JP5068845B2 - A method and system for integrated production management with full development of core management process using management process matrix table - Google Patents

A method and system for integrated production management with full development of core management process using management process matrix table Download PDF

Info

Publication number
JP5068845B2
JP5068845B2 JP2010138081A JP2010138081A JP5068845B2 JP 5068845 B2 JP5068845 B2 JP 5068845B2 JP 2010138081 A JP2010138081 A JP 2010138081A JP 2010138081 A JP2010138081 A JP 2010138081A JP 5068845 B2 JP5068845 B2 JP 5068845B2
Authority
JP
Japan
Prior art keywords
management
plan
production
management process
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2010138081A
Other languages
Japanese (ja)
Other versions
JP2010257476A (en
Inventor
隆雄 岩田
実 小出
弘 工藤
英寿 柴田
好夫 星
淳 高橋
監市 井坂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Resonac Corp
Original Assignee
Hitachi Chemical Co Ltd
Hitachi Ltd
Showa Denko Materials Co Ltd
Resonac Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Chemical Co Ltd, Hitachi Ltd, Showa Denko Materials Co Ltd, Resonac Corp filed Critical Hitachi Chemical Co Ltd
Priority to JP2010138081A priority Critical patent/JP5068845B2/en
Publication of JP2010257476A publication Critical patent/JP2010257476A/en
Application granted granted Critical
Publication of JP5068845B2 publication Critical patent/JP5068845B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/40Minimising material used in manufacturing processes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は複数の管理工程からなる製造ラインでの製品の生産を管理する統合生産管理システムに関し、特に受注変動や生産実績変動を踏まえて、受注生産品または見込み生産品に対し、顧客ニーズの少量多品種化・短納期化及び製品特性の高度化に対応する為の製造ライン工程の複雑化に対応するため、コア管理工程を中軸とした工程スケジューリング及びMRP(資材所要量計画)を含む実需対応型の生産管理システムの短サイクル化によって、納期回答及び生産管理情報のフィードバックの即時化、棚卸資産の最小化、各設備稼働効率の最大化を実現させる統合生産管理システムに適用して有効な技術に関するものである。   The present invention relates to an integrated production management system that manages the production of products on a production line composed of a plurality of management processes, and in particular, in consideration of fluctuations in orders and fluctuations in production results, a small amount of customer needs with respect to order-made products or prospective products. Responding to actual demand, including process scheduling and MRP (material requirements planning) with core management processes at the core, to cope with the complexity of production line processes to cope with increasing variety and shortening of delivery times and sophistication of product characteristics Technology that is effective when applied to an integrated production management system that realizes immediate response of delivery date and feedback of production management information, minimization of inventory assets, and maximization of operating efficiency of each facility by shortening the cycle of the production management system It is about.

従来、複数種類の工程から成り立つ上工程に対して分流し得る複数の下流工程が存在する多品種の物品を加工・製造できる製造ラインにおいて、製造条件等により、下工程の製造手配量を再編成させ、工程指示量を適正化し、品種毎の必要量の変動に対応可能な生産管理方法を提供するものが提案されている(例えば特許文献1参照)。   Conventionally, in a production line that can process and manufacture a wide variety of articles that have multiple downstream processes that can be divided with respect to the upper process that consists of multiple types of processes, the production order of the lower process is reorganized according to the manufacturing conditions, etc. Thus, there has been proposed a method for optimizing the process instruction amount and providing a production management method capable of coping with fluctuations in the necessary amount for each type (see, for example, Patent Document 1).

特開平11−151642号公報JP-A-11-151642

しかし前記従来技術では、複数種類の多段工程が合流同時処理する多品種の製造ライン等、生産プロセス一般に適用することが出来る生産管理の方法が提案されていない。特に、顧客への回答納期、各工程の材料所要量及び物質収支、リードタイム、工数等の生産性情報をフィードバックさせ、各工程の負荷山積計画等の短サイクル・ローリングによる納期遵守、棚卸資産縮減と原価低減の仕掛け作りの高度化を図り、企業経営の視点からサプライチェーン経営効率の最大化を実現する生産管理プロセス全体の操業計画最適化の考慮がされていなかった。   However, the conventional technology has not proposed a production management method that can be applied to general production processes such as a multi-product production line in which a plurality of types of multi-stage processes are combined and processed simultaneously. In particular, we will provide feedback on product delivery information such as the response delivery date to customers, material requirements and material balance of each process, lead time, man-hours, etc., comply with the delivery date by short cycle rolling such as load pile planning of each process, reduce inventory In addition, it was not considered to optimize the operation plan of the entire production management process, aiming at the sophistication of the mechanism of cost reduction and the optimization of supply chain management efficiency from the viewpoint of corporate management.

例えば、工程Xからの製品Aと工程Yからの製品Bについて同じ処理を行う場合、それらの複数の製品A及びBを工程Zで同時に処理することにより生産性の向上が見込めるが、その際に工程Xで製品Aの処理が遅れると、他方の製品Bの工程Zでの処理も遅れることになり、製品Aだけでなく製品Bの生産性も低下してしまう。しかしながら前記従来技術では、前記の工程Zの様に基軸となる工程が製造ライン中に存在しているかどうかを考慮していないという問題がある。   For example, when the same processing is performed on the product A from the process X and the product B from the process Y, the productivity can be improved by simultaneously processing the products A and B in the process Z. If the process of the product A is delayed in the process X, the process of the other product B in the process Z is also delayed, and the productivity of the product B as well as the product A is reduced. However, the conventional technique has a problem that it does not consider whether or not a process serving as a basic axis exists in the production line as in the process Z.

本発明の目的は上記問題を解決し、生産プロセス全体にわたる操業計画の一元的立案による顧客要求納期への対応力向上と棚卸資産の最小化を行うことが可能な技術を提供することにある。本発明の他の目的は生産性情報の即時フィードバックによる設備稼働率・生産性の最大化を実現することが可能な技術を提供することにある。   An object of the present invention is to provide a technique capable of solving the above-described problems and improving the ability to meet customer demand delivery date and minimizing inventory by centralized planning of an operation plan over the entire production process. Another object of the present invention is to provide a technology capable of maximizing equipment operation rate and productivity by immediate feedback of productivity information.

本発明は、複数の管理工程からなる製造ラインでの製品の生産を管理する統合生産管理システムにおいて、生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程の工程計画を基点として上流及び下流の工程計画を順次立案するものである。   The present invention is based on the process plan of the core management process that is the basis for controlling the entire operation plan in the production process in the integrated production management system that manages the production of the product on the production line composed of a plurality of management processes. The upstream and downstream process plans are developed in sequence.

本発明の統合生産管理システムでは、先ず各管理工程の情報を格納している管理工程マトリックステーブルを参照し、その管理工程マトリックステーブル中の管理工程の情報が、生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程の設定基準に該当するかどうかを判定することにより、前記コア管理工程を設定する。例えば、その生産プロセスを構成する複数の管理工程の内、多品種の製品を同時に処理する工程、リードタイムの最も長い工程、または多品種の材料を多量に消費する工程等の設定基準に該当するものを前記コア管理工程に設定する。そして、受注残情報や見込み生産情報から決定される最終的な製品生産量と、前記設定したコア管理工程から最下流工程までの各工程での製品歩留りとを用いて当該コア管理工程で処理する必要のある生産必要量を算出する。   In the integrated production management system of the present invention, first, a management process matrix table storing information of each management process is referred to, and the management process information in the management process matrix table controls the entire operation plan in the production process. The core management process is set by determining whether or not the setting criteria of the core management process, which is a basic axis for doing so, is met. For example, among the multiple management processes that make up the production process, it corresponds to setting criteria such as a process that processes multiple types of products simultaneously, a process that has the longest lead time, or a process that consumes a large amount of various types of materials. A thing is set in the core management process. Then, the final product production amount determined from the backorder information and the expected production information and the product yield in each process from the set core management process to the most downstream process are processed in the core management process. Calculate the necessary production requirements.

次に、前記算出された生産必要量の製品を生産する際のコア管理工程での負荷山積展開シミュレーションを行って当該コア管理工程における工程計画を立案し、前記設定したコア管理工程を基点として当該コア管理工程の上流及び下流に位置する管理工程の工程計画を順次立案するドミノ連動を実行する。このドミノ連動では、例えば、各管理工程の情報を格納する為の管理工程マトリックステーブルに、その管理工程で処理される製品の製品ラインを識別する為の識別情報を格納しておき、前記コア管理工程の管理工程マトリックスに格納されている前記識別情報と同じ識別情報を持つ管理工程を、管理工程コードの順にコア管理工程から上流及び下流へ順に辿り、その前のステップで立案した工程計画の内容を基にその管理工程での工程計画を立案することによって、当該コア管理工程の上流及び下流の双方向に位置する全管理工程の工程計画を順次立案する。   Next, a load pile development simulation in the core management process when producing the product of the calculated production required amount is performed, a process plan in the core management process is drawn up, and the core management process is used as a base point. Execute Domino linkage that sequentially creates process plans for management processes located upstream and downstream of the core management process. In this Domino linkage, for example, in the management process matrix table for storing information of each management process, identification information for identifying the product line of the product processed in the management process is stored, and the core management The management process having the same identification information as the identification information stored in the process management process matrix is traced in the order of the management process code from the core management process to the upstream and downstream, and the contents of the process plan formulated in the previous step Based on the above, the process plan in the management process is drawn up, so that the process plans of all the management processes located in both directions upstream and downstream of the core management process are sequentially made.

前記の様にして全管理工程の工程計画が立案されると、中長期売上計画・月次生産計画及び週次工程計画に基づいて、資材所要量計画を製品勘定部門毎に策定し、部門固有資材、部門共通資材及び中長期戦略資材を分類体系管理して日別MRPを展開し、資材の発注を依頼する処理を行う。   When the process plan for all management processes is established as described above, a material requirement plan is formulated for each product account department based on the medium- to long-term sales plan, monthly production plan, and weekly process plan. The material, department common material and medium- and long-term strategic materials are classified and managed, and the daily MRP is developed, and processing for requesting material order is performed.

また、前記の様にしてコア管理工程の工程計画を立案した際や全工程計画を立案した後に、その立案した工程計画の内容と実際の製造ラインでの工程実績進捗情報の内容とを比較し、進捗実績情報に示された設備稼働率や計画に対する進捗状況に応じて日程や生産量を変更する等の工程計画の微調整を行う様にしても良い。更に、前記工程計画の内容と工程実績進捗情報の内容とを比較して納期遅れが発生するかどうかを判定し、納期遅れの発生が検出された場合にアラート情報を出力する様にしても良い。   In addition, when the process plan of the core management process is made as described above or after making the entire process plan, the contents of the prepared process plan are compared with the contents of the process performance progress information on the actual production line. Further, fine adjustment of the process plan such as changing the schedule and the production amount according to the equipment operation rate indicated in the progress record information and the progress status with respect to the plan may be performed. Furthermore, the contents of the process plan may be compared with the contents of the process performance progress information to determine whether or not a delivery date delay occurs, and alert information may be output when the delivery date delay is detected. .

前記の様に本発明では、生産プロセス全体をコントロールする上で特に重要なコア管理工程での工程計画を最適化しているので、ある製造品の処理の遅れが他の製造品に波及するのを防ぐことにより生産プロセス全体の遅れをできるだけ減らし、また、ある製造品の処理待ちに伴う仕掛かりを減らして資産を効率的に使用することができる。   As described above, in the present invention, the process plan in the core management process, which is particularly important in controlling the entire production process, is optimized, so that a delay in processing of one manufactured product can affect other manufactured products. By preventing this, the delay in the entire production process can be reduced as much as possible, and the in-process associated with the processing of a certain manufactured product can be reduced to efficiently use the assets.

以上の様に本発明の統合生産管理システムによれば、生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程の工程計画を基点として上流及び下流の工程計画を順次立案するので、生産プロセス全体にわたる操業計画の一元的立案による顧客要求納期への対応力向上と棚卸資産の最小化を行うことが可能である。   As described above, according to the integrated production management system of the present invention, the upstream and downstream process plans are sequentially developed based on the process plan of the core management process which is the basis for controlling the entire operation plan in the production process. In addition, it is possible to improve the ability to meet customer demand delivery date and minimize inventory by centralized planning of operation plans throughout the production process.

