JP4388413B2 - Pile head treatment method for cast-in-place concrete piles - Google Patents

Pile head treatment method for cast-in-place concrete piles Download PDF

Info

Publication number
JP4388413B2
JP4388413B2 JP2004145119A JP2004145119A JP4388413B2 JP 4388413 B2 JP4388413 B2 JP 4388413B2 JP 2004145119 A JP2004145119 A JP 2004145119A JP 2004145119 A JP2004145119 A JP 2004145119A JP 4388413 B2 JP4388413 B2 JP 4388413B2
Authority
JP
Japan
Prior art keywords
pile
concrete
pile head
treatment material
defective
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2004145119A
Other languages
Japanese (ja)
Other versions
JP2005325607A (en
Inventor
宗一 木谷
光範 洗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2004145119A priority Critical patent/JP4388413B2/en
Publication of JP2005325607A publication Critical patent/JP2005325607A/en
Application granted granted Critical
Publication of JP4388413B2 publication Critical patent/JP4388413B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

この発明は、場所打ちコンクリート杭の杭頭部に発生する不良コンクリート部分を静的に無騒音、無振動に近い状態で除去処理する杭頭処理工法の技術分野に属する。   The present invention belongs to a technical field of a pile head processing method in which a defective concrete portion generated at a pile head of a cast-in-place concrete pile is statically removed without noise and vibration.

場所打ちコンクリート杭の構築においては、杭頭部に、杭孔掘削時の不純物が混じったり安定液に晒されて劣化した不良コンクリート部分が発生する。そこで通例は、杭頭部を杭の有効部よりも不良コンクリート部分の長さ分だけ高く打ち上げ(余盛り)、コンクリートの硬化後に前記不良コンクリート部分を除去することが行われている。
上記不良コンクリート部分の除去方法として、古くはブレーカー等で斫り取る方法が一般的に実施されてきた。しかし、この作業には大きな振動と騒音を伴い、環境を損なう公害問題を発生するほか、市街地では作業時間を制限される等々の問題点を抱えている。
その他、コンクリート打設直後の未だ硬化しない段階で、不良コンクリート部分をバキューム吸引装置で吸引し除去する方法も実施される。しかし、吸引装置の設置場所が場所打ちコンクリート杭の不良コンクリート部分の位置よりもはるかに高いと、物理的に吸引除去ができないという欠陥があるほか、吸引した不良コンクリートの処理費用などが嵩み、施工単価が高いという問題点も指摘されている。
In the construction of cast-in-place concrete piles, the pile head is contaminated with impurities during excavation of the pile holes or exposed to stable liquid, resulting in deteriorated defective concrete parts. Therefore, usually, the pile head is raised (excess) by the length of the defective concrete portion higher than the effective portion of the pile, and the defective concrete portion is removed after the concrete is hardened.
As a method for removing the defective concrete portion, a method of scraping with a breaker or the like has been generally used in the past. However, this work involves a lot of vibration and noise, and causes pollution problems that damage the environment. In addition, the work time is limited in urban areas.
In addition, a method of sucking and removing a defective concrete portion with a vacuum suction device at a stage where the concrete has not yet hardened immediately after placing the concrete is also carried out. However, if the installation location of the suction device is much higher than the position of the defective concrete part of the cast-in-place concrete pile, there is a defect that it cannot be physically removed by suction, and the processing cost of the sucked defective concrete is increased, The problem of high construction unit cost has also been pointed out.

一方、下記の特許文献1ほかに、不良コンクリート部分(余盛りコンクリート)を固めないように遅延剤を混入して処理する杭頭余盛りコンクリート処理機が開示されている。固めないコンクリートは、例えば杭孔に接して掘った横穴へ横流しをして除去する。しかし、この方法も、杭頭部が地盤面に近い高さである場合にのみ施工可能であり、施工条件の制約が厳しい。
下記の特許文献2その他多数に、杭孔へ打設したコンクリートが未だ硬化しない段階で、不良コンクリート部分へ混和剤やアルミ粉等の破壊剤、又は発泡剤を水に溶かした懸濁液、或いはベントナイト溶液に粘調性高分子化合物を混合した溶液などのいわゆる強度劣化剤を注入、攪拌してコンクリート強度を低下させ、杭頭処理を容易にする方法が開示されている。しかし、使用する強度劣化剤が高価である上に、予定した薬効が確実に得られず、杭頭処理に難渋する場合が多々あり、確実性に欠ける。
On the other hand, in addition to the following patent document 1, a pile head surplus concrete processing machine is disclosed that mixes and processes a retarder so as not to harden a defective concrete portion (extra concrete). The concrete which is not hardened is removed by, for example, flowing into a side hole dug in contact with the pile hole. However, this method can also be constructed only when the pile head is close to the ground surface, and the construction conditions are severely restricted.
In the following Patent Document 2 and many others, in the stage where the concrete placed in the pile hole has not yet hardened, a suspension in which a destructive agent such as an admixture or aluminum powder or a foaming agent is dissolved in water, or a defective concrete part, A method is disclosed in which a so-called strength degrading agent such as a solution obtained by mixing a viscous polymer compound in a bentonite solution is injected and stirred to reduce the concrete strength and facilitate the pile head treatment. However, the strength deterioration agent to be used is expensive, and the planned medicinal effect cannot be obtained with certainty, and there are many cases where it is difficult to treat the pile head, and the certainty is lacking.

特許文献3には、コンクリート切削用のビットを取り付けたアースドリル状の杭頭処理装置で、不良コンクリート部分のうち杭主筋の内側部分のコンクリートを切削除去する方法が開示されている。しかし、切削時の振動、騒音の発生を避けられないし、杭主筋の外側部分に残存するコンクリートを解砕し除去する作業を別途行わなければならないので、必ずしも作業効率が高いとはいえない。
特許文献4には、杭孔へ打設したコンクリートが未だ硬化しない段階で、杭主筋の内側部分の不良コンクリート部分へ、環状枠の内側へ薄板による格子を縦に形成した治具を沈めてコンクリートの硬化状況を見極め、一定時間の経過後に前記治具を引き上げて不良コンクリート部分へ格子形の切れ目を形成する方法が開示されている。しかし、前記切れ目は完全に切れたままではなく、不完全に復旧するので、せいぜい不良コンクリートの斫り作業を少し容易にする程度の効果しか期待できない。
Patent Document 3 discloses a method of cutting and removing concrete in an inner portion of a pile main bar among defective concrete portions with an earth drill-like pile head processing apparatus attached with a bit for cutting concrete. However, the generation of vibration and noise during cutting cannot be avoided, and the work of crushing and removing the concrete remaining on the outer side of the pile main reinforcement must be performed separately, so the work efficiency is not necessarily high.
In Patent Document 4, when the concrete placed in the pile hole is not yet cured, the concrete is formed by sinking a jig in which a thin lattice is vertically formed inside the annular frame to the defective concrete portion inside the pile main bar. Is disclosed, and a method of forming a grid-like cut in a defective concrete part by lifting the jig after a certain time has elapsed is disclosed. However, since the cut is not completely cut and is restored incompletely, it can be expected that only the effect of slightly facilitating the work of scraping the defective concrete at most.

