CN102493434B - Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile - Google Patents

Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile Download PDF

Info

Publication number
CN102493434B
CN102493434B CN201110384951.XA CN201110384951A CN102493434B CN 102493434 B CN102493434 B CN 102493434B CN 201110384951 A CN201110384951 A CN 201110384951A CN 102493434 B CN102493434 B CN 102493434B
Authority
CN
China
Prior art keywords
pile
pile crown
reinforcement
concrete
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110384951.XA
Other languages
Chinese (zh)
Other versions
CN102493434A (en
Inventor
王同民
秦顺全
韩胜利
任文辉
杨沙沙
焦儒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No.1 Engineering Co., Ltd., Zhongtie Bridge Bureau Group
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
China Railway Major Bridge Engineering Co Ltd
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No1 Engineering Co Ltd Zhongtie Bridge Bureau Group, China Railway Major Bridge Engineering Co Ltd, China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
Priority to CN201110384951.XA priority Critical patent/CN102493434B/en
Publication of CN102493434A publication Critical patent/CN102493434A/en
Application granted granted Critical
Publication of CN102493434B publication Critical patent/CN102493434B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a construction method for integrally and quickly hoisting and removing the pile head of a bored cast-in-place pile. The method specifically comprises the following steps: when a reinforcement cage is processed and manufactured, ensuring that a main reinforcement on the pile head is not bent; and a protecting tube is sheathed on each main reinforcement; when the reinforcement is installed, surrounding a steel wire rope sheathed with a plastic hose on the elevation position of a design pile; when the bored cast-in-place pile is filled with concrete, embedding a reinforcement hand ring in advance; after a foundation pit is dug on a proper position, hoisting the steel wire rope sheathed with a plastic hose by an excvavtor to girdle reinforcement protection layer concrete; along the girdling position, symmetrically and horizontally inserting and biting steel wedge blocks to separate the pile head and the pile body; and directly hoisting by a crane to remove the pile head. According to the construction method for integrally and quickly hoisting and removing the pile head of a bored cast-in-place pile, the modes of protecting pile foundation reinforcement, improving the pile head processing efficiency and clearing the pile head are innovated to effectively prevent from damaging the reinforcement and the pile body in the construction process, the efficiency is improved, and the project quality is guaranteed.

