JP2018058673A - Elevator renewal operation method - Google Patents

Elevator renewal operation method Download PDF

Info

Publication number
JP2018058673A
JP2018058673A JP2016197819A JP2016197819A JP2018058673A JP 2018058673 A JP2018058673 A JP 2018058673A JP 2016197819 A JP2016197819 A JP 2016197819A JP 2016197819 A JP2016197819 A JP 2016197819A JP 2018058673 A JP2018058673 A JP 2018058673A
Authority
JP
Japan
Prior art keywords
new
car
existing
hoistway
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016197819A
Other languages
Japanese (ja)
Other versions
JP6626809B2 (en
Inventor
安井 啓二
Keiji Yasui
啓二 安井
海山 福永
Kaizan Fukunaga
海山 福永
健治 安藤
Kenji Ando
健治 安藤
国藤 和夫
Kazuo Kunito
和夫 国藤
宏修 山中
Hironao Yamanaka
宏修 山中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP2016197819A priority Critical patent/JP6626809B2/en
Publication of JP2018058673A publication Critical patent/JP2018058673A/en
Application granted granted Critical
Publication of JP6626809B2 publication Critical patent/JP6626809B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide an elevator renewal operation method that enables shortening of a construction period by efficiently removing a plunger of an existing hydraulic elevator.SOLUTION: A plunger, a cylinder, and a plunger rail are removed by using a lifting device installed by using an existing car and a liftable foothold using a new car floor to be installed. Thus, a construction period can be shortened by making liftable the new car floor to be installed early and efficiently removing the plunger or the like.SELECTED DRAWING: Figure 8

Description

本発明は、エレベータのリニューアル作業方法に関し、特に、老朽化した既設の油圧エレベータを新しい(以下「新設の」ともいう)ロープ式エレベータにリニューアルするエレベータのリニューアル作業方法に適用して好適なものである。   The present invention relates to an elevator renewal work method, and is particularly suitable for application to an elevator renewal work method for renewing an old, existing hydraulic elevator to a new (hereinafter also referred to as “new”) rope type elevator. is there.

従来、経年によりエレベータ設備をリニューアルする場合には、一般に既設の油圧エレベータを撤去してから新設のロープ式エレベータを据え付ける工法が採用されている。ところが、こうした工法では、リニューアル作業を行っている期間に亘って既設のエレベータが使用できなくなるため、利用者側からはリニューアル作業時におけるエレベータの不稼動時間を短縮することが要求されている。   Conventionally, when an elevator facility is renewed over time, a method of installing a new rope type elevator after removing an existing hydraulic elevator is generally employed. However, in such a construction method, the existing elevator cannot be used over the period during which the renewal work is performed. Therefore, the user is required to reduce the elevator downtime during the renewal work.

既設の油圧エレベータを新設のロープ式エレベータにリニューアルする場合、一般的には、既設の油圧エレベータ用の設備であるプランジャー、プランジャーレール、配管及び油圧ユニット等の機器を全て撤去した後、ロープ式エレベータ用の設備である釣り合い重り、釣り合い重り用ガイドレール及び巻上機等を新たに設置する。即ち、既設の油圧エレベータで使用していた機器を全て撤去してから新設のロープ式エレベータで使用する機器を新たに設置する工法が採用されている。   When renewing an existing hydraulic elevator to a new rope-type elevator, in general, after removing all equipment such as plungers, plunger rails, pipes and hydraulic units that are equipment for existing hydraulic elevators, the rope Newly installed counterweight equipment, counterweights, counterweight guide rails and hoisting machines. That is, a construction method is adopted in which all the equipment used in the existing hydraulic elevator is removed and then the equipment used in the new rope type elevator is newly installed.

しかしながら、このような一般的な工法では工期が長くなるため、これを短縮するために、既設の油圧エレベータの乗かごを用いて既設の油圧エレベータの乗かご用ガイドレール及びプランジャーレールを撤去する方法が提案されていた(特許文献1参照)。   However, since the construction period becomes longer in such a general construction method, in order to shorten this, the existing hydraulic elevator car guide rail and plunger rail are removed using the existing hydraulic elevator car. A method has been proposed (see Patent Document 1).

特開2013−241239号公報JP 2013-241239 A

しかしながら、上述した従来技術では、既設の油圧エレベータにおいて最も大型の機材であるプランジャーの撤去方法について考慮されていなかったため、その工期を十分に短縮することができなかった。   However, in the above-described conventional technology, since the method for removing the plunger, which is the largest equipment in the existing hydraulic elevator, has not been considered, the construction period cannot be sufficiently shortened.

