発明に係る販売生産計画システムの動作方法は、製造プロセスの通過ラインのスケジューリングがなされた注文の数量を累積して所定期間内の生産量を算出するとともに、その計画された生産量を注文単位で特定して、該注文が生産可能か判断して、生産できない場合には、前記販売計画データ調整ステップで販売計画を調整する。 The operation method of the sales production planning system according to the present invention calculates the production amount within a predetermined period by accumulating the quantity of orders for which the passing line of the manufacturing process is scheduled, and also calculates the planned production amount as an order unit. In this case, it is determined whether the order can be produced. If the order cannot be produced, the sales plan is adjusted in the sales plan data adjustment step .

本発明に係る販売生産計画システムの動作方法は、需要家への製品輸送計画を、前記生産計画に基づき、前記実績注文及び前記見込注文の納期を基準として作成する。 In the operation method of the sales production planning system according to the present invention, a product transportation plan to a customer is created based on the delivery date of the actual order and the expected order based on the production plan.

本発明に係る販売生産計画システムの動作方法は、前記実績注文データまたは前記見込注文データの少なくとも一方が変更された場合、上記のステップを繰り返して販売計画及び生産計画を作成し直す。 In the operation method of the sales production planning system according to the present invention, when at least one of the actual order data or the expected order data is changed, the above steps are repeated to recreate the sales plan and the production plan.

本発明に係るコンピュータプログラムは、コンピュータを、前記第1の見込み注文作成手段、前記第2の見込み注文作成手段、前記販売計画データ作成手段、前記能力検証手段、前記販売計画データ調整手段として機能させるためのものである。 A computer program according to the present invention causes a computer to function as the first prospective order creation means, the second prospective order creation means, the sales plan data creation means, the capability verification means, and the sales plan data adjustment means . Is for.

本発明によれば、全ての顧客に対して注文データの構造を同じにし、繰り返し注文される製品の注文(リピート注文)の見込注文データの作成においては、納期と数量以外のデータを確定した雛型のデータ構造を持つ「基本注文」を用いて、数量と納期のみを入力するだけとし、さらにリピート注文以外でも、数量、納期のみを入力し、実績受注データから注文単位のデータに展開するようにしたので、需要家の使用予定が変更された場合においても、迅速に、効率よく、販売計画や生産計画に対応することができる。   According to the present invention, the order data structure is made the same for all customers, and in the creation of the expected order data for the repeated product order (repeat order), data other than the delivery date and quantity are determined. Using the “basic order” with a data structure of the type, enter only the quantity and delivery date, and enter only the quantity and delivery date in addition to repeat orders, and expand from the actual order data to the order unit data. Therefore, even when the use schedule of the customer is changed, it is possible to respond to the sales plan and the production plan quickly and efficiently.

また、販売計画の注文の情報(納期、数量、工場、製造プロセスの製造ラインの情報)と、当該注文が指定している工場の製造プロセスの製造ラインの能力とに基づいて、注文の数量が前記製造ラインの能力の範囲にあるかどうかを判定し、製造ラインの能力の範囲にない場合には、注文が製造ラインの能力の範囲になるように、納期や当該注文で指定された製造ラインを変更するようにして、製造ラインの生産能力を販売計画に反映させ、さらには、生産量や納期遵守率といった指標も考慮して最適な販売計画及び生産計画を作成するようにしているので、販売計画及び生産計画を高精度に作成することが可能になっている。   Also, based on the sales plan order information (delivery date, quantity, factory, production process production line information) and the production line capability of the factory production process specified by the order, the order quantity It is determined whether it is within the capacity range of the production line, and if it is not within the capacity range of the production line, the delivery date or the production line specified in the order is set so that the order falls within the capacity range of the production line. As a result, the production capacity of the production line is reflected in the sales plan, and the optimal sales plan and production plan are created by taking into consideration the indicators such as production volume and delivery date compliance rate. Sales plans and production plans can be created with high accuracy.

実施形態1.
本発明は、注文単位で、販売計画、生産計画を作成するため、各注文が持っている全ての項目を処理・管理ができるように、全ての需要家に対して、注文データの構成を統一する。図3は、そのデータの構成例を示したものであり、注文番号、顧客、納期、番号、品種、規格、サイズ、納入先、仕様項目(製造工程通過ライン、工場振替可否を示す振替コード、振替先工場)を含んだ項目からなっている。一般に、数ヶ月単位の販売計画や生産計画を作成するためには、数ヶ月先までの注文データが必要である。図18の概念図に示すように、たとえば、当月を含んで3ヶ月分の計画を作成するには、その3か月分の注文データが必要である。しかし、通常、翌月半ば頃までは注文が確定している「実績注文」であるが、それ以降はこれから注文がされると見込まれるものであり、現時点では確定していない「見込注文」である。したがって、この「見込注文」も計画作成に使われることになるので、本発明では、「見込注文」にも「実績注文」同様の詳細情報を持たせる仕組みを構築した。
Embodiment 1. FIG.
Since the present invention creates a sales plan and production plan for each order, the order data structure is unified for all customers so that all items in each order can be processed and managed. To do. FIG. 3 shows an example of the configuration of the data. The order number, customer, delivery date, number, product type, standard, size, delivery destination, specification item (manufacturing process passage line, transfer code indicating whether factory transfer is possible, It consists of items including the destination factory. Generally, in order to create a sales plan and a production plan in units of several months, order data up to several months ahead is required. As shown in the conceptual diagram of FIG. 18, for example, in order to create a plan for three months including the current month, order data for the three months is required. However, it is usually a “actual order” for which the order has been confirmed until around the next month, but after that, it is expected that an order will be placed in the future, and it is a “prospective order” that has not been confirmed at this time. . Therefore, since this “expected order” is also used for creating a plan, in the present invention, a mechanism for providing detailed information similar to “actual order” in “expected order” is constructed.

そこで、図17の概念図に示すように、注文の形態を、(A)製品仕様や諸元などが同一で、繰り返しされる注文(「リピート注文」)と、(B)製品仕様や諸元などは注文1件ごとに決定し、指定されなければならない注文(「非リピート注文」)、の2つに分けた。そして、(A)「リピート注文」の「見込注文」の設定に関しては、「納期」と「数量」以外の製造仕様や諸元などの項目を、予め全て設定したデータ形式(以降「基本注文」とも記す)と、(B)「非リピート注文」の「見込注文」の設定に関しては、顧客、品種程度の概要項目のデータを予め設定したデータ形式「一般注文」を用意しておき、「見込注文」の設定においては、「リピート注文」、「非リピート注文」で、使用するデータ形式(雛型データ)を区別するようにした。   Therefore, as shown in the conceptual diagram of FIG. 17, the order form is (A) the product specifications and specifications are the same, repeated orders (“repeat order”), and (B) the product specifications and specifications. Are determined for each order, and are divided into two orders that must be specified ("non-repeat orders"). And (A) “Repetitive order” “estimated order” setting, data format (hereinafter referred to as “basic order”) in which all items such as production specifications and specifications other than “delivery date” and “quantity” are set in advance. (B) “For non-repeat orders”, “Predicted order” is set with a data format “general order” in which data of summary items such as customers and product types are set in advance. In the “order” setting, the data format (model data) to be used is distinguished by “repeat order” and “non-repeat order”.

具体的には、図4は基本注文の構成例を示したものであり、図3との対比においては納期及び数量が空欄になっている。一方、図16は一般注文の構成例を示したものであり、図4に比べて、あらかじめ設定されている項目は、顧客、品種程度と少ない。なお、以下、本明細書では、図17に示すように、「リピート注文」、「非リピート注文」ともに、実績注文を「納期注文」、リピート注文の見込注文を「仮納期注文」、非リピート注文の見込注文を「予定注文」として説明する。よって、基本注文により、数量、納期が設定された見込注文が仮納期注文であり、一般注文により、数量、納期が設定されたものが予定注文である。以下にこの分類を適用した本発明の販売生産計画システムを説明する。   Specifically, FIG. 4 shows a configuration example of a basic order. In comparison with FIG. 3, the delivery date and quantity are blank. On the other hand, FIG. 16 shows a configuration example of a general order. Compared with FIG. 4, the number of items set in advance is as few as customers and varieties. In the following, in this specification, as shown in FIG. 17, both “repeat order” and “non-repeat order”, the actual order is “delivery order”, the repeat order expected order is “provisional delivery order”, and non-repeat The expected order is described as “scheduled order”. Therefore, the expected order in which the quantity and the delivery date are set by the basic order is the provisional delivery date order, and the order in which the quantity and the delivery date are set by the general order is the scheduled order. The sales production planning system of the present invention to which this classification is applied will be described below.