Description

A kind of bored pile pile crown Integral quick hoisting is got the construction method of removing
Technical field
The present invention relates to bridge drilling stake filling pile construction, is that a kind of bored pile pile crown Integral quick hoisting is got the construction method of removing specifically.
Background technology
In existing bridge drilling stake filling pile construction; current conventional pile crown cuts method and is: be manually aided with small machine and cut; or to pile crown, adopt abrasive machine to carry out ring cutting in design elevation position; then artificial chisel is except the cover concrete of super envelope pile crown; main muscle is peeled off to concrete from side direction, then pile crown concrete piecemeal is cleared up.Existing these pile crowns cut method and have the following disadvantages:
1, cut pile crown and can cause bending damage to reinforcing bar;
The following pile body reinforcement cover of easy damaged cushion cap concrete when 2, pile crown cuts, weakens the connection between pile foundation and cushion cap;
3, easily cause the following pile body reinforcement cover of cushion cap cracking or peel off, burying the disease of main muscle corrosion and be difficult to examination and make up;
4, the pile crown processing time long, cause the foundation pit construction cycle long, precipitation and protection, artificial, machinery expenses is high.
Summary of the invention
For the defect existing in prior art, the object of the present invention is to provide a kind of bored pile pile crown Integral quick hoisting to get the construction method of removing, object is to solve pile crown long processing period, the main muscle of easy damaged and the concrete problem of main muscle external protection.
For reaching above object, the technical scheme that the present invention takes is:
Bored pile pile crown Integral quick hoisting is got a construction method of removing, and it is characterized in that, its concrete steps are as follows:
Step 1, reinforcing cage processing: during reinforcing cage processing and fabricating, the main muscle 1 that pile crown stretches in cushion cap does not bend, keeping parallelism state, and be inserted in protection tube 2 on every main muscle, make not bond between pile crown reinforcing bar and the concrete of perfusion;
Step 2, reinforcement installation: when reinforcement installation, need accurately to control reinforcing cage absolute altitude, and in a design stake top mark eminence, around and fix a cover and have the wire rope 3 of plastic flexible pipe, have the fag end of the wire rope of plastic flexible pipe to be placed in outside concrete in cover;
Step 3, bored pile perfusion: when bored pile carries out filling concrete, embedded reinforcement suspension ring 4 in advance;
Step 4, excavation of foundation pit;
Step 5, after excavation of foundation pit is in place, with excavator, playing hanging sleeve has the wire rope of plastic flexible pipe, and wire rope automatic ring is to realizing reinforcement cover concrete " ring cutting ";
Step 6, along ring cutting position, symmetrical horizontal inserted to play gad piece 5, makes pile crown separation with pile body;
Step 7, directly slings and removes pile crown by loop wheel machine entirety.
On the basis of technique scheme, described protection tube 2 is foamed pipe, or is sponge pipe or for mao bamboon.
On the basis of technique scheme, described reinforcing bar suspension ring 4 are for meeting the reinforcing bar suspension ring of pile crown integral hoisting force request at pile crown concrete embedded set.
On the basis of technique scheme, directly by loop wheel machine entirety, sling and remove after pile crown, pile crown end face is carried out after manual amendment, enter next procedure construction.
Bored pile pile crown Integral quick hoisting of the present invention is got the construction method of removing; in protection pile foundation reinforcing bar, raising pile crown treatment effeciency, pile crown reset mode, innovate; this construction method can effectively solve the damage to reinforcing bar and pile body in work progress; raise the efficiency, guarantee workmanship.
The invention has the beneficial effects as follows:
1, make main muscle parallel, do not bend, and nothing bonding between realization and concrete, entirety upwards vertical lifting departs from pile body, effectively avoids the damage to reinforcing bar in pile crown processing procedure;
2, pile crown upwards entirety hang out, pile concrete is not impacted or is damaged, guarantee the connection between pile foundation and cushion cap.
3, operation is simple, and efficiency of construction is high.
4, reduced the input of construction equipment, flexible pipe, old wire rope can reuse, and the materials such as foam sleeve can be gathered materials on the spot, and substitute is many, can effectively reduce costs.
5, construction noise and dust reduce greatly, and construction environment is improved, and effectively protect constructor's health.
Accompanying drawing explanation
The present invention has following accompanying drawing:
Fig. 1 construction schematic diagram of the present invention.
The specific embodiment
Below in conjunction with accompanying drawing, the present invention is described in further detail.
The processing of bored pile pile crown is an important procedure of Bridge Pile Foundation Construction, and Traditional Man cuts method length consuming time, and pile body reinforcing bar and topping are easily destroyed, once pile body cracking, the dew muscle below cushion cap bottom surface will have a strong impact on structural safety and durability.
As shown in Figure 1, bored pile pile crown Integral quick hoisting of the present invention is got the construction method of removing, and its concrete steps are as follows:
Step 1, reinforcing cage processing: during reinforcing cage processing and fabricating, the main muscle 1 that pile crown stretches in cushion cap does not bend, keeping parallelism state, and be inserted in protection tube 2 on every main muscle, make not bond between pile crown reinforcing bar and the concrete of perfusion;
Described protection tube 2 is foamed pipe, or is sponge pipe or for mao bamboon, also can gather materials on the spot according to actual conditions, as long as can guarantee not bond between pile crown reinforcing bar and the concrete of perfusion, material is not limit;
Step 2, reinforcement installation: when reinforcement installation, need accurately to control reinforcing cage absolute altitude, and in a design stake top mark eminence, around and fix a cover and have the wire rope 3 of plastic flexible pipe, have the fag end of the wire rope of plastic flexible pipe to be placed in outside concrete in cover;
Step 3, bored pile perfusion: when bored pile carries out filling concrete, embedded reinforcement suspension ring 4 in advance;
At pile crown concrete embedded set, meet the reinforcing bar suspension ring of pile crown integral hoisting force request, while processing for pile crown as the use of hanger (suspension centre);
Step 4, excavation of foundation pit;
Step 5, after excavation of foundation pit is in place, with excavator, playing hanging sleeve has the wire rope of plastic flexible pipe, and wire rope automatic ring is to realizing reinforcement cover concrete " ring cutting ";
Along with excavator plays hanging sleeve, there is the wire rope of plastic flexible pipe, around the wire rope automatic ring of pile crown, to peeling off reinforcement cover concrete, reach " ring cutting " target;
Step 6, along ring cutting position, symmetrical horizontal inserted to play gad piece 5, makes pile crown separation with pile body; Utilize the characteristic that concrete tensile strength is extremely low, by the horizontal inserted to play gad of symmetry piece, can more easily make pile crown separation with pile body;
Step 7, directly slings and removes pile crown by loop wheel machine entirety.Pile crown end face is carried out after manual amendment, enter next procedure construction.
Bored pile pile crown Integral quick hoisting of the present invention is got the construction method of removing, and to covering foamed pipe (or sponge pipe or mao bamboon) without the main muscle cover of pile crown of bending, makes it with concrete without bonding; At main muscle, curling cover outward has the old wire rope of flexible pipe to realize " ring cutting "; In stake, push up pre-buried hanger and realize integral hoisting taking-up, solve pile crown fast processing, avoid pile damage problem.It is simple that the present invention has constructing operation, and construction quality is high, cost is low, work efficiency advantages of higher, is easy to promote.
The content not being described in detail in this manual belongs to the known prior art of professional and technical personnel in the field.