特許文献5には、杭主筋にコンクリートとの接触を断つ発泡ウレタン等の縁切り材を取り付け、同杭主筋の内側部へはコンクリートの打設前、又は打設後の未だコンクリートが硬化しない段階で、膨脹発現時間が異なる2種の静的膨脹破砕剤を取り付けた捨て治具を設置し、硬化した不良コンクリート部分を前記2種の静的膨脹破砕剤の膨脹作用により破砕する方法が開示されている。しかし、2種の静的膨脹破砕剤の膨脹作用によって、硬化した不良コンクリート部分の破砕が確実に行われるかは大いに疑問視される。
特許文献6には、杭孔へ打設したコンクリートが未だ硬化しない段階で、杭主筋の内側の不良コンクリート部分へ杭頭処理治具を押し込んで、杭の設計天端高さ位置にカット板を水平に設置し、コンクリートが硬化した後に、地盤を掘削して杭頭部分が露出した段階で、杭体の前記カット板の外周位置に切削溝を形成し、更に孔を開け、この孔に破砕工具を挿入し打撃を加えて前記カット板の位置でコンクリートを割裂させ、不良コンクリート部分を吊り上げて除去する方法が開示されている。しかし、カット板の設置や切削溝の形成、孔開け、並びに破砕工具を挿入し打撃を加えて前記カット板の位置で割裂させるまで、多くの手数と工具等の使用を必要とする。その割にカット板の位置でコンクリートを確実に割裂させることができるかに不安定要素が多くある。また、破砕工具に打撃を加えて割裂させるまでの間に騒音と振動の発生を避けられないという多くの問題点がある。
In Patent Document 5, an edge cutting material such as urethane foam that cuts contact with concrete is attached to the pile main reinforcement, and the concrete inside the pile main reinforcement is not yet hardened before or after the concrete is placed. A method for disposing hardened defective concrete parts by the expansion action of the two types of static expansion crushing agents by disposing a jig for attaching two types of static expansion crushing agents having different expansion onset times is disclosed. Yes. However, it is highly questionable whether the hardened defective concrete part can be reliably crushed by the expansion action of the two static expansion crushing agents.
In Patent Document 6, when the concrete placed in the pile hole is not yet cured, the pile head processing jig is pushed into the defective concrete portion inside the pile main reinforcement, and the cut plate is placed at the design top edge height position of the pile. Installed horizontally, and after the concrete has hardened, when the ground is excavated and the head of the pile is exposed, a cutting groove is formed in the outer peripheral position of the cut plate of the pile body, further holes are drilled, and the holes are crushed A method is disclosed in which a tool is inserted and hammered to split concrete at the position of the cut plate, and a defective concrete portion is lifted and removed. However, it takes a lot of work and the use of tools, etc., until the cutting plate is installed, the cutting groove is formed, the hole is drilled, and the crushing tool is inserted and hammered to split at the position of the cutting plate. On the other hand, there are many unstable factors in how concrete can be reliably split at the position of the cut plate. There are also many problems that noise and vibration are unavoidable before the crushing tool is hit and split.

その他、特許文献7には、コンクリート構造物の外周にワイヤーソーにより切断溝を形成し、この切断溝の内部に金属製袋体を挿入し、前記金属製袋体をポンプと接続し、ポンプの運転により前記金属製袋体へ高圧水を送り込んで膨脹させ、その膨脹力によりコンクリート構造物の割裂を進行させる切断方法が開示されている。   In addition, in Patent Document 7, a cutting groove is formed on the outer periphery of a concrete structure by a wire saw, a metal bag body is inserted into the cutting groove, the metal bag body is connected to a pump, A cutting method is disclosed in which high-pressure water is fed into the metal bag body by operation to be expanded, and the splitting of the concrete structure is advanced by the expansion force.

実公平3−24663号公報Japanese Utility Model Publication No. 3-24663 特開昭64−6413号公報Japanese Unexamined Patent Publication No. 64-6413 特公平7−6185号公報Japanese Patent Publication No. 7-6185 特開2002−212946号公報JP 2002-221946 A 特開平7−207661号公報Japanese Patent Laid-Open No. 7-207661 特許第2726241号公報Japanese Patent No. 2726241 特開2003−74197号公報JP 2003-74197 A

本発明の目的は、従来技術が抱える上述したような諸問題点を解決すること、具体的には振動や騒音の発生をなくし、施工条件の制約をなくし、施工費用を安価にし、施工の手間と時間の節減並びに工期の短縮を図ることができ、施工の確実性を期待できる場所打ちコンクリート杭の杭頭処理工法を提供することである。
本発明の次の目的は、上記の特許文献7に見られる流体圧ジャッキの静的破壊力に着目して、これを薄板形状に構成した杭頭処理材を効果的に用いる場所打ちコンクリート杭の杭頭処理工法を提供することである。
The object of the present invention is to solve the above-mentioned problems of the prior art, specifically, eliminate the occurrence of vibration and noise, eliminate the restrictions on the construction conditions, reduce the construction cost, and the labor of construction. It is to provide a pile head treatment method for cast-in-place concrete piles that can save time and shorten the construction period and can be expected to be reliable.
The next object of the present invention is to pay attention to the static destructive force of the fluid pressure jack found in the above-mentioned Patent Document 7, and to make a cast-in-place concrete pile that effectively uses a pile head treatment material configured in a thin plate shape. It is to provide a pile head processing method.

上述した従来技術の課題を解決するための手段として、請求項1に記載した発明に係る場所打ちコンクリート杭の杭頭処理工法は、
2枚の鉄板を上下に重ね合わせ、その内外の周辺部を溶接して密閉した袋構造で、入り口バルブ2aを備えた薄板形状流体圧ジャッキとして構成し、外径が杭孔4の孔径とほぼ等しく、内径は杭孔中心部へトレミー管を挿入可能な大きさのリング形状部材とされ、前記袋構造部分に杭鉄筋1の各主筋1aを通す孔2bを同一のピッチで貫通させて成る杭頭処理材2を、前記の各孔2bへ杭鉄筋1の各主筋1aを通して杭鉄筋上部の不良コンクリート領域の下限相当部位へ略水平に設置し、更に前記杭頭処理材2より上方へ立ち上がる杭主筋1aの外周にコンクリートと縁切りするチューブ形状の養生材3を取り付ける段階と、
前記構成とした杭鉄筋1を杭孔4の中へ建て込み、同杭孔4中へコンクリート6を打設する段階と、
打設コンクリートが硬化した後に、杭頭部の少なくとも前記杭頭処理材2が露出する深さまで地盤11の掘削を行う段階と、
露出した前記杭頭処理材2の入り口バルブ2a流体ポンプ8の配管8aを接続し、前記ポンプ8を運転して高圧流体を杭頭処理材2の袋構造中へ送り込み、薄板形状流体圧ジャッキとした杭頭処理材2を膨脹させて杭頭部のコンクリートと不良コンクリート6”との境界部に亀裂を生じさせ、不良コンクリート部分6”を破砕し除去する段階とから成ることを特徴とする。
As means for solving the above-described problems of the prior art, a pile head processing method for a cast-in-place concrete pile according to the invention described in claim 1 is:
It is configured as a thin plate-shaped fluid pressure jack with an inlet valve 2a with a bag structure in which two steel plates are stacked one above the other and the inner and outer peripheral portions are welded and sealed , and the outer diameter is substantially equal to the hole diameter of the pile hole 4 A pile having an inner diameter equal to that of a ring-shaped member having a size capable of inserting a tremely tube into the center of the pile hole, and a hole 2b through which each main reinforcing bar 1a of the pile rebar 1 passes through the bag structure portion at the same pitch. the head treatment material 2, the substantially horizontally disposed to the lower limit corresponding site of defective concrete area of pile rebar top through each main reinforcement 1a of the pile reinforcement 1 into each hole 2b, and each rises further upward from the pile head processing member 2 A step of attaching a tube-shaped curing material 3 that is edged with concrete to the outer periphery of the pile main reinforcement 1a,
Building the pile rebar 1 having the above-described configuration into the pile hole 4 and placing concrete 6 into the pile hole 4;
After the casting concrete has hardened, excavating the ground 11 to a depth at which at least the pile head treatment material 2 of the pile head is exposed;
The exposed the pile head processing member 2 to the inlet valve 2a is connected a pipe 8a of the fluid pump 8, feed high pressure fluid to the pile head processing member 2 of the bag structure to operate the pump 8, thin plate hydraulic jack and characterized in that it consists of a the pile head treatment material 2 'so that a crack is generated in the boundary between the defective concrete portions 6 "concrete and bad concrete 6 of the swelling pile head and the removing crushing To do.