本発明は以上の点を考慮してなされたもので、既設の油圧エレベータのプランジャーを効率良く撤去することにより工期を短縮することができるエレベータのリニューアル作業方法を提案しようとするものである。   The present invention has been made in view of the above points, and an object of the present invention is to propose an elevator renewal work method capable of shortening the construction period by efficiently removing the plunger of an existing hydraulic elevator.

かかる課題を解決するため、本発明においては、昇降路内において既存のプランジャーを用いて既設の乗りかごを既設のガイドレールに沿って昇降させる既設の油圧エレベータを撤去し、前記昇降路内において巻上機によるロープの巻き上げ下げに応じて前記ロープの一端に固定された新設の乗りかごを新設のガイドレールに沿って昇降させるロープ式エレベータへリニューアルするエレベータのリニューアル作業方法において、前記昇降路内における最上部に位置させた前記既設の乗かごを足場として前記昇降路内の頂部に仮設の昇降装置を取り付け、前記既設の乗かごを前記最上部から下降させながら前記既設の乗かごを足場として前記既設のガイドレールを撤去し、その後、前記既設の乗かごを撤去するとともに、前記昇降路の底部において前記新設のガイドレールの一部を前記昇降路内に設置し、前記新設の乗りかご、又は前記新設の乗りかごの一部を構成する新設のかご床を、前記新設のガイドレールの一部に装着するとともに、前記仮設の昇降装置から前記底部に延びるロープの一端に固定した状態で、前記仮設の昇降装置による前記ロープの巻き上げに応じて前記新設の乗りかご又は前記新設のかご床を上昇させながら前記新設のガイドレールの一部の続きである前記新設のガイドレールの残りを前記昇降路内に設置し、前記昇降路の上部に設けられた揚重機によって前記既存のプランジャーを吊り下げ、前記仮設の昇降装置により前記新設の乗りかご又は前記新設のかご床を昇降させながら前記既存のプランジャーを撤去し、前記巻上機を含む必要な新設の設備を設置し、その後前記新設の乗りかごを足場として前記仮設の昇降装置を撤去して前記ロープ式エレベータを構成することを特徴とする。   In order to solve such a problem, in the present invention, an existing hydraulic elevator that lifts and lowers an existing car along an existing guide rail using an existing plunger in the hoistway is removed, In an elevator renewal work method in which a new elevator car fixed to one end of the rope is lifted and lowered along a new guide rail in accordance with the hoisting and lowering of the rope by a hoisting machine, A temporary lifting device is attached to the top of the hoistway using the existing car positioned at the top of the hoistway, and the existing car is used as a footing while lowering the existing car from the top. Remove the existing guide rail, then remove the existing car and at the bottom of the hoistway A part of the new guide rail is installed in the hoistway, and the new car or a new car floor constituting a part of the new car is a part of the new guide rail. And the new elevator car or the new car floor is raised in response to the hoisting of the rope by the temporary lifting device while being fixed to one end of a rope extending from the temporary lifting device to the bottom. The rest of the new guide rail, which is a continuation of a part of the new guide rail, is installed in the hoistway, and the existing plunger is suspended by a hoist provided at the upper part of the hoistway. The existing plunger is removed while raising and lowering the new car or the new car floor by the temporary lifting device, and necessary new equipment including the hoisting machine is removed. Location, and characterized by constituting the roped elevator by removing the lifting device of the temporary the car thereafter the newly as a scaffold.

本発明によれば、既設の油圧エレベータのプランジャーを効率良く撤去することにより工期を短縮することができる。   According to the present invention, the construction period can be shortened by efficiently removing the plunger of the existing hydraulic elevator.