Claims (4)

1. bored pile pile crown Integral quick hoisting is got a construction method of removing, and it is characterized in that, its concrete steps are as follows:
Step 1, reinforcing cage processing: during reinforcing cage processing and fabricating, the main muscle (1) that pile crown stretches in cushion cap does not bend, keeping parallelism state, and on every main muscle, be inserted in protection tube (2), make not bond between pile crown reinforcing bar and the concrete of perfusion;
Step 2, reinforcement installation: when reinforcement installation, need accurately to control reinforcing cage absolute altitude, and in a design stake top mark eminence, around and fix a cover and have the wire rope (3) of plastic flexible pipe, have the fag end of the wire rope of plastic flexible pipe to be placed in outside concrete in cover;
Step 3, bored pile perfusion: when bored pile carries out filling concrete, embedded reinforcement suspension ring (4) in advance;
Step 4, excavation of foundation pit;
Step 5, after excavation of foundation pit is in place, with excavator, playing hanging sleeve has the wire rope of plastic flexible pipe, and wire rope automatic ring is to realizing reinforcement cover concrete " ring cutting ";
Step 6, along ring cutting position, symmetrical horizontal inserted to play gad piece (5), makes pile crown separation with pile body;
Step 7, directly slings and removes pile crown by loop wheel machine entirety.
2. bored pile pile crown Integral quick hoisting as claimed in claim 1 is got the construction method of removing, and it is characterized in that: described protection tube (2) is foamed pipe, or is sponge pipe or for mao bamboon.
3. bored pile pile crown Integral quick hoisting as claimed in claim 1 is got the construction method of removing, and it is characterized in that: described reinforcing bar suspension ring (4) are for meeting the reinforcing bar suspension ring of pile crown integral hoisting force request at pile crown concrete embedded set.
4. bored pile pile crown Integral quick hoisting as claimed in claim 1 is got the construction method of removing, and it is characterized in that: directly by loop wheel machine entirety, sling and remove after pile crown, pile crown end face is carried out after manual amendment, enter next procedure construction.
CN201110384951.XA 2011-11-28 2011-11-28 Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile Active CN102493434B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110384951.XA CN102493434B (en) 2011-11-28 2011-11-28 Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110384951.XA CN102493434B (en) 2011-11-28 2011-11-28 Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile

Publications (2)

Publication Number Publication Date
CN102493434A CN102493434A (en) 2012-06-13
CN102493434B true CN102493434B (en) 2014-04-16

Family

ID=46185290

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110384951.XA Active CN102493434B (en) 2011-11-28 2011-11-28 Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile

Country Status (1)

Country Link
CN (1) CN102493434B (en)

