JP3094423U - Waterway block for drainage pavement - Google Patents

Waterway block for drainage pavement

Info

Publication number
JP3094423U
JP3094423U JP2002007645U JP2002007645U JP3094423U JP 3094423 U JP3094423 U JP 3094423U JP 2002007645 U JP2002007645 U JP 2002007645U JP 2002007645 U JP2002007645 U JP 2002007645U JP 3094423 U JP3094423 U JP 3094423U
Authority
JP
Japan
Prior art keywords
drainage
block
water
pavement
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002007645U
Other languages
Japanese (ja)
Inventor
進治 花村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hokukon Co Ltd
Original Assignee
Hokukon Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hokukon Co Ltd filed Critical Hokukon Co Ltd
Priority to JP2002007645U priority Critical patent/JP3094423U/en
Application granted granted Critical
Publication of JP3094423U publication Critical patent/JP3094423U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Sewage (AREA)

Abstract

(57)【要約】 【課題】 排水性舗装部を浸透した浸透水を効率よく排
水可能とする排水性舗装構造を、将来の必要に応じて容
易に施工可能とする水路ブロックを提供する。 【解決手段】 排水性舗装部の縁部分に沿って敷設され
該排水性舗装部の浸透水を排水させるために用いる水路
ブロックである。長さ方向に水路9が設けられてなるブ
ロック本体7の、排水性舗装部の縁部分の端面に臨む上
角部分において、水路9に連通して浸透水を排出させる
排水孔を形成するための排水用盲孔22が設けられてい
る。排水用盲孔22は、ブロック本体7の外面側から、
ブロック本体の配筋を避けて設けられており、排水用盲
孔22の、鉄筋の存在しない底部分26を破ることによ
って排水孔を形成する。
(57) [Problem] To provide a drainage pavement structure capable of easily constructing a drainage pavement structure capable of efficiently draining permeated water that has penetrated into a drainage pavement portion, as required in the future. SOLUTION: This is a waterway block laid along an edge portion of a drainable pavement portion and used for draining permeated water of the drainage pavement portion. A drain hole for communicating with the water channel 9 and discharging permeated water is formed at an upper corner portion of the block body 7 having the water channel 9 provided in the length direction facing the end surface of the edge portion of the drainage pavement portion. A drainage blind hole 22 is provided. The drainage blind hole 22 is formed from the outer surface side of the block body 7.
The drain hole is formed by avoiding the reinforcement of the block body, and the drain hole is formed by breaking the bottom part 26 of the drain blind hole 22 where no reinforcing bar is present.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【考案の属する技術分野】[Technical field to which the device belongs]

本考案は、排水性舗装部を浸透した浸透水を効率よく排水可能とする排水性舗 装構造を、将来の必要に応じて容易に施工可能とする水路ブロックに関するもの である。   The present invention is a drainage pavement that enables efficient drainage of permeated water that has permeated the drainage pavement. Concerning canal blocks that can be easily constructed according to future needs Is.

【0002】[0002]

【従来の技術】[Prior art]

従来における道路の排水構造の一例は、図27に示すように、対向する側壁a ,aの両端部分の上部相互を連結梁b,bで連結すると共に該連結梁間の開口部 cにグレーチング(図示せず)を設置可能となされた、下端開放の門形をなすプ レキャストコンクリート製の水路ブロックdを用い、該水路ブロックdの側壁a ,a間の水路eを連通状態に敷設して排水路fを構築するものであり、路面gの 降雨水を、矢印で示すように、前記グレーチングを通して排水路f内に流入させ る構成のものであった。   An example of a conventional road drainage structure is shown in FIG. , A are connected to each other at their upper parts by connecting beams b and b, and an opening between the connecting beams is formed. A gate-shaped opening with an open bottom that allows a grating (not shown) to be installed on c. A water channel block d made of recast concrete is used, and a side wall a of the water channel block d is used. , A is laid in communication with a water channel e to build a drainage channel f. Rainwater is allowed to flow into the drainage channel f through the grating as shown by the arrow. It was of a composition.

【0003】 しかしながら、かかる排水構造によるときは、路面gの降雨水が前記開口部c に順次流入するとは言え、単位時間当たりの降雨量が多い場合は、路面gに水の 層が形成されて自動車のスリップ事故を誘発する問題があった。[0003]   However, in the case of such a drainage structure, the rainwater on the road surface g is not exposed to the opening c. However, if there is a large amount of rainfall per unit time, water will flow to the road surface g. There is a problem that the layer is formed to induce a slip accident of a car.

【0004】 そのため近年、降雨水を舗装部に浸透させ、この浸透水を排水路に流すように した排水性舗装構造も提案されている。[0004]   Therefore, in recent years, rainwater has been infiltrated into the pavement section, and this infiltrated water must be drained into A drainage pavement structure has also been proposed.

【0005】 このような排水性舗装構造は、道路の交通状況等に応じて道路舗装と同時に施 工される場合もあるが、水路を具えた既設の舗装部を、道路の交通量等に応じて 排水性の舗装部に変更する必要が、将来的に生ずることがある。[0005]   Such a drainage pavement structure should be applied at the same time as road pavement, depending on the road traffic conditions. It may be constructed, but the existing pavement with a waterway can be installed according to the traffic volume of the road. The need to change to a drainage pavement may arise in the future.

【0006】 ところで前記既設の舗装状態を、前記した排水性舗装構造に変更する従来の施 工法の一例は、図28に示すように、水路ブロックdの上側角部分jの所要部位 をドリルで穿孔して、前記水路eに連通する排水孔kを形成した後、通常のアス ファルト舗装部又はコンクリート舗装部からなる不透水性の基盤m上に重ねて所 要厚さで設けられた排水性舗装部nの縁部分の端面pを前記上側角部分jに当接 状態とし、図28に矢印で示すように、該排水性舗装部nを浸透して前記基盤m の上面qに達した水を該上面qで流下させ、前記排水路fに流入させるものであ った。[0006]   By the way, the existing pavement condition is changed to the drainage pavement structure described above. An example of the construction method is, as shown in FIG. 28, a required portion of the upper corner portion j of the waterway block d. After forming a drain hole k communicating with the water channel e by drilling the Placed on a water-impermeable base m consisting of pavement pavement or concrete pavement The end surface p of the edge portion of the drainage pavement portion n having a required thickness is brought into contact with the upper corner portion j. In this state, as shown by the arrow in FIG. The water that has reached the upper surface q of the above is made to flow down on the upper surface q and flow into the drainage channel f. It was.

【0007】[0007]

【考案が解決しようとする課題】[Problems to be solved by the device]

しかしながら、前記水路ブロックdの上側の比較的厚い角部分jに排水孔kを ドリルで穿孔する際、穿孔に無理が生じて上側角部分jが割れ易かった。又、水 路ブロック内の配筋状態が外部からは分からないために、ドリルで鉄筋を切断す る場合も生じてブロック強度を低下させる恐れがあったし、このように鉄筋に当 たって穿孔する際には上側角部分jが一層割れ易かった。このように、排水孔の 後加工を伴う前記施工法によるときは、ブロックを損傷することなく正確且つ容 易に排水孔を設けることが極めて困難であったのである。   However, the drain hole k is formed in the relatively thick corner portion j on the upper side of the water channel block d. When drilling, the upper corner j was liable to crack due to excessive force in the drilling. Also, water Since the reinforcing bar inside the road block is not known from the outside, cut the reinforcing bar with a drill. In some cases, the strength of the block may decrease and the reinforcing bar may be touched in this way. The upper corner portion j was more liable to break when drilling. In this way, the drain hole When the above-mentioned construction method involving post-processing is used, the block is accurate and It was extremely difficult to easily provide drainage holes.