請求項2に記載した発明に係る場所打ちコンクリート杭の杭頭処理工法
2枚の鉄板を上下に重ね合わせ、その内外の周辺部を溶接して密閉した袋構造の薄板形状流体圧ジャッキとして構成した、少なくとも内外二つのリング20、21を同心状配置に組み合わせて成り、外側のリング20に入り口バルブ2aを設け、外側のリング20の外径は杭孔4の孔径とほぼ等しくし、内径は杭鉄筋1の各主筋1aの外周径にほぼ接する大きさとし、内側のリング21の外径は杭鉄筋1の各主筋1aの内周径にほぼ接する大きさとし、内径は杭孔中心部へトレミー管を挿入可能な大きさとし、前記内外二つのリング20、21は放射方向に配置した複数の連通管22で連通させて成る杭頭処理材2を、前記内外二つのリング20と21の隙間へ杭鉄筋1の各主筋1aを通して杭鉄筋上部の不良コンクリート領域の下限相当部位へ略水平に設置し、更に前記杭頭処理材2より上方へ立ち上がる各杭主筋1aの外周にコンクリートと縁切りするチューブ形状の養生材3を取り付ける段階と、
前記構成とした杭鉄筋1を杭孔4の中へ建て込み、同杭孔4中へコンクリート6を打設する段階と、
打設コンクリートが硬化した後に、杭頭部の少なくとも前記杭頭処理材2が露出する深さまで地盤11の掘削を行う段階と、
露出した前記杭頭処理材2の入り口バルブ2aへ流体ポンプ8の配管8aを接続し、前記ポンプ8を運転して高圧流体を杭頭処理材2の袋構造中へ送り込み、薄板形状流体圧ジャッキとした杭頭処理材2を膨脹させて杭頭部のコンクリートと不良コンクリート6”との境界部に亀裂を生じさせ、不良コンクリート部分6”を破砕し除去する段階とから成ることを特徴とする。
Pile processing method of place concrete piles according to the invention described in claim 2,
Constructed as a concentric arrangement of at least two inner and outer rings 20 and 21 configured as a thin plate-shaped fluid pressure jack with a bag structure in which two steel plates are stacked one above the other and the inner and outer peripheral portions are welded and sealed, The outer ring 20 is provided with an inlet valve 2a, the outer diameter of the outer ring 20 is substantially equal to the hole diameter of the pile hole 4, the inner diameter is set to be in contact with the outer diameter of each main reinforcing bar 1a of the pile reinforcing bar 1, and the inner ring The outer diameter of 21 is set to a size that is substantially in contact with the inner peripheral diameter of each main reinforcing bar 1a of the pile reinforcing bar 1, and the inner diameter is set to a size capable of inserting a tremey tube into the center of the pile hole. The pile head treatment material 2 formed by communicating with a plurality of communication pipes 22 arranged is passed through the main reinforcement 1a of the pile rebar 1 to the gap between the two inner and outer rings 20 and 21 and corresponds to the lower limit portion of the defective concrete region above the pile rebar. A substantially horizontally placed, the step of further attaching the curing material 3 of the tube shape concrete and edge cutting the outer periphery of the pile main reinforcement 1a rising upward from the pile head processing member 2 to,
Building the pile rebar 1 having the above-described configuration into the pile hole 4 and placing concrete 6 into the pile hole 4;
After the casting concrete has hardened, excavating the ground 11 to a depth at which at least the pile head treatment material 2 of the pile head is exposed;
The pipe 8a of the fluid pump 8 is connected to the exposed inlet valve 2a of the pile head treatment material 2, and the pump 8 is operated to feed high-pressure fluid into the bag structure of the pile head treatment material 2, and a thin plate-shaped fluid pressure jack The pile head treatment material 2 is expanded to cause a crack at the boundary between the pile head concrete and the defective concrete 6 ″, and the defective concrete portion 6 ″ is crushed and removed. .

請求項3に記載した発明は、請求項に記載した場所打ちコンクリート杭の杭頭処理工法において、
少なくとも内外二つのリング20、21を放射方向に連通させる複数の連通管22は、薄板形状流体圧ジャッキとして構成した直線状処理材23を兼ねていることを特徴とする。
The invention described in claim 3 is a pile head processing method for a cast-in-place concrete pile according to claim 2 ,
The plurality of communication pipes 22 for communicating at least the two inner and outer rings 20 and 21 in the radial direction also serve as a linear processing member 23 configured as a thin plate-shaped fluid pressure jack .

請求項4に記載した発明は、請求項1又は2に記載した場所打ちコンクリート杭の杭頭処理工法において、
杭頭処理材2は、杭頭部の不良コンクリート領域6”の下限相当部位に設置するほか、それより上方の不良コンクリート領域6”の内部にも間隔をあけて複数略水平に設置し、地盤11の掘削後にはそれぞれへ高圧流体を送り込み、杭頭部のコンクリートと不良コンクリート6”との境界部に亀裂を生じさせるほか、不良コンクリート部分6”にも直接水平方向の亀裂を複数段生じさせて破砕を進めることを特徴とする。
Invention of Claim 4 is the pile head processing method of the cast-in-place concrete pile described in Claim 1 or 2 ,
In addition to installing the pile head treatment material 2 at the lower limit part of the defective concrete area 6 ″ of the pile head, a plurality of pile head treatment materials 2 are also installed approximately horizontally in the interior of the defective concrete area 6 ″ above it. After excavating 11, high-pressure fluid is sent to each of them to cause cracks at the boundary between the pile head concrete and the defective concrete 6 ″, and also to cause multiple horizontal cracks directly in the defective concrete portion 6 ″ It is characterized by proceeding crushing .

請求項5に記載した発明は、請求項1又は2に記載した場所打ちコンクリート杭の杭頭処理工法において、
リング形状部材であり、密閉した袋構造の薄板形状流体圧ジャッキとして構成した杭頭処理材2の袋構造上面部から上方へ杭鉄筋1の主筋1aに沿ってほぼ垂直に立ち上がる直線状処理部材26を杭鉄筋1の各主筋1a、1aの間の位置へ設置し、地盤11の掘削後には、杭頭処理材2と共に前記の各直線状処理部材26へもそれぞれ高圧流体を送り込み、杭頭部のコンクリートと不良コンクリートとの境界部に亀裂を生じさせるほか、不良コンクリート部分6”にも直接縦の亀裂を複数生じさせて破砕を進めることを特徴とする。
The invention described in claim 5 is the pile head processing method of the cast-in-place concrete pile described in claim 1 or 2 ,
A linear processing member 26 which is a ring-shaped member and rises substantially perpendicularly along the main reinforcing bar 1a of the pile reinforcing bar 1 from the bag structure upper surface portion of the pile head processing material 2 configured as a thin plate-shaped fluid pressure jack having a sealed bag structure. Is installed at a position between the main reinforcing bars 1a and 1a of the pile reinforcing bar 1, and after excavation of the ground 11, a high-pressure fluid is sent to each of the linear processing members 26 together with the pile head treating material 2, respectively. In addition to causing a crack at the boundary between the concrete and the defective concrete, a plurality of vertical cracks are also generated directly in the defective concrete portion 6 ″ to proceed the crushing .