図1は、本発明の実施形態1に係る販売生産計画システムの構成を示すブロック図である。この販売生産計画システム1は、図1に示されるように、受注システム10、見込注文生成システム20、販売計画システム30、能力検証システム40、生産管理システム50及び輸送計画システム60から構成されている。受注システム10は、受注処理部11、納期注文データベース(以下、納期注文DBという。また、他のデータベースもDBと略称する)12、過去実績注文DB13から構成されている。なお、納期注文とは、すでに受注された注文であり、その納期や数量、製造使用や製品諸元を含めた全ての情報が確定されているデータである。また、この納期注文DB12に記憶されている納期注文データは、図10に示すような項目をもった構造である。また、過去実績注文DB13は、すでに製造され、出荷された製品に関する注文データを記憶したものである。データ構造は、納期注文データと同じであるが、納期注文データは販売生産計画の対象データであるのに対し、過去実績注文DB13のデータは、すでに出荷済みのものであるので、計画の対象にはならない点で異なる。そして、出荷されて、計画の対象でなくなった時点で、受注システム10により、その注文データは、納期注文DB12から削除されて、過去実績注文DB13に記憶される。また、両者のデータをまとめて、以下では、実績注文データとも称する。   FIG. 1 is a block diagram showing a configuration of a sales production planning system according to Embodiment 1 of the present invention. As shown in FIG. 1, the sales production planning system 1 includes an order receiving system 10, a prospective order generation system 20, a sales planning system 30, a capacity verification system 40, a production management system 50, and a transportation planning system 60. . The order receiving system 10 includes an order receiving processing section 11, a delivery date order database (hereinafter referred to as delivery date order DB. Other databases are also abbreviated as DB) 12, and a past performance order DB 13. Note that the delivery date order is an order that has already been received, and is data in which all information including the delivery date, quantity, production use, and product specifications is confirmed. The delivery date order data stored in the delivery date order DB 12 has a structure having items as shown in FIG. The past performance order DB 13 stores order data relating to products already manufactured and shipped. Although the data structure is the same as the delivery date order data, the delivery date order data is the target data of the sales production plan, whereas the data of the past actual order DB 13 is already shipped, so It is different in that it must not. Then, at the time when the product is shipped and is no longer the target of planning, the order receiving system 10 deletes the order data from the delivery date order DB 12 and stores it in the past performance order DB 13. In addition, both data are collectively referred to as performance order data below.

見込注文生成システム20は、端末21、仮納期注文生成部22、仮納期注文DB23、端末25、予定注文生成部26及び予定注文DB27から構成されている。仮納期注文生成部22は、端末21において、リピート注文の製品について、顧客の使用予定を、図4に示される「基本注文」の「数量」「納期」の入力を受け付けると、その情報に基づいて、仮納期注文データを作成し、仮納期注文DB23に記憶する。一方、予定注文生成部26は、端末25において、非リピート注文の製品について、顧客の使用予定を、図16に示される「一般注文」の「数量」「納期」の入力を受け付ける。そして、その入力データと、納期注文DB12及び過去実績注文DB13の少なくとも一方のデータとから非リピート注文に係る実績注文データを抽出し、そのデータに基づいて、製造仕様を付与して、予定注文データを作成し、予定注文DB27に記憶する。   The expected order generation system 20 includes a terminal 21, a provisional delivery date order generation unit 22, a provisional delivery date order DB 23, a terminal 25, a planned order generation unit 26, and a planned order DB 27. The provisional delivery date order generation unit 22 receives the input of “quantity” and “delivery date” of “basic order” shown in FIG. Temporary delivery date order data is created and stored in the temporary delivery date order DB 23. On the other hand, the planned order generation unit 26 receives input of “quantity” and “delivery date” of “general order” shown in FIG. Then, the actual order data related to the non-repeat order is extracted from the input data and at least one of the delivery date order DB 12 and the past actual order DB 13, and based on the data, the production specification is given, and the planned order data Is stored in the planned order DB 27.

仮納期注文データは、リピート注文に係る見込注文データであり、図3のデータ形式で、仮納期注文DB23に記憶される。一方、予定注文データは、非リピート注文に係る見込注文データであり、端末25で図16のデータ形式で入力されるが、予定注文生成部26において、図3のデータ形式に変換されて、予定注文DB27に記憶される。   The provisional delivery date order data is expected order data relating to repeat orders, and is stored in the provisional delivery date order DB 23 in the data format of FIG. On the other hand, the planned order data is prospective order data relating to non-repeat orders, and is input in the data format of FIG. 16 at the terminal 25, but is converted into the data format of FIG. Stored in the order DB 27.

ここで、端末21、25は、製品を使用する顧客や販売活動をする、例えば商社に設置されて、使用予定を入力してもよいが、仮納期注文については、製造仕様や製品諸元はわかっており、製造者側で数量、納期を入れることも可能なので、端末21は製造者側の工場などに設置して、製造管理者により入力してもよい。   Here, the terminals 21 and 25 may be installed in a trading company, for example, a customer who uses the product or a sales activity, and may input a use schedule. Since it is known and the manufacturer can enter the quantity and delivery date, the terminal 21 may be installed in a factory on the manufacturer side and input by the manufacturing manager.

販売計画システム30は、販売計画処理部31、販売計画DB32及び端末33から構成されており、上記の納期注文DB12、仮納期注文DB23、予定注文DB27から、販売計画、生産計画を作成する対象期間に該当する期間、例えば、現時点から3ヶ月分までの、納期注文データ、仮納期注文データ、予定注文データを抽出し、これらを統合して、当該期間の販売計画データを作成する。作成された販売計画データは、販売計画DB32に記憶される。   The sales plan system 30 includes a sales plan processing unit 31, a sales plan DB 32, and a terminal 33, and a target period for creating a sales plan and a production plan from the delivery date order DB 12, the provisional delivery date order DB 23, and the planned order DB 27. For example, delivery date order data, provisional delivery date order data, and planned order data from the present time to three months are extracted and integrated to create sales plan data for the period. The created sales plan data is stored in the sales plan DB 32.

能力検証システム40は、能力検証処理部41及び月間生産能力DB42から構成されている。能力検証処理部41は、全社の工場を管理している本社部門に設置されており、月間生産能力DB42の各工場、製造プロセス、製造ラインの生産能力データを参照して、販売計画データが工場の生産能力に適合しているかどうかを検証し、その検証結果を、販売計画処理部31に出力する。販売計画処理部31では、能力検証処理部41から、販売計画データが生産能力を超えているという結果を入力した場合には、納期を変更するなどして、必要に応じて販売計画を変更し、販売計画DB32に再度記憶する。なお、この処理は、能力検証処理部41において満足される結果が得られるまで繰り返される。また、販売計画の変更にあたっては、単に納期の変更のみでなく、製造ラインの生産量の最適化(生産量の最大化)や納期遵守率の最適化(納期遵守率の最大化)も指標として、販売計画の最適化の演算や検討も行う。また、自動計算で満足できる解が得られないときは、端末33を用いて、人によって修正の検討を行うこともできる。   The capacity verification system 40 includes a capacity verification processing unit 41 and a monthly production capacity DB 42. The capacity verification processing unit 41 is installed in the head office that manages the factories of the entire company. The sales plan data is stored in the factory by referring to the production capacity data of each factory, manufacturing process, and manufacturing line in the monthly production capacity DB 42. Whether the production capacity is suitable is output to the sales plan processing unit 31. In the sales plan processing unit 31, when the result that the sales plan data exceeds the production capacity is input from the capacity verification processing unit 41, the sales plan is changed as necessary, for example, by changing the delivery date. The data is stored in the sales plan DB 32 again. This process is repeated until a satisfactory result is obtained in the capability verification processing unit 41. In addition, when changing the sales plan, not only the delivery date but also the optimization of production line production (maximization of production volume) and delivery date compliance rate (maximization of delivery date compliance rate) are used as indicators. Also, calculate and study sales plan optimization. If a satisfactory solution cannot be obtained by automatic calculation, the terminal 33 can be used to examine corrections by a person.