本発明によれば生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程の工程計画を基点として上流及び下流の工程計画を順次立案するので、生産プロセス全体にわたる操業計画の一元的立案による顧客要求納期への対応力向上と棚卸資産の最小化を行うことが可能である。   According to the present invention, since the upstream and downstream process plans are sequentially formulated based on the process plan of the core management process which is the basis for controlling the entire operation plan in the production process, the operation plan over the entire production process is unified. It is possible to improve the ability to respond to customer demand delivery by planning and minimize inventory.

本実施形態の統合生産管理の全体構成を示す図である。It is a figure which shows the whole structure of the integrated production management of this embodiment. 本実施形態の生産計画手段1の全体構成を示す図である。It is a figure which shows the whole structure of the production planning means 1 of this embodiment. 本実施形態の全工程計画展開による工程計画実績MRP変動対応と生産活動実需ローリングの全体構成を示す図である。It is a figure which shows the whole structure of the process plan performance MRP fluctuation | variation response by the whole process plan expansion | deployment of this embodiment, and production activity actual demand rolling. 本実施形態の管理工程マトリックス、生産性管理基準、製造仕様設計管理、資材発注管理基準のテーブル構成を示す図である。It is a figure which shows the table structure of the management process matrix of this embodiment, productivity management reference | standard, manufacture specification design management, and material order management reference | standard. 本実施形態の計画制約条件及び段取切替時間展開のテーブル構成を示す図である。It is a figure which shows the table structure of the plan constraint conditions of this embodiment, and setup switching time expansion | deployment. 本実施形態の生産計画立案処理の処理フローを示す図である。It is a figure which shows the processing flow of the production plan planning process of this embodiment. 本実施形態のコア管理工程設定処理の処理フローを示す図である。It is a figure which shows the processing flow of the core management process setting process of this embodiment. 本実施形態の複数の管理工程から成る生産プロセスの概要を示す図である。It is a figure which shows the outline | summary of the production process which consists of a some management process of this embodiment. 本実施形態の管理工程マトリックステーブル8の一例を示す図である。It is a figure which shows an example of the management process matrix table 8 of this embodiment. 本実施形態の負荷山積展開シミュレーション処理部33の処理フローを示す図である。It is a figure which shows the processing flow of the load mountain deployment simulation process part 33 of this embodiment. 本実施形態のドミノ連動による全工程計画展開処理の処理フローを示す図である。It is a figure which shows the processing flow of all the process plan expansion | deployment processes by the Domino interlocking of this embodiment. 本実施形態の所要量計画処理部18の処理フローを示す図である。It is a figure which shows the processing flow of the requirement plan process part 18 of this embodiment. 本実施形態の生産必要量策定対象一覧画面のレイアウトを示す図である。It is a figure which shows the layout of the production requirement formulation object list screen of this embodiment. 本実施形態の工程計画・進捗実績管理一覧画面のレイアウトを示す図である。It is a figure which shows the layout of the process plan and progress results management list screen of this embodiment.

以下に複数の管理工程からなる製造ラインでの製品の生産を管理する一実施形態の統合生産管理システムについて説明する。   Hereinafter, an integrated production management system according to an embodiment for managing production of products on a production line including a plurality of management processes will be described.

図1は本実施形態の統合生産管理の全体構成を示す図である。図1に示す様に本実施形態の統合生産管理システムは、生産計画手段1と所要量計画手段2とを備えている。   FIG. 1 is a diagram showing an overall configuration of integrated production management according to the present embodiment. As shown in FIG. 1, the integrated production management system of the present embodiment includes a production planning unit 1 and a requirement planning unit 2.

生産計画手段1は、受注受付処理において製品在庫及び作業仕掛りと既計画確定分への引き当て処理を実施した後に、コア管理工程3に対して負荷山積シミュレーションを行い、前記コア管理工程3を基点として全工程計画を自動展開する手段である。   The production planning means 1 performs a load pile simulation for the core management process 3 after executing the allocation process for the product inventory and work in progress and the already planned fixed amount in the order receiving process. As a means for automatically expanding the entire process plan.

ここで基点となるコア管理工程3は、製造品名毎に製造仕様設計管理テーブル7によって定義される生産プロセス毎にインデックス化された管理工程マトリックステーブル8に基づいて、管理工程毎のリードタイム等を記憶する生産性管理基準テーブル9及び使用資材情報等を記憶する資材発注管理基準テーブル6から後述の設定基準により自動導出することができる様になっている。   Here, the core management process 3 as a base point is based on the management process matrix table 8 indexed for each production process defined by the manufacturing specification design management table 7 for each manufactured product name, and the lead time for each management process is calculated. It can be automatically derived from the productivity management standard table 9 to be stored and the material order management standard table 6 to store the used material information and the like according to the setting standard described later.

すなわちコア管理工程は、優先度1の設定基準である多品種同時処理型工程であるか(複数の多品種同時処理型工程が存在する場合には最上流工程を設定)、優先度2の設定基準であるリードタイム最長管理工程であるか、優先度3の設定基準である材料の多品種多量を消費する工程であるか等の基準により設定される。   In other words, whether the core management process is a multi-product simultaneous process type process that is a priority 1 setting criterion (if there are multiple multi-product simultaneous process processes, the most upstream process is set), or priority 2 is set It is set according to a criterion such as whether it is the longest lead time management step that is a reference, or a step that consumes a large variety of materials, which is a priority 3 setting criterion.

尚、全工程計画の情報は、コア管理工程を基点として上流・下流の双方向に製造仕様設計管理テーブル7と生産性管理基準テーブル9に基づいて、連続する管理工程の工程計画を連鎖的に自動展開する様になっている。一方、モノの流れ5は、所要量計画手段2により資材発注され上流のサプライヤーから納入された材料から製品化までの所定の生産プロセスの短サイクル・システム化を図ることにより、下流の顧客・市場が求める要求に即応できるシステムになっている。   Note that the information of all process plans is based on the core management process, based on the manufacturing specification design management table 7 and the productivity management reference table 9 in both upstream and downstream directions. It is designed to automatically deploy. On the other hand, the flow of goods 5 is the downstream customer / market by making a short cycle systemization of the predetermined production process from the material ordered by the requirement planning means 2 to the commercialization from the material delivered from the upstream supplier. It is a system that can respond immediately to demands.

図2は本実施形態の生産計画手段1の全体構成を示す図である。図2に示す様に本実施形態の統合生産管理システムは、コア管理工程設定処理部31と、生産必要量算定処理部32と、負荷山積展開シミュレーション処理部33と、工程計画立案処理部34と、資材所要量計画処理部35と、上流・下流管理工程展開処理部36と、工程生産制約条件チェック処理部37とを有している。   FIG. 2 is a diagram showing the overall configuration of the production planning means 1 of the present embodiment. As shown in FIG. 2, the integrated production management system of the present embodiment includes a core management process setting processing unit 31, a production requirement calculation processing unit 32, a load pile development simulation processing unit 33, and a process plan planning processing unit 34. , A material requirement plan processing unit 35, an upstream / downstream management process development processing unit 36, and a process production constraint condition check processing unit 37.

コア管理工程設定処理部31は、各管理工程の情報を格納している管理工程マトリックステーブルを参照し、その管理工程マトリックステーブル中の管理工程の情報が、生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程の設定基準に該当するかどうかを判定することにより、前記コア管理工程を設定する処理部である。   The core management process setting processing unit 31 refers to the management process matrix table storing the information of each management process, and the management process information in the management process matrix table controls the entire operation plan on the production process. It is a processing unit that sets the core management process by determining whether or not it meets the setting standard of the core management process that is the basic axis for the above.

生産必要量算定処理部32は、前記設定したコア管理工程での生産必要量を算出する処理部である。負荷山積展開シミュレーション処理部33は、前記算出された生産必要量の製品を生産する際のコア管理工程での負荷山積展開シミュレーションを行う処理部である。   The production requirement calculation processing unit 32 is a processing unit that computes the production requirement in the set core management process. The load mountain deployment simulation processing unit 33 is a processing unit that performs a load mountain deployment simulation in the core management process when producing the calculated production required amount of the product.

工程計画立案処理部34は、当該コア管理工程における工程計画を立案する処理部である。資材所要量計画処理部35は、前記コア管理工程における資材所要量を算出する処理部である。上流・下流管理工程展開処理部36は、前記設定したコア管理工程を基点として管理工程マトリックステーブルを検索し、当該コア管理工程の上流及び下流に位置する管理工程の情報を管理工程マトリックステーブルから読み出し、前記コア管理工程に対して実施した処理をコア管理工程を含む全工程に対して実施する処理部である。工程生産制約条件チェック処理部37は、前記処理の実施結果が生産計画の内容とその工程の設備能力や制約条件に合わない場合に是正措置38を実施して前記の処理を繰り返す処理部である。   The process plan formulation processing unit 34 is a processing unit that formulates a process plan in the core management process. The material requirement plan processing unit 35 is a processing unit that calculates the material requirement in the core management process. The upstream / downstream management process development processing unit 36 searches the management process matrix table using the set core management process as a base point, and reads information on management processes located upstream and downstream of the core management process from the management process matrix table. And a processing unit that performs the process performed on the core management process for all processes including the core management process. The process production constraint condition check processing unit 37 is a processing unit that performs the corrective action 38 and repeats the above process when the execution result of the process does not match the content of the production plan and the facility capacity or constraint condition of the process. .

統合生産管理システムをコア管理工程設定処理部31、生産必要量算定処理部32、負荷山積展開シミュレーション処理部33、工程計画立案処理部34、資材所要量計画処理部35、上流・下流管理工程展開処理部36及び工程生産制約条件チェック処理部37として機能させる為のプログラムは、CD−ROM等の記録媒体に記録され磁気ディスク等に格納された後、メモリにロードされて実行されるものとする。なお前記プログラムを記録する記録媒体はCD−ROM以外の他の記録媒体でも良い。また前記プログラムを当該記録媒体から情報処理装置にインストールして使用しても良いし、ネットワークを通じて当該記録媒体にアクセスして前記プログラムを使用するものとしても良い。   The integrated production management system includes a core management process setting processing unit 31, a production requirement calculation processing unit 32, a load pile development simulation processing unit 33, a process plan planning processing unit 34, a material requirement planning processing unit 35, and upstream / downstream management process development. A program for functioning as the processing unit 36 and the process production constraint condition check processing unit 37 is recorded on a recording medium such as a CD-ROM and stored in a magnetic disk or the like, and then loaded into a memory and executed. . The recording medium for recording the program may be a recording medium other than the CD-ROM. The program may be used by installing it from the recording medium into the information processing apparatus, or the program may be used by accessing the recording medium through a network.

図2の様に生産計画手段1において、先ず受注受付を始点として受注残情報からコア管理工程設定処理部31及び生産必要量算定処理部32の処理を行い、コア管理工程の設定と生産必要量算定処理を行う。次に製造仕様設計管理テーブル7により製造設備が設定され、負荷山積展開シミュレーション処理部33及び工程計画立案処理部34の処理を行って、負荷山積展開シミュレーション処理と工程計画立案処理を実行した後、資材所要量計画処理部35により資材所要量計画処理を行う。   As shown in FIG. 2, in the production planning means 1, the core management process setting processing unit 31 and the production requirement calculation processing unit 32 are first processed from the received order information starting from the receipt of an order, and the setting of the core management process and the production requirement are performed. Perform the calculation process. Next, after the manufacturing equipment is set by the manufacturing specification design management table 7, the load mountain development simulation processing unit 33 and the process plan planning processing unit 34 are processed, and the load mountain development simulation process and the process plan planning process are executed. The material requirement plan processing unit 35 performs material requirement planning processing.