【0008】 そのため、このような問題を回避せんとして、既に敷設されている水路ブロッ クを、部分的に、排水溝が設けられている水路ブロックと交換して施工したり、 敷設されている水路ブロックの上部に排水用ブロックを設置して施工することも 行われていたが、このような水路ブロックの取り替え施工や排水ブロックの設置 施工は大掛かりなものとなり、多くの手間を要し又施工コストの上昇を招く問題 があった。[0008]   Therefore, in order to avoid such a problem, the waterway block already installed Partly replace the water channel block with a drainage channel for construction, It is also possible to install a drainage block on top of the laid waterway block for construction. It was done, but replacement construction of such a waterway block and installation of a drainage block Construction becomes a large-scale work, requires a lot of labor, and causes a rise in construction cost. was there.

【0009】 なお若しも、排水孔kをドリル穿孔で無理に形成せんとするときは、上側角部 分jの破損を極力生じさせないために、例えば図29に示すように、その排水孔 kを、より下方に位置させて設ける必要が生じた。しかしながら、このように下 方に位置させて排水孔kを設けたときは、排水性舗装部nを浸透して前記基盤m の上面qに達した水を該上面qで流下させて水路ブロックの排水路fに流入させ る必要上、少なくとも、水路ブロックの上側角部分jに近接した部分においては 、排水性舗装部nを厚く施工する必要があり、それだけ施工コストの上昇を招く 問題が生じた。また排水孔kの位置を下げた結果、水路ブロックの排水路fを流 れる水の水位が、図29に一点鎖線rで示すように高い場合は、その流水が排水 路kを逆流して前記排水性舗装部nの上面に湧出する恐れもあった。[0009]   In addition, if you want to force the drainage hole k by drilling, the upper corner In order to prevent the damage of the portion j as much as possible, for example, as shown in FIG. It was necessary to position k so that it was located lower. However, like this When the drainage hole k is provided at one side, the drainage pavement n is permeated to penetrate the foundation m. The water reaching the upper surface q of the water is flowed down on the upper surface q to flow into the drainage channel f of the water channel block. Therefore, at least in a portion close to the upper corner portion j of the waterway block, , It is necessary to construct the drainage pavement part n thick, which causes an increase in construction cost. There was a problem. Also, as a result of lowering the position of the drainage hole k, the drainage channel f of the waterway block flows. When the level of the water to be discharged is high as indicated by the one-dot chain line r in FIG. 29, the running water is drained. There is also a possibility that the water may flow backward through the road k and spring out onto the upper surface of the drainage pavement n.

【0010】 本考案は、かかる問題点に鑑みて開発されたものであり、排水性舗装構造の構 築が将来的に必要となった場合に、確実且つ能率的に然も比較的低コストでこれ に応ずることのできる排水性舗装用の水路ブロックの提供を課題とするものであ る。[0010]   The present invention was developed in view of such problems, and the structure of the drainage pavement structure is If construction is needed in the future, this can be done reliably and efficiently at relatively low cost. The problem is to provide a waterway block for drainage pavement that can respond to It

【0011】[0011]

【課題を解決するための手段】[Means for Solving the Problems]

前記課題を解決するため、本考案は以下の手段を採用する。 即ち本考案に係る排水性舗装用の水路ブロック(以下水路ブロックという)は 、排水性舗装部の縁部分に沿って敷設され該排水性舗装部の浸透水を排水させる ために用いる水路ブロックであって、長さ方向に水路が設けられてなるブロック 本体の、前記排水性舗装部の縁部分の端面に臨む上角部分において、前記水路に 連通して前記浸透水を排出させる排水孔を形成するための有底の排水用盲孔を、 ブロック本体の前記上角部分の外側面側及び/又は前記上角部分の内側面側から 、ブロック本体の配筋を避けて設けると共に、該排水用盲孔の、鉄筋の存在しな い底部分を破ることによって前記排水孔を形成可能としたことを特徴とするもの である。   In order to solve the above problems, the present invention employs the following means.   That is, the drainage block for drainage pavement according to the present invention (hereinafter referred to as the drainage block) is Laid along the edge of the drainage pavement to drain the permeated water from the drainage pavement A waterway block used for the purpose of providing a waterway in the longitudinal direction. At the upper corner portion of the main body facing the end surface of the edge portion of the drainage pavement, A bottomed drainage blind hole for forming a drainage hole that communicates to discharge the permeated water, From the outer surface side of the upper corner portion and / or the inner surface side of the upper corner portion of the block body The block body should be installed avoiding the bar arrangement, and the drainage blind hole should not have any reinforcing bars. Characterized in that the drain hole can be formed by breaking the bottom portion Is.

【0012】 前記水路ブロックにおいて、前記排水用盲孔は、ブロック本体の前記上角部分 の外側面で開放する如く設けその底面を、ブロック本体の前記上角部分の内側面 に近接させるのがよい。或いは、前記排水用盲孔を、ブロック本体の前記上角部 分の内側面で開放させ、且つその底面を、ブロック本体の前記上角部分の外側面 に近接させてもよい。[0012]   In the waterway block, the blind hole for drainage is the upper corner portion of the block body. The outer surface of the block is opened so that its bottom surface is the inner surface of the upper corner of the block body. It is good to be close to. Alternatively, the blind hole for drainage is provided in the upper corner portion of the block body. The inner surface of the block is open, and the bottom surface is the outer surface of the upper corner portion of the block body. May be close to.

【0013】 本考案に係る水路ブロックの他の態様は、排水性舗装部の縁部分に沿って敷設 され該排水性舗装部の浸透水を排水させるために用いる水路ブロックであって、 長さ方向に水路が設けられてなるブロック本体の、前記排水性舗装部の縁部分の 端面に臨む水路ブロックの水路に連通する貫通孔を設け、該貫通孔の前記排水性 舗装部の縁部分側の開口端部を、取り外し可能の蓋体で閉蓋することによって有 底の排水用盲孔を形成してなり、該蓋体を取り外すことによって、前記水路に連 通して前記浸透水を排出させる排水孔を形成可能としたことを特徴とするもので ある。[0013]   Another aspect of the waterway block according to the present invention is that the waterway block is laid along the edge portion of the drainage pavement. A channel block used to drain the permeated water of the drainage pavement, Of the edge part of the drainage pavement part of the block main body provided with a water channel in the length direction A through hole communicating with the water channel of the water channel block facing the end face is provided, and the drainage property of the through hole is provided. Exists by closing the open end of the pavement on the edge side with a removable lid. A drainage blind hole is formed at the bottom, and the lid is removed to connect to the waterway. It is characterized in that it is possible to form a drain hole through which the permeated water is discharged. is there.

【0014】 前記水路ブロックを構成するブロック本体としては、対向する側壁の上部相互 を連結梁で連結してなる下端開放の門形をなすものを用い、該連結梁が存在する 部分で前記排水用盲孔を設けるのがよい。又、両端が開放し周方向に閉じた水路 を有するブロック本体を用いることもでき、U字溝としてのブロック本体を用い ることもできる。[0014]   As the block body that constitutes the water channel block, the upper parts of the opposite side walls are mutually There is a connecting beam that has a gate shape that is open at the lower end and is connected by a connecting beam. It is preferable to provide the drainage blind hole at a portion. In addition, a waterway with both ends open and closed in the circumferential direction It is also possible to use a block body having a You can also do it.

【0015】 前記各ブロック本体において、ブロック本体の、前記排水性舗装部の縁部分の 端面に臨む上角部分の外側面に、その長さ方向に連続し且つブロック本体の両端 部で開放する如く集水溝を設け、該集水溝の溝幅を、舗装用の骨材が入り込んで 集水溝を遮断しないように設定し、且つ該集水溝の長さ方向の所要部分に連通す る状態で排水孔を形成できるように前記排水用盲孔を設けるのがよい。[0015]   In each of the block bodies, of the block body, of the edge portion of the drainage pavement Both ends of the block body that are continuous in the lengthwise direction on the outer surface of the upper corner facing the end surface The water collecting groove is provided so that it is opened at the section, and the groove width of the water collecting groove is filled with the aggregate for paving. Set so that the water collection groove is not blocked, and communicate with the required part in the length direction of the water collection groove. It is preferable to provide the drainage blind hole so that the drainage hole can be formed in a state where the drainage hole is formed.