生産管理システム50は、生産計画スケジューラー51及び生産計画DB52から構成されている。また、この生産管理システム50は、例えば鉄鋼製品を製造する工場に設置されており、能力検証システム40により検証され、適正と判断された販売計画に基づいて、各工場の各製造ラインに適用した生産計画データを作成し、生産計画DB52に記憶する。この作成された生産計画データには製造の日時(製造ラインの各工程を通過する日時)が付与される。なお、上記の能力検証システム40での生産量や納期遵守率の最適化は、全社的な能力検証を行うものであり、各工場における生産の詳細条件まで考慮できない場合がある。よって、生産計画スケジューラー51で生産計画を作成した結果を販売計画処理部31に出力し、能力検証システム40で適正とされた販売計画が、各工場の生産条件に合致せず、修正をする必要があれば、販売計画処理部31で修正されて、その修正された販売計画データが販売計画DB32に記憶される。なお、この処理は、生産計画スケジューラー51にて満足される結果が得られるまで繰り返される。これによって、最終の販売計画データが確定するとともに、生産計画も確定することになる。   The production management system 50 includes a production plan scheduler 51 and a production plan DB 52. The production management system 50 is installed in a factory that manufactures steel products, for example, and is applied to each production line of each factory based on a sales plan that is verified by the capability verification system 40 and determined to be appropriate. Production plan data is created and stored in the production plan DB 52. The created production plan data is given the date of manufacture (date and time of passing through each process of the production line). Note that the optimization of the production amount and the delivery date compliance rate in the capacity verification system 40 described above is for company-wide capacity verification, and it may not be possible to consider the detailed production conditions in each factory. Therefore, the result of creating the production plan by the production plan scheduler 51 is output to the sales plan processing unit 31, and the sales plan determined to be appropriate by the capacity verification system 40 does not match the production conditions of each factory and needs to be corrected. If there is, the sales plan processing unit 31 corrects it, and the corrected sales plan data is stored in the sales plan DB 32. This process is repeated until a satisfactory result is obtained in the production plan scheduler 51. As a result, the final sales plan data is confirmed and the production plan is also confirmed.

輸送計画システム60は、輸送計画処理部61、輸送対象注文DB62及び稼働予定車両DB63、輸送計画DB64及び端末65から構成されており、生産計画スケジューラー51により作成された生産計画データを生産計画DB52から入力し、その生産計画データに基づいて、鉄鋼製品の輸送計画を作成する。   The transportation plan system 60 includes a transportation plan processing unit 61, a transportation target order DB 62, an operation scheduled vehicle DB 63, a transportation plan DB 64, and a terminal 65. The production plan data created by the production plan scheduler 51 is transferred from the production plan DB 52. Enter and create a transport plan for steel products based on the production plan data.

なお、受注処理部11、仮納期注文生成部22、予定注文生成部26、販売計画処理部31、能力検証処理部41、生産計画スケジューラー51及び輸送計画処理部61は、説明の便宜上、それぞれが独立したものとして図示したが、これらの全体を1又は複数のコンピュータにより実現してもよい。また、上記の各DB12、23、27、32、42、52、62、63、64についても同様であり、これらの全体を1又は複数のDBにより実現してもよい。端末21、25、33、65も同様であり、同一の顧客や商社から、予定注文を入力するにあたっては、一般注文と基本注文の入力を別の端末で行う必要はなく、同一の端末から情報入力を行ってもよい。また、上記の各部11、21、26、31、41、51をコンピュータにより実現した場合には、その演算処理は、コンピュータの記憶装置(図示せず)に格納されたプログラムによって実行される。   The order processing unit 11, the provisional delivery order generation unit 22, the planned order generation unit 26, the sales plan processing unit 31, the capacity verification processing unit 41, the production plan scheduler 51, and the transportation plan processing unit 61 are each for convenience of explanation. Although illustrated as independent, the whole may be realized by one or a plurality of computers. The same applies to each of the DBs 12, 23, 27, 32, 42, 52, 62, 63, and 64, and the whole of these may be realized by one or a plurality of DBs. The same applies to the terminals 21, 25, 33, and 65. When inputting a planned order from the same customer or trading company, it is not necessary to input a general order and a basic order on different terminals, but information from the same terminal. Input may be made. Further, when each of the above-described units 11, 21, 26, 31, 41, 51 is realized by a computer, the arithmetic processing is executed by a program stored in a storage device (not shown) of the computer.

図2は図1の販売生産計画作成システムの処理過程を示したフローチャートである。
(S11)受注処理部11は、例えばネットワークを介して外部のコンピュータから基本注文受注実績の情報を受信すると、その情報を納期注文DB12に記憶する。納期注文DB12のデータ構成は、たとえば、前述した図3や図10のような項目を有する。このデータ構成が、本願発明の注文単位でのデータ処理において、需要家、製品の相違にかかわらず、全ての注文について統一されて、共通的に使用される注文データ形式である。
(S12)仮納期注文生成部22では、リピート注文に関して、端末21に需要家の使用予定の入力を促すための表示を行う。たとえば、図8に示すような、入力者に対して、計画対象期間の、リピート注文の予定される納期と数量の入力を促す基本注文入力画面を表示させる。入力画面は、図4と同様に、納期及び数量は空欄とし、それ以外の項目は確定させた注文を発行し、確定していない見込注文を作成するために、納期及び数量のみの入力を要求するものである。この基本注文入力画面を用いて、操作者は、端末21を操作して注文毎に納期と数量を入力する。そのデータを入力し、仮納期注文生成部22では仮納期注文データを生成して、そのデータを仮納期注文DB23に記憶する。入力は、例えば商社が、需要家の使用予定と在庫状況から納期と数量の情報を把握しているので、その情報から、この先、注文を受けるであろう納期及び数量を設定する。また、需要家から使用予定の情報を入手して、工場の生産管理者が入力するようにしてもよい。
FIG. 2 is a flowchart showing a process of the sales production plan creation system of FIG.
(S11) When the order processing unit 11 receives basic order order record information from an external computer, for example, via a network, the information is stored in the delivery date order DB 12. The data structure of the delivery date order DB 12 includes, for example, the items shown in FIGS. 3 and 10 described above. This data structure is an order data format that is unified and used in common for all orders regardless of differences in consumers and products in data processing in order units according to the present invention.
(S12) The provisional delivery date order generation unit 22 displays a display for prompting the terminal 21 to input the use schedule of the customer regarding the repeat order. For example, as shown in FIG. 8, a basic order input screen for prompting the input person to input the scheduled delivery date and quantity of the repeat order in the planning target period is displayed. In the input screen, as in FIG. 4, the delivery date and quantity are blank, the other items are issued, and a confirmed order is issued. To do. Using this basic order input screen, the operator operates the terminal 21 and inputs the delivery date and quantity for each order. The data is input, and the provisional delivery date order generation unit 22 generates provisional delivery date order data and stores the data in the provisional delivery date order DB 23. As for the input, for example, since the trading company grasps the information on the delivery date and quantity from the usage schedule and the stock status of the customer, the delivery date and quantity that will receive the order are set from that information. In addition, the production manager of the factory may input the information scheduled to be used from the consumer.

(S13)一方、予定注文処理部26では、非リピート注文に関して、端末25に需要家の使用予定の入力を促すための表示を行う。たとえば、図9に示すような、操作者に対して、計画対象期間の、非リピート注文の想定される納期と数量の入力を促す一般注文入力画面を表示させる。この入力画面を用いて、端末25を操作して、各注文(ここでは、詳細仕様が不明のため、顧客や品種などで大まかに区分分けされた単位)に対応させて、納期と数量を入力する。なお、非リピート注文は、リピート注文のように仕様や製造に関する詳細情報が不足しているので、納期注文データや仮納期注文データとは単純には統合できない。したがって、非リピート注文の見込注文も、納期注文や仮納期注文のデータ形式で扱えるように、変換処理を予定注文処理部26によって行う。納期注文DB12や過去実績注文DB13には、過去に受注した非リピート注文のデータも含まれており、そのデータには仕様や製造の詳細諸元が確定された情報が付加されている。よって、納期注文DB12や過去実績注文DB13から、顧客や品種の情報が入力された非リピート注文と同じ実績注文データを抽出する。そして、抽出されたデータを累積したのち、その実績注文が有している仕様や製造の詳細情報の内訳比率を算出し、その比率により、非リピート注文に仕様や諸元の詳細情報を付与して分類するとともに、分類された各データの数量を決定し、予定注文データとする。 (S13) On the other hand, the planned order processing unit 26 displays a display for prompting the terminal 25 to input the usage schedule of the customer regarding the non-repeat orders. For example, as shown in FIG. 9, a general order input screen that prompts the operator to input the expected delivery date and quantity of the non-repeat order in the planning target period is displayed. Using this input screen, operate the terminal 25 to input the delivery date and quantity corresponding to each order (here, the detailed specifications are unknown, so the units are roughly divided by customers, product types, etc.) To do. It should be noted that non-repeat orders cannot be simply integrated with delivery date order data or provisional delivery date order data because detailed information regarding specifications and manufacturing is lacking like repeat orders. Therefore, the planned order processing unit 26 performs the conversion process so that the expected order of the non-repeat order can be handled in the data format of the delivery date order or provisional delivery date order. The delivery date order DB 12 and the past performance order DB 13 also include data of non-repeat orders received in the past, and information in which detailed specifications and detailed specifications of production are confirmed is added to the data. Therefore, the same result order data as the non-repeat order in which the customer and product type information is input is extracted from the delivery date order DB 12 and the past result order DB 13. Then, after accumulating the extracted data, calculate the breakdown ratio of the specifications and manufacturing detailed information that the actual order has, and give the detailed information of the specifications and specifications to the non-repeat orders based on the ratio. And the quantity of each classified data is determined and used as scheduled order data.