更に、上流・下流管理工程展開処理部36が、リードタイム、歩留り等の情報を持つ生産性管理基準テーブル9と、各工程の進捗情報を持つ工程実績進捗情報テーブル14を参照して、連続する管理工程の負荷山積み計画を連鎖的に、コア管理工程の工程計画を中心としたP1工程計画、P2工程計画からPn-1工程計画、Pn工程計画に到る、生産プロセスの全工程計画を自動作成する。工程生産制約条件チェック処理部37は、各工程計画15に対して各工程の生産制約がある場合にその旨を生産必要量算定処理部32に伝えて前述の一連の処理を繰り返して全工程計画を立て直す。加えて、オプション機能として、加工工程の一部を外部に発注する為の加工外注展開機能も備えているものとする。   Further, the upstream / downstream management process development processing unit 36 refers to the productivity management reference table 9 having information such as the lead time and the yield, and the process performance progress information table 14 having the progress information of each process. Automatic management of all process plans for production processes from P1 process plans and P2 process plans to Pn-1 process plans and Pn process plans centering on core management process process plans create. The process production constraint condition check processing unit 37, when there is a production constraint for each process with respect to each process plan 15, informs the fact to the production requirement calculation processing unit 32 and repeats the above-described series of processes to complete the entire process plan. Rebuild. In addition, as an optional function, a processing subcontract development function for ordering a part of the processing process to the outside is also provided.

図3は本実施形態の全工程計画展開による工程計画実績MRP変動対応と生産活動実需ローリングの全体構成を示す図である。図3に示す様に本実施形態の統合生産管理システムは、工程計画実績MRP変動対応/生産活動実需ローリング処理手段17と、所要量計画処理部18と、生産性管理アラート処理部19とを有している。   FIG. 3 is a diagram showing an overall configuration of the process plan actual MRP variation response and the production activity actual demand rolling by the entire process plan development of the present embodiment. As shown in FIG. 3, the integrated production management system of this embodiment has a process plan actual MRP fluctuation response / production activity actual demand rolling processing means 17, a requirement planning processing unit 18, and a productivity management alert processing unit 19. is doing.

全工程計画展開20では、コア管理工程を基準として自動作成された各工程P1〜Pnの生産計画の内容と、それらの工程の設備能力や制約(設備の稼働時間、各工程で利用可能な資材、人員数、担当人員の技能や能力等)とを比較して、各工程の生産計画の内容がその工程の設備能力や制約条件に合わない場合に各工程P1〜Pnの再計画を行うことにより、全工程の生産計画の実需のローリングが行われる。例えば再計画には各工程の資材所要量の見直しがある。   In the entire process plan development 20, the contents of the production plan of each process P1 to Pn automatically created based on the core management process and the equipment capacity and restrictions of those processes (equipment operating time, materials available in each process) , The number of personnel, the skills and abilities of the personnel in charge, etc.), and if the contents of the production plan for each process do not match the facility capacity or constraints of that process, replan each process P1 to Pn As a result, the actual demand of the production plan for all processes is rolled. For example, replanning involves reviewing the material requirements for each process.

工程計画実績MRP変動対応/生産活動実需ローリング処理手段17は、前記立案した工程計画の内容と工程実績進捗情報の内容とを比較して工程計画の微調整を行う手段である。所要量計画処理部18は、中長期売上計画・月次生産計画及び週次工程計画に基づいて、資材所要量計画を製品勘定部門毎に策定し、部門固有資材、部門共通資材及び中長期戦略資材を分類体系管理して日別MRPを展開し、資材の発注依頼を行う処理部である。   The process plan result MRP fluctuation response / production activity actual demand rolling processing means 17 is a means for finely adjusting the process plan by comparing the contents of the prepared process plan with the contents of the process result progress information. The requirement plan processing unit 18 formulates a material requirement plan for each product account department based on the medium-to-long-term sales plan, monthly production plan, and weekly process plan. This is a processing unit that manages the classification system of materials, develops daily MRP, and requests for ordering of materials.

生産性管理アラート処理部19は、前記工程計画に基づいた生産活動における、リードタイム生産性、物質収支生産性や品質情報が所定の管理基準に達した場合や、前記工程計画の内容と工程実績進捗情報の内容とを比較して納期遅れが発生するかどうかを判定し、納期遅れの発生が検出された場合にアラート情報を出力する処理部である。   The productivity management alert processing unit 19 is used when the lead time productivity, the material balance productivity, and the quality information in the production activity based on the process plan reach predetermined management standards, or the contents of the process plan and the process results. The processing unit compares the contents of the progress information with each other to determine whether or not a delivery delay occurs, and outputs alert information when the delivery delay is detected.

統合生産管理システムを工程計画実績MRP変動対応/生産活動実需ローリング処理手段17、所要量計画処理部18及び生産性管理アラート処理部19として機能させる為のプログラムは、CD−ROM等の記録媒体に記録され磁気ディスク等に格納された後、メモリにロードされて実行されるものとする。なお前記プログラムを記録する記録媒体はCD−ROM以外の他の記録媒体でも良い。また前記プログラムを当該記録媒体から情報処理装置にインストールして使用しても良いし、ネットワークを通じて当該記録媒体にアクセスして前記プログラムを使用するものとしても良い。   A program for causing the integrated production management system to function as the process plan actual MRP fluctuation response / production activity actual demand rolling processing means 17, the requirement planning processing unit 18 and the productivity management alert processing unit 19 is stored on a recording medium such as a CD-ROM. It is assumed that after being recorded and stored in a magnetic disk or the like, it is loaded into a memory and executed. The recording medium for recording the program may be a recording medium other than the CD-ROM. The program may be used by installing it from the recording medium into the information processing apparatus, or the program may be used by accessing the recording medium through a network.

図3では、本実施形態に係る全工程計画展開による工程計画実績進捗管理と連動したMRP資材発注管理、いわゆる実需ローリング型生産活動管理の全体構成図を概略的に表している。   FIG. 3 schematically shows an overall configuration diagram of MRP material ordering management, so-called actual demand rolling type production activity management, which is linked with process plan result progress management by developing all process plans according to the present embodiment.

全工程に展開された管理工程計画に基づいて生産活動が行われ、そのリードタイム生産性、物質収支生産性、及び、品質情報が即時に把握された状態で、生産性管理アラート処理部19の処理を実施することで、各々の管理基準に従い、アラートが表示される。アラートに従った是正アクションの入力を受け付けてその是正アクションによる改善状況をフィードバックし、必要に応じて全工程の再スケジューリング及び各管理基準等の変更を行える構成としている。   Production activities are performed based on the management process plan developed in all processes, and the lead time productivity, material balance productivity, and quality information are immediately grasped, and the productivity management alert processing unit 19 By executing the process, an alert is displayed according to each management standard. It is configured to receive an input of corrective action according to the alert, feed back the improvement status by the corrective action, and can reschedule all processes and change each control standard as necessary.

全工程への展開を行い、資材発注ロジックを用いて所要量計画処理部18の処理を実施することで、資材調達の為のMRPが全工程計画に連動し自動展開される。更に、展開結果を短サイクルでローリング集計し、部門固有資材、共通資材、中長期戦略品に分類した上で、日別に新規発注・変更依頼情報等を画面表示する構成としている。   By deploying to all processes and executing the processing of the requirement plan processing unit 18 using the material ordering logic, the MRP for material procurement is automatically deployed in conjunction with the entire process plan. Furthermore, the rollout results are rolled and aggregated in a short cycle and classified into department-specific materials, common materials, and medium- to long-term strategic products, and then new order / change request information and the like are displayed on the screen on a daily basis.

図4は本実施形態の管理工程マトリックス、生産性管理基準、製造仕様設計管理、資材発注管理基準のテーブル構成を示す図である。生産プロセス毎にインデックス化された管理工程マトリックステーブル8は、製造品名毎に管理工程を定義したものであり、製造品名毎に連続する管理工程や、当該生産プロセスに対応する管理工程に関する情報を記憶している。   FIG. 4 is a diagram showing a table configuration of a management process matrix, productivity management standard, manufacturing specification design management, and material order management standard according to this embodiment. The management process matrix table 8 indexed for each production process defines management processes for each manufactured product name, and stores information on management processes that are continuous for each manufactured product name and management processes corresponding to the production process. is doing.

更に管理工程マトリックステーブル8は、当該管理工程に対応するリードタイム(LT)、物質収支、品質規格基準等を記憶する生産性管理基準テーブル9、製造品名と製造設備との制約やその工程で用いられる材料の品種名及び使用量等を記憶する製造仕様設計管理テーブル7、資材発注方式や所要量算出基準等を記憶する資材発注管理基準テーブル6を関係付けて定義している。   Further, the management process matrix table 8 is used in the productivity management standard table 9 for storing the lead time (LT), material balance, quality standard standard, etc. corresponding to the management process, restrictions on the product name and the manufacturing equipment, and the process. A production specification design management table 7 for storing the product type name and amount used, and a material order management reference table 6 for storing a material ordering method, a required amount calculation standard, and the like are defined in association with each other.

図4において、製造ラインNoはその管理工程で処理される製造品に対応する製品の生産が行われる製品ラインを識別する為の識別情報であり、ある製品は同一の製造ラインNoで識別される複数の管理工程を流れることにより生産されるものとする。また生産性管理基準書Noや製造仕様設計書Noは、その管理工程で用いられる生産性管理基準書や製造仕様設計書に対応した、生産性管理基準テーブル9や製造仕様設計管理テーブル7上のデータを識別する為の番号であり、資材発注管理基準テーブル6についても同様の番号が格納されているものとする。そして管理工程コードは、その管理工程を識別する為のコードであり、上流工程から下流工程に向かうに従って大きい値となる様に番号が付けられているものとする。   In FIG. 4, a production line No. is identification information for identifying a product line on which a product corresponding to a manufactured product processed in the management process is produced, and a certain product is identified by the same production line No. It shall be produced by flowing through a plurality of management processes. Further, the productivity management standard document No. and the manufacturing specification design document No. are on the productivity management standard table 9 and the manufacturing specification design management table 7 corresponding to the productivity management standard document and the manufacturing specification design document used in the management process. It is a number for identifying data, and the same number is also stored in the material order management reference table 6. The management process code is a code for identifying the management process, and is numbered so as to increase in value from the upstream process toward the downstream process.

図5は本実施形態の計画制約条件及び段取切替時間展開のテーブル構成を示す図である。図5では、製造品名、製造仕様設計書Noと製造設備、製造設備配置(割り付けロケーション)等を記憶する計画制約条件テーブル22と、設備毎に前作業製造品名と後作業製造品名及び段取り時間を記憶する段取切替時間展開テーブル23を表している。   FIG. 5 is a diagram showing a table configuration of the plan constraint condition and the setup switching time development of this embodiment. In FIG. 5, the plan constraint condition table 22 for storing the product name, the manufacturing specification design document number, the manufacturing equipment, the manufacturing equipment layout (allocation location), etc., and the pre-work product name, the post-work product name, and the setup time for each equipment. The setup switching time expansion table 23 is stored.

図6は本実施形態の生産計画立案処理の処理フローを示す図である。図6の処理では、コア管理工程を基点として双方向に連続する管理工程の工程計画を、製造仕様設計管理テーブル7と生産性管理基準テーブル9に基づいて連鎖的に自動展開するドミノ連動により全管理工程の工程計画を自動生成する。   FIG. 6 is a diagram showing a process flow of the production plan planning process of the present embodiment. In the process of FIG. 6, the process plan of the management process that continues in both directions based on the core management process is completely linked by domino linkage that automatically and chainably develops based on the manufacturing specification design management table 7 and the productivity management reference table 9. Automatically generate a process plan for the management process.

以下、処理フローに従ってステップS10からステップS90について説明する。先ずコア管理工程設定処理部31は、管理工程マトリックステーブル8よりコア管理工程の決定を行う。ここでは受注受付による受注残を示す受注残情報テーブル及び見込み生産の内容を示す月次生産計画テーブルの読み出しと、決定されたコア管理工程の情報の読み出しを行い、以下の処理ステップ実行の準備を行う(ステップS10)。   Hereinafter, steps S10 to S90 will be described according to the processing flow. First, the core management process setting processing unit 31 determines a core management process from the management process matrix table 8. Here, the order backlog information table indicating the backlog of orders received and the monthly production plan table indicating the contents of the prospective production are read out, and the information on the determined core management process is read out, and the following processing steps are prepared for execution. It performs (step S10).