【0016】[0016]

【考案の実施の形態】[Embodiment of device]

以下、本考案の実施の形態を図面に基づいて説明する。 〔第1の実施の形態〕 図1〜3において本考案に係る水路ブロック1は、図6〜7に示すような排水 性舗装部2に隣接状態で敷設されることによって排水性舗装構造3を構築するも のであり、所要間隔を隔てて対向する左右側壁5,5の両端部分の上部相互を連 結梁6で連結してなる下端開放の門形をなすブロック本体7を有し、その両側壁 5,5間に水路9が形成されている。なお本実施の形態において該ブロック本体 7の上面10は、一方の側壁5aから他方の側壁5bに向けて傾斜している。又 左右側壁5,5の下部相互は、適宜補強梁で連結されることがある。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. [First Embodiment]   1 to 3, the water channel block 1 according to the present invention is a drainage block as shown in FIGS. The drainage pavement structure 3 is constructed by being laid adjacent to the water-resistant pavement section 2. Therefore, the upper portions of both end portions of the left and right side walls 5 and 5 facing each other with a required space therebetween are connected to each other. It has a block-shaped block main body 7 which is connected at its lower end and has an open lower end, and both side walls thereof. A waterway 9 is formed between 5 and 5. In the present embodiment, the block body is The upper surface 10 of 7 is inclined from one side wall 5a toward the other side wall 5b. or The lower portions of the left and right side walls 5, 5 may be appropriately connected by a reinforcing beam.

【0017】 そして該ブロック本体7の一方の側壁5aの、前記排水性舗装部2の縁部分の 端面11(図7)に臨む上角部分8の外側面が、ブロック本体7の長さ方向に連 続する受水面12とされている。該受水面12の上下幅は、例えば10cm程度 に設定する。[0017]   Then, the edge portion of the drainage pavement 2 on one side wall 5a of the block body 7 is The outer surface of the upper corner portion 8 facing the end surface 11 (FIG. 7) is continuous in the length direction of the block body 7. It is assumed to be the continuous water receiving surface 12. The vertical width of the water receiving surface 12 is, for example, about 10 cm. Set to.

【0018】 そして該受水面12の下端寄り部分の上下には、集水溝13,13が、ブロッ ク本体7の両端で開放するように設けられている。なお該集水溝13の溝幅は、 舗装用の骨材が入り込んで集水溝を遮断しないように例えば20mm程度に設定 されている。又該ブロック本体7の、前記連結梁6,6が存在する両端側部分1 5,15の前後には、前記受水面において排水孔形成凹部16(図2)が配置さ れており、該排水孔形成凹部16は、前記上下の集水溝13,13を、その溝底 面17,17と面一の底面19を有する凹部20で連結して設けられている。[0018]   The water collecting grooves 13, 13 are provided above and below the lower end portion of the water receiving surface 12. It is provided so as to be open at both ends of the main body 7. The groove width of the water collecting groove 13 is For example, set to about 20 mm so that aggregates for paving do not enter and block the water collection groove. Has been done. Further, both end side portions 1 of the block main body 7 where the connecting beams 6 and 6 exist The drainage hole forming recesses 16 (Fig. 2) are arranged on the water receiving surface before and after 5, 5 and 15, respectively. The drainage hole forming recess 16 includes the upper and lower water collecting grooves 13 and 13 at the bottom thereof. It is provided so as to be connected by a recess 20 having a bottom surface 19 flush with the surfaces 17, 17.

【0019】 そして、これらの排水孔形成凹部16の底面には、斜め下方に延びて前記水路 9に連通する、横断面円形で下端側ほど細くなるテーパ状の排水孔21(図6〜 7)を形成するための有底の排水用盲孔22が、ブロック本体7の配筋を避けて 設けられている。該排水用盲孔22の底面23は、図3に示すようにブロック本 体の前記上角部分の内側面25に近接状態にあり、該排水用盲孔22の、鉄筋の 存在しない底部分26を該排水用盲孔の軸線方向に破ることによって前記排水孔 21を形成できる。このように形成された排水孔21の上端開口の孔縁下端(即 ち排水用盲孔22の孔縁下端)29(図2、図7)は、前記排水孔形成凹部16 の底面下縁に略合致させるのがよい。[0019]   Then, on the bottom surfaces of these drainage hole forming recesses 16, the water passages extending obliquely downward are formed. 9 and a tapered drainage hole 21 (FIG. 6 to FIG. The bottomed drainage blind hole 22 for forming 7) avoids the bar arrangement of the block body 7. It is provided. The bottom surface 23 of the drainage blind hole 22 is a block book as shown in FIG. In the state of being close to the inner side surface 25 of the upper corner portion of the body, By breaking the nonexisting bottom portion 26 in the axial direction of the drainage blind hole, the drainage hole is formed. 21 can be formed. The hole edge lower end of the upper end opening of the drainage hole 21 thus formed (immediately The bottom edge of the drainage blind hole 22) 29 (FIGS. 2 and 7) is the drainage hole forming recess 16 It is good to match the bottom edge of the bottom.

【0020】 該水路ブロック1は、図4に示すように、排水性舗装構造の施工が将来的に予 定されている舗装部30の縁部分に沿って敷設され、所要の排水路31を構築す る。[0020]   As shown in FIG. 4, construction of drainage pavement structure is planned for the waterway block 1 in the future. It is laid along the specified edge of the pavement 30 to build the required drainage channel 31. It

【0021】 かかる構成の水路ブロック1を用いて、差し当たって、図4に示す排水路31 を構築するには、舗装用の骨材等が前記排水用盲孔22内に入り込まないように するため、該排水用盲孔22の上端開口を、図4〜5に示すように、取り外し可 能の蓋33で閉蓋しておくのがよい。[0021]   Using the water channel block 1 having such a structure, the water channel 31 shown in FIG. In order to build the structure, make sure that aggregates for paving do not get inside the blind hole 22 for drainage. Therefore, the upper end opening of the drainage blind hole 22 is removable as shown in FIGS. It is better to close it with the Noh lid 33.

【0022】 そして、将来的に排水性舗装構造3の構築が必要となったときには、図4に示 す既存の舗装部30を撤去すると共に前記蓋33を取り外して後、排水用盲孔2 2内に棒状工具を差し込んで盲孔の底部分26を突き破り、図6〜7に示すよう な排水孔21を形成するのである。なお該排水孔21の寸法は、例えば、上端径 を40mmに設定し下端径を20mmに設定する。[0022]   Then, when it becomes necessary to construct the drainage pavement structure 3 in the future, as shown in FIG. After removing the existing pavement 30 and removing the lid 33, the drainage blind hole 2 Insert a rod-shaped tool into 2 to break through the bottom portion 26 of the blind hole, as shown in FIGS. The drainage holes 21 are formed. The size of the drain hole 21 is, for example, the upper end diameter. Is set to 40 mm and the lower end diameter is set to 20 mm.

【0023】 このように形成した排水孔21内に舗装用の骨材等が侵入するのを防ぐため、 図8に示すように、網状板や孔明き板等のフイルタ部材35を前記排水孔形成凹 部16に嵌め込み、該凹部の底面に固定するのがよい。或いは図8に一点鎖線で 示すように、フイルタ孔34が多数設けられた孔明き板等のフイルタ部材35を 、排水孔21及び上下の集水溝13,13を覆うようにブロック外面に固定する のがよい。なお該固定手段として粘着テープを用いるときは、フイルタ部材35 が目詰まりしたときにその交換を容易に行うことができて好ましい。[0023]   In order to prevent the pavement aggregate and the like from entering the drain hole 21 formed in this way, As shown in FIG. 8, a filter member 35 such as a mesh plate or a perforated plate is provided with the drain hole forming recess. It is preferable to fit it in the portion 16 and fix it to the bottom surface of the recess. Alternatively, in FIG. As shown, a filter member 35 such as a perforated plate having a large number of filter holes 34 is provided. , Fixed to the outer surface of the block so as to cover the drain hole 21 and the upper and lower water collecting grooves 13, 13. Is good. When an adhesive tape is used as the fixing means, the filter member 35 Is preferable because it can be easily replaced when it is clogged.