例えば、一般注文の使用予定として、非リピート注文である顧客P向け・溶融亜鉛鍍金鋼板1200トンが入力された場合、図10のような実績注文データを参照し、至近の期間(例えば、1ヶ月、3ヶ月、6ヶ月など)の顧客P向けで、品種が溶融亜鉛鍍金鋼板のデータを抽出し、抽出されたデータを集計して、規格、サイズ、納入先、製造工場、通過ラインで区分される数量比率を算出し、その比率にしたがって、1200トンを振り分けていく。これによって、非リピート注文の見込注文も、納期注文、仮納期注文と同様のデータ形式の予定注文に展開されて、販売生産計画システム1において統一して処理できるようになる。その予定注文データを予定注文DB27に記憶する。なお、参照するデータは、納期注文DB12のみ、過去実績注文DB13のみ、でもよいし、両方のDBのデータを用いてもよい。また、過去実績注文DB13のデータの参照に際しては、記憶されている全てのデータでなくとも、過去1ヶ月、3ヶ月、半年、1年など期間を区切ってもよい。この期間を定める目安としては、計画対象期間(例えば、今後3ヶ月)と需要動向や市場動向がほぼ同じような期間とすればよい。また、需要動向や市場動向が極端に異なる期間を除いた期間としてもよい。
なお、上述のS12、S13での販売要求入力において、図8、図9の入力画面の前に、図7に示すような「基本注文入力」「一般注文入力」の選択画面を用意しておけば、1台の端末で両方の入力が可能となる。
For example, when 1200 tons of hot-dip galvanized steel sheet for customer P, which is a non-repeat order, is input as a general order use schedule, referring to the actual order data as shown in FIG. For customer P (3 months, 6 months, etc.), the data of the hot dip galvanized steel sheet is extracted and the extracted data is aggregated and classified by standard, size, delivery destination, manufacturing plant, and passing line The quantity ratio is calculated and 1200 tons are distributed according to the ratio. As a result, the expected order of the non-repeat order is also developed into a scheduled order having the same data format as the delivery date order and provisional delivery date order, and can be processed in the sales production planning system 1 in a unified manner. The planned order data is stored in the planned order DB 27. The data to be referred to may be only the delivery date order DB 12 or only the past performance order DB 13, or the data of both DBs may be used. Further, when referring to the data of the past performance order DB 13, periods such as the past one month, three months, half a year, one year, etc. may be divided, not all stored data. As a guideline for determining this period, a period in which the demand trend and market trend are almost the same as the plan target period (for example, the next three months) may be used. Moreover, it is good also as a period except the period when a demand trend or a market trend differs extremely.
In addition, in the above-described sales request input in S12 and S13, a selection screen of “basic order input” and “general order input” as shown in FIG. 7 can be prepared before the input screens of FIGS. For example, both inputs are possible with one terminal.

(S14)販売計画処理部31は、納期注文DB12、仮納期注文DB23、予定注文DB27から、納期を基準として、これから計画を作成する期間(1ヶ月や3ヶ月など)に該当する注文データを検索して、入力し、販売計画に用いる注文明細と個々の注文の数量及び合計数量を求めて販売計画DB32に記憶する。 (S14) The sales plan processing unit 31 searches the delivery date order DB 12, the provisional delivery date order DB 23, and the planned order DB 27 for order data corresponding to the period (1 month, 3 months, etc.) for which a plan is to be created based on the delivery date. Then, the order details used for the sales plan, the quantity of each order, and the total quantity are obtained and stored in the sales plan DB 32.

(S15)能力検証処理部41には、上記の販売計画DB32に記憶された販売計画が製造可能であるかどうか(販売量が生産能力以下か)を検証する。そして、製造可能でない場合には、納期や製造ラインなどを変更することによって、販売計画を修正し、製造可能となるようにする。また、この能力検証においては、製造可能に調整するだけでなく、製造効率を最適にするような調整も行う。その詳細を図14のフローチャートに基づいて説明する。 (S15) The capacity verification processing unit 41 verifies whether the sales plan stored in the sales plan DB 32 can be manufactured (whether the sales volume is equal to or less than the production capacity). If the production is not possible, the sales plan is modified by changing the delivery date, the production line, etc., so that the production is possible. Further, in this capability verification, not only adjustment is made so that manufacture is possible, but also adjustment that optimizes manufacturing efficiency is performed. The details will be described based on the flowchart of FIG.

(S100)能力検証処理部41は、製造工場の月間能力データが格納されている月間生産能力DB42からそのデータを読み込んで、工場、ライン別の生産能力を収集する。
(S101)能力検証処理部41は、販売計画DB32に格納された販売計画データ(注文データ)を読み込む。
(S102)能力検証処理部41は、販売計画の注文データを工場、ライン別に振り分ける。
図5は販売計画の注文データを工場のライン毎に振り分けた例を示すものであり、各ラインの注文の数量を、生産能力と比較するために所定の期間単位(例えば、月単位)の注文数量の合計を求める。
(S100) The capacity verification processing unit 41 reads the data from the monthly production capacity DB 42 in which the monthly capacity data of the manufacturing factory is stored, and collects the production capacity by factory and line.
(S101) The capability verification processing unit 41 reads the sales plan data (order data) stored in the sales plan DB 32.
(S102) The capability verification processing unit 41 sorts the sales plan order data by factory and line.
FIG. 5 shows an example in which the sales plan order data is distributed for each line of the factory. The order quantity of each line is ordered in a predetermined period unit (for example, monthly unit) in order to compare the quantity of the order with the production capacity. Find the total quantity.

(S103)工場のライン毎の生産能力と販売計画の注文とを対比する。
図6は工場のラインにおける能力(X1、X2…)、当該ラインの販売計画の注文の数量の合計(Yl、Y2…)、及び両者の差(Z1、Z2…)を示したものである。差(Zl、Z2…)が負であるかどうかを判定する。差(Zl、Z2…)が負の場合には販売計画は成立しないことになる。
(S109)能力検証処理部41は、差(Z1、Z2…)が負であると判定した場合には、販売計画DB32にアクセスして上記の差が負になった工場のラインに含まれる販売計画の注文データを読み込む。
(S110)能力検証処理部41は、その読み込んだ注文データの納期や通過ライン(または振替コード)を参照して、注文明細データの変更(納期、余裕がある別の通過ラインへの変更)が可能かどうかを判定する。たとえば、能力検証処理部41において、図15に示すような手順で判断すればよい。
(S103) The production capacity for each line of the factory is compared with the order of the sales plan.
FIG. 6 shows the capacity (X1, X2...) In the factory line, the total quantity (Y1, Y2...) Of orders in the sales plan of the line, and the difference (Z1, Z2...) Between the two. Determine if the difference (Zl, Z2 ...) is negative. If the difference (Zl, Z2 ...) is negative, the sales plan will not be established.
(S109) If the capability verification processing unit 41 determines that the difference (Z1, Z2,...) Is negative, the sales verification DB 41 accesses the sales plan DB 32 and sells the sales included in the factory line where the difference is negative. Read plan order data.
(S110) The capability verification processing unit 41 refers to the delivery date and passage line (or transfer code) of the read order data, and changes the order details data (delivery date, change to another passage line with a margin). Determine if it is possible. For example, the capability verification processing unit 41 may make a determination as shown in FIG.