Families Citing this family (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926380A (en) * 2012-11-20 2013-02-13 中铁十九局集团第三工程有限公司 Bridge cast-in-place pile chiseling-free pile head and construction method thereof
CN103266612B (en) * 2013-06-06 2015-07-01 大连大金马基础建设有限公司 Pile splicing anchor bar protecting frame
CN104234038A (en) * 2014-03-03 2014-12-24 王磊 Bored concrete pile construction technology without breaking of pile head
CN105178318B (en) * 2014-05-30 2017-06-30 中国二十冶集团有限公司 A kind of steel pipe downcast pipe well removal method
CN104343115B (en) * 2014-11-13 2016-08-24 中交隧道工程局有限公司 A kind of pile foundation pile crown entirety abolishes structures and methods
CN104727306A (en) * 2015-03-19 2015-06-24 中交二航局第三工程有限公司 Cast-in place pile pouring and pile head cutting-off method
CN105297729B (en) * 2015-11-23 2017-12-01 中国葛洲坝集团第六工程有限公司 Bridge pile foundation pile head breaking device and method
CN105350524A (en) * 2015-12-04 2016-02-24 中交隧道工程局有限公司 Steel reinforcement cage structure, concrete filling pile structure and construction method of concrete filling pile structure
CN106120792A (en) * 2016-08-11 2016-11-16 北京城建七建设工程有限公司 A kind of pile foundation pile crown concrete prestripping assembly and construction method
CN106400802B (en) * 2016-08-24 2019-02-26 中交一公局厦门工程有限公司 A kind of drilled pile pile crown is pre-buried to exempt from the whole quickly lifting method of ring cutting that drills
CN106400803A (en) * 2016-10-31 2017-02-15 中国葛洲坝集团第六工程有限公司 Integral cast-in-situ bored pile head breaking process
CN106400804A (en) * 2016-11-17 2017-02-15 宁波市政工程建设集团股份有限公司 Obstructing pulling method pile digging construction device and method
CN106759336A (en) * 2016-12-19 2017-05-31 中交路桥建设有限公司 A kind of cast-in-situ bored pile quickly abolishes pile crown construction method
CN107034887A (en) * 2017-03-30 2017-08-11 河南大建桥梁钢构股份有限公司 Bored piles headring cuts construction method
CN106958245A (en) * 2017-04-07 2017-07-18 中交二公局第工程有限公司 The quick structure and method for abolishing concrete pile head
CN106968251A (en) * 2017-05-26 2017-07-21 中交第二航务工程局有限公司 A kind of concrete filling pile head abolishes device and its construction method
CN107542092A (en) * 2017-08-18 2018-01-05 广州市公路工程公司 High efficiency honeycomb method broken pile head construction technology
CN108104116A (en) * 2018-01-19 2018-06-01 中建筑港集团有限公司 A kind of filling pile head processing method and Quick Release pile crown bored concrete pile
CN108487238A (en) * 2018-05-24 2018-09-04 北京良乡蓝鑫水利工程设计有限公司 A kind of filling pile head processing unit and its construction method
CN110468842B (en) * 2019-08-14 2024-06-18 中交第二公路工程局有限公司 Breaking structure and breaking method of concrete pile head
CN112030960A (en) * 2020-07-22 2020-12-04 中铁十局集团第一工程有限公司 Construction method of separable fulcrum pile
CN113622427B (en) * 2021-07-06 2023-03-28 中国二十冶集团有限公司 Auxiliary device for chiseling pile head and construction method for chiseling pile head

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03107017A (en) * 1989-09-21 1991-05-07 Nitto Kensetsu Kk Pile head treatment method for cast-in-place concrete pile
JP2003055962A (en) * 2001-08-17 2003-02-26 Achilles Corp Head edge treatment sheet for cast-in-place pile and head edge cutting treatment method
JP2005325607A (en) * 2004-05-14 2005-11-24 Takenaka Komuten Co Ltd Pile head treating method of cast-in-place concrete pile
JP2006037492A (en) * 2004-07-27 2006-02-09 Takenaka Komuten Co Ltd Pile head processing construction method of cast-in-place concrete pile
CN101333811A (en) * 2008-08-05 2008-12-31 中国建筑材料科学研究总院 Concrete filling pile head static cutting and crushing method
JP2010007397A (en) * 2008-06-28 2010-01-14 索郎 ▲廣▼▲瀬▼ Pile head treating method and pile head treating apparatus
JP5287734B2 (en) * 2010-01-07 2013-09-11 トヨタ自動車株式会社 Parking assistance device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05287734A (en) * 1992-04-02 1993-11-02 Taisei Corp Pile head processing method
JP2726241B2 (en) * 1994-10-04 1998-03-11 日本国土開発株式会社 Pile head treatment method of cast-in-place foundation pile and tool for performing this treatment