【0024】 前記排水性舗装部(道路勾配は約2%)2は、図6〜7に示すように、通常の アスファルト舗装部又はコンクリート舗装部からなる不透水性の基盤36上に重 ねて所定厚さで設けられ、その上面37が前記ブロック本体7の前記傾斜した上 面10に連なるようにする。該排水性舗装部2の端部厚さは、前記受水面12の 上下幅に略等しく設定されている。このように排水性舗装部2を設けた場合、前 記集水溝13の溝幅が20mm程度に設定されているため、該集水溝13内に骨 材が入り込んで該溝を遮断する恐れを防止でき、良好な集水性を維持させ得る。[0024]   The drainage pavement (road slope is about 2%) 2 is a normal drainage pavement as shown in FIGS. Overlays an impermeable base 36 consisting of asphalt pavement or concrete pavement. It is provided with a predetermined thickness, and the upper surface 37 of the block main body 7 It is connected to the surface 10. The edge thickness of the drainage pavement 2 is equal to that of the water receiving surface 12. It is set to be approximately equal to the vertical width. When the drainage pavement section 2 is provided in this way, Since the groove width of the water collecting groove 13 is set to about 20 mm, the water collecting groove 13 has a bone It is possible to prevent the material from entering and blocking the groove, and maintain good water collection.

【0025】 なお該排水性舗装部2は、前記受水面12の上下幅の厚さで全幅を形成しても よいのであるが、本実施の形態においては、排水性舗装部の施工経済を考慮して 、図6〜7に示すように、受水面12に近接した部分39だけを、受水面の上下 幅の厚さ(例えば10cm)とし、その他の部分はこれよりも薄く形成している 。なお図6において符号40は、歩車道境界ブロックである。[0025]   It should be noted that the drainage pavement portion 2 may have a full width in the vertical width of the water receiving surface 12. It is good, but in this embodiment, considering the construction economy of drainage pavement As shown in FIGS. 6 to 7, only the portion 39 close to the water receiving surface 12 is located above and below the water receiving surface. Thickness of width (eg 10 cm) and other parts thinner than this . In FIG. 6, reference numeral 40 is a pedestrian road boundary block.

【0026】 然してかかる排水性舗装部2に降雨があった場合、その降雨水は、該排水性舗 装部2を浸透して前記基盤36の上面41に達し、該上面41を、埋設状態の水 路ブロック1に向けて流下する。そして前記受水面12に達した水は、前記排水 孔21に直接流入し、又は前記集水溝13に流入し、該集水溝13に沿って流れ て排水孔21に流入する。この際、前記のように集水溝13の溝幅を、骨材が入 り込まない程度のものに小さく設定しているため、良好な集水性が永続して確保 されることになる。又該集水溝13は、その両端がブロック本体7の両端部で開 放しているため、図9に示すように、隣り合う水路ブロック1,1に設けられて いる集水溝13,13相互は連通状態となる。従って、ある水路ブロックにおけ る浸透水の水量が多い場合であっても、この浸透水は、連通状態の集水溝13を 流れて他の水路ブロックの排水孔21に流入できることから、全体として効率的 な排水を達成できることになる。なお図6〜7において矢印は、水の浸透状態と 排水路31への浸透水の流入状態を示す。[0026]   However, when there is rainfall in the drainage pavement 2, the rainwater is It penetrates through the mounting portion 2 and reaches the upper surface 41 of the base 36, and the upper surface 41 is filled with water in an embedded state. Run down toward road block 1. The water reaching the water receiving surface 12 is the drainage water. It directly flows into the hole 21, or flows into the water collecting groove 13 and flows along the water collecting groove 13. And flows into the drain hole 21. At this time, as described above, the aggregate width is set to the groove width of the water collecting groove 13. Since it is set to a size that does not allow it to penetrate, good water collection is secured permanently Will be done. Further, both ends of the water collecting groove 13 are opened at both ends of the block body 7. Since it is released, as shown in FIG. 9, it is installed in the adjacent water channel blocks 1, 1. The existing water collecting grooves 13, 13 are in communication with each other. Therefore, in a certain waterway block Even if there is a large amount of permeated water, the permeated water will flow through the water collecting groove 13 in the communicating state. Since it can flow and flow into the drainage holes 21 of other waterway blocks, it is efficient as a whole. It will be possible to achieve efficient drainage. The arrows in FIGS. 6 to 7 indicate the state of water penetration. The inflow state of the permeated water to the drainage channel 31 is shown.

【0027】 〔第2の実施の形態〕 図10〜12は、本考案に係る水路ブロック1の他の態様を示すものであり、 図15〜16に示すような排水性舗装部2に隣接状態で敷設されることによって 排水性舗装構造3を構築するものである。[0027] [Second Embodiment]   10 to 12 show another embodiment of the waterway block 1 according to the present invention, By laying adjacent to the drainage pavement 2 as shown in FIGS. The drainage pavement structure 3 is constructed.

【0028】 該水路ブロック1は、より具体的には、横断面外形が略正方形状をなすブロッ ク本体7を有し、長手方向に延び且つ両端で開口する円形の水路9が形成されて いる。そして該ブロック本体7の、前記排水性舗装部2の縁部分の端面に臨む上 角部分8の外側面は、受水面12とされている。なお該受水面12の上下幅は、 例えば10cm程度に設定する。[0028]   More specifically, the water channel block 1 is a block having a substantially square cross section. A circular water channel 9 is formed which has a main body 7 and which extends in the longitudinal direction and is open at both ends. There is. Then, the block main body 7 faces the end surface of the edge portion of the drainage pavement 2. The outer surface of the corner portion 8 is a water receiving surface 12. The vertical width of the water receiving surface 12 is For example, it is set to about 10 cm.

【0029】 そして前記受水面12の下端寄り部分の上下には、集水溝13,13が、ブロ ック本体7の両端で開放するように設けられている。なお該集水溝13の溝幅は 、舗装用の骨材が入り込んで集水溝を遮断しないように例えば20mm程度に設 定されている。又該ブロック本体7の前記受水面12には、排水孔形成凹部16 が並設されており、該排水孔形成凹部16は、前記上下の集水溝13を、その溝 底面17,17と面一の底面19を有する凹部20で連結して設けられている。[0029]   Water collecting grooves 13, 13 are provided above and below the lower end portion of the water receiving surface 12, respectively. It is provided so as to open at both ends of the dock body 7. The width of the water collecting groove 13 is , So that the aggregate for pavement does not enter and block the water collection groove It is fixed. Further, the water receiving surface 12 of the block body 7 has a drain hole forming recess 16 Are arranged side by side, and the drain hole forming concave portion 16 has the upper and lower water collecting grooves 13 The bottom surfaces 17 and 17 are connected to each other through a recess 20 having a flush bottom surface 19.

【0030】 そして、これらの排水孔形成凹部16の底面には、斜め下方に延びて前記水路 9に連通する、横断面円形で下端側ほど細くなるテーパ状の排水孔21(図15 〜16)を形成するための有底の排水用盲孔22が、ブロック本体7の配筋を避 けて設けられている。該排水用盲孔22の底面23は、図12に示すようにブロ ック本体の前記上角部分の内側面25に近接状態にあり、該排水用盲孔22の、 鉄筋の存在しない底部分26を該排水用盲孔の軸線方向に破ることによって前記 排水孔21を形成できる。このように形成された排水孔21の上端開口の孔縁下 端(即ち排水用盲孔22の孔縁下端)29(図11、図16)は、前記排水孔形 成凹部16の底面下縁に略合致させるのがよい。[0030]   Then, on the bottom surfaces of these drainage hole forming recesses 16, the water passages extending obliquely downward are formed. 9, a drain hole 21 having a circular cross section and tapered toward the lower end (FIG. 15). ~ 16) to form a bottomed blind hole 22 for drainage to avoid the reinforcement of the block body 7. It is installed on the phone. As shown in FIG. 12, the bottom surface 23 of the drainage blind hole 22 has a Of the blind hole 22 for drainage, which is in a state of being close to the inner side surface 25 of the upper corner portion of the dock main body, By breaking the rebar-free bottom portion 26 in the axial direction of the drainage blind hole, The drain hole 21 can be formed. Below the hole edge of the upper end opening of the drainage hole 21 formed in this way The end (that is, the lower end of the hole edge of the drainage blind hole 22) 29 (FIGS. 11 and 16) is the drainage hole shape. It is preferable that the bottom edge of the bottom surface of the recess 16 is substantially matched.