(S201)仮納期注文や予定注文の納期が変更可能であるか否かを判断する。例えば、設定された納期が、現時点より所定日数以上先である注文(つまり、実際に受注される確立が低いので、納期を遅らせてもよい注文)があるか否かを判断する。
(S202)納期変更が可能な注文がある場合には、納期を次月に変更する。まず、納期変更を優先するのは、データが予定にもとづくものであり不確定な要素があること、一部の注文のみ製造工程を変更するのは製造・出荷管理上、できれば避けたいということである。
(S203)納期変更が可能な注文がない場合には、製造通過工程を変更可能(工場振替可能)か否かを判断する。
(S204)製造通過工程の変更が可能な注文があれば、製造通過工程を変更する。
(S205)製造通過工程の変更が可能な注文が無い場合は、納期を変更するしか手段がないので、納期を次月に変更する。例えば、納期が遅いものから、次月に変更する。
(S201) It is determined whether the delivery date of the provisional delivery date order or the scheduled order can be changed. For example, it is determined whether or not there is an order whose set delivery date is a predetermined number of days or more ahead of the current time (that is, an order whose delivery date may be delayed because there is a low probability of actually receiving an order).
(S202) If there is an order whose delivery date can be changed, the delivery date is changed to the next month. First, changing the delivery date is given priority because the data is based on the schedule and there are uncertain factors, and it is desirable to avoid changing the manufacturing process for only a part of the orders, if possible in manufacturing and shipping management. is there.
(S203) If there is no order whose delivery date can be changed, it is determined whether or not the production passing process can be changed (factory transfer is possible).
(S204) If there is an order that can change the manufacturing passing process, the manufacturing passing process is changed.
(S205) If there is no order that can change the production passing process, the only way to change the delivery date is to change the delivery date to the next month. For example, change from a late delivery date to the next month.

なお、納期変更や通過工程の変更は自動的に処理してもよいが、自動処理で全て対応できない場合には、図11に示すような画面表示を行って、計画検討者に、生産能力と販売計画との関係を表示し、修正処理を行わせるようにしてもよい。図11の例では、注文量が生産能力を上回っているライン(「熱延」「CGL(溶融亜鉛)」)について、☆マークや着色表示などを行って、そのラインに関する注文データを変更するように促す画面を表示する。さらに、ライン位置にカーソルを移動させて、クリックすることにより、図12のような該当ラインを通過する注文リストが表示され、顧客や納期や品種などで、並び替え(ソーティング)や、特定にデータを選択表示(フィルタリング)したりし、検討者がデータ変更の判断をし易くする機能を持たせた画面表示をすればよい。   Note that delivery date changes and passing process changes may be processed automatically. However, if all of the automatic processing cannot handle them, a screen display as shown in FIG. The relationship with the sales plan may be displayed and correction processing may be performed. In the example of FIG. 11, the order data related to the line is changed by performing a ☆ mark or coloring display on the line where the order quantity exceeds the production capacity (“hot rolling” “CGL (molten zinc)”). Display a screen prompting you to Furthermore, when the cursor is moved to the line position and clicked, an order list passing through the corresponding line as shown in FIG. 12 is displayed, and sorting (sorting) by customer, delivery date, product type, etc., or specific data May be selected and displayed (filtered), or the screen may be displayed with a function that makes it easy for the examiner to determine data change.

このような処理を図14の処理S103で、販売計画数量が生産能力の範囲内になるまで、繰り返す。
(S104)販売計画数量が生産能力の範囲内になった場合には、そのデータについて、各ラインについて生産量(最大生産能力に対する比率である生産率でもよい)を算出する。なお、生産率を算出する場合には、最大生産能力を予めテーブルなどに記憶しておき、それと対比すればよい。
(S105)さらに、その販売計画の納期達成率を算出する。
(S106)この注文明細データ、生産率、納期達成率を一時記憶する。
Such a process is repeated in the process S103 of FIG. 14 until the sales plan quantity is within the range of the production capacity.
(S104) When the sales plan quantity falls within the range of the production capacity, the production quantity (a production rate that is a ratio to the maximum production capacity) is calculated for each line for the data. When calculating the production rate, the maximum production capacity may be stored in advance in a table or the like and compared with it.
(S105) Further, the delivery date achievement rate of the sales plan is calculated.
(S106) This order detail data, production rate, and delivery date achievement rate are temporarily stored.

(S107)能力検証処理部41は、処理を終了するかどうかを判断する。たとえば、この生産率・納期達成率の算出処理がN回(例えば5回)以下であるかどうか、所望の生産量、生産率、納期達成率の値が得られたなどで判定し、それらの条件に達するまでは販売計画の修正(S102)以降を繰り返す。ここでの処理も、S110の注文明細データの変更処理にあたっては、前回の変更データを記憶しておき、それとは異なるデータ(変更優先度が次に高いデータ)と入れ替えるようにして、データを自動的に変更していけばよい。通過工程が複数の工場に設定されている場合には、通過ラインを入れ替えたり、一つの工場に集約したりする。
また、自動で変更しなくとも、図13に示すような画面表示して、検討者に、各ラインの生産量や最大生産量に対する比率(生産率)を表示して、そのなかで生産率が低い、あるいは、最大生産率に近づける必要があるラインに注目させて、そのラインに対応する注文データを変更入力させるようにしてもよい。
(S108)以上の処理を繰り返すことにより、一定の期間単位毎(1ヶ月)に算出した販売計画データの合計数量を、工場・ラインの対応する期間(例えば1ヶ月)の生産能力の範囲内に収めた上で、さらに、生産量や納期遵守率が最適化された販売計画データを販売計画DB32に再度、格納する。
(S107) The capability verification processing unit 41 determines whether to end the process. For example, whether or not the calculation process of the production rate / delivery date achievement rate is N times (for example, 5 times) or less is determined based on the desired production volume, production rate, delivery date achievement rate value, etc. Until the condition is reached, the sales plan correction (S102) and subsequent steps are repeated. Also in this processing, in the order detail data change processing of S110, the previous change data is stored, and the data is automatically changed so that it is replaced with data different from that (data having the next highest change priority). Change it. When the passing process is set in a plurality of factories, the passing lines are replaced or integrated into one factory.
Even if it is not automatically changed, the screen as shown in FIG. 13 is displayed, and the examiner is displayed the production amount of each line and the ratio (production rate) with respect to the maximum production amount. Focusing on a line that needs to be low or close to the maximum production rate, the order data corresponding to the line may be changed and input.
(S108) By repeating the above processing, the total quantity of the sales plan data calculated for each fixed period unit (one month) is within the range of the production capacity of the corresponding period (for example, one month) of the factory / line. In addition, the sales plan data in which the production amount and the delivery date compliance rate are optimized is stored again in the sales plan DB 32.