工程生産制約条件チェック処理部37は、コア管理工程を基準として自動作成された各工程の生産計画の内容がその工程の設備能力や制約条件に合わない場合に、以下のステップS20からステップS90まで、全工程の生産計画の実需のローリングを行う(ステップS15)。   The process production constraint condition check processing unit 37 performs the following steps S20 to S90 when the content of the production plan of each process automatically created based on the core management process does not match the facility capacity and constraint conditions of the process. Then, the actual demand of the production plan for all processes is rolled (step S15).

生産必要量算定処理部32は、前記決定されたコア管理工程を基点として受注残情報と生産性管理基準テーブル9に基づいて生産必要量を算出し、コア管理工程における生産必要量の確定登録を行う(ステップS20)。   The production requirement calculation processing unit 32 calculates the production requirement based on the backorder information and the productivity management reference table 9 with the determined core management process as a base point, and performs final registration of the production requirement in the core management process. It performs (step S20).

次のステップで負荷山積展開シミュレーション処理部33は、前記ステップで算出された生産必要量を示す生産必要量策定対象一覧の内容を対象とし、前記の製造仕様設計管理テーブル7、生産性管理基準テーブル9、計画制約条件テーブル22、段取切替時間展開テーブル23等を用いてコア管理工程の負荷山積展開シミュレーションを行い、最適解を求めて工程計画立案処理部34によりコア管理工程の工程計画を確定した後、資材所要量計画処理部35によりコア管理工程の資材所要量を算出する(ステップS30)。   In the next step, the load pile development simulation processing unit 33 targets the contents of the production requirement formulation target list indicating the production requirement calculated in the step, and includes the manufacturing specification design management table 7 and the productivity management reference table. 9. Perform a load pile development simulation of the core management process using the plan constraint condition table 22, the setup switching time development table 23, etc., find the optimal solution, and confirm the process plan of the core management process by the process planning processing unit 34 After that, the material requirement planning processing unit 35 calculates the material requirement for the core management process (step S30).

次のステップで上流・下流管理工程展開処理部36は、前記の生産性管理基準テーブル9を用いて累積歩留りを考慮し、コア管理工程を基点として双方向に連続する全管理工程の工程計画を、ドミノ連動により自動生成する(ステップS40)。   In the next step, the upstream / downstream management process development processing unit 36 considers the cumulative yield using the productivity management reference table 9 and prepares a process plan for all the management processes that continue in both directions starting from the core management process. Then, it is automatically generated by Domino linkage (step S40).

次のステップでは、工程計画実績MRP変動対応/生産活動実需ローリング処理手段17により、オプション機能として、自動生成された工程計画に対する工程計画の微調整を行える仕組みを提供しており、全管理工程の負荷バランスを考慮する為に、ローリング負荷山積み展開シミュレーションを行える様にしている。例えば特急注文の対応、及び突発的な工程遅れの是正の為に、特急指定を登録することにより、各管理工程作業のディスパッチングを可能とし、且つ当該管理工程における加工外注依頼処理が行える様に構成している(ステップS50)。   In the next step, the process plan actual MRP fluctuation response / production activity actual demand rolling processing means 17 provides an optional function that allows fine adjustment of the process plan for the automatically generated process plan. In order to consider the load balance, a rolling load pile development simulation can be performed. For example, by registering an express designation for the handling of express orders and correction of sudden process delays, it is possible to dispatch each management process work and to perform processing subcontract request processing in the management process (Step S50).

更に次のステップ60で生産性管理アラート処理部19は、展開結果として割り付けられた各管理工程計画について、工程計画の内容と工程実績進捗情報の内容とを比較し、納期遅れが発生するかどうかを前記比較結果に基づいて予測し、納期遅れが存在すると予測された場合には、次のステップS70で、納期遅れが存在することを示すアラート情報を出力する。ここでは例えば各管理工程の工程計画進捗実績管理一覧画面の該当データについて赤色表示を行うものとする。そしてステップS80では、残業/休日出勤、外注、納期変更等の是正措置の内容の入力を受け付けてステップS20へ戻る。一方、納期遅れが存在しない場合にはステップS90を経て生産計画立案処理を終了する。   Further, in the next step 60, the productivity management alert processing unit 19 compares the contents of the process plan with the contents of the process result progress information for each management process plan assigned as the development result, and whether or not a delivery delay occurs. Is predicted based on the comparison result, and when it is predicted that there is a delivery delay, alert information indicating that there is a delivery delay is output in the next step S70. Here, for example, the corresponding data on the process plan progress record management list screen of each management process is displayed in red. In step S80, input of the content of corrective actions such as overtime / holiday work, outsourcing, and delivery date change is accepted, and the process returns to step S20. On the other hand, if there is no delivery delay, the production planning process is terminated through step S90.

図7は本実施形態のコア管理工程設定処理の処理フローを示す図である。図7では、図6の生産計画手段1の処理フロー図のステップ10の詳細ステップを表している。本実施形態のコア管理工程設定処理部31は、生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程を、多品種の製品を同時に処理する工程、リードタイムの最も長い工程、多品種の材料を多量に消費する工程の優先順位で設定する処理を行うものとするが、他の設定基準を用いるものとしても良い。   FIG. 7 is a diagram showing a processing flow of the core management process setting process of the present embodiment. FIG. 7 shows detailed steps of step 10 in the process flow diagram of the production planning means 1 of FIG. The core management process setting processing unit 31 of the present embodiment is a core management process that is the basis for controlling the entire operation plan in the production process, a process of simultaneously processing various products, a process with the longest lead time, The setting process is performed in the priority order of the process of consuming a large amount of various kinds of materials, but other setting criteria may be used.

ステップ701でコア管理工程設定処理部31は、管理工程マトリックステーブル8中のデータを順次参照してそのデータ中の管理工程コードと製品名を読み出し、各管理工程の品種数をカウントする。カウントされる品種数は管理工程マトリックステーブル8中の品種数全体であるものとするが、前回計画時の計画品種数がカウントされる場合もあるものとする。 Core Management process setting processing unit 31 at step 701, control step sequentially referring to the data in the matrix table 8 reads out the management process code and manufacturing product name in the data, and counts the varieties number in each administration process. It is assumed that the number of varieties to be counted is the total number of varieties in the management process matrix table 8, but the number of varieties planned at the time of the previous plan may be counted.

ステップ702では、前記カウントした全管理工程の品種数を参照し、多品種(例えば2品種以上)の製品を同時に処理する管理工程が存在しているかどうかを調べて、その様な管理工程が存在している場合にはステップ703へ進む。   In step 702, referring to the counted number of varieties in all management processes, it is checked whether there is a management process for simultaneously processing products of multiple types (for example, two or more types), and such a management process exists. If yes, go to Step 703.

ステップ703では、前記カウントした品種数の値の内で最大値のものが複数存在しているかどうかを調べ、最大値のものが複数存在している場合、すなわち最大の品種数を処理する管理工程が複数存在している場合にはステップ704へ進み、そうでない場合にはステップ705へ進む。   In step 703, it is checked whether or not there are a plurality of maximum values among the counted values of the number of varieties, and if there are a plurality of maximum values, that is, a management step for processing the maximum number of varieties. If there is a plurality, the process proceeds to step 704, and if not, the process proceeds to step 705.

ステップ704では、前記最大の品種数を処理する複数の管理工程の各管理工程コードの値を参照し、それらの内で最も値の小さい管理コードの管理工程、すなわち前記最大の品種数を処理する管理工程の内で最も上流の管理工程をコア管理工程とし、その管理工程コードをコア管理工程コードとしてメモリに格納してコア管理工程設定処理を終了する。   In step 704, the value of each management process code of the plurality of management processes for processing the maximum number of products is referred to, and the management process of the management code having the smallest value among them, that is, the maximum number of products is processed. The most upstream management process among the management processes is set as the core management process, the management process code is stored in the memory as the core management process code, and the core management process setting process is terminated.

またステップ704では、前記最大の品種数を処理する管理工程をコア管理工程とし、その管理工程コードをコア管理工程コードとしてメモリに格納してコア管理工程設定処理を終了する。   In step 704, the management process for processing the maximum number of products is set as a core management process, the management process code is stored in the memory as a core management process code, and the core management process setting process is terminated.

ステップ706では、管理工程マトリックステーブル8中のデータを順次参照してそのデータ中の生産性管理基準書Noを読み出した後、生産性管理基準テーブル9を参照し、前記読み出した生産性管理基準書Noに対応するデータ中のリードタイム(LT)を読み出して、リードタイムの最も長い管理工程の管理工程コードをメモリに格納する。   In step 706, the data in the management process matrix table 8 are sequentially referred to, and the productivity management standard document No. in the data is read out. Then, the productivity management standard table 9 is referred to, and the read productivity management standard document is read out. The lead time (LT) in the data corresponding to No is read, and the management process code of the management process with the longest lead time is stored in the memory.

ステップ707では、前記処理により得られたリードタイムの最も長い管理工程におけるリードタイムの値を参照して、その値が所定の値よりも小さいかどうかを判定し、所定の値よりも小さい場合にはステップ708へ進む。   In step 707, referring to the lead time value in the management process with the longest lead time obtained by the process, it is determined whether or not the value is smaller than a predetermined value. Proceeds to step 708.

ステップ708では、前記参照したリードタイムの値の内で最大値のものが複数存在しているかどうかを調べ、最大値のものが複数存在している場合、すなわちリードタイムが最大である管理工程が複数存在している場合にはステップ709へ進み、そうでない場合にはステップ710へ進む。   In step 708, it is checked whether or not there are a plurality of the maximum values among the referenced lead time values. If there are a plurality of the maximum values, that is, a management process in which the lead time is maximum is performed. If there are a plurality, the process proceeds to step 709; otherwise, the process proceeds to step 710.

ステップ709では、前記リードタイムが最大である複数の管理工程から特定の管理工程(例えば管理工程コードが最小のもの)を選択し、その管理工程コードをコア管理工程コードとしてメモリに格納してコア管理工程設定処理を終了する。またステップ710では、前記リードタイムが最大である管理工程をコア管理工程とし、その管理工程コードをコア管理工程コードとしてメモリに格納してコア管理工程設定処理を終了する。   In step 709, a specific management process (for example, the management process code having the smallest management process code) is selected from a plurality of management processes having the maximum lead time, and the management process code is stored in the memory as a core management process code. The management process setting process ends. In step 710, the management process having the maximum lead time is set as the core management process, the management process code is stored in the memory as the core management process code, and the core management process setting process is terminated.

ステップ711では、管理工程マトリックステーブル8中のデータを順次参照してそのデータ中の製造仕様設計書Noを読み出した後、製造仕様設計管理テーブル7を参照し、前記読み出した製造仕様設計書Noに対応するデータ中の材料の品種名及び使用量を読み出して、各管理工程で用いられる材料の品種数及び使用量をメモリに格納する。   In step 711, the data in the management process matrix table 8 are sequentially referred to and the manufacturing specification design document No. in the data is read out. Then, the manufacturing specification design management table 7 is referred to and the read manufacturing specification design document No. is referred to. The type name and usage amount of the material in the corresponding data are read, and the number of types and usage amount of the material used in each management process are stored in the memory.

ステップ712では、前記格納した材料の品種数の値の内で最大値のものが複数存在しているかどうかを調べ、最大値のものが複数存在している場合にはステップ713へ進み、そうでない場合にはステップ716へ進む。   In step 712, it is checked whether or not there are a plurality of maximum values among the values of the number of varieties of the stored materials. If there are a plurality of maximum values, the process proceeds to step 713; If so, go to Step 716.

ステップ713では、前記材料の品種数が最大である複数の管理工程の材料の使用量を比較して、その使用量が同量であるものが複数存在しているかどうかを調べ、使用量が同量であるものが複数存在している場合にはステップ714へ進み、そうでない場合にはステップ715へ進む。   In step 713, the amount of material used in a plurality of management processes having the maximum number of varieties of the material is compared to check whether there are a plurality of materials having the same amount, and the amount used is the same. If there are a plurality of quantities, the process proceeds to step 714, and if not, the process proceeds to step 715.