本発明に係る場所打ちコンクリート杭の杭頭処理工法は、施工の準備段階として、杭鉄筋1を杭孔4へ建て込む前に、地上作業として、杭鉄筋上部の不良コンクリート領域の下限相当部位に、薄板形状の流体圧ジャッキとして構成された杭頭処理材2を略水平に設置し、更に前記杭頭処理材より上方に立ち上がる杭鉄筋1の外周にコンクリートと縁切りする養生材3を取り付けるだけであり、後は前記杭鉄筋1を杭孔4の中へ建て込み、コンクリート6を打設するだけで良く、簡単に効率よく作業を進められる。
打設コンクリート6が硬化した後、杭頭部の少なくとも前記杭頭処理材2が露出する深さまで地盤11の掘削を行い、露出した前記流体圧ジャッキとして構成された杭頭処理材2の入り口バルブ2aに流体ポンプ8の配管8aを接続し、前記ポンプ8を運転して高圧流体を杭頭処理材2へ送り込み、同杭頭処理材2を膨脹させる静的破壊力によって杭頭部のコンクリートに亀裂を生じさせ、不良コンクリート部分6”を破砕し除去するから、騒音や振動の発生は皆無に等しい。また、物理的に確実な破壊処理の効果が得られる。勿論、場所打ちコンクリート杭の不良コンクリート部分6”の位置が、施工場所の高さ位置とどのような関係にあるか等の施工条件に左右されることも全くない。
The pile head treatment method for cast-in-place concrete piles according to the present invention is a ground preparation work before the pile rebar 1 is built into the pile hole 4 as a preparation stage of construction. The pile head treatment material 2 configured as a thin plate-shaped fluid pressure jack is installed almost horizontally, and the curing material 3 that cuts off the concrete is simply attached to the outer periphery of the pile rebar 1 rising above the pile head treatment material. After that, it is only necessary to build the pile rebar 1 into the pile hole 4 and to cast the concrete 6, and the work can be easily and efficiently carried out.
After the cast concrete 6 is hardened, the ground 11 is excavated to a depth at which the pile head treatment material 2 is exposed at least at the pile head, and the inlet valve of the pile head treatment material 2 configured as the exposed hydraulic pressure jack The pipe 8a of the fluid pump 8 is connected to 2a, the pump 8 is operated, high pressure fluid is sent to the pile head treatment material 2, and the pile head treatment material 2 is inflated to the pile head concrete by static destructive force. Since cracks are generated and the defective concrete portion 6 "is crushed and removed, no noise or vibration is generated. In addition, a physically reliable destruction effect is obtained. Of course, cast-in-place concrete piles are defective. The position of the concrete portion 6 ″ is not affected by construction conditions such as how the height of the construction site is related.

不良コンクリート領域の下限相当部位より上方の不良コンクリート6”に、薄板形状の流体圧ジャッキとして構成された杭頭処理材2(及び26、27)で確実に亀裂を生じさせ、不良コンクリート部分6”を破砕することが可能である。破砕したコンクリートは吊り上げる等して速やかに除去することができ、工期の短縮化を図ることもできる。
また、本発明の工法に使用される消耗材は、極端に言えば杭頭処理材2より上方に立ち上がる杭鉄筋1の外周にコンクリートと縁切りするため取り付けた養生材3だけであるから、安価な費用で実施することができる。
The defective concrete 6 "above the lower limit equivalent part of the defective concrete area is reliably cracked by the pile head treatment material 2 (and 26, 27) configured as a thin plate-shaped fluid pressure jack, and the defective concrete portion 6" Can be crushed. The crushed concrete can be quickly removed by lifting it up, etc., and the construction period can be shortened.
Moreover, since the consumable material used for the construction method of this invention is only the curing material 3 attached in order to cut off with concrete on the outer periphery of the pile rebar 1 which stands up above the pile head processing material 2 in an extreme case, it is inexpensive. Can be implemented at cost.

杭鉄筋1の上部の不良コンクリート領域の下限相当部位に、薄板形状の流体圧ジャッキとして構成された杭頭処理材2を略水平に設置し、前記杭頭処理材2より上方に立ち上がる杭鉄筋1の外周にコンクリートと縁切りする養生材3を取り付け、この杭鉄筋1を杭孔4の中へ建て込み、コンクリート6を打設する。
打設コンクリート6が硬化した後に、杭頭部の少なくとも前記杭頭処理材2が露出するまで地盤11の掘削を行い、前記薄板形状の流体圧ジャッキとして構成された杭頭処理材2の入り口バルブ2aに流体ポンプ8の配管8aを接続し、前記ポンプ8を運転して高圧流体を杭頭処理材2へ送り込み、同杭頭処理材2を膨脹させることによって杭頭部のコンクリートに亀裂を生じさせ、不良コンクリート部分6”を破砕し除去する。
A pile head treatment material 2 configured as a thin plate-shaped fluid pressure jack is installed substantially horizontally in a portion corresponding to the lower limit of the defective concrete area above the pile reinforcement 1, and the pile reinforcement 1 that rises above the pile head treatment material 2. A curing material 3 for cutting the edge with concrete is attached to the outer periphery of the steel, and this pile rebar 1 is built into a pile hole 4 and concrete 6 is placed.
After the cast concrete 6 has hardened, the ground 11 is excavated until at least the pile head treatment material 2 of the pile head is exposed, and the inlet valve of the pile head treatment material 2 configured as the thin plate-shaped fluid pressure jack. The pipe 8a of the fluid pump 8 is connected to 2a, and the pump 8 is operated to feed the high-pressure fluid to the pile head treatment material 2, and the pile head treatment material 2 is expanded to cause cracks in the pile head concrete. Crush and remove the defective concrete part 6 ″.

先ず図1は、地上作業として、横置きされた杭用鉄筋篭1(以下、単に杭鉄筋という場合がある。)の上部の不良コンクリート領域の下限相当部位に、薄板形状の流体圧ジャッキとして構成された杭頭処理材2を杭孔中で略水平となる姿勢に設置する。更に前記杭頭処理材2より上方に立ち上がる杭主筋1aの外周に、コンクリートと縁切りする養生材3を取り付ける作業の段階を示している。養生材3としてはプラスチックチューブが好適に使用される。
前記薄板形状の流体圧ジャッキとして構成された杭頭処理材2は、例えば図2A、Bに原理図を示したように、上下に重ね合わせた2枚の鉄板の周辺部を溶接して密閉された袋構造に構成したもので、入り口バルブ2aを通じて水、その他の高圧流体を注入すると2枚の鉄板が変形して膨脹し、前記流体圧力が破壊力Fとしてコンクリートに作用する構成である。破壊力Fは、水圧と鉄板の面積との積に比例して大きな値となる。
First, FIG. 1 is constructed as a fluid pressure jack having a thin plate shape at a portion corresponding to the lower limit of a defective concrete region above a horizontally placed pile reinforcing bar 1 (hereinafter sometimes simply referred to as a pile reinforcing bar) as a ground work. The made pile head processing material 2 is installed in the attitude | position which becomes substantially horizontal in a pile hole. Furthermore, the stage of the operation | work which attaches the hardening material 3 cut | disconnected with concrete to the outer periphery of the pile main reinforcement 1a which stands up from the said pile head processing material 2 is shown. A plastic tube is preferably used as the curing material 3.
The pile head treatment material 2 configured as the thin plate-shaped fluid pressure jack is sealed by welding the peripheral portions of two steel plates stacked one above the other as shown in FIGS. 2A and 2B, for example. In this configuration, when water or other high-pressure fluid is injected through the inlet valve 2a, the two iron plates are deformed and expanded, and the fluid pressure acts on the concrete as the destructive force F. The breaking force F takes a large value in proportion to the product of the water pressure and the area of the iron plate.