以上のようにして図2の能力検証の処理(S15)が終了すると、図2のフローチャートの処理(S16)に移行する。
(S16)各工場に設置されている生産計画スケジューラー51は、能力検証で適正と判断された販売計画データを販売計画DB32から入力する。このとき、各工場の生産計画スケジューラー51では、販売計画DB32から、自工場に関するデータのみ抽出して、入力する。生産計画スケジューラー51は、納期(荷揃予定日)を基準に注文毎に各生産ラインの製造順番を決定する。そして、注文毎に各生産ラインの通過予定日及び時刻を決定する。注文毎に各生産ラインの製造順番を決定する際には、例えばそれぞれの注文で指定された納期と生産製造プロセスとそのプロセスの生産能力とから、生産ラインの生産量が最大となるか或いはコストが最小となるように、生産製造工程の負荷検証と調整を行って注文毎の荷揃予定日を算出する。なお、この作成情報自体は、一般的な技術であるからここでの説明は省略する。また、生産計画スケジューラー51で、生産計画を作成した結果、詳細条件により生産できないとなった注文があるか否かの生産可否判断を行い、その情報を販売計画処理部31に出力して、再検討する。例えば、生産計画スケジューラー51で最適な生産計画を作成する際に、生産対象から除外された注文データを販売計画処理部31に出力し、販売計画データを変更するようにすればよい。そして、変更・調整された販売計画に基づいて、実現可能な生産計画となるまで、繰り返される。そして、生産計画で適正と判断された結果、販売計画が確定するとともに、生産計画も確定する。この生産計画データは、生産計画DB52に格納される。
これによって、販売計画の注文の数量を累積計算して例えば1ヶ月の販売量(荷揃量)が算出され、また、その販売量(荷揃量)が注文単位で構成されることになる。また、販売生産計画システム1では、販売計画DB32に格納された販売計画の納期(予定日)を端末33に表示させる。これにより作業者が目視にて納期(予定日)を確認することが可能となる。
When the capability verification process (S15) in FIG. 2 is completed as described above, the process proceeds to the process (S16) in the flowchart in FIG.
(S16) The production plan scheduler 51 installed in each factory inputs from the sales plan DB 32 the sales plan data determined to be appropriate in the capacity verification. At this time, the production plan scheduler 51 of each factory extracts and inputs only data relating to the own factory from the sales plan DB 32. The production plan scheduler 51 determines the production order of each production line for each order on the basis of the delivery date (planned assortment date). And the scheduled passage date and time of each production line are determined for every order. When determining the production order of each production line for each order, for example, the production amount of the production line is maximized or the cost is determined based on the delivery date, production production process, and production capacity of the process specified in each order. In order to minimize the load, the load verification and adjustment of the production and manufacturing process are performed to calculate the scheduled date of assortment for each order. Note that the creation information itself is a general technique, and thus description thereof is omitted here. In addition, as a result of creating the production plan by the production plan scheduler 51, it is determined whether or not there is an order that cannot be produced due to the detailed conditions, and whether the production is possible or not is output to the sales plan processing unit 31, consider. For example, when an optimal production plan is created by the production plan scheduler 51, the order data excluded from the production target may be output to the sales plan processing unit 31 to change the sales plan data. Then, based on the changed / adjusted sales plan, the process is repeated until the production plan becomes feasible. As a result of determining that the production plan is appropriate, the sales plan is confirmed and the production plan is also confirmed. This production plan data is stored in the production plan DB 52.
As a result, the quantity of orders in the sales plan is cumulatively calculated to calculate, for example, a monthly sales amount (assortment amount), and the sales amount (assortment amount) is configured in order units. In the sales production planning system 1, the delivery date (scheduled date) of the sales plan stored in the sales plan DB 32 is displayed on the terminal 33. As a result, the worker can visually confirm the delivery date (scheduled date).

(S17)輸送計画処理部61は、生産計画DB52に格納された生産計画データから、輸送対象データを抽出し、その注文データを輸送対象注文DB62に格納する。そして、生産計画の注文情報の納期を基準として、納入先と納期毎に集約して、輸送計画の対象となる輸送一車両あたりの注文を特定し、稼働予定車両DB63に格納されている輸送に使える車両情報をもとに、輸送計画の対象となる一車両あたりの注文を特定して配車計画を作成し、その配車計画に基づいて輸送計画を作成する。
なお、上記において、需要家の使用予定の数量、納期等が変更された場合には、販売計画に用いられる個々の予定注文の情報も変更されることになるが、そのような場合には端末21、23を操作して該当する予定注文の情報(販売計画DB32)を変更して、上記の演算処理を繰り返す。それによって、販売計画データが再作成されて納期(荷揃予定日)も変更されることになる。また、工場の生産計画スケジューラー51で生産計画データも作成され、各製造ラインの通過予定日、時刻も変更される。この工場の生産スケジューラー51の処理の結果、例えば荷揃予定日が遅く顧客への納入遅れが発生するような場合には、販売計画で想定した納期を早めて荷揃予定日を早いタイミングに変更することができる。
(S17) The transport plan processing unit 61 extracts transport target data from the production plan data stored in the production plan DB 52, and stores the order data in the transport target order DB 62. Then, based on the delivery date of the order information of the production plan, it is aggregated for each delivery destination and delivery date, the order for each transportation vehicle subject to transportation planning is specified, and the transportation stored in the scheduled operation vehicle DB 63 Based on the vehicle information that can be used, an order for each vehicle that is the target of the transportation plan is identified and a vehicle dispatch plan is created, and a transportation plan is created based on the vehicle dispatch plan.
In addition, in the above, when the customer's scheduled use quantity, delivery date, etc. are changed, the information of each scheduled order used in the sales plan will also be changed. In such a case, the terminal 21 and 23 are operated, the information of the corresponding scheduled order (sales plan DB32) is changed, and said arithmetic processing is repeated. As a result, the sales plan data is re-created and the delivery date (scheduled assortment date) is also changed. In addition, production plan data is also created by the production plan scheduler 51 of the factory, and the scheduled passage date and time of each production line are also changed. As a result of the processing of the production scheduler 51 of this factory, for example, when the scheduled date of assortment is late and delivery delay to the customer occurs, the estimated date of assortment in the sales plan is advanced and the scheduled date of assortment is changed to an earlier timing. can do.

以上のように本実施形態においては、非リピート注文の注文予定も過去実績に基づいてリピート注文と同じ形式に変換し、全てのデータを注文明細データの形態で、注文単位で計画を作成しているので、例えば、需要家の使用予定が変更された場合においても対応し易いものとなっており、顧客の使用予定が変更された場合には、迅速に販売計画及び生産計画を変更することにより、無駄な製品を生産しなくても済むようになり、不良在庫を削減することができる。また、注文単位で販売計画及び生産計画を作成するようにしたので、販売と生産の状況を注文単位で可視化することができる。   As described above, in the present embodiment, the order schedule of non-repeat orders is also converted into the same format as repeat orders based on past results, and a plan is created for each order in the form of order details data. Therefore, for example, it is easy to respond when the customer's use schedule is changed, and when the customer's use schedule is changed, the sales plan and production plan can be changed quickly. As a result, it is not necessary to produce useless products, and defective stock can be reduced. In addition, since the sales plan and production plan are created for each order, the sales and production status can be visualized for each order.

また、販売計画が精度の高いものとなっているので、その販売計画をもとに生産計画を作成し、その生産計画どおりに製造すれば顧客の使用予定に合わせて製造することができ、設備の生産能力を無駄なく使用することができる上に、不良在庫を削減することができる。
また、輸送計画は、上記のように高精度に販売生産計画を作成することができるので、荷揃完了時点まで待つ必要がなく、納期(又は荷揃いの予定日)をもとに作成することができ、1〜2ヶ月先を考慮しながら輸送資源を効率的に活用することができる。
さらには、需要家に対して、注文単位で、その納期を提供することが可能となり、需要家側における製品の使用計画にも有効活用されることになる。
In addition, since the sales plan is highly accurate, if a production plan is created based on the sales plan and manufactured according to the production plan, it can be manufactured according to the customer's usage schedule. Production capacity can be used without waste, and defective inventory can be reduced.
In addition, since the production plan can be created with high accuracy as described above, it is not necessary to wait until the completion of assortment, and the transportation plan should be created based on the delivery date (or scheduled assortment date). It is possible to efficiently use transportation resources while considering one to two months ahead.
Furthermore, it is possible to provide the customer with a delivery date for each order, and it is effectively utilized for the product use plan on the consumer side.

本発明の実施形態1に係る販売生産計画システムの構成を示すブロック図である。It is a block diagram which shows the structure of the sales production planning system which concerns on Embodiment 1 of this invention. 図1の販売生産計画作成システムの処理過程を示したフローチャートである。It is the flowchart which showed the process of the sales production plan creation system of FIG. 基本注文受注実績の情報の構成例を示したものである。The example of a structure of the information of a basic order receipt track record is shown. 基本予定注文の情報の構成例を示したものである。The example of a structure of the information of a basic scheduled order is shown. 販売計画注文を工場のライン毎に振り分けた例を示すものである。It shows an example of distribution of sales plan orders for each line of a factory. 工場のラインにおける能力、販売計画の注文数量の合計及び両者の差を示したものである。It shows the capacity in the factory line, the total order quantity in the sales plan, and the difference between the two. 予定注文入力画面の例を示した図である。It is the figure which showed the example of the scheduled order input screen. 基本注文予定入力画面の例を示した図である。It is the figure which showed the example of the basic order schedule input screen. 一般注文予定入力画面の例を示した図である。It is the figure which showed the example of the general order schedule input screen. 実績注文データの例を示した図である。It is the figure which showed the example of performance order data. 能力検証結果確認画面の例を示した図である。It is the figure which showed the example of the capability verification result confirmation screen. 注文明細表示画面の例を示した図である。It is the figure which showed the example of the order details display screen. 評価結果確認画面の例を示した図である。It is the figure which showed the example of the evaluation result confirmation screen. 図2の処理(S15)の詳細を示したフローチャートである。It is the flowchart which showed the detail of the process (S15) of FIG. 図14の処理(S110)の詳細を示したフローチャートである。It is the flowchart which showed the detail of the process (S110) of FIG. 一般注文のデータの例を示した図である。It is the figure which showed the example of the data of a general order. 注文データ(リピート注文と非リピート注文のデータ)の概念図である。It is a conceptual diagram of order data (data of repeat orders and non-repeat orders). 生産計画に必要なデータの概念図である。It is a conceptual diagram of the data required for a production plan.