【0031】 該水路ブロック1は、図13に示すように、将来的に排水性舗装構造の施工が 予定されている舗装部30の縁部分に沿って敷設され、所要の排水路31を構築 する。[0031]   As shown in FIG. 13, the waterway block 1 will be constructed with a drainage pavement structure in the future. It is laid along the planned edge of the pavement section 30 to build the required drainage channel 31. To do.

【0032】 かかる構成の水路ブロック1を用いて、差し当たって、図13に示す排水路3 1を構築するには、舗装用の骨材等が前記排水用盲孔22内に入り込まないよう にするために、該排水用盲孔22の上端開口を、図13〜14に示すように、取 り外し可能の蓋33で閉蓋しておくのがよい。[0032]   Using the water channel block 1 having such a structure, the water channel 3 shown in FIG. In order to build No. 1, pavement aggregates, etc. do not enter the drainage blind hole 22. In order to ensure that the drainage blind hole 22 has an upper opening, as shown in FIGS. It is preferable to close the cover with a removable lid 33.

【0033】 そして、将来的に排水性舗装構造3の構築が必要となったときには、図13に 示す既存の舗装部30を撤去すると共に前記蓋33を取り外して後、排水用盲孔 22内に棒状工具を差し込んで盲孔の底部分26を突き破り、図15〜16に示 すような排水孔21を形成するのである。なお該排水孔21の寸法は、例えば、 上端径を40mmに設定し下端径を20mmに設定する。[0033]   Then, when it becomes necessary to construct the drainage pavement structure 3 in the future, as shown in FIG. After removing the existing pavement section 30 and removing the lid 33, a blind hole for drainage is shown. Insert a rod-shaped tool into 22 to break through the bottom portion 26 of the blind hole, as shown in FIGS. The drain hole 21 is formed. The dimensions of the drain hole 21 are, for example, The upper end diameter is set to 40 mm and the lower end diameter is set to 20 mm.

【0034】 このように形成した排水孔21内に舗装用の骨材等が侵入するのを防ぐため、 図17に示すように、網状板や孔明き板等のフイルタ部材35を前記排水孔形成 凹部16に嵌め込み、該凹部の底面に固定するのがよい。或いは図17に一点鎖 線で示すように、フイルタ孔34が多数設けられた孔明き板等フイルタ部材35 を、排水孔21及び上下の集水溝13,13を覆うようにブロック外面に固定す るのがよい。なお該固定手段として粘着テープを用いるときは、フイルタ部材3 5が目詰まりしたときにその交換を容易に行うことができて好ましい。[0034]   In order to prevent the pavement aggregate and the like from entering the drain hole 21 formed in this way, As shown in FIG. 17, a filter member 35 such as a mesh plate or a perforated plate is used to form the drain holes. It is preferable to fit it in the recess 16 and fix it to the bottom surface of the recess. Alternatively, as shown in FIG. As shown by the line, a filter member 35 such as a perforated plate provided with a number of filter holes 34. Is fixed to the outer surface of the block so as to cover the drain hole 21 and the upper and lower water collecting grooves 13, 13. It is good to When an adhesive tape is used as the fixing means, the filter member 3 When 5 is clogged, it can be easily replaced, which is preferable.

【0035】 前記排水性舗装部(道路勾配は約2%)2は、図15〜16に示すように、通 常のアスファルト舗装部又はコンクリート舗装部からなる不透水性の基盤36上 に重ねて所定厚さで設けられ、その上面37が前記ブロック本体7の傾斜した上 面38に連なるようにする。該排水性舗装部2の端部厚さは、前記受水面12の 上下幅に略等しく設定されている。このように排水性舗装部2を設けた場合、前 記集水溝13の溝幅が20mm程度に設定されているため、該集水溝13内に骨 材が入り込んで該溝を遮断する恐れを防止でき、良好な集水性を維持させ得る。[0035]   As shown in FIGS. 15 to 16, the drainage pavement 2 (road slope is about 2%) 2 On an impermeable base 36 consisting of regular asphalt pavement or concrete pavement Is provided with a predetermined thickness so that the upper surface 37 of the block main body 7 is inclined. It should be continuous with the surface 38. The edge thickness of the drainage pavement 2 is equal to that of the water receiving surface 12. It is set to be approximately equal to the vertical width. When the drainage pavement section 2 is provided in this way, Since the groove width of the water collecting groove 13 is set to about 20 mm, the water collecting groove 13 has a bone It is possible to prevent the material from entering and blocking the groove, and maintain good water collection.

【0036】 なお該排水性舗装部2は、前記受水面12の上下幅の厚さで全幅を形成しても よいのであるが、本実施の形態においては、排水性舗装部の施工経済を考慮して 、図15〜16に示すように、受水面12に近接した部分39だけを、受水面の 上下幅の厚さ(例えば10cm)とし、その他の部分はこれよりも薄く形成して いる。なお図15において符号40は、歩車道境界ブロックである。[0036]   It should be noted that the drainage pavement portion 2 may have a full width in the vertical width of the water receiving surface 12. It is good, but in this embodiment, considering the construction economy of drainage pavement As shown in FIGS. 15 to 16, only the portion 39 close to the water receiving surface 12 is The thickness of the top and bottom width (eg 10 cm), and the other parts should be thinner than this There is. In FIG. 15, reference numeral 40 is a pedestrian road boundary block.

【0037】 然してかかる排水性舗装部2に降雨があった場合、その降雨水は、該排水性舗 装部2を浸透して前記基盤36の上面41に達し、該上面41を、埋設状態の水 路ブロック1に向けて流下する。そして前記受水面12に達した水は、前記排水 孔21に直接流入し、又は前記集水溝13に流入し、該集水溝13に沿って流れ て排水孔21に流入する。この際、前記のように集水溝13の溝幅を、骨材が入 り込まない程度のものに小さく設定しているため、良好な集水性が永続して確保 されることになる。又該集水溝13は、その両端がブロック本体7の両端部で開 放しているため、図18に示すように、隣り合う水路ブロック1,1に設けられ ている集水溝13,13相互は連通状態となる。従って、ある水路ブロックにお ける浸透水の水量が多い場合であっても、この浸透水は、連通状態の集水溝13 を流れて他の水路ブロックの排水孔21に流入できることから、全体として効率 的な排水を達成できることになる。なお図15〜16において矢印は、水の浸透 状態と排水路31への浸透水の流入状態を示す。[0037]   However, when there is rainfall in the drainage pavement 2, the rainwater is It penetrates through the mounting portion 2 and reaches the upper surface 41 of the base 36, and the upper surface 41 is filled with water in an embedded state. Run down toward road block 1. The water reaching the water receiving surface 12 is the drainage water. It directly flows into the hole 21, or flows into the water collecting groove 13 and flows along the water collecting groove 13. And flows into the drain hole 21. At this time, as described above, the aggregate width is set to the groove width of the water collecting groove 13. Since it is set to a size that does not allow it to penetrate, good water collection is secured permanently Will be done. Further, both ends of the water collecting groove 13 are opened at both ends of the block body 7. Since it is released, it is installed in the adjacent waterway blocks 1, 1 as shown in FIG. The existing water collecting grooves 13, 13 are in communication with each other. Therefore, in a certain waterway block Even if there is a large amount of permeated water, the permeated water will not pass through the water collecting groove 13 in the communicating state. Can flow into the drainage holes 21 of other waterway blocks, thus improving overall efficiency. Drainage can be achieved. In addition, in FIGS. 15 to 16, arrows indicate water penetration. The state and the inflow state of the permeated water into the drainage channel 31 are shown.