上記薄板形状の流体圧ジャッキとして構成された杭頭処理材2はまた、図3に例示したように、杭鉄筋1の各主筋1a…を通す孔2b…を上記袋構造部分に各主筋1aの配置と同一ピッチに同数貫通させたリング形状部材として構成し使用される。このリング形状部材2の外径は、杭孔4の孔径とほぼ等しくして孔内壁にほぼ内接する形状、大きさとする。リング形状部材2の平面形状は、図示した円形の限りではなく、杭孔4の平面形状と同形・同大とする。リング形状部材2の内径は、小さいほど杭頭部のコンクリートに亀裂を生じさせて除去する作業に好ましいが、コンクリートの打設作業等の便宜、特にトレミー管の挿入等の便宜を考慮して適宜決定する。 As shown in FIG. 3, the pile head treatment material 2 configured as the thin plate-shaped fluid pressure jack also has holes 2 b through which the main reinforcing bars 1 a of the pile reinforcing bars 1 are passed through the bag structure portion of the main reinforcing bars 1 a. configured as a ring-shaped member which is the same number through the arrangement of the same pitch is used. The outer diameter of the ring-shaped member 2 has a shape and a size that are substantially equal to the hole diameter of the pile hole 4 and substantially inscribed in the hole inner wall. The planar shape of the ring-shaped member 2 is not limited to the illustrated circular shape, and is the same shape and size as the planar shape of the pile hole 4. The smaller the inner diameter of the ring-shaped member 2 is, the more preferable it is for the work of removing cracks in the concrete of the pile head, but it is appropriate in consideration of the convenience of placing concrete, especially the convenience of inserting a tremy tube, etc. decide.

図4は、地盤11中に掘削された杭孔4の中へ、上記のように構成した杭鉄筋1を建て込んだ状況を示す。符号5は地盤安定液、10は孔入口の保護ケーシングを示す。
図5は前記杭孔4の中へトレミー管7を通じて杭孔底から先行してコンクリート6を打設する要領を示す。符号6”は予め予定した不良コンクリート領域の下限相当部位に位置する上記杭頭処理材2を超えて立ち上がってきた不良コンクリートを指す。不良コンクリート6”の余盛り量は、通例の現場打ちコンクリート杭と同じく、70cm〜80cm程度の高さとする。
FIG. 4 shows a situation in which the pile rebar 1 configured as described above is built into the pile hole 4 excavated in the ground 11. Reference numeral 5 denotes a ground stabilizing liquid, and 10 denotes a protective casing at the hole entrance.
FIG. 5 shows a procedure for placing the concrete 6 in advance in the pile hole 4 through the tremy tube 7 from the bottom of the pile hole. Reference numeral 6 "indicates a defective concrete that has risen beyond the pile head treatment material 2 located in a portion corresponding to the lower limit of a predetermined defective concrete area. The amount of surplus of the defective concrete 6" is a conventional on-site concrete pile. The height is about 70 cm to 80 cm.

図6と図7は、上記の打設コンクリート6が硬化した後に、杭頭部の少なくとも前記杭頭処理材2が露出する深さまで地盤11の掘削を行い、その掘削底面へポンプユニット8を据え付け、前記薄板形状の流体圧ジャッキとして構成された杭頭処理材2の入り口バルブ2aと流体ポンプ8の配管8aを接続し、前記ポンプ8を運転して高圧流体を杭頭処理材2へ送り込む状況を示す。高圧流体を杭頭処理材2へ送り込むと、杭頭処理材2を構成する鉄板が高品質コンクリート6との境界部に亀裂を生じさせ、不良コンクリート部分6”を破砕し除去する要領を示している。例えばコンクリートの一次圧縮強度が21N/mmであるとき、杭頭処理材2へは約10MP〜30MPの高圧流体を圧入すると、容易に破壊することができる。 6 and 7 show that after the above-described cast concrete 6 is hardened, the ground 11 is excavated to a depth at which the pile head treatment material 2 is exposed at least at the pile head, and the pump unit 8 is installed on the bottom of the excavation. The situation is that the inlet valve 2a of the pile head treatment material 2 configured as the thin plate-shaped fluid pressure jack is connected to the pipe 8a of the fluid pump 8, and the pump 8 is operated to feed high pressure fluid to the pile head treatment material 2. Indicates. When high-pressure fluid is sent to the pile head treatment material 2, the iron plate constituting the pile head treatment material 2 causes a crack at the boundary with the high-quality concrete 6, and shows the procedure for crushing and removing the defective concrete portion 6 " it is. for example, when primary compression strength of the concrete is 21N / mm 2, when the to pile treatment material 2 is press-fitted to the high pressure fluid of about 10MP a ~30MP a, can be easily destroyed.

上記のようにして杭頭処理材2を膨脹させると、不良コンクリート6”が接触する各主筋1a…には予め縁切りする養生材3を取り付けてあり、また、下方の高品質コンクリート6は周辺の地盤から絶対的に大きい支持反力を受けているため、図7に例示した如く、不良コンクリート6”の方が浮き上がるように変形し、リング形状の杭頭処理材2の設置面に沿ってほぼ水平方向に主たる亀裂が発生する。更には縦方向にも亀裂が発生するなどして、不良コンクリート6”の割裂による破壊、解砕が静的に無騒音、無振動で確実に速やかに進む。よって、その後は破壊された不良コンクリート塊を、例えば養生材3と共に杭主筋1aから抜き取る等々の方法できれいに手際よく除去することができる。従って、杭頭処理の作業性が高く、工期の短縮化に寄与する。用済みとなった杭頭処理材2も杭主筋1aから抜き取って撤去することができ、他の場所に転用することも可能であり、有効利用による省資源化と費用の節減を図ることができる。杭頭処理材2を膨脹させる流体に水を使用すると、撤去時に多少漏れ出しても何の支障も生じない。   When the pile head treatment material 2 is expanded as described above, the curing material 3 to be preliminarily attached is attached to each main reinforcing bar 1a to which the defective concrete 6 ″ contacts, and the high-quality concrete 6 below is attached to the surroundings. Since it receives an absolutely large support reaction force from the ground, as illustrated in FIG. 7, the deformed concrete 6 ″ is deformed so as to float up, and is almost along the installation surface of the ring-shaped pile head treatment material 2. Main cracks occur in the horizontal direction. Furthermore, cracks also occur in the vertical direction, so that the failure and crushing of the defective concrete 6 "proceeds promptly without static noise and vibration without fail. The lump can be removed neatly and neatly by, for example, removing the lump from the pile main bar 1a together with the curing material 3. Therefore, the workability of the pile head processing is high, which contributes to shortening the construction period. The pile head treatment material 2 can also be removed from the pile main bar 1a and removed, and can be diverted to other places, saving resources and reducing costs through effective use. If water is used as the fluid for inflating 2, it will not cause any trouble even if it leaks slightly during removal.