ステップ714では、前記材料の使用量が同量である複数の管理工程から特定の管理工程(例えば管理工程コードが最小のもの)を選択し、その管理工程コードをコア管理工程コードとしてメモリに格納してコア管理工程設定処理を終了する。またステップ715では、前記材料の品種数及び使用量が最大である管理工程をコア管理工程とし、その管理工程コードをコア管理工程コードとしてメモリに格納してコア管理工程設定処理を終了する。一方ステップ716では、前記材料の品種数が最大である管理工程をコア管理工程とし、その管理工程コードをコア管理工程コードとしてメモリに格納してコア管理工程設定処理を終了する。   In step 714, a specific management process (for example, the one with the smallest management process code) is selected from a plurality of management processes having the same amount of material used, and the management process code is stored in the memory as a core management process code. Then, the core management process setting process ends. In step 715, the management process in which the number of materials and the amount of use are the maximum is set as the core management process, the management process code is stored in the memory as the core management process code, and the core management process setting process is terminated. On the other hand, in step 716, the management process in which the number of types of the material is the maximum is set as the core management process, the management process code is stored in the memory as the core management process code, and the core management process setting process is terminated.

次に、本実施形態の統合生産管理システムにおいて、多品種の製品を同時に処理する工程をコア管理工程として設定する処理を以下の図8及び図9を用いて説明する。   Next, in the integrated production management system of the present embodiment, a process for setting a process for simultaneously processing various products as a core management process will be described with reference to FIGS. 8 and 9 below.

図8は本実施形態の複数の管理工程から成る生産プロセスの概要を示す図である。図8では製品A、製品B、製品Cを管理工程801〜812で処理する生産プロセスの概要を表しており、各製品はそれぞれ製造ライン821〜823に沿って次の工程に渡されるものとする。ここで、図8における製造品名A1〜A5、B1〜B5、C1〜C4は、各製品のそれぞれの管理工程での名称であるものとする。   FIG. 8 is a diagram showing an outline of a production process including a plurality of management steps according to the present embodiment. FIG. 8 shows an outline of a production process in which the products A, B, and C are processed in the management steps 801 to 812, and each product is transferred to the next step along the production lines 821 to 823, respectively. . Here, the manufactured product names A1 to A5, B1 to B5, and C1 to C4 in FIG. 8 are names in the respective management processes of the respective products.

図9は本実施形態の管理工程マトリックステーブル8の一例を示す図である。図9に示す様にこの管理工程マトリックステーブル8の例では、図8に示した管理工程801〜812に関する情報が格納されている。   FIG. 9 is a diagram showing an example of the management process matrix table 8 of the present embodiment. As shown in FIG. 9, in the example of the management process matrix table 8, information regarding the management processes 801 to 812 shown in FIG. 8 is stored.

ステップ701でコア管理工程設定処理部31が、管理工程マトリックステーブル8中のデータを順次参照して各管理工程の品種数をカウントする場合、先ず管理工程コード905及び製品名902を読み出して、同一の管理工程コード905に対して異なる製品名902が設定されているものをカウントする。図9の場合では、管理工程コード905の値が「807」の製品名902が「A3」、「B3」、「C3」であるので、この管理工程807では3品種の製品が同時に処理されることが判り、この例では、他に多品種の管理工程が存在していないので、この管理工程807がコア管理工程となる。 Core Management process setting processing unit 31 at step 701, when counting the varieties number of managed process matrix table 8 in the data sequentially referring to the management process, and is first reads the management process code 905 and manufacturing product name 902, different manufacturing Name 902 for the same management process code 905 counts the ones that have been set. In the case of FIG. 9, the management value of the process code 905 is manufacturing product name 902 of "807", "A3", "B3", because it is "C3", product of cultivars in this management process 807 are processed simultaneously In this example, since there are no other multi-product management processes, this management process 807 is the core management process.

またステップ706の処理を行う場合では、管理工程マトリックステーブル8中のデータを順次参照してそのデータ中の生産性管理基準書Noの「901」「902」「903」等を読み出した後、生産性管理基準テーブル9を参照し、前記読み出した生産性管理基準書Noに対応するデータ中のリードタイム(LT)を読み出して、リードタイムの最も長い管理工程を検出し、コア管理工程の決定に利用する。   In the case of performing the processing of step 706, the data in the management process matrix table 8 are sequentially referred to, and the productivity management standard document numbers “901”, “902”, “903”, etc. in the data are read out, and then the production is performed. Referring to the productivity management standard table 9, the lead time (LT) in the data corresponding to the read productivity management standard document No. is read, the management process with the longest lead time is detected, and the core management process is determined. Use.

さらにステップ711の処理を行う場合では、管理工程マトリックステーブル8中のデータを順次参照してそのデータ中の製造仕様設計書Noの「921」「922」「923」等を読み出した後、製造仕様設計管理テーブル7を参照し、前記読み出した製造仕様設計書Noに対応するデータ中の材料の品種名及び使用量を読み出して、各管理工程で用いられる材料の品種数及び使用量をカウントし、コア管理工程の決定に利用する。   Further, when the processing of step 711 is performed, the data in the management process matrix table 8 are sequentially referred to, and the manufacturing specification design document No. “921”, “922”, “923”, etc. in the data is read out, and then the manufacturing specification. Refer to the design management table 7, read the material type name and amount used in the data corresponding to the read manufacturing specification design document No., and count the number and amount of materials used in each management process, Used to determine the core management process.

前記の様にしてコア管理工程が決定されると、図6の生産計画手段1の処理フロー図のステップ20で生産必要量算定処理部32は、その決定されたコア管理工程を基点として受注残情報及び月次生産計画と生産性管理基準テーブル9に基づいて生産必要量を算出し、確定登録を行う。   When the core management process is determined as described above, the production requirement calculation processing unit 32 at step 20 in the process flow diagram of the production planning means 1 in FIG. 6 receives the order backlog based on the determined core management process. Based on the information, the monthly production plan, and the productivity management standard table 9, the required production amount is calculated and finalized registration is performed.

すなわち、図6のステップ20で生産必要量算定処理部32は、管理工程マトリックステーブル8中のデータを参照して、前記メモリに格納しておいたコア管理工程コードと一致する管理工程のデータを検索した後、コア管理工程以降の後工程に位置する管理工程の歩留情報を読み出し、コア管理工程から最終工程までの累積歩留を算出して、前記受注残情報及び月次生産計画で示される製品量を前記算出した累積歩留で除算する等の処理により、前記製品量を生産する為にコア管理工程で処理しなければならない製造品の必要量を算出し、生産必要量策定対象一覧等への出力を行う。   That is, in step 20 in FIG. 6, the production requirement calculation processing unit 32 refers to the data in the management process matrix table 8 and stores the management process data that matches the core management process code stored in the memory. After the search, the yield information of the management process located in the subsequent process after the core management process is read, the cumulative yield from the core management process to the final process is calculated, and is indicated in the order backlog information and the monthly production plan. The required amount of manufactured products that must be processed in the core management process to produce the product amount is calculated by processing such as dividing the product amount to be calculated by the calculated cumulative yield, and a list of production requirement formulation targets Output to etc.

図10は本実施形態の負荷山積展開シミュレーション処理部33の処理フローを示す図である。図10では、図6の生産計画手段1の処理フロー図のステップ30の詳細ステップを表している。ここでは、先ず前記ステップで作成された生産必要量策定対象一覧に基づき、製造仕様設計管理テーブル7と生産性管理基準テーブル9及び計画制約条件テーブル22を読出し、これらによりコア管理工程の工程計画を決定する。   FIG. 10 is a diagram showing a processing flow of the load pile development simulation processing unit 33 of the present embodiment. FIG. 10 shows a detailed step of step 30 in the process flow diagram of the production planning means 1 of FIG. Here, based on the production requirement formulation target list created in the above step, the manufacturing specification design management table 7, the productivity management reference table 9, and the plan constraint condition table 22 are read out, and the process plan of the core management process is thereby read out. decide.

以下、処理フローに従ってステップS10000からステップS70000について説明する。先ず負荷山積展開シミュレーション処理部33は、計画制約条件テーブル22、製造仕様設計管理テーブル7及び生産性管理基準テーブル9を読出す(ステップS10000)。次に、コア管理工程に対する工程計画情報テーブル15及び工程実績情報テーブル16等を読出し、以下の処理ステップ実行の準備を行う(ステップS20000)。   Hereinafter, steps S10000 to S70000 will be described according to the processing flow. First, the load pile development simulation processing unit 33 reads the plan constraint condition table 22, the manufacturing specification design management table 7, and the productivity management reference table 9 (step S10000). Next, the process plan information table 15 and the process performance information table 16 for the core management process are read out, and preparation for execution of the following processing steps is performed (step S20000).

納期遅れが存在する間は、以下のステップS30000からステップS70000まで、負荷山積みシミュレーションのローリングを行う(ステップS25000)。   While there is a delivery delay, the load pile simulation is rolled from step S30000 to step S70000 (step S25000).

先ず次のステップでは、生産必要量の算出結果に基づいて負荷山積み優先順位ソートを実行する。ここでは例えば(1)製品在庫切れで受注残納期が短い注文、(2)受注引当残製品在庫が目標在庫切っている製品等の順位についてソートを実行する(ステップS30000)。   First, in the next step, load stack priority order sorting is executed based on the calculation result of the required production amount. In this case, for example, (1) an order that is out of product stock and the order backlog is short, and (2) a product such as a product in which the remaining product stock for order acceptance is out of target stock is sorted (step S30000).

更に次のステップでは、計画制約条件テーブル22、製造仕様設計管理テーブル7、及び生産性管理基準テーブル9に従って段取り時間を含めた負荷山積み展開を実行する。ここでは例えば(1)前後の製造品名の制約条件、(2)製造品名、製造設備毎の段取り時間の設定、(3)製品製造勘定部門、設備毎の稼働カレンダーの調整を実行する(ステップS40000)。   In the next step, load pile development including setup time is executed according to the plan constraint condition table 22, the manufacturing specification design management table 7, and the productivity management reference table 9. Here, for example, (1) restrictions on the names of manufactured products before and after, (2) setting of product names, setup time for each manufacturing facility, and (3) adjustment of operation calendar for each product manufacturing account department and facility are executed (step S40000). ).

次に前記ステップで決定された情報に基づきコア管理工程の負荷山積みシミュレーションを行い、コア管理工程の工程計画を作成する(ステップS50000)。   Next, a load accumulation simulation of the core management process is performed based on the information determined in the above step, and a process plan of the core management process is created (step S50000).

次にステップS60000で生産性管理アラート処理部19は、前記作成された工程計画と工程実績進捗情報とを比較して当該コア管理工程の工程計画について納期遅れの有無を判定し、納期遅れが存在すると判定された場合には、次のステップS70000を実行して納期遅れのアラート情報を出力する。ここでは、例えばコア管理工程計画画面の該当データの赤色表示を行うものとする。尚、納期遅れが避けられない場合は、顧客との納期調整を実施後、変更された納期を基に再度シミュレーションを行って最終的な工程計画を確定させる。   In step S60000, the productivity management alert processing unit 19 compares the created process plan with the process performance progress information to determine whether there is a delivery deadline for the process plan of the core management process, and there is a delivery deadline. If it is determined, the next step S70000 is executed to output the delivery delay information. Here, for example, the corresponding data on the core management process plan screen is displayed in red. If a delay in delivery date is unavoidable, the delivery schedule is adjusted with the customer, and then a simulation is performed again based on the changed delivery date to finalize the final process plan.

前記の様にしてコア管理工程での工程計画を決定した後、負荷山積展開シミュレーション処理部33は、管理工程マトリックステーブル8中のコア管理工程の工程計画コードで識別される工程計画情報テーブル15中の格納位置に前記決定した工程計画を格納する。   After determining the process plan in the core management process as described above, the load pile development simulation processing unit 33 in the process plan information table 15 identified by the process plan code of the core management process in the management process matrix table 8 The determined process plan is stored in the storage position.