【0038】 〔その他の実施の形態〕 (1) 排水孔21を形成する排水用盲孔22は、排水性舗装部2の浸透水を水路9 に流入させ得る排水孔を形成するものであれば、前記した横断面円形孔に限られ ず、横断面楕円形孔やその他の形態に構成されてもよい。又その孔は、前記のよ うなテーパ孔であることの他、全長に亘って同径の孔であってもよい。又、孔径 が長さ方向で変化するものであってもよい。[0038] [Other Embodiments] (1) The drainage blind hole 22 that forms the drainage hole 21 allows the permeated water of the drainage pavement 2 to pass through the water channel 9. As long as it forms a drain hole that can be introduced into Instead, the holes may be elliptical in cross section or other forms. Also, the hole is as described above. In addition to the tapered hole, the hole may have the same diameter over the entire length. Also, the hole diameter May vary in the length direction.

【0039】 (2) ブロック本体は、前記したものの他、U字溝を以って形成されてもよい。[0039] (2) The block body may be formed with a U-shaped groove other than the above.

【0040】 (3) ブロック本体が門形を呈する場合、ブロック本体の強度を極力損なわないよ うにするため、図1に示すように、連結梁6が存する部分で排水用盲孔22を設 けるのが好ましいが、ブロック本体の強度に問題がなければ、連結梁間に排水用 盲孔を設けてもよい。[0040] (3) When the block body has a gate shape, the strength of the block body is not impaired as much as possible. In order to do so, as shown in FIG. 1, a drainage blind hole 22 is provided at the portion where the connecting beam 6 exists. Although it is preferable to drain it, if there is no problem with the strength of the block body, drainage between the connecting beams Blind holes may be provided.

【0041】 (4) 排水用盲孔22は、図3や図12に示すように、ブロック本体7の外面側で 開放するように設けるのが製造上好ましいが、例えば図19〜20に示すように 、ブロック本体7の内側から設けることもある。 この場合は、鉄筋が存在しない盲孔底部分26をブロック本体7の外側から破 ることによって、排水孔を形成する。そのために、盲孔底部分の位置を明示する 目印をブロック本体の外面に設けておくのがよい。 又排水用盲孔22は、例えば図21〜22に示すように、ブロック本体7の前 記上角部分の外側面側及び内側面側から設け、盲孔底部分26を、形成される排 水孔の中間に位置させることもある。[0041] (4) The blind hole 22 for drainage is provided on the outer surface side of the block body 7 as shown in FIG. 3 and FIG. Although it is preferable to provide the opening so as to be open, for example, as shown in FIGS. It may be provided from the inside of the block body 7.   In this case, the blind hole bottom portion 26 where there is no reinforcing bar is broken from the outside of the block body 7. To form a drainage hole. Therefore, the position of the bottom part of the blind hole is specified It is preferable that the mark is provided on the outer surface of the block body.   Further, the drainage blind hole 22 is provided in front of the block main body 7 as shown in FIGS. The blind hole bottom portion 26 is formed from the outer surface side and the inner surface side of the above-mentioned corner portion, and the blind hole bottom portion 26 is formed. It may be located in the middle of the water hole.

【0042】 (5) 本考案に係る水路ブロックは、図23〜24に示すように、その製造時点で 設けた貫通孔41の端部を、取り外し可能の蓋体42で閉蓋して構成した排水性 盲孔22を具えるものとして構成されることもある。この場合は該蓋体42を取 り外すことによって、前記水路9に連通する排水孔を形成できる。[0042] (5) The waterway block according to the present invention, as shown in FIGS. Drainability by closing the end of the provided through-hole 41 with a removable lid 42. It may be configured as having a blind hole 22. In this case, remove the lid 42. By removing it, a drain hole communicating with the water channel 9 can be formed.

【0043】 (6) ブロック本体の、排水性舗装部の端面に臨む受水面12は、図1や図10に 示すような垂直面に形成されることの他、例えば図25〜26に示すように傾斜 面42と垂直面43とからなる屈曲面として形成し、該傾斜面42に排水用盲孔 22を設ける構成とすることもある。[0043] (6) The water receiving surface 12 of the block body facing the end surface of the drainage pavement is shown in Figs. In addition to being formed on a vertical surface as shown, for example, as shown in FIGS. It is formed as a curved surface consisting of a surface 42 and a vertical surface 43, and the inclined surface 42 has a blind hole for drainage. 22 may be provided.

【0044】[0044]

【考案の効果】[Effect of device]

本考案は以下の如き優れた効果を奏する。 (1) 本考案は、排水性舗装部の浸透水を排水させる排水孔を形成可能とする排水 用盲孔を、ブロック本体の、前記排水性舗装部の縁部分の端面に臨む上角部分に おいて設けているため、従来の水路ブロックと同様に敷設して水路を形成できな がら、排水性舗装部を構築する必要が将来的に生じたときは、前記排水用盲孔の 底部分を破って或いは蓋体を取り外して排水孔を形成することにより、排水性舗 装構造を直ちに施工できることになる。 そしてこの排水孔の形成は、排水用盲孔がブロック本体の配筋を避けて設けら れているため、従来のように鉄筋が障害となることなく、又、ブロック本体の割 れ等の損傷を防止してブロック本体の強度低下を回避しながら、前記排水孔を容 易且つ確実に形成できる。 従って従来のように、水路ブロックの取り替えを行ったり排水用ブロックを乗 載して排水性舗装構造を施工する場合に比し、施工手間を大幅に削減でき又施工 コストの大幅な低減を期し得ることとなる。   The present invention has the following excellent effects. (1) The present invention is a drainage capable of forming a drainage hole for draining permeated water of a drainage pavement. For the blind hole in the upper corner of the block body facing the end face of the edge of the drainage pavement Since it is provided in advance, it cannot be laid like a conventional waterway block to form a waterway. However, if it becomes necessary in the future to construct a drainage pavement, the drainage blind hole Drainable pavement by breaking the bottom or removing the lid to form drainage holes. The mounting structure can be immediately constructed.   This drainage hole should be formed with the drainage blind hole avoiding the reinforcement of the block body. Therefore, the reinforcing bar does not become an obstacle as in the past, and the block body is not broken. While preventing such damage and avoiding a decrease in the strength of the block body, It can be easily and reliably formed.   Therefore, as in the past, the waterway block must be replaced or the drainage block must be installed. Compared with the case where the drainage pavement structure is installed, the construction work can be significantly reduced and the construction can be performed. The cost can be significantly reduced.

【0045】 (2) 特にブロック本体を門形に構成する場合、両側壁を連結する連結梁部分で排 水用盲孔を設ける構成を採用することにより、厚肉部分で排水用盲孔を形成でき ることとなり、従って、ブロック強度を低下させることなく排水用盲孔をより確 実に形成できる利点がある。[0045] (2) Especially when the block body is constructed in the shape of a gate, the connecting beam part that connects both side walls By adopting a structure that provides a blind hole for water, it is possible to form a blind hole for drainage in thick parts. Therefore, the drainage blind hole can be made more reliable without reducing the block strength. There is an advantage that it can be formed.

【0046】 (3) ブロック本体の、前記排水性舗装部の縁部分の端面に臨む上角部分の外側面 に、その長さ方向に連続し且つブロック本体の両端部で開放する如く集水溝を設 け、該集水溝の長さ方向の所要部分に連通する状態で排水孔を形成するときは、 ブロック相互を連設状態に敷設したときに、隣り合う水路ブロックの集水溝を連 通状態にでき、従って、集水された水を集水溝の長さ方向に移動させることがで き、集水された浸透水を水路内に効率よく排水できることとなる。そして該集水 溝の溝幅を、舗装用の骨材が入り込んで集水溝を遮断しない程度に設定すること により、良好な排水を永続的に確保できることとなる。[0046] (3) Outer surface of the upper corner of the block body facing the end surface of the edge of the drainage pavement , And a water collecting groove is provided so that it is continuous in the lengthwise direction and opens at both ends of the block body. When forming a drain hole in a state of communicating with a required portion in the length direction of the water collecting groove, When laying blocks in a row, the water collecting grooves of adjacent waterway blocks are It is possible to keep the water flowing through, so it is possible to move the collected water along the length of the water collecting groove. Therefore, the collected permeated water can be efficiently drained into the waterway. And the water collection Set the groove width so that the pavement aggregate does not block the water collection groove. As a result, good drainage can be secured permanently.