図8には、薄板形状の流体圧ジャッキとして構成された杭頭処理材2の種々な実施形態を示す。
図8Aは、杭鉄筋1における各主筋1a…が円形状に配置された外周及び内周にほぼ接する内外二つのリング20と21を同心円状に配置して成り、前記内外二つのリング20と21は複数個の連通管22で放射方向に一連に連通されて内外二重リング構造に一体化され、外リング20に入り口バルブ2aを設けた構成の実施例を示す。内外二つのリング20と21の間が、各主筋1aを通す孔24として貫通されている。図3の実施例に比して、主筋1aを通す孔2bを加工する手間を省略した構成である。
図8Bは、内外二つのリング20と21が内外二重リング構造に一体化された構成までは、前記図8Aの実施形態と共通する。そして、前記内リング21の面内に、連通管22を兼ねて直交する4方向に放射状の配置で直線状処理部材(膨張材)23、23を併設した実施例を示す(請求項に記載した発明)。この実施例によれば、放射状配置に併設した直線状処理部材23が杭の中心部に確実に亀裂を発生させて割裂を完全に実現することに有用である。
In FIG. 8, various embodiment of the pile head processing material 2 comprised as a thin-plate-shaped fluid pressure jack is shown.
Figure 8A is comprised of the inner and outer two rings 20 and 21 to each main reinforcement 1a in pile rebar 1 ... almost in contact with the peripheral diameter and the inner circumference are disposed in a circular shape arranged concentrically, the inner and outer two rings 20 When 21 is integrated in communication with a series in the radial direction by a plurality of communication pipe 22 to the inner and outer double ring structure, showing an example of a configuration in which an inlet valve 2a to the outer side ring 20. Between gap of the inner and outer two rings 20 and 21, it extends through a hole 24 through which the main reinforcement 1a. Compared to the embodiment of FIG. 3, the labor for machining the hole 2 b through which the main muscle 1 a passes is omitted.
FIG. 8B is common to the embodiment of FIG. 8A up to the configuration in which the inner and outer rings 20 and 21 are integrated into an inner and outer double ring structure. Then, in the plane of the inner side ring 21, showing an embodiment in which features a linear processing member (expansion member) 23, 23 in a radial arrangement in the four directions perpendicular serves as a communicating pipe 22 (to claim 3 Described invention). According to this embodiment, the linear processing member 23 provided in the radial arrangement is useful for generating a crack reliably in the center portion of the pile and realizing the split completely.

図8Cは、やはり内外二つのリング20と21が内外二重リング構造に一体化された構成までは、上記図8Aの実施形態と共通する。そして、前記二重リング構造の内リング21の面内に、更にもう一つのリング25が同心円状に配置され前記三つのリング20、21、25それぞれ連通管22で一連に連通されて内外三重リング構造に一体化された構成の実施例を示す。
図8Dは、単に杭鉄筋1の各主筋1a…の内周側にほぼ内接する一つのリング21でのみ構成された杭頭処理材2の実施例を示す。したがって、敢えて図示することは省略したが、逆に、杭鉄筋1の各主筋1a…の外周側にほぼ外接する一つのリング20でのみ構成された杭頭処理材2も同様に実施することができる。
FIG. 8C is also common to the embodiment of FIG. 8A up to the configuration in which the inner and outer rings 20 and 21 are integrated into an inner and outer double ring structure. Then, the double ring inner side ring surface of 21 structures, is passed through further communicating said another ring 25 is arranged concentrically three rings 20, 21, 25 is in series with the communicating pipe 22, respectively inside and outside It shows the embodiment of an integrated structure in triple ring structure.
FIG. 8D shows an embodiment of the pile head treatment material 2 constituted only by one ring 21 that is substantially inscribed on the inner peripheral side of each main reinforcing bar 1a. Accordingly, although illustration is omitted, the pile head treatment material 2 composed of only one ring 20 that is substantially circumscribed on the outer peripheral side of each main reinforcing bar 1a of the pile reinforcing bar 1 can be similarly implemented. it can.

次に、図9と図10は、薄板形状の流体圧ジャッキとして構成された杭頭処理材2を、杭鉄筋1へ設置する態様の異なる実施例を示す。
図9は、杭頭処理材として、杭鉄筋1の上部の不良コンクリート領域の下限相当部位に、略水平なリング形状部材2を設置するとともに、前記リング形状部材2より上方へ杭主筋1aに沿ってほぼ垂直に立ち上がる直線状処理部材26を複数併設した実施例を示している(請求項に記載した発明)。各直線状処理部材26は、リング形状部材2と一連に連通した構成とされている。このように実施すると、不良コンクリート領域の下限相当部位において高品質のコンクリート6との境界部位を水平なリング形状部材2がほぼ水平方向に割裂させると同時に、各直線状処理部材26によって不良コンクリート6”自体の縦割りも可能となり、不良コンクリートの解砕度を高めて、除去作業を容易に出来る。
Next, FIG. 9 and FIG. 10 show the Example from which the aspect which installs the pile head processing material 2 comprised as a thin-plate-shaped fluid pressure jack in the pile reinforcement 1 is different.
FIG. 9 shows a substantially horizontal ring-shaped member 2 as a pile head treatment material at the lower limit equivalent part of the defective concrete region at the top of the pile rebar 1 and along the pile main reinforcement 1a above the ring-shaped member 2. An embodiment in which a plurality of linear processing members 26 rising substantially vertically are provided side by side (invention according to claim 5 ) is shown. Each linear processing member 26 is configured to communicate with the ring-shaped member 2 in series. If implemented in this way, the horizontal ring-shaped member 2 splits the boundary portion with the high-quality concrete 6 in the portion corresponding to the lower limit of the defective concrete region in the substantially horizontal direction, and at the same time, each straight processing member 26 causes the defective concrete 6 to break. "It is possible to divide itself vertically, increasing the degree of crushing of defective concrete and making removal work easy.

図10は、杭頭処理材として、杭鉄筋1の上部の不良コンクリート領域の下限相当部位に、略水平なリング形状部材2を設置するとともに、それより上方の不良コンクリート領域部位であって杭鉄筋1の主筋1aより内側の部位に、井桁形状で板状の杭頭処理部材27を一段(又は必要に応じて複数段)略水平に設置した実施例を示している(請求項に記載した発明)。この実施例によれば、板状の杭頭処理部材27によって不良コンクリート6”を上下二段ないし複数段に割裂させることができて、不良コンクリート6”の解砕度を高められ、除去作業を容易に出来る。もっとも、略水平なリング形状部材2より上方部位に設置する杭頭処理部材27の形態は、図示した井桁形状の限りではなく、リング形状部材その他を適用することが可能である。 FIG. 10 shows a pile-shaped member 2 as a pile head treatment material, in which a substantially horizontal ring-shaped member 2 is installed at a lower portion corresponding to the lower limit of the defective concrete region above the pile rebar 1, and is a defective concrete region portion above it. An example is shown in which a cross- shaped and plate-like pile head processing member 27 is installed substantially horizontally in a region inside the main reinforcing bar 1a of 1 (appropriately described in claim 4 ). invention). According to this embodiment, the defective concrete 6 ″ can be split into two or more stages by the plate-shaped pile head processing member 27, the degree of crushing of the defective concrete 6 ″ can be increased, and the removal work can be performed. Easy to do. However, the form of the pile head processing member 27 to be installed from a substantially horizontal ring-shaped member 2 to the upper part, not as far as the parallel-cross shape illustrated, it is possible to apply a ring-shaped member other.

地上で杭鉄筋に杭頭処理材を取り付ける要領を示す立面図である。It is an elevation view which shows the point which attaches a pile head processing material to a pile reinforcement on the ground. A、Bは流体圧ジャッキの原理説明図である。A and B are explanatory diagrams of the principle of a fluid pressure jack. 杭頭処理材の設置態様を示す斜視図である。It is a perspective view which shows the installation aspect of a pile head processing material. 杭鉄筋を杭孔中へ建て込んだ状況の立面図である。It is an elevation view of the situation which pile reinforcement was built in the pile hole. コンクリート打設の状況を示す立面図である。It is an elevation which shows the condition of concrete placement. 杭頭処理材へポンプユニットを接続した状態の説明図である。It is explanatory drawing of the state which connected the pump unit to the pile head processing material. 図6中A部のコンクリートの割裂状況の説明図である。It is explanatory drawing of the split condition of the concrete of A section in FIG. A〜Dは杭頭処理材の異なる実施形態を示す平面図である。AD is a top view which shows different embodiment of a pile head processing material. 杭鉄筋に対する杭頭処理材の設置態様を示した説明図である。It is explanatory drawing which showed the installation aspect of the pile head processing material with respect to a pile reinforcement. 杭鉄筋に対する杭頭処理材の設置態様の異なる例を示した説明図である。It is explanatory drawing which showed the example from which the installation aspect of the pile head processing material with respect to a pile reinforcement is different.