本実施の形態によるエレベータリニューアル作業方法が適用される油圧エレベータの概略構成を示す断面図である。It is sectional drawing which shows schematic structure of the hydraulic elevator to which the elevator renewal work method by this Embodiment is applied. 本実施の形態によるエレベータのリニューアル作業方法の一例を示すフローチャートである。It is a flowchart which shows an example of the renewal work method of the elevator by this Embodiment. 既設の乗りかごを足場として昇降装置を取り付ける手順を示す断面図である。It is sectional drawing which shows the procedure which attaches a raising / lowering apparatus using an existing cage as a scaffold. 既設の乗りかごを足場としてメインレールを取り外す手順を示す断面図である。It is sectional drawing which shows the procedure which removes a main rail using an existing car as a scaffold. 既設の乗りかごを解体する手順を示す断面図である。It is sectional drawing which shows the procedure of demolishing the existing passenger car. 昇降路の底部において最下部足場を組立て最下部の新設のメインレールを据付ける手順を示す断面図である。It is sectional drawing which shows the procedure in which the lowest footing is assembled in the bottom part of a hoistway, and the newly installed main rail of the lowermost part is installed. 新設のかご床を活用し、事前に取付けた昇降装置にて昇降する作業床を設置する手順を示す断面図である。It is sectional drawing which shows the procedure which installs the working floor which raises / lowers by the raising / lowering apparatus attached beforehand using the newly installed car floor. 作業床を使用してプランジャーを解体する手順を示す断面図である。It is sectional drawing which shows the procedure which disassembles a plunger using a working floor. 解体したプランジャーを切断し搬出する手順を示す断面図である。It is sectional drawing which shows the procedure which cut | disconnects the disassembled plunger and carries out. プランジャーを切断し搬出する手順を示す断面図である。It is sectional drawing which shows the procedure which cut | disconnects a plunger and carries out. 作業床を使用してシリンダーを解体する手順を示す断面図である。It is sectional drawing which shows the procedure which disassembles a cylinder using a working floor. 作業床を使用してプランジャーレールを解体する手順を示す断面図である。It is sectional drawing which shows the procedure which disassembles a plunger rail using a working floor. 新設のロープ式エレベータが設置されエレベータのリニューアル工事が完了際における断面図である。It is sectional drawing in the time of completion of the renewal construction of a new rope type elevator installed.

以下、図面について、本発明の一実施の形態について詳述する。
(1)本実施の形態によるエレベータのリニューアル作業方法
図1は、本実施の形態によるエレベータのリニューアル作業方法が実施されるエレベータの構成例を示す断面図である。本実施の形態では、エレベータ設備として、間接式の油圧エレベータを例示する。この油圧エレベータは、昇降路1内に設置されており、鉛直方向に伸縮するプランジャー4と、このプランジャー4の鉛直方向における伸縮動作を案内するプランジャーレール6とを備えている。
Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings.
(1) Elevator Renewal Work Method According to the Present Embodiment FIG. 1 is a cross-sectional view showing a configuration example of an elevator in which the elevator renewal work method according to the present embodiment is implemented. In the present embodiment, an indirect hydraulic elevator is exemplified as the elevator equipment. The hydraulic elevator is installed in the hoistway 1 and includes a plunger 4 that expands and contracts in the vertical direction and a plunger rail 6 that guides the expansion and contraction operation of the plunger 4 in the vertical direction.

この油圧エレベータでは、プランジャー4の頂部には図示しない回転シーブが設けられている。この回転シーブには主索4aが巻き掛けられている。主索4aの一方の端部は乗りかご2に固定されているとともに、主索4aの他方の端部は昇降路1の底部にあるプランジャー4の下部のスタンドに固定されている。   In this hydraulic elevator, a rotary sheave (not shown) is provided on the top of the plunger 4. A main rope 4a is wound around the rotating sheave. One end of the main rope 4a is fixed to the car 2, and the other end of the main rope 4a is fixed to a stand below the plunger 4 at the bottom of the hoistway 1.

プランジャー4が上下に伸縮すると、それに連動して乗りかご2が昇降路1内をメインレール3に沿って昇降する仕組みとなっている。なお、以下の説明においては、設置済みの乗りかごを「既設の乗りかご」と呼ぶ。なお、本実施の形態では、既設の設備と区別し易いように新規に設ける設備を「新設の」とも表現する。   When the plunger 4 expands and contracts up and down, the car 2 moves up and down along the main rail 3 in the hoistway 1 in conjunction with it. In the following description, the installed car is referred to as an “existing car”. In the present embodiment, a newly installed facility is also expressed as “newly installed” so that it can be easily distinguished from an existing facility.

図2は、本実施の形態によるエレベータのリニューアル作業方法における各作業手順の一例を示すフローチャートである。このリニューアル作業方法は、例えば機械室が設けられていないエレベータに関するものである。なお、以下の説明においては従前から実施されている作業手順については簡素化して説明する一方、本実施の形態において特徴的な作業については詳細に説明する。   FIG. 2 is a flowchart showing an example of each work procedure in the elevator renewal work method according to the present embodiment. This renewal work method relates to an elevator in which no machine room is provided, for example. In the following description, the work procedure that has been performed in the past will be described in a simplified manner, while the characteristic work in the present embodiment will be described in detail.

本実施の形態によるエレベータのリニューアル作業方法では、昇降路1内において既存のプランジャー4を用いて既設の乗りかご2を既設のメインレール3に沿って昇降させる既設の油圧エレベータを撤去