符号の説明Explanation of symbols

1 販売生産計画システム、10 受注システム、11 受注処理部、12 納期注文DB、13 過去実績注文DB、20 見込注文生成システム、21 端末、22 仮納期注文生成部、23 仮納期注文DB、25 端末、26 予定注文生成部、27 予定注文DB、30 販売計画システム、31 販売計画処理部、 32 販売計画DB、33 端末、40 能力検証システム、41 能力検証処理部、42 月間生産能力DB、50 生産管理システム、51 生産計画スケジューラー、52 生産計画DB、60 輸送計画システム、61 輸送計画処理部、62 輸送対象注文DB、63 稼働予定車両DB、64 輸送計画DB、65 端末。   DESCRIPTION OF SYMBOLS 1 Sales production planning system, 10 Order reception system, 11 Order reception processing part, 12 Delivery date order DB, 13 Past performance order DB, 20 Expected order generation system, 21 Terminal, 22 Temporary delivery date order generation part, 23 Temporary delivery date order DB, 25 Terminal , 26 Scheduled order generation unit, 27 Scheduled order DB, 30 Sales planning system, 31 Sales plan processing unit, 32 Sales plan DB, 33 Terminal, 40 Capacity verification system, 41 Capacity verification processing unit, 42 Monthly production capacity DB, 50 Production Management system, 51 Production plan scheduler, 52 Production plan DB, 60 Transport plan system, 61 Transport plan processing unit, 62 Transport target order DB, 63 Scheduled operation vehicle DB, 64 Transport plan DB, 65 terminal.

Claims (9)

種々の素材製品を商品として製造する素材生産企業における販売計画及び生産計画を作成するための販売生産計画システムであって、
既に受注した製品の実績注文データが格納される第1の記憶手段と、
既に出荷済の過去実績データが格納されている第2の記憶手段と、
リピート注文の見込注文データが格納される第3の記憶手段と、
非リピート注文の見込注文データが格納される第4の記憶手段と、
販売計画データが格納される第5の記憶手段と、
納期及び数量を除いた製造仕様の情報が予め設定されたフォーマット・データを用いて、需要家における製品の使用予定に基づいて、納期及び数量の入力を促す表示を端末にし、該入力された納期及び数量により、前記実績注文データと同じデータ構造のリピート注文の見込注文データを作成し、前記第3の記憶手段に格納する第1の見込み注文作成手段と、
需要家における製品の使用予定に基づいて、納期及び数量の入力を促す表示を端末に行い、該入力された納期、数量と、前記第1の記憶手段及び前記第2の記憶手段の少なくとも一方に格納されている、当該製品に対応するデータの製造仕様の情報とに基づいて、前記実績注文データと同じデータ構造の非リピート注文の見込注文データを作成し、前記第4の記憶手段に格納する第2の見込み注文作成手段と、
前記実績注文データ、前記リピート注文の見込注文データ及び前記非リピート注文の見込注文データから販売計画データを作成し、前記第5の記憶手段に格納する販売計画データ作成手段と、
所定期間における、前記販売計画データの注文の合計数量と前記注文が指定している製造ラインの製造能力とを比較する能力検証手段と、
前記注文の合計数量が前記製造能力範囲になるように、前記実績注文データ、前記リピート注文の見込注文データ及び前記非リピート注文の見込注文データの少なくとも何れかの、納期及び製造通過工程のデータの少なくとも一方を変更して販売計画を調整する販売計画データ調整手段と
を備え、
前記各手段において注文単位で処理を行って販売計画を作成することを特徴とする販売生産計画システム。
A sales production planning system for creating a sales plan and a production plan in a material production company that manufactures various material products as products,
First storage means for storing the actual order data of the products that have already been ordered;
A second storage means for storing past performance data that has already been shipped;
Third storage means for storing expected order data for repeat orders;
Fourth storage means for storing expected order data of non-repeat orders;
Fifth storage means for storing sales plan data;
Using format data in which manufacturing specification information excluding the delivery date and quantity is set in advance, the display prompting the customer to input the delivery date and quantity based on the planned use of the product by the consumer is used as the terminal, and the inputted delivery date And a first prospective order creating means for creating expected order data of a repeat order having the same data structure as the actual order data, and storing it in the third storage means, according to the quantity;
A display prompting the terminal to input the delivery date and quantity is performed on the terminal based on the use schedule of the product in the consumer, and the inputted delivery date and quantity are displayed on at least one of the first storage means and the second storage means. Based on the stored manufacturing specification information of the data corresponding to the product, non-repeat order prospective order data having the same data structure as the actual order data is created and stored in the fourth storage means. A second prospective order creation means;
Sales plan data creation means for creating sales plan data from the actual order data, the expected order data for the repeat order and the expected order data for the non-repeat order, and storing the data in the fifth storage means;
Capacity verification means for comparing the total quantity of orders in the sales plan data with the manufacturing capacity of the production line specified by the orders in a predetermined period;
In order for the total quantity of the order to fall within the manufacturing capacity range, at least one of the actual order data, the expected order data of the repeat order, and the expected order data of the non-repeat order, A sales plan data adjusting means for adjusting the sales plan by changing at least one of them,
A sales production planning system characterized in that a sales plan is created by performing processing for each order in each means.
前記販売計画データ調整手段は、さらに、
イ)製造ラインの生産量
ロ)納期遵守率
を最適化の制約条件として、前記実績注文データ及び前記見込注文データの少なくとも一方の、納期及び製造通過工程のデータの少なくとも一方を変更することを特徴とする請求項1記載の販売生産計画システム。
The sales plan data adjustment means further includes:
B) Production volume on production line b) Delivery rate compliance rate
2. The sales production planning system according to claim 1, wherein at least one of delivery date and production pass process data of at least one of the actual order data and the expected order data is changed under the restriction condition of optimization.
前記販売計画データ調整手段で調整された販売計画データを入力し、該販売計画データに基づいて、生産製造プロセスの通過ラインのスケジューリングを行うことにより、各ラインの予定通過日及び時刻を決定して、生産計画を作成する生産計画作成手段を、さらに備えたことを特徴とする請求項1又は2に記載の販売生産計画システム。   By inputting the sales plan data adjusted by the sales plan data adjusting means and scheduling the passage lines of the production manufacturing process based on the sales plan data, the scheduled passage date and time of each line are determined. The sales production planning system according to claim 1, further comprising production plan creation means for creating a production plan. 既に受注した製品の実績注文データが格納される第1の記憶手段と、既に出荷済の過去実績データが格納されている第2の記憶手段と、リピート注文の見込注文データが格納される第3の記憶手段と、非リピート注文の見込注文データが格納される第4の記憶手段と、販売計画データが格納される第5の記憶手段とを備える、種々の素材製品を商品として製造する素材生産企業における販売計画及び生産計画を作成するための販売生産計画システムの動作方法であって、First storage means for storing actual order data of products that have already been ordered, second storage means for storing past actual result data that has already been shipped, and third storage for storing expected order data for repeat orders Production means for producing various material products as commodities, comprising: a storage means for storing non-repeat orders, fourth storage means for storing prospective order data, and a fifth storage means for storing sales plan data An operation method of a sales production planning system for creating a sales plan and a production plan in a company,
納期及び数量を除いた製造仕様の情報が予め設定されたフォーマット・データを用いて、需要家における製品の使用予定に基づいて、納期及び数量の入力を促す表示を端末にし、該入力された納期及び数量により、前記実績注文データと同じデータ構造のリピート注文の見込注文データを作成し、前記第3の記憶手段に格納する第1の見込み注文ステップと、Using format data in which manufacturing specification information excluding the delivery date and quantity is set in advance, the display prompting the customer to input the delivery date and quantity based on the planned use of the product by the consumer is used as the terminal, and the inputted delivery date And a first prospective order step of creating expected order data of a repeat order having the same data structure as the actual order data according to the quantity and storing the data in the third storage means;
需要家における製品の使用予定に基づいて、納期及び数量の入力を促す表示を端末に行い、該入力された納期、数量と、前記第1の記憶手段及び前記第2の記憶手段の少なくとも一方に格納されている、当該製品に対応するデータの製造仕様の情報とに基づいて、前記実績注文データと同じデータ構造の非リピート注文の見込注文データを作成し、前記第4の記憶手段に格納する第2の見込み注文作成ステップと、A display prompting the terminal to input the delivery date and quantity is performed on the terminal based on the use schedule of the product in the consumer, and the inputted delivery date and quantity are displayed on at least one of the first storage means and the second storage means. Based on the stored manufacturing specification information of the data corresponding to the product, non-repeat order prospective order data having the same data structure as the actual order data is created and stored in the fourth storage means. A second potential order creation step;
前記実績注文データ、前記リピート注文の見込注文データ及び前記非リピート注文の見込注文データから販売計画データを作成し、前記第5の記憶手段に格納する販売計画データ作成ステップと、A sales plan data creating step of creating sales plan data from the actual order data, the expected order data of the repeat order and the expected order data of the non-repeat order, and storing in the fifth storage means;
所定期間における、前記販売計画データの注文の合計数量と前記注文が指定している製造ラインの製造能力とを比較する能力検証ステップと、A capability verification step of comparing a total quantity of orders in the sales plan data with a manufacturing capacity of a production line specified by the orders in a predetermined period;
前記注文の合計数量が前記製造能力の範囲内になるように、前記実績注文データ、前記リピート注文の見込注文データ及び前記非リピート注文の見込注文データの少なくとも何れかの、納期及び製造通過工程のデータの少なくとも一方を変更して販売計画を調整する販売計画データ調整ステップとThe delivery date and the production passing process of at least one of the actual order data, the expected order data of the repeat order, and the expected order data of the non-repeat order so that the total quantity of the order falls within the range of the manufacturing capacity A sales plan data adjustment step that adjusts the sales plan by changing at least one of the data;
を実行し、Run
前記各ステップにおいて注文単位で処理を行って販売計画を作成することを特徴とする販売生産計画システムの動作方法。A method for operating a sales production planning system, wherein a sales plan is created by performing processing in units of orders in each step.
前記販売計画データ調整ステップで調整された販売計画データを入力し、該販売計画データに基づいて、生産製造プロセスの通過ラインのスケジューリングを行うことにより、各ラインの予定通過日及び時刻を決定して、生産計画を作成する生産計画作成ステップを、さらに備えたことを特徴とする請求項4に記載の販売生産計画システムの動作方法。 By inputting the sales plan data adjusted in the sales plan data adjustment step and scheduling the passage lines of the production manufacturing process based on the sales plan data, the scheduled passage date and time of each line are determined. The operation method of the sales production planning system according to claim 4, further comprising a production plan creation step of creating a production plan . 製造プロセスの通過ラインのスケジューリングがなされた注文の数量を累積して所定期間内の生産量を算出するとともに、その計画された生産量を注文単位で特定して、該注文が生産可能かどうかを判断し、生産できない場合には、前記販売計画データ調整ステップで販売計画を調整することを特徴とする請求項5記載の販売生産計画システムの動作方法。 Accumulate the quantity of orders that have been scheduled for the passing line of the manufacturing process to calculate the production volume within a given period, and specify the planned production volume for each order to determine whether the order can be produced. 6. The method of operating a sales production planning system according to claim 5, wherein if the production cannot be determined, the sales plan is adjusted in the sales plan data adjustment step . 需要家への製品輸送計画を、前記生産計画に基づき、前記実績注文及び前記見込注文の納期を基準として作成することを特徴とする請求項5又は6に記載の販売生産計画システムの動作方法。 7. The operation method of the sales production planning system according to claim 5 or 6, wherein a product transportation plan to a consumer is created based on the delivery date of the actual order and the expected order based on the production plan. 前記実績注文データまたは前記見込注文データの少なくとも一方が変更された場合には、上記のステップを繰り返して販売計画及び生産計画を作成し直すことを特徴とする請求項4〜7の何れかに記載の販売生産計画システムの動作方法。 The sales plan and the production plan are recreated by repeating the above steps when at least one of the actual order data or the expected order data is changed. Method of sales and production planning system. コンピュータを、請求項1〜3の何れかに記載の前記第1の見込み注文作成手段、前記第2の見込み注文作成手段、前記販売計画データ作成手段、前記能力検証手段、前記販売計画データ調整手段として機能させるためのコンピュータプログラム。 4. The computer according to claim 1, wherein the first prospective order creation means, the second prospective order creation means, the sales plan data creation means, the capability verification means, and the sales plan data adjustment means. Computer program to function as .
JP2007308443A 2007-11-29 2007-11-29 Sales production planning system, operation method of sales production planning system, and computer program Active JP5089352B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007308443A JP5089352B2 (en) 2007-11-29 2007-11-29 Sales production planning system, operation method of sales production planning system, and computer program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007308443A JP5089352B2 (en) 2007-11-29 2007-11-29 Sales production planning system, operation method of sales production planning system, and computer program