符号の説明Explanation of symbols

1 杭鉄筋
6” 不良コンクリート
2 杭頭処理材
1a 杭主筋
3 養生材
4 杭孔
6 コンクリート
2a 入り口バルブ
8 ポンプ
2b 孔
24 孔
25 リング形状部材
26 直線状処理部材
27 板状の杭頭処理部材
1 Pile rebar 6 ”Defective concrete 2 Pile head treatment material 1a Pile main reinforcement 3 Curing material 4 Pile hole 6 Concrete 2a Entrance valve 8 Pump 2b Hole 24 Hole 25 Ring-shaped member 26 Linear processing member 27 Plate-like pile head processing member

Claims (5)

2枚の鉄板を上下に重ね合わせ、その内外の周辺部を溶接して密閉した袋構造で、入り口バルブを備えた薄板形状流体圧ジャッキとして構成し、外径が杭孔の孔径とほぼ等しく、内径は杭孔中心部へトレミー管を挿入可能な大きさのリング形状部材とされ、前記袋構造部分に杭鉄筋の各主筋を通す孔を同一のピッチで貫通させて成る杭頭処理材を、前記の各孔へ杭鉄筋の各主筋を通して杭鉄筋上部の不良コンクリート領域の下限相当部位へ略水平に設置し、更に前記杭頭処理材より上方へ立ち上がる杭主筋の外周にコンクリートと縁切りするチューブ形状の養生材を取り付ける段階と、
前記構成とした杭鉄筋を杭孔中へ建て込み、同杭孔中へコンクリートを打設する段階と、
打設コンクリートが硬化した後に、杭頭部の少なくとも前記杭頭処理材が露出する深さまで地盤の掘削を行う段階と、
露出した前記杭頭処理材の入り口バルブ流体ポンプの配管を接続し、前記ポンプを運転して高圧流体を杭頭処理材の袋構造中へ送り込み、薄板形状流体圧ジャッキとした杭頭処理材を膨脹させて杭頭部のコンクリートと不良コンクリートとの境界部に亀裂を生じさせ、不良コンクリート部分を破砕し除去する段階とから成ることを特徴とする、場所打ちコンクリート杭の杭頭処理工法。
A bag structure in which two steel plates are stacked one above the other and the inner and outer peripheral portions are welded and sealed, and is configured as a thin plate-shaped fluid pressure jack equipped with an inlet valve . The outer diameter is almost equal to the hole diameter of the pile hole. The inner diameter is a ring-shaped member of a size capable of inserting a tremey pipe into the center of the pile hole, and a pile head treatment material formed by penetrating holes through each main reinforcing bar of the pile rebar at the same pitch through the bag structure part , A tube that is installed approximately horizontally to the lower limit part of the defective concrete area above the pile reinforcement bar through each reinforcement of the pile reinforcement to each hole, and is further edged with concrete on the periphery of each pile reinforcement that rises above the pile head treatment material Attach the shape curing material,
Incorporating the pile rebar having the above configuration into the pile hole, and placing concrete into the pile hole;
After the cast concrete has hardened, excavating the ground to a depth where at least the pile head treatment material is exposed at the pile head; and
Connect the pipe of the fluid pump to the exposed inlet valve of the pile head treatment material, operate the pump to send high-pressure fluid into the bag structure of the pile head treatment material, and use the thin plate shape fluid pressure jack as the pile head treatment material was allowed to expand so that a crack is generated in the boundary between the concrete and the defective concrete pile head, characterized in that it consists of a step of removing crushed defective concrete portions, pile head processing method of cast-in-place concrete pile .
2枚の鉄板を上下に重ね合わせ、その内外の周辺部を溶接して密閉した袋構造の薄板形状流体圧ジャッキとして構成した、少なくとも内外二つのリングを同心状配置に組み合わせて成り、外側のリングに入り口バルブを設け、外側リングの外径は杭孔の孔径とほぼ等しくし、内径は杭鉄筋の各主筋の外周径にほぼ接する大きさとし、内側のリングの外径は杭鉄筋の各主筋の内周径にほぼ接する大きさとし、内径は杭孔中心部へトレミー管を挿入可能な大きさとし、前記内外二つのリングは放射方向に配置した複数の連通管で連通させて成る杭頭処理材を、前記内外二つのリングの隙間へ杭鉄筋の各主筋を通して杭鉄筋上部の不良コンクリート領域の下限相当部位へ略水平に設置し、更に前記杭頭処理材より上方へ立ち上がる各杭主筋の外周にコンクリートと縁切りするチューブ形状の養生材を取り付ける段階と、
前記構成とした杭鉄筋を杭孔中へ建て込み、同杭孔中へコンクリートを打設する段階と、
打設コンクリートが硬化した後に、杭頭部の少なくとも前記杭頭処理材が露出する深さまで地盤の掘削を行う段階と、
露出した前記杭頭処理材の入り口バルブへ流体ポンプの配管を接続し、前記ポンプを運転して高圧流体を杭頭処理材の袋構造中へ送り込み、薄板形状流体圧ジャッキとした杭頭処理材を膨脹させて杭頭部のコンクリートと不良コンクリートとの境界部に亀裂を生じさせ、不良コンクリート部分を破砕し除去する段階とから成ることを特徴とする、場所打ちコンクリート杭の杭頭処理工法。
Constructed as a thin plate-shaped fluid pressure jack with a bag structure in which two steel plates are stacked one above the other and the inner and outer peripheral parts are welded and sealed. The outer ring is a combination of at least two inner and outer rings in a concentric arrangement. The outer diameter of the outer ring is approximately the same as the hole diameter of the pile hole, the inner diameter is approximately in contact with the outer diameter of each main bar of the pile reinforcement, and the outer diameter of the inner ring is the same as the main reinforcement of the pile reinforcement. The inner diameter of the pile is such that the inner diameter of the pile hole can be inserted into the center of the pile hole, and the two inner and outer rings are connected by a plurality of communication pipes arranged in the radial direction. In the gap between the two inner and outer rings, each pile reinforcing bar passes through the main reinforcing bars to the lower equivalent part of the defective concrete area above the pile reinforcing bars, and is installed on the outer periphery of each pile reinforcing bar that rises above the pile head treatment material. And affixing the curing material of the tube shape Nkurito and edge cutting,
Incorporating the pile rebar having the above configuration into the pile hole, and placing concrete into the pile hole;
After the cast concrete has hardened, excavating the ground to a depth where at least the pile head treatment material is exposed at the pile head; and
Connect the pipe of the fluid pump to the exposed inlet valve of the pile head treatment material, operate the pump to send high-pressure fluid into the bag structure of the pile head treatment material, and use the thin plate shape fluid pressure jack as the pile head treatment material A pile head treatment method for cast- in- place concrete piles , comprising the step of expanding the crack to cause cracks at the boundary between the concrete of the pile head and the defective concrete, and crushing and removing the defective concrete portion .
少なくとも内外二つのリングを放射方向に連通させる複数の連通管は、薄板形状流体圧ジャッキとして構成した直線状処理材を兼ねていることを特徴とする、請求項2に記載した場所打ちコンクリート杭の杭頭処理工法。 The cast-in-place concrete pile according to claim 2, wherein the plurality of communication pipes for communicating at least two inner and outer rings in the radial direction also serve as a straight processing material configured as a thin plate-shaped fluid pressure jack . Pile head processing method. 杭頭処理材は、杭頭部の不良コンクリート領域の下限相当部位に設置するほか、それより上方の不良コンクリート領域内部にも間隔をあけて複数略水平に設置し、地盤の掘削後にはそれぞれへ高圧流体を送り込み、杭頭部のコンクリートと不良コンクリートとの境界部に亀裂を生じさせるほか、不良コンクリート部分にも直接水平方向の亀裂を複数段生じさせて破砕を進めることを特徴とする、請求項1又は2に記載した場所打ちコンクリート杭の杭頭処理工法。 In addition to installing the pile head treatment material at the lower limit part of the defective concrete area of the pile head, multiple piles are installed in the interior of the defective concrete area above it. It is characterized by feeding high-pressure fluid and causing cracks at the boundary between the pile head concrete and defective concrete, and by proceeding with crushing by generating multiple horizontal cracks directly in the defective concrete part. The pile head processing method of the cast-in-place concrete pile described in claim | item 1 or 2 . リング形状部材であり、密閉した袋構造の薄板形状流体圧ジャッキとして構成した杭頭処理材の袋構造上面部から上方へ杭鉄筋の主筋に沿ってほぼ垂直に立ち上がる直線状処理部材を杭鉄筋の各主筋の間の位置へ設置し、地盤の掘削後には、杭頭処理材と共に前記の各直線状処理部材へもそれぞれ高圧流体を送り込み、杭頭部のコンクリートと不良コンクリートとの境界部に亀裂を生じさせるほか、不良コンクリート部分にも直接縦の亀裂を複数生じさせて破砕を進めることを特徴とする、請求項1又は2に記載した場所打ちコンクリート杭の杭頭処理工法。 A ring-shaped member, a straight processing member that rises almost vertically along the main bar of the pile rebar upward from the bag structure top surface of the pile head treatment material configured as a thin plate-shaped fluid pressure jack with a sealed bag structure. Installed at a position between the main bars, and after excavation of the ground, high pressure fluid is sent to each of the linear processing members together with the pile head treatment material, and cracks occur at the boundary between the pile head concrete and defective concrete. The pile head processing method for cast-in-place concrete piles according to claim 1 or 2, wherein a plurality of vertical cracks are directly generated in a defective concrete portion to cause crushing .
JP2004145119A 2004-05-14 2004-05-14 Pile head treatment method for cast-in-place concrete piles Expired - Fee Related JP4388413B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004145119A JP4388413B2 (en) 2004-05-14 2004-05-14 Pile head treatment method for cast-in-place concrete piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004145119A JP4388413B2 (en) 2004-05-14 2004-05-14 Pile head treatment method for cast-in-place concrete piles