図11は本実施形態のドミノ連動による全工程計画展開処理の処理フローを示す図である。図11では、図6の生産計画手段1の処理フロー図のステップ40の詳細ステップを表しており、上流・下流管理工程展開処理部36は、前記設定したコア管理工程を基点として、そのコア管理工程で処理される製品の製品ラインに該当する上流または下流の管理工程を順次辿ることによって当該コア管理工程の上流及び下流に位置する管理工程の工程計画を順次立案する処理を行う。   FIG. 11 is a diagram showing a process flow of the all process plan development process by the Domino interlocking of this embodiment. FIG. 11 shows the detailed steps of step 40 in the process flow diagram of the production planning means 1 in FIG. 6, and the upstream / downstream management process development processing unit 36 uses the set core management process as a base point to manage its core management. By sequentially following the upstream or downstream management process corresponding to the product line of the product processed in the process, the process plan of the management process located upstream and downstream of the core management process is sequentially developed.

ステップ1101で上流・下流管理工程展開処理部36は、管理工程マトリックステーブル8中のデータを参照し、前記の処理でメモリに格納しておいたコア管理工程コードと一致する管理工程コードを持つデータを検索する。   In step 1101, the upstream / downstream management process development processing unit 36 refers to the data in the management process matrix table 8 and has data having a management process code that matches the core management process code stored in the memory by the above process. Search for.

ステップ1102では、前記検索されたデータ中の工程計画コードを読み出し、そのコードで識別される工程計画データを工程計画情報テーブル15から読み出してメモリ上に格納しておく。   In step 1102, the process plan code in the retrieved data is read, and the process plan data identified by the code is read from the process plan information table 15 and stored in the memory.

ステップ1103では、前記読み出した工程計画中に示されている製造品名を読み出した後、その製造品名に該当する製造ラインNoを管理工程マトリックステーブル8から読み出してメモリに格納しておく処理と、ステップ1104及びステップ1108の処理とを、前記工程計画中に示された製造品の種類の数だけ繰り返す。   In step 1103, after reading out the manufactured product name indicated in the read out process plan, the manufacturing line number corresponding to the manufactured product name is read from the management process matrix table 8 and stored in the memory; The processing of 1104 and step 1108 is repeated for the number of types of manufactured products indicated in the process plan.

ステップ1104では、ステップ1102でメモリ上に格納したコア管理工程の工程計画データから、ステップ1103で読み出されている製造品名の工程計画データをメモリ上の他の領域にコピーした後、管理工程の検索位置を示す検索対象管理工程コードの格納領域をメモリ上に確保し、前記メモリに格納しておいたコア管理工程コードを前記検索対象管理工程コードに格納して、その検索対象管理工程コードが最も上流の管理工程コードに達するまでステップ1105からステップ1107までの処理を繰り返すことにより、コア管理工程よりも上流に位置する管理工程の工程計画を順次立案する。   In step 1104, after copying the process plan data of the product name read in step 1103 from the process plan data of the core management process stored in the memory in step 1102 to another area on the memory, A storage area for a search target management process code indicating a search position is secured on a memory, and a core management process code stored in the memory is stored in the search target management process code. By repeating the processing from step 1105 to step 1107 until the most upstream management process code is reached, the process plan of the management process located upstream from the core management process is sequentially developed.

ステップ1105では、前記検索位置情報で示される管理工程の前工程を検索する。すなわち、前記検索対象管理工程コードを「1」減算した後、検索対象管理工程コードで示される管理工程の製造ラインNoを管理工程マトリックステーブル8から読み出して、ステップ1103でメモリに格納しておいた製造ラインNoと比較し、それらが一致する場合には検索対象管理工程コードで示される管理工程が前工程であると判定する。また、一致しない場合には更に前記検索対象管理工程コードを「1」減算して次の管理工程の製造ラインNoとの比較を行う。   In step 1105, the previous process of the management process indicated by the search position information is searched. That is, after subtracting “1” from the search target management process code, the production line number of the management process indicated by the search target management process code is read from the management process matrix table 8 and stored in the memory in step 1103. Compared with the production line No., if they match, it is determined that the management process indicated by the search target management process code is the previous process. If they do not match, “1” is further subtracted from the search target management process code and compared with the production line number of the next management process.

ステップ1106では、前記判定された前工程の生産必要量を算出する。すなわち、前記メモリにコピーしておいた工程計画中の生産必要量について、その生産必要量を後工程に提供する為に必要な製造品の量を、生産必要量算定処理部32の場合と同様にして当該管理工程の歩留等の値を用いて算出する。   In step 1106, the production requirement amount of the determined previous process is calculated. That is, for the production required amount in the process plan that has been copied to the memory, the amount of manufactured product necessary to provide the production necessary amount to the subsequent process is the same as in the case of the production requirement calculation processing unit 32. Thus, it is calculated using the value of the yield of the management process.

ステップ1107では、前記判定された前工程の工程計画を立案する。すなわち、前記算出された前工程で処理する製造品の量について、前記の負荷山積展開シミュレーション処理と同様の処理を行い、当該管理工程における工程計画を決定する。そして、その決定した工程計画を工程計画情報テーブル15中に格納した後、前記メモリにコピーしておいた工程計画データをこのステップで決定した工程計画データで更新し、その次の前工程についても前記と同様の処理を行う。   In step 1107, a process plan for the determined previous process is created. That is, a process similar to the load pile development simulation process is performed on the calculated amount of the manufactured product to be processed in the previous process, and a process plan in the management process is determined. After the determined process plan is stored in the process plan information table 15, the process plan data copied to the memory is updated with the process plan data determined in this step, and the next previous process is also updated. The same processing as described above is performed.

一方、ステップ1108では、ステップ1102でメモリ上に格納したコア管理工程の工程計画データから、ステップ1103で読み出されている製造品名の工程計画データをメモリ上の他の領域にコピーした後、前記メモリに格納しておいたコア管理工程コードを前記検索対象管理工程コードに格納し、その検索対象管理工程コードが最も下流の管理工程コードに達するまでステップ1109からステップ1111までの処理を繰り返すことにより、コア管理工程よりも下流に位置する管理工程の工程計画を順次立案する。   On the other hand, in step 1108, after copying the process plan data of the product name read in step 1103 from the process plan data of the core management process stored in the memory in step 1102 to the other area on the memory, By storing the core management process code stored in the memory in the search target management process code and repeating the processing from step 1109 to step 1111 until the search target management process code reaches the most downstream management process code. Develop process plans for management processes located downstream from the core management process.

ステップ1109では、前記検索位置情報で示される管理工程の後工程を検索する。すなわち、前記検索対象管理工程コードに「1」加算した後、検索対象管理工程コードで示される管理工程の製造ラインNoを管理工程マトリックステーブル8から読み出して、ステップ1103でメモリに格納しておいた製造ラインNoと比較し、それらが一致する場合には検索対象管理工程コードで示される管理工程が後工程であると判定する。また、一致しない場合には更に前記検索対象管理工程コードに「1」加算して次の管理工程の製造ラインNoとの比較を行う。   In step 1109, a subsequent process of the management process indicated by the search position information is searched. That is, after adding “1” to the search object management process code, the production line number of the management process indicated by the search object management process code is read from the management process matrix table 8 and stored in the memory in step 1103. Compared with the production line No. If they match, it is determined that the management process indicated by the search target management process code is a subsequent process. If they do not match, “1” is further added to the search target management process code and compared with the production line number of the next management process.

ステップ1110では、前記判定された後工程の生産必要量を算出する。すなわち、前記メモリにコピーしておいた工程計画中の生産必要量にその管理工程での歩留を乗じた量の製造品が後工程に提供されるものとして、その後工程で処理する製造品の量を算出する。   In step 1110, the required production amount of the determined post-process is calculated. That is, it is assumed that a product manufactured by multiplying the production requirement in the process plan copied to the memory by the yield in the management process is provided to the subsequent process. Calculate the amount.

ステップ1111では、前記判定された後工程の工程計画を立案する。すなわち、前記算出された後工程で処理する製造品の量について、前記の負荷山積展開シミュレーション処理と同様の処理を行い、当該管理工程における工程計画を決定する。そして、その決定した工程計画を工程計画情報テーブル15中に格納した後、前記メモリにコピーしておいた工程計画データをこのステップで決定した工程計画データで更新し、その次の後工程についても前記と同様の処理を行う。   In step 1111, a process plan for the determined post-process is created. That is, a process similar to the load pile development simulation process is performed on the calculated amount of manufactured product to be processed in the subsequent process, and a process plan in the management process is determined. Then, after the determined process plan is stored in the process plan information table 15, the process plan data copied to the memory is updated with the process plan data determined in this step, and the subsequent subsequent process is also updated. The same processing as described above is performed.

図12は本実施形態の所要量計画処理部18の処理フローを示す図である。図12に示す様に本実施形態においては、中長期売上計画・月次生産計画及び、週次工程計画に基づいて、資材所要量計画を製品勘定部門毎に自動策定し、部門固有資材、部門共通資材(まとめ発注)、中長期戦略資材を分類体系管理し、日別MRPを展開し、確定納期資材発注依頼処理を行う。   FIG. 12 is a diagram showing a processing flow of the requirement plan processing unit 18 of the present embodiment. As shown in FIG. 12, in this embodiment, a material requirement plan is automatically formulated for each product account department based on a medium- to long-term sales plan, a monthly production plan, and a weekly process plan. Manages the classification system for common materials (bundled ordering) and medium- to long-term strategic materials, develops daily MRP, and processes material order requests for fixed delivery dates.

以下、処理フローに従って、S100からS900について説明する。先ず所要量計画処理部18は、当日材料在庫データを読み出し、以下の処理ステップの実行準備を行う(ステップS100)。   Hereinafter, S100 to S900 will be described according to the processing flow. First, the requirement planning processing unit 18 reads out the material stock data on the day and prepares for execution of the following processing steps (step S100).

次に、今回の管理工程計画の材料分解を行い、日別使用量算出データを取り込む(ステップS200)。次に、前回所要量計画発注残データを取り込む(ステップS300)。次に、所要量の日別発注予定量の算出を行う(ステップS400)。次に、サプライヤーのロット指定情報を入力する(ステップS500)。   Next, material decomposition of the current management process plan is performed, and daily usage amount calculation data is captured (step S200). Next, the previous requirement plan order remaining data is fetched (step S300). Next, the daily planned order quantity for the required quantity is calculated (step S400). Next, supplier lot designation information is input (step S500).

次に、中長期購入戦略品の所要量計画として、例えば当期・翌期、翌々期月別発注計画を行う(ステップS600)。次に、部門共通材料の所要量計画管理として、例えば部門別所要量の日別発注量計画を行う。(ステップS700)。次に、部門固有材料の所要量計画管理として、例えば部門別所要量の日別発注量計画を行う(ステップS800)。最後に、発注依頼確定処理として、例えば(1)中長期購入戦略品、(2)部門共通材料、(3)部門固有材料を行う構成にしている(ステップS900)。   Next, as a required amount plan for the medium- to long-term purchase strategy product, for example, an order plan for the current period, the next period, and the next period is performed (step S600). Next, as the requirement plan management of the department common material, for example, the daily order quantity plan of the department requirement is performed. (Step S700). Next, as the requirement plan management of the department-specific material, for example, a daily order quantity plan for the department-specific requirement is performed (step S800). Finally, as the order request confirmation process, for example, (1) medium to long-term purchase strategy product, (2) department common material, and (3) department specific material are configured (step S900).

図13は本実施形態の生産必要量策定対象一覧画面のレイアウトを示す図である。図13に示す様に本実施形態に係る生産必要量策定対象一覧画面では、製品勘定部門毎に受注情報、前記受注残情報に基づいてコア管理工程の工程計画情報を表示している。尚、受注残情報に紐付けされない作業仕掛在庫が存在する場合に限り、コア管理工程を基点にして、仕掛在庫情報を加味した前後管理工程を設定・表示を行うものとする。また受注情報では、受注残の数物量、納期、特急区分等の表示を行う。   FIG. 13 is a diagram showing the layout of the production requirement formulation target list screen of the present embodiment. As shown in FIG. 13, in the production requirement formulation target list screen according to the present embodiment, the process plan information of the core management process is displayed for each product account department based on the order information and the remaining order information. It should be noted that only when there is a work-in-process inventory that is not linked to the remaining order information, the pre- and post-management processes that take into account the work-in-progress inventory information are set and displayed based on the core management process. In the order information, the number of remaining orders, delivery date, express category, etc. are displayed.