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03107017A (en) * 1989-09-21 1991-05-07 Nitto Kensetsu Kk Pile head treatment method for cast-in-place concrete pile
JP2003055962A (en) * 2001-08-17 2003-02-26 Achilles Corp Head edge treatment sheet for cast-in-place pile and head edge cutting treatment method
JP2005325607A (en) * 2004-05-14 2005-11-24 Takenaka Komuten Co Ltd Pile head treating method of cast-in-place concrete pile
JP2006037492A (en) * 2004-07-27 2006-02-09 Takenaka Komuten Co Ltd Pile head processing construction method of cast-in-place concrete pile
JP2010007397A (en) * 2008-06-28 2010-01-14 索郎 ▲廣▼▲瀬▼ Pile head treating method and pile head treating apparatus
CN101333811A (en) * 2008-08-05 2008-12-31 中国建筑材料科学研究总院 Concrete filling pile head static cutting and crushing method
JP5287734B2 (en) * 2010-01-07 2013-09-11 トヨタ自動車株式会社 Parking assistance device

Also Published As

Publication number Publication date
CN102493434A (en) 2012-06-13

Similar Documents

Publication Publication Date Title
CN102493434B (en) Construction method for integrally and quickly hoisting and removing pile head of bored cast-in-place pile
CN106759336A (en) A kind of cast-in-situ bored pile quickly abolishes pile crown construction method
CN102312429B (en) Rapid separation and integral hoisting method for pile head of cast-in-place concrete pile
CN106400802B (en) A kind of drilled pile pile crown is pre-buried to exempt from the whole quickly lifting method of ring cutting that drills
CN103243745B (en) A kind of method of pile tube deviation rectification
CN106958245A (en) The quick structure and method for abolishing concrete pile head
CN103485343B (en) Filling pile head processing method
CN207739259U (en) A kind of filling pile head cuts device
CN105297729A (en) Bridge pile foundation pile head breaking device and method
CN205116185U (en) A supporting construction for weak soil foundation ditch
CN104631460A (en) Girdling splitting type integral pile breaking method
CN107604920A (en) A kind of quick construction method for abolishing filling pile head
CN108612109A (en) The carrierless method for dismounting of concrete support beam
CN206859222U (en) The quick structure for abolishing concrete pile head
CN101634147A (en) Method for demolishing ultra high cast-in-place pile head
CN110144899A (en) Shallow foundation building foundation pit Deformation control structure and construction method are closed in a kind of soft soil layer underground parking
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN205224036U (en) Device is abolished to bridge pile foundation pile head
CN114232628A (en) Cutting hoop for integrally breaking pile head of cast-in-situ bored pile and construction method
CN206941586U (en) A kind of device for improving pile crown and abolishing efficiency
CN105908991A (en) Floor suspension type reverse demolition construction method
CN206110122U (en) Bridge drilled pile convenient to get rid of pile head
CN109944246A (en) A kind of construction method of broken pile head
CN206667233U (en) A kind of steel wire rope, steel pipe, buckle combine detachable hangs muscle
CN105350524A (en) Steel reinforcement cage structure, concrete filling pile structure and construction method of concrete filling pile structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150302

Owner name: NO.1 ENGINEERING CO., LTD., ZHONGTIE BRIDGE BUREAU

Free format text: FORMER OWNER: NO.1 ENGINEERING CO., LTD., ZHONGTIE BRIDGE BUREAU GROUP GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Effective date: 20150302

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430074 WUHAN, HUBEI PROVINCE TO: 430050 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20150302

Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No.

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Patentee after: No.1 Engineering Co., Ltd., Zhongtie Bridge Bureau Group

Address before: 430074 Hubei province Wuhan Dongxin East Lake New Technology Development Zone Road SBI Venture Street No. 6 Building 12 layer

Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd.

Patentee before: No.1 Engineering Co., Ltd., Zhongtie Bridge Bureau Group

Patentee before: Group Co., Ltd., Zhongtie Daqiao Bureau