Publications (2)

Publication Number Publication Date
JP2005325607A JP2005325607A (en) 2005-11-24
JP4388413B2 true JP4388413B2 (en) 2009-12-24

Family

ID=35472145

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004145119A Expired - Fee Related JP4388413B2 (en) 2004-05-14 2004-05-14 Pile head treatment method for cast-in-place concrete piles

Country Status (1)

Country Link
JP (1) JP4388413B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759336A (en) * 2016-12-19 2017-05-31 中交路桥建设有限公司 A kind of cast-in-situ bored pile quickly abolishes pile crown construction method
CN108999188A (en) * 2018-08-30 2018-12-14 中建五局土木工程有限公司 Crushing device, restructuring bankrupt and the application of cast-in-situ bored pile pile crown

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425159B (en) * 2011-08-31 2013-12-18 浙江大学城市学院 Pile cutting construction method of bored concrete pile
CN102493434B (en) * 2011-11-28 2014-04-16 中铁大桥局股份有限公司 Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile
CN104234038A (en) * 2014-03-03 2014-12-24 王磊 Bored concrete pile construction technology without breaking of pile head
CN108104116A (en) * 2018-01-19 2018-06-01 中建筑港集团有限公司 A kind of filling pile head processing method and Quick Release pile crown bored concrete pile
CN108203979B (en) * 2018-02-27 2023-06-06 中建路桥集团有限公司 Pile head breaking system and pile head breaking method adopting vanishing breaking method
CN108487238A (en) * 2018-05-24 2018-09-04 北京良乡蓝鑫水利工程设计有限公司 A kind of filling pile head processing unit and its construction method
CN110219302B (en) * 2019-07-09 2024-02-06 宁夏第三建筑有限公司 Method for breaking pile head of reinforced concrete bored concrete pile and matched device thereof
CN110656644B (en) * 2019-09-26 2024-02-09 广东省建筑工程机械施工有限公司 Reinforcement cage erecting structure and method for breaking pile head of cast-in-place pile through reverse static blasting
CN114875912A (en) * 2022-05-29 2022-08-09 中国五冶集团有限公司 Reinforcing steel bar protection method for hydraulic pile breaking head
CN115324053B (en) * 2022-08-08 2023-04-07 福建省岩田基建工程技术有限公司 Cutting hoop for integrally breaking pile head of cast-in-situ bored pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759336A (en) * 2016-12-19 2017-05-31 中交路桥建设有限公司 A kind of cast-in-situ bored pile quickly abolishes pile crown construction method
CN108999188A (en) * 2018-08-30 2018-12-14 中建五局土木工程有限公司 Crushing device, restructuring bankrupt and the application of cast-in-situ bored pile pile crown

Also Published As

Publication number Publication date
JP2005325607A (en) 2005-11-24

Similar Documents

Publication Publication Date Title
JP4388413B2 (en) Pile head treatment method for cast-in-place concrete piles
EP1738031B1 (en) Hydraulic pile cap removal
JP2018024982A (en) Reinforcement method and reinforcement structure of existing pile foundation
JP3733533B2 (en) Foundation reinforcement method under pressure of existing structures
JP4700937B2 (en) Pile head treatment method for cast-in-place concrete piles
JP2008208533A (en) Caisson and its construction method
JP5540044B2 (en) Hydraulic jack jig used for restoration work for uneven settlement of buildings and repair method for unevenly settled buildings using this jig
KR100505301B1 (en) The structure for underground tunnel formation
JP2016023540A (en) Environmentally-considerate pile head processing method
JP5872724B1 (en) Construction method of underwater temporary closing structure
JP2018024988A (en) Excavation method od sediment and excavator
JP6715663B2 (en) Steel pipe pile construction method
JPH08105054A (en) Construction of shaft
JP5378066B2 (en) Mountain fastening method
JP2007146538A (en) Method of treating pile head of on-site-formed pile
JP4378277B2 (en) Vertical loading test method for existing piles below the groundwater level
JP2000008398A (en) Correcting method and correcting device for building having uneven settlement
JP4820325B2 (en) caisson
JP2016205119A (en) Segment and construction method for immersion structure
JP4381855B2 (en) Temporary cut-off structure and temporary cut-off method for underwater existing structures
JP2008303623A (en) Settlement correction method for building
JP3704686B2 (en) Support device for retaining liner plate and retaining method using the same
JP4236959B2 (en) Embankment concrete excavation method
KR200317830Y1 (en) The structure for underground tunnel formation
KR102575701B1 (en) A method of open cut excavation tunnel using a messer plate

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070329

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090319

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090331

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090527

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090915

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091002

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121009

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131009

Year of fee payment: 4

LAPS Cancellation because of no payment of annual fees