【0047】 (4) ブロック本体に排水用盲孔を設け、その底部分を破ることによって排水孔を 形成可能に構成することにより、前記のように、将来的に排水孔を形成できる他 、その底部分を破った状態でブロックを出荷することにより、施工現場において はこれをそのまま排水性舗装に用いることができる。 かかることから、排水性盲孔を具える一種類の水路ブロックを製造しさえすれ ば、排水用盲孔の底部分をどの時点で破るかによって用途の選択を行うことがで きる。その結果、排水用盲孔を具える水路ブロックと、貫通した排水孔を具える ブロックの2種類を製造する場合に比べて製造管理や在庫管理等が容易となる経 済性が得られる。[0047] (4) A blind hole for drainage is provided in the block body, and the bottom hole is broken to open the drainage hole. As described above, the drainage holes can be formed in the future by configuring the structure so that the drainage holes can be formed. At the construction site, by shipping the block with the bottom part broken. Can be used as is for drainage pavements.   As such, it is even easier to manufacture one type of waterway block with drainage blind holes. For example, the application can be selected depending on when the bottom part of the drainage blind hole is broken. Wear. As a result, it has a drainage block with drainage blind holes and through drainage holes. Compared to the case of manufacturing two types of blocks, manufacturing management and inventory management become easier. You get the money.

【0048】 (5) 底部分を破ることによって排水孔を形成する排水用盲孔を具えた水路ブロッ クにあっては、その製造と同時に所要の水路ブロックを完成でき、ブロック本体 に設けた貫通孔を、取り外し可能の蓋体で閉蓋する水路ブロックにおけるような 、閉蓋等の後処理を必要としない利点がある。[0048] (5) A waterway block equipped with a drainage blind hole that forms a drainage hole by breaking the bottom part. In the case of Ku, the required waterway block can be completed at the same time as its manufacture. Like a waterway block that closes the through hole provided in the with a removable lid. There is an advantage that no post-treatment such as a lid is required.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案に係る水路ブロックを示す斜視図であ
る。
FIG. 1 is a perspective view showing a water channel block according to the present invention.

【図2】その部分斜視図である。FIG. 2 is a partial perspective view thereof.

【図3】その排水用盲孔を示す断面図である。FIG. 3 is a sectional view showing the drainage blind hole.

【図4】本考案に係る水路ブロックを用いた通常の施工
状態を示す断面図である。
FIG. 4 is a cross-sectional view showing a normal construction state using the water channel block according to the present invention.

【図5】排水用盲孔の上端を蓋で閉蓋した状態を示す斜
視図である。
FIG. 5 is a perspective view showing a state in which the upper end of the drainage blind hole is closed with a lid.

【図6】本考案に係る水路ブロックを用いて構築した舗
装構造を示す断面図である。
FIG. 6 is a cross-sectional view showing a pavement structure constructed by using a waterway block according to the present invention.

【図7】その部分拡大断面図である。FIG. 7 is a partially enlarged cross-sectional view thereof.

【図8】排水孔の上端をフイルタ部材で覆った状態を示
す斜視図である。
FIG. 8 is a perspective view showing a state in which the upper end of the drainage hole is covered with a filter member.

【図9】本考案に係る水路ブロック相互の接続部分を示
す部分側面図である。
FIG. 9 is a partial side view showing a connecting portion between the waterway blocks according to the present invention.

【図10】本考案に係る水路ブロックの他の態様を示す
斜視図である。
FIG. 10 is a perspective view showing another embodiment of the water channel block according to the present invention.

【図11】その部分拡大斜視図である。FIG. 11 is a partially enlarged perspective view of the same.

【図12】その排水用盲孔を示す断面図である。FIG. 12 is a cross-sectional view showing the drainage blind hole.

【図13】図10に示す水路ブロックを用いて構築した
舗装構造を示す断面図である。
13 is a cross-sectional view showing a pavement structure constructed by using the water channel block shown in FIG.

【図14】図10に示す排水用盲孔の上端を蓋体で閉蓋
した状態を示す斜視図である。
14 is a perspective view showing a state in which the upper end of the drainage blind hole shown in FIG. 10 is closed by a lid.

【図15】図10に示す水路ブロックを用いて構築した
排水性舗装構造を示す断面図である。
15 is a cross-sectional view showing a drainage pavement structure constructed using the water channel block shown in FIG.

【図16】その部分拡大断面図である。FIG. 16 is a partially enlarged cross-sectional view thereof.

【図17】排水孔の上端をフイルタ部材で覆った状態を
示す斜視図である。
FIG. 17 is a perspective view showing a state in which the upper end of the drainage hole is covered with a filter member.

【図18】図10に係る水路ブロック相互の連結部分を
示す部分側面図である。
FIG. 18 is a partial side view showing a connecting portion between the waterway blocks according to FIG. 10.

【図19】本考案に係る水路ブロックのその他の態様を
示す部分断面図である。
FIG. 19 is a partial cross-sectional view showing another aspect of the water channel block according to the present invention.

【図20】本考案に係る水路ブロックのその他の態様を
示す部分断面図である。
FIG. 20 is a partial cross-sectional view showing another embodiment of the water channel block according to the present invention.

【図21】本考案に係る水路ブロックのその他の態様を
示す部分断面図である。
FIG. 21 is a partial cross-sectional view showing another aspect of the water channel block according to the present invention.

【図22】本考案に係る水路ブロックのその他の態様を
示す部分断面図である。
FIG. 22 is a partial cross-sectional view showing another aspect of the water channel block according to the present invention.

【図23】本考案に係る水路ブロックのその他の態様を
示す部分断面図である。
FIG. 23 is a partial cross-sectional view showing another aspect of the water channel block according to the present invention.

【図24】本考案に係る水路ブロックのその他の態様を
示す部分断面図である。
FIG. 24 is a partial cross-sectional view showing another embodiment of the water channel block according to the present invention.

【図25】本考案に係る水路ブロックのその他の態様を
示す部分断面図である。
FIG. 25 is a partial cross-sectional view showing another embodiment of the water channel block according to the present invention.

【図26】本考案に係る水路ブロックのその他の態様を
示す部分断面図である。
FIG. 26 is a partial cross-sectional view showing another aspect of the water channel block according to the present invention.

【図27】水路ブロックを用いる従来の舗装構造を示す
斜視図である。
FIG. 27 is a perspective view showing a conventional pavement structure using a waterway block.

【図28】図27で用いられている水路ブロックを用い
て構成した排水性舗装構造を示す断面図である。
FIG. 28 is a cross-sectional view showing a drainage pavement structure configured by using the water channel block used in FIG. 27.

【図29】図27で用いられている水路ブロックを用い
て構成した排水性舗装構造の問題点を説明する断面図で
ある。
FIG. 29 is a cross-sectional view illustrating a problem of the drainage pavement structure configured by using the waterway block used in FIG. 27.