図14は本実施形態の工程計画・進捗実績管理一覧画面のレイアウトを示す図である。図14に示す様に本実施形態に係る工程計画・進捗実績管理一覧画面では、製品勘定部門毎の全管理工程の計画と実績進捗管理を行う際に、生産性情報を即時提供すると共に、異常発生時にアラートを発し、その異常に対する是正措置の入力とフィードバック機能を実行する際のユーザインタフェースを提供している。   FIG. 14 is a diagram showing a layout of the process plan / progress result management list screen of the present embodiment. As shown in FIG. 14, in the process plan / progress result management list screen according to the present embodiment, productivity information is provided immediately when performing plan and result progress management for all management processes for each product account department, An alert is issued when an error occurs, and a user interface is provided for executing corrective action input and feedback functions for the abnormality.

本実施形態においては、基本情報は作業指示日、着手実績日時、特急区分、遅延日数等により構成される。計画情報は生産性管理基準に基づいた各管理工程の計画数物量と歩留まりを加味した実行数物量等により構成させている。実績情報は作業進捗情報である工程進捗情報、実績数物量、品質情報等により構成させている。生産性情報は実績トランザクション情報と生産性管理基準を随時対比させ、歩留まり生産性、工数リードタイム生産性、不良品質情報等により構成させている。   In the present embodiment, the basic information is composed of a work instruction date, an actual start date / time, an express category, a delay days, and the like. The plan information is composed of the planned quantity of each management process based on the productivity management standard and the number of executed quantities taking into account the yield. The track record information is composed of process progress information that is work progress information, the number of track records, quality information, and the like. The productivity information is composed of yield transaction productivity, man-hour lead time productivity, defect quality information, and the like by comparing actual transaction information and productivity management standards as needed.

以上説明した様に本実施形態の統合生産管理システムによれば、生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程の工程計画を基点として上流及び下流の工程計画を順次立案するので、生産プロセス全体にわたる操業計画の一元的立案による顧客要求納期への対応力向上と棚卸資産の最小化を行うことが可能である。   As described above, according to the integrated production management system of the present embodiment, the upstream and downstream process plans are sequentially developed based on the process plan of the core management process which is the basis for controlling the entire operation plan in the production process. As a result, it is possible to improve the ability to meet customer demand deadlines and minimize inventory by centralizing the operation plan throughout the production process.

また本実施形態の統合生産管理システムによれば、生産プロセス全体にわたる操業計画の一元的立案による工程計画の内容と工程実績進捗情報の内容とを比較して工程計画の微調整を行うので、生産性情報の即時フィードバックによる設備稼働率・生産性の最大化を実現することが可能である。   Further, according to the integrated production management system of the present embodiment, the contents of the process plan based on the unified planning of the operation plan over the entire production process are compared with the contents of the process result progress information, so that the process plan is finely adjusted. It is possible to maximize equipment availability and productivity through immediate feedback of sex information.

1…生産計画手段、2…所要量計画手段、3…コア管理工程、4…情報の流れ、5…モノの流れ、6…資材発注管理基準テーブル、7…製造仕様設計管理テーブル、8…管理工程マトリックステーブル、9…生産性管理基準テーブル、10…ネットワーク手段、14…工程実績進捗情報テーブル、15…工程計画情報テーブル、16…工程実績情報テーブル、31…コア管理工程設定処理部、32…生産必要量算定処理部、33…負荷山積展開シミュレーション処理部、34…工程計画立案処理部、35…資材所要量計画処理部、36…上流・下流管理工程展開処理部、37…工程生産制約条件チェック処理部、38…是正措置、20…全工程計画展開、17…工程計画実績MRP変動対応/生産活動実需ローリング処理手段、18…所要量計画処理部、19…生産性管理アラート処理部、22…計画制約条件テーブル、23…段取切替時間展開テーブル、801〜812…管理工程、821〜823…製造ライン、901…製造ラインNo、902…製品名、903…生産性管理基準書No、904…製造仕様設計書No、905…管理工程コード。 DESCRIPTION OF SYMBOLS 1 ... Production planning means, 2 ... Requirements planning means, 3 ... Core management process, 4 ... Information flow, 5 ... Material flow, 6 ... Material order management reference table, 7 ... Manufacturing specification design management table, 8 ... Management Process matrix table, 9 ... productivity management reference table, 10 ... network means, 14 ... process performance progress information table, 15 ... process plan information table, 16 ... process performance information table, 31 ... core management process setting processing unit, 32 ... Production required quantity calculation processing unit, 33 ... load pile development simulation processing unit, 34 ... process plan planning processing unit, 35 ... material requirement planning processing unit, 36 ... upstream / downstream management process development processing unit, 37 ... process production constraint conditions Check processing unit, 38 ... corrective action, 20 ... development of all process plans, 17 ... process plan results MRP fluctuation response / production activity actual demand rolling processing means, 18 ... required amount Image processing unit, 19 ... Productivity management alert processing unit, 22 ... Plan constraint table, 23 ... Setup switching time expansion table, 801-812 ... Management process, 821-823 ... Production line, 901 ... Production line No, 902 ... manufacturing product name, 903 ... productivity management standards No, 904 ... manufacturing specifications design document No, 905 ... management process code.

Claims (3)