Publications (2)

Publication Number Publication Date
JP2009134399A JP2009134399A (en) 2009-06-18
JP5089352B2 true JP5089352B2 (en) 2012-12-05

Family

ID=40866237

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007308443A Active JP5089352B2 (en) 2007-11-29 2007-11-29 Sales production planning system, operation method of sales production planning system, and computer program

Country Status (1)

Country Link
JP (1) JP5089352B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015207086A (en) * 2014-04-18 2015-11-19 株式会社Jvcケンウッド Connected value chain support system and connected value chain support method
KR102184007B1 (en) * 2017-07-28 2020-11-27 주식회사 엘지화학 Method for predicting content of residual monomer and preparation method of polycarbonate resin
JP7489082B2 (en) * 2019-08-23 2024-05-23 株式会社オーティス Order Product Identification Support System
CN113657647B (en) * 2021-07-16 2023-10-10 东华大学 Order distribution method for textile and clothing industry Internet

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05250392A (en) * 1992-03-06 1993-09-28 Dainippon Printing Co Ltd Automatic issue system for repeat order reception ledger
JP2002329108A (en) * 2001-05-01 2002-11-15 Sumitomo Metal Ind Ltd Distribution managing method for raw material product
JP3744441B2 (en) * 2002-03-01 2006-02-08 Jfeスチール株式会社 Steel intermediate product and steel product production plan creation method, apparatus thereof, program for realizing the method or apparatus
JP4769920B2 (en) * 2005-04-28 2011-09-07 新日本製鐵株式会社 Production plan creation system for steel products and production plan creation method thereof
JP4883939B2 (en) * 2005-05-31 2012-02-22 新日本製鐵株式会社 Steel product production shipment plan creation system and production shipment plan creation method thereof

Also Published As

Publication number Publication date
JP2009134399A (en) 2009-06-18

Similar Documents

Publication Publication Date Title
US6415195B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US6393332B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
CN101329746A (en) System and method for automatically arranging production plan
Weng Strategies for integrating lead time and customer-order decisions
AU769097B2 (en) System and method of scheduling manufacturing resources
JP5089352B2 (en) Sales production planning system, operation method of sales production planning system, and computer program
US6415194B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US20030171963A1 (en) Production planning method and system for production planning
US6397118B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
JP5056962B2 (en) Sales production delivery system and sales production delivery method for steel strip products
JP2010244228A (en) Support method for efficiency promotion of supply chain
JP4716151B2 (en) Sales production delivery system and sales production delivery method for steel strip products
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program
JP2847276B2 (en) Delivery management system for coiled products
JP2009042810A (en) Efficiency improvement support method for supply chain
WO2024147352A1 (en) Device for producing steel sheets, order/production/sales assistance device, method for ordering/ producing/selling steel sheets, and program for ordering/ producing /selling steel sheets
JP5068845B2 (en) A method and system for integrated production management with full development of core management process using management process matrix table
JP2008269214A (en) Support method for improving supply chain efficiency
JP2004287693A (en) Core management process full-expansion type integrated production management method and system using management process matrix table
Luo et al. A Case Study of Supply Chain Management in a Manufacturing Company in China
JP2847275B2 (en) Delivery management system for coiled products
JP4718960B2 (en) Supply chain planning program and supply chain planning device
Comenzo Process Improvement at Sjogren Industries
Schönsleben The MRP II/ERP Concept: Business Processes and Methods
Šurka et al. Implementation of manufacturing resource planning issues in practice

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100716

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120227

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120327

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120525

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120612

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120809

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120828

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120911

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150921

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5089352

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250