【符号の説明】[Explanation of symbols]

1 水路ブロック 2 排水性舗装部 3 排水性舗装構造 5 側壁 6 連結梁 7 ブロック本体 9 水路 13 集水溝 21 排水孔 22 排水用盲孔 1 waterway block 2 Drainage pavement 3 Drainage pavement structure 5 side walls 6 connecting beams 7 block body 9 waterways 13 water collection ditch 21 drainage hole 22 Blind hole for drainage

Claims (8)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 排水性舗装部の縁部分に沿って敷設され
該排水性舗装部の浸透水を排水させるために用いる水路
ブロックであって、長さ方向に水路が設けられてなるブ
ロック本体の、前記排水性舗装部の縁部分の端面に臨む
上角部分において、前記水路に連通して前記浸透水を排
出させる排水孔を形成するための有底の排水用盲孔を、
ブロック本体の前記上角部分の外側面側及び/又は前記
上角部分の内側面側から、ブロック本体の配筋を避けて
凹設すると共に、該排水用盲孔の、鉄筋の存在しない底
部分を破ることによって前記排水孔を形成可能としたこ
とを特徴とする排水性舗装用の水路ブロック。
1. A water channel block which is laid along an edge portion of a drainage pavement and is used for draining permeated water of the water drainage pavement, the block main body having a water channel provided in a longitudinal direction. , A bottomed drainage blind hole for forming a drainage hole communicating with the water channel and discharging the permeated water in an upper corner portion facing the end surface of the edge portion of the drainage pavement,
The bottom portion of the blind hole for drainage, which is recessed from the outer surface side of the upper corner portion of the block body and / or the inner side surface of the upper corner portion, avoids the bar arrangement of the block body, and has no reinforcing bars. A drainage canal block for drainage pavement, characterized in that the drainage hole can be formed by breaking.
【請求項2】 排水性舗装部の縁部分に沿って敷設され
該排水性舗装部の浸透水を排水させるために用いる水路
ブロックであって、長さ方向に水路が設けられてなるブ
ロック本体の、前記排水性舗装部の縁部分の端面に臨む
上角部分に、前記水路ブロックの水路に連通する貫通孔
を設け、該貫通孔の前記排水性舗装部の縁部分側の開口
端部を、取り外し可能の蓋体で閉蓋することによって有
底の排水用盲孔を形成してなり、該蓋体を取り外すこと
によって、前記水路に連通して前記浸透水を排出させる
排水孔を形成可能としたことを特徴とする排水性舗装用
の水路ブロック。
2. A waterway block which is laid along an edge portion of a drainage pavement and is used for draining permeated water of the drainage pavement, the block main body having a waterway provided in a longitudinal direction. The upper corner portion facing the end face of the edge portion of the drainage pavement, a through hole communicating with the water channel of the water channel block is provided, the opening end of the through hole on the edge portion side of the drainage pavement portion, By forming a bottomed drainage blind hole by closing the lid with a removable lid, it is possible to form a drainage hole communicating with the water channel and discharging the permeated water by removing the lid. A waterway block for drainage pavement characterized by the above.
【請求項3】 前記ブロック本体は、対向する側壁の上
部相互を連結梁で連結してなる下端開放の門形をなし、
前記排水用盲孔は、該連結梁が存在する部分で設けられ
ていることを特徴とする請求項1又は2記載の排水性舗
装用の水路ブロック。
3. The block body has a gate shape in which lower ends are opened by connecting upper portions of opposite side walls with a connecting beam.
The water drainage block for drainage pavement according to claim 1 or 2, wherein the drainage blind hole is provided at a portion where the connecting beam is present.
【請求項4】 前記ブロック本体は、両端が開放し周方
向に閉じた前記水路を有することを特徴とする請求項1
又は2記載の排水性舗装用の水路ブロック。
4. The block main body has the water channel which is open at both ends and is closed in the circumferential direction.
Or the waterway block for drainage pavement according to 2.
【請求項5】 前記ブロック本体は、U字溝であること
を特徴とする請求項1又は2記載の排水性舗装用の水路
ブロック。
5. The waterway block for drainage pavement according to claim 1, wherein the block body is a U-shaped groove.
【請求項6】 前記排水用盲孔を、前記ブロック本体の
前記上角部分の外側面で開放させ、且つその底面を、前
記ブロック本体の前記上角部分の内側面に近接させたこ
とを特徴とする請求項1記載の排水性舗装用の水路ブロ
ック。
6. The blind hole for drainage is opened on the outer surface of the upper corner portion of the block body, and the bottom surface thereof is brought close to the inner surface of the upper corner portion of the block body. The waterway block for drainage pavement according to claim 1.
【請求項7】 前記排水用盲孔を、前記ブロック本体の
前記上角部分の内側面で開放させ、且つその底面を、前
記ブロック本体の前記上角部分の外側面に近接させたこ
とを特徴とする請求項1記載の排水性舗装用の水路ブロ
ック。
7. The blind hole for drainage is opened on the inner side surface of the upper corner portion of the block body, and the bottom surface thereof is brought close to the outer side surface of the upper corner portion of the block body. The waterway block for drainage pavement according to claim 1.
【請求項8】 前記ブロック本体の、前記排水性舗装部
の縁部分の端面に臨む上角部分の外側面に、ブロック本
体の長さ方向に連続し且つブロック本体の両端部で開放
する如く集水溝を設け、該集水溝の溝幅は舗装用の骨材
が入り込んで集水溝を遮断しないように設定するものと
し、該集水溝の長さ方向の所要部分に連通する状態で排
水孔を形成可能に、前記排水用盲孔が設けられているこ
とを特徴とする請求項1〜7いずれかに記載の排水性舗
装用の水路ブロック。
8. An outer surface of an upper corner portion of the block main body which faces an end surface of an edge portion of the drainage pavement portion is formed so as to be continuous in the length direction of the block main body and open at both end portions of the block main body. A water groove is provided, and the groove width of the water collection groove is set so as not to block the water collection groove by entering the pavement aggregate, and in a state of communicating with a required portion in the length direction of the water collection groove. The drainage block for drainage pavement according to any one of claims 1 to 7, wherein the drainage blind hole is provided so that a drainage hole can be formed.
JP2002007645U 2002-12-02 2002-12-02 Waterway block for drainage pavement Expired - Lifetime JP3094423U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002007645U JP3094423U (en) 2002-12-02 2002-12-02 Waterway block for drainage pavement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002007645U JP3094423U (en) 2002-12-02 2002-12-02 Waterway block for drainage pavement

Publications (1)

Publication Number Publication Date
JP3094423U true JP3094423U (en) 2003-06-20

Family

ID=43248400

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002007645U Expired - Lifetime JP3094423U (en) 2002-12-02 2002-12-02 Waterway block for drainage pavement

Country Status (1)

Country Link
JP (1) JP3094423U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006052626A (en) * 2004-07-14 2006-02-23 Shigeru Ishikawa Form for structure intending weedproofing, etc. structure making use of the form and block intending weedproofing, etc. having the same effect

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006052626A (en) * 2004-07-14 2006-02-23 Shigeru Ishikawa Form for structure intending weedproofing, etc. structure making use of the form and block intending weedproofing, etc. having the same effect

Similar Documents

Publication Publication Date Title
JP4690067B2 (en) Boundary block set for drainage pavement, drainage structure using the same, and construction method thereof
JP3094423U (en) Waterway block for drainage pavement
JP2005023776A (en) Side ditch structure for water permeability paved road, side ditch lid for water permeability paved road, its side ditch work execution method, and water permeability paved road
JP3119258U (en) Side plate cover plate block
JP2007162350A (en) Drainage lead-in implement and side-ditch block
JP4445850B2 (en) Construction method of curb block for drainage pavement
JP5713566B2 (en) Remodeling method of gutter and adjacent road
JP2003253611A (en) Boundary block
JP4504220B2 (en) Drainage channel
JP2000129634A (en) Channel block for drainable pavement
JP3986665B2 (en) Side groove block
JP2000179034A (en) Side ditch, cover member for side ditch, and boundary block
JP2003184165A (en) Water channel block for drainage pavement
JP2000054474A (en) Culvert block for drainable thin layer pavement
JP3861205B2 (en) Pedestrian boundary waterway building block
JP4237071B2 (en) Drainage device and drainage method for road structures
JPH09158304A (en) Culvert for surface drainage and method for constructing the same
JP7499163B2 (en) Water storage type drain and water storage type drain equipment using the same
JP2003268861A (en) Side ditch
JP2005097999A (en) Protrusion sidewalk structure and foundation part block used for the same
JP3605537B2 (en) Drainage structure on drainage pavement
JP3154698U (en) Drainage equipment structure
JP2006233429A (en) Drainage block
JP3334947B2 (en) Structure of permeable pavement culvert and culvert block
JP4052934B2 (en) Drainage basin and drainage structure of paved road using this

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term