複数の管理工程からなる製造ラインでの最終完成品である製品の生産プロセスを管理し、前記任意の管理工程での負荷山積シミュレーションを行い全管理工程の工程計画を立案し、中長期売上計画、月次生産計画及び週次工程計画の情報に基づき、資材所要量を算出する統合生産管理システムにおける統合生産管理方法において、
前記統合生産管理システムは、前記製品の各管理工程における名称を示す製造品名、リードタイム、歩留、材料品種名及びその使用量の情報を含む各管理工程に関連する情報と、受注残情報、見込み生産情報を記憶する記憶手段と、情報処理手段と、を備え、
前記情報処理手段により、
前記記憶手段に記憶されている情報に基づき、前記生産プロセスを構成する複数の管理工程の内、多品種の製品を処理する管理工程、または前記リードタイムの最も長い管理工程、または多品種の材料を多量に消費する管理工程を、前記生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程として決定し、当該コア管理工程識別情報をメモリに格納する第1の処理と、
前記受注残情報及び前記見込み生産情報から決定される最終的な、最下流管理工程の製品生産量を算出し、前記コア管理工程から最下流管理工程までの各管理工程での製品歩留情報とを用いてコア管理工程から最下流管理工程までの累積歩留を算出し、累積歩留で前記最下流管理工程の製品生産量を除算する処理により、該コア管理工程で処理しなければならない前記製造品の必要量を算出する第2の処理と、
前記算出された該コア管理工程の前記製造品の必要量を生産する際のコア管理工程での負荷山積展開シミュレーションを行って該コア管理工程の最適な工程計画を立案し、該コア管理工程の最適な負荷山積工程計画における日別の資材所要量計画(MRP)を資材所要量処理部にて策定する第3の処理と、
前記製造品の必要量を設定したコア管理工程を基点として、各管理工程のリードタイム、歩留りの情報を持つ生産性管理基準テーブルと、各管理工程の進捗情報を持つ工程実績進捗情報テーブルに基づき、当該コア管理工程の上流管理工程及び下流管理工程の前記製造品の必要量及び各管理工程の負荷山積計画を連鎖的に自動作成する第4の処理と、
前記全管理工程の負荷山積計画に基づいて資材所要量処理部にて資材発注につなげる日別の資材所要量計画(MRP)を展開策定する第5の処理と、
前記第5の処理まで実施した結果が顧客要求納期を含む生産計画の内容とその管理工程の設備能力や制約条件に合わない場合に、是正措置を実施して前記第2の処理から前記第5の処理を繰り返し行い、最適な全管理工程計画を策定する第6の処理と、を実施する、
ことを特徴とする統合生産管理方法。
Manage the production process of products that are final finished products in a production line consisting of multiple management processes, perform load pile simulation in the above-mentioned arbitrary management processes, draft process plans for all management processes, In the integrated production management method in the integrated production management system that calculates the material requirements based on the information of the monthly production plan and the weekly process plan,
The integrated production management system includes a product name, a lead time, a yield, a material type name, and information on the amount of use and information related to each management process indicating a name in each management process of the product; Storage means for storing the expected production information, and information processing means,
By the information processing means,
Based on the information stored in the storage means, among the plurality of management steps constituting the production process, a management step for processing a wide variety of products, or a management step with the longest lead time, or a variety of materials the large amounts manage consuming process, said determined as a core management process comprising the cornerstone for controlling the entire operation plan on the production process, a first process of storing the core management process identification information in a memory,
Calculate final product production amount of the most downstream management process determined from the backlog information and the expected production information, and product yield information in each management process from the core management process to the most downstream management process; calculating the cumulative yield of from the core control step to the most downstream management process using, by the process of dividing the product yield of the most downstream management process in a cumulative yield, it must be treated with the core control step wherein A second process for calculating the required amount of manufactured goods;
Formulates an optimal process plan of the core control step performs load piling deployment simulation in the core control step in producing the required amount of the manufactured goods of the calculated the core management process, the core management process A third process for formulating a daily material requirement plan (MRP) in the optimum load pile process plan in the material requirement processing unit;
Based on the core management process that sets the required amount of the manufactured product as a base, based on the productivity management reference table that has the lead time and yield information of each management process, and the process performance progress information table that has the progress information of each management process a fourth processing required amount of the manufactured goods of the upstream control step and downstream management step of the core management process and the load piling plan for each control step to create automatically a chain reaction,
A fifth process for developing and formulating a daily material requirement plan (MRP) that leads to material ordering in the material requirement processing unit based on the load pile plan of all the management processes;
When the result of the execution up to the fifth process does not match the contents of the production plan including the customer requested delivery date and the facility capacity and constraint conditions of the management process, corrective measures are taken and the second process to the fifth process are performed. Repeat the above process and implement the 6th process to formulate an optimal all management process plan.
An integrated production management method characterized by that.
複数の管理工程からなる製造ラインでの最終完成品である製品の生産プロセスを管理し、前記任意の管理工程での負荷山積シミュレーションを行い全管理工程の工程計画を立案し、中長期売上計画、月次生産計画及び週次工程計画の情報に基づき、資材所要量を算出する統合生産管理システムにおいて、
前記製品の各管理工程における名称を示す製造品名、リードタイム、歩留、材料品種名及びその使用量の情報を含む各管理工程に関連する情報と、受注残情報、見込み生産情報を記憶する記憶手段と、情報処理手段と、を備え、
前記情報処理手段により、
前記記憶手段に記憶されている情報に基づき、前記生産プロセスを構成する複数の管理工程の内、多品種の製品を処理する管理工程、または前記リードタイムの最も長い管理工程、または多品種の材料を多量に消費する管理工程を、前記生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程として決定し、当該コア管理工程識別情報をメモリに格納する第1の処理と、
前記受注残情報及び前記見込み生産情報から決定される最終的な、最下流管理工程の製品生産量を算出し、前記コア管理工程から最下流管理工程までの各管理工程での製品歩留情報とを用いてコア管理工程から最下流管理工程までの累積歩留を算出し、累積歩留で前記最下流管理工程の製品生産量を除算する処理により、該コア管理工程で処理しなければならない前記製造品の必要量を算出する第2の処理と、
前記算出された該コア管理工程の前記製造品の必要量を生産する際のコア管理工程での負荷山積展開シミュレーションを行って該コア管理工程の最適な工程計画を立案し、該コア管理工程の最適な負荷山積工程計画における日別の資材所要量計画(MRP)を資材所要量処理部にて策定する第3の処理と、
前記製造品の必要量を設定したコア管理工程を基点として、各管理工程のリードタイム、歩留りの情報を持つ生産性管理基準テーブルと、各管理工程の進捗情報を持つ工程実績進捗情報テーブルに基づき、当該コア管理工程の上流管理工程及び下流管理工程の前記製造品の必要量及び各管理工程の負荷山積計画を連鎖的に自動作成する第4の処理と、
前記全管理工程の負荷山積計画に基づいて資材所要量処理部にて資材発注につなげる日別の資材所要量計画(MRP)を展開策定する第5の処理と、
前記第5の処理まで実施した結果が顧客要求納期を含む生産計画の内容とその管理工程の設備能力や制約条件に合わない場合に、是正措置を実施して前記第2の処理から前記第5の処理を繰り返し行い、最適な全管理工程計画を策定する第6の処理と、を実施する、
ことを特徴とする統合生産管理システム。
Manage the production process of products that are final finished products in a production line consisting of multiple management processes, perform load pile simulation in the above-mentioned arbitrary management processes, draft process plans for all management processes, In an integrated production management system that calculates material requirements based on information on monthly production plans and weekly process plans,
Storage for storing information related to each management process including information on the name of the product in each management process, product name, lead time, yield, material type name and usage amount, order backlog information, and expected production information Means and information processing means,
By the information processing means,
Based on the information stored in the storage means, among the plurality of management steps constituting the production process, a management step for processing a wide variety of products, or a management step with the longest lead time, or a variety of materials the large amounts manage consuming process, said determined as a core management process comprising the cornerstone for controlling the entire operation plan on the production process, a first process of storing the core management process identification information in a memory,
Calculate final product production amount of the most downstream management process determined from the backlog information and the expected production information, and product yield information in each management process from the core management process to the most downstream management process; calculating the cumulative yield of from the core control step to the most downstream management process using, by the process of dividing the product yield of the most downstream management process in a cumulative yield, it must be treated with the core control step wherein A second process for calculating the required amount of manufactured goods;
Formulates an optimal process plan of the core control step performs load piling deployment simulation in the core control step in producing the required amount of the manufactured goods of the calculated the core management process, the core management process A third process for formulating a daily material requirement plan (MRP) in the optimum load pile process plan in the material requirement processing unit;
Based on the core management process that sets the required amount of the manufactured product as a base, based on the productivity management reference table that has the lead time and yield information of each management process, and the process performance progress information table that has the progress information of each management process a fourth processing required amount of the manufactured goods of the upstream control step and downstream management step of the core management process and the load piling plan for each control step to create automatically a chain reaction,
A fifth process for developing and formulating a daily material requirement plan (MRP) that leads to material ordering in the material requirement processing unit based on the load pile plan of all the management processes;
When the result of the execution up to the fifth process does not match the contents of the production plan including the customer requested delivery date and the facility capacity and constraint conditions of the management process, corrective measures are taken and the second process to the fifth process are performed. Repeat the above process and implement the 6th process to formulate an optimal all management process plan.
Integrated production management system characterized by that.
複数の管理工程からなる製造ラインでの最終完成品である製品の生産プロセスを管理し、前記任意の管理工程での負荷山積シミュレーションを行い全管理工程の工程計画を立案し、中長期売上計画、月次生産計画及び週次工程計画の情報に基づき、資材所要量を算出する統合生産管理システムにおける統合生産管理方法をコンピュータに実行させる為のプログラムにおいて、
前記統合生産管理システムは、前記製品の各管理工程における名称を示す製造品名、リードタイム、歩留、材料品種名及びその使用量の情報を含む各管理工程に関連する情報と、受注残情報、見込み生産情報を記憶する記憶手段と、情報処理手段と、を備え、
前記情報処理手段により、
前記記憶手段に記憶されている情報に基づき、前記生産プロセスを構成する複数の管理工程の内、多品種の製品を処理する管理工程、または前記リードタイムの最も長い管理工程、または多品種の材料を多量に消費する管理工程を、前記生産プロセス上の操業計画全体をコントロールする為の基軸となるコア管理工程として決定し、当該コア管理工程識別情報をメモリに格納する第1の処理と、
前記受注残情報及び前記見込み生産情報から決定される最終的な、最下流管理工程の製品生産量を算出し、前記コア管理工程から最下流管理工程までの各管理工程での製品歩留情報とを用いてコア管理工程から最下流管理工程までの累積歩留を算出し、累積歩留で前記最下流管理工程の製品生産量を除算する処理により、該コア管理工程で処理しなければならない前記製造品の必要量を算出する第2の処理と、
前記算出された該コア管理工程の前記製造品の必要量を生産する際のコア管理工程での負荷山積展開シミュレーションを行って該コア管理工程の最適な工程計画を立案し、該コア管理工程の最適な負荷山積工程計画における日別の資材所要量計画(MRP)を資材所要量処理部にて策定する第3の処理と、
前記製造品の必要量を設定したコア管理工程を基点として、各管理工程のリードタイム、歩留りの情報を持つ生産性管理基準テーブルと、各管理工程の進捗情報を持つ工程実績進捗情報テーブルに基づき、当該コア管理工程の上流管理工程及び下流管理工程の前記製造品の必要量及び各管理工程の負荷山積計画を連鎖的に自動作成する第4の処理と、
前記全管理工程の負荷山積計画に基づいて資材所要量処理部にて資材発注につなげる日別の資材所要量計画(MRP)を展開策定する第5の処理と、
前記第5の処理まで実施した結果が顧客要求納期を含む生産計画の内容とその管理工程の設備能力や制約条件に合わない場合に、是正措置を実施して前記第2の処理から前記第5の処理を繰り返し行い、最適な全管理工程計画を策定する第6の処理と、を実施する、
ことをコンピュータに実行させる為のプログラム。
Manage the production process of products that are final finished products in a production line consisting of multiple management processes, perform load pile simulation in the above-mentioned arbitrary management processes, draft process plans for all management processes, In a program for causing a computer to execute an integrated production management method in an integrated production management system that calculates material requirements based on information of a monthly production plan and a weekly process plan,
The integrated production management system includes a product name, a lead time, a yield, a material type name, and information on the amount of use and information related to each management process indicating a name in each management process of the product; Storage means for storing the expected production information, and information processing means,
By the information processing means,
Based on the information stored in the storage means, among the plurality of management steps constituting the production process, a management step for processing a wide variety of products, or a management step with the longest lead time, or a variety of materials the large amounts manage consuming process, said determined as a core management process comprising the cornerstone for controlling the entire operation plan on the production process, a first process of storing the core management process identification information in a memory,
Calculate final product production amount of the most downstream management process determined from the backlog information and the expected production information, and product yield information in each management process from the core management process to the most downstream management process; calculating the cumulative yield of from the core control step to the most downstream management process using, by the process of dividing the product yield of the most downstream management process in a cumulative yield, it must be treated with the core control step wherein A second process for calculating the required amount of manufactured goods;
Formulates an optimal process plan of the core control step performs load piling deployment simulation in the core control step in producing the required amount of the manufactured goods of the calculated the core management process, the core management process A third process for formulating a daily material requirement plan (MRP) in the optimum load pile process plan in the material requirement processing unit;
Based on the core management process that sets the required amount of the manufactured product as a base, based on the productivity management reference table that has the lead time and yield information of each management process, and the process performance progress information table that has the progress information of each management process a fourth processing required amount of the manufactured goods of the upstream control step and downstream management step of the core management process and the load piling plan for each control step to create automatically a chain reaction,
A fifth process for developing and formulating a daily material requirement plan (MRP) that leads to material ordering in the material requirement processing unit based on the load pile plan of all the management processes;
When the result of the execution up to the fifth process does not match the contents of the production plan including the customer requested delivery date and the facility capacity and constraint conditions of the management process, corrective measures are taken and the second process to the fifth process are performed. Repeat the above process and implement the 6th process to formulate an optimal all management process plan.
A program that causes a computer to execute this.
JP2010138081A 2010-06-17 2010-06-17 A method and system for integrated production management with full development of core management process using management process matrix table Expired - Lifetime JP5068845B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010138081A JP5068845B2 (en) 2010-06-17 2010-06-17 A method and system for integrated production management with full development of core management process using management process matrix table

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010138081A JP5068845B2 (en) 2010-06-17 2010-06-17 A method and system for integrated production management with full development of core management process using management process matrix table

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2003077324A Division JP2004287693A (en) 2003-03-20 2003-03-20 Core management process full-expansion type integrated production management method and system using management process matrix table

Publications (2)

Publication Number Publication Date
JP2010257476A JP2010257476A (en) 2010-11-11
JP5068845B2 true JP5068845B2 (en) 2012-11-07

Family

ID=43318242

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010138081A Expired - Lifetime JP5068845B2 (en) 2010-06-17 2010-06-17 A method and system for integrated production management with full development of core management process using management process matrix table

Country Status (1)

Country Link
JP (1) JP5068845B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101373369B1 (en) * 2011-04-21 2014-03-13 주식회사 썬스타 Network-Based Production Management System And Method

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0790450B2 (en) * 1987-04-14 1995-10-04 株式会社日立製作所 Multi-product flow shop production method
JPH077286B2 (en) * 1988-08-03 1995-01-30 日本電気株式会社 Flow shop production system simulation device
JPH04233073A (en) * 1990-12-28 1992-08-21 Fujitsu Ltd Method for piling-up loads
JP2513543B2 (en) * 1991-07-25 1996-07-03 新日本製鐵株式会社 Production management system in the steel industry
JPH07182420A (en) * 1993-12-22 1995-07-21 Kobe Steel Ltd Production planning device
JP2973930B2 (en) * 1996-06-28 1999-11-08 日本電気株式会社 Production planning simulation device
JPH11852A (en) * 1997-06-12 1999-01-06 Honda Motor Co Ltd Machining schedule planning system
JP2000113080A (en) * 1998-10-06 2000-04-21 Open Manufacturing Kk Method for managing product of supply chain
JP2000148855A (en) * 1998-11-13 2000-05-30 Nippon Steel Corp Device and method for making schedule and recording medium
JP2001282341A (en) * 2000-03-30 2001-10-12 Nec Corp System and method for production planning and system and method for material required calculation and recording medium
JP2002073149A (en) * 2000-08-31 2002-03-12 Teijin Ltd Production planning method and integrated operation system for dyeing factory
JP2002244716A (en) * 2001-02-15 2002-08-30 Hitachi Ltd Line capacity evaluation system

Also Published As

Publication number Publication date
JP2010257476A (en) 2010-11-11

Similar Documents

Publication Publication Date Title
US6876895B2 (en) Order assembly production system and method
US6119102A (en) MRP system with viewable master production schedule
US7853491B2 (en) Purchase orders based on purchasing list, capacity plans, assortment plans, and area spread assortment plans
CN112270444B (en) Lightweight APS double-bridge planning system
JP2004517378A (en) Systems and methods for optimizing shipping and transportation
JP2006503352A (en) Systems and methods for improving planning, scheduling and supply chain management
EP1350177A1 (en) System and method for optimizing resource plans
US7584113B2 (en) Method for simultaneously considering customer commit dates and customer request dates
JP2004021364A (en) Management intention decision support system
JP2007323680A (en) Management decision support system
JP2011065224A (en) Supply chain efficiency improvement support method
JP2008152382A (en) Production plan preparation system and production plan preparation method
JP4966831B2 (en) Material requirements planning device, material requirements planning method, and material requirements planning program
JP2002541564A (en) System and method for scheduling manufacturing resources
JP2009301466A (en) Efficiency enhancement support method for supply chain
WO2016079843A1 (en) Production plan adjustment assisting device and production plan adjustment assisting method
JP5068845B2 (en) A method and system for integrated production management with full development of core management process using management process matrix table
JP5089352B2 (en) Sales production planning system, operation method of sales production planning system, and computer program
TW573270B (en) Multiple constrains planning and scheduling system
JP2010244228A (en) Support method for efficiency promotion of supply chain
JP2010055258A (en) Method for supporting improvement in supply chain efficiency
JP2004287693A (en) Core management process full-expansion type integrated production management method and system using management process matrix table
JP4239767B2 (en) Design change support system, design change method, design change support program, and recording medium recording the same
JP2011170737A (en) Method for supporting promotion of efficiency of supply chain
JP2011123912A (en) Sales, production, and delivery system, and sales, production, and delivery method of steel plate steel strip product

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120127

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120207

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120405

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120814

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120815

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150824

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5068845

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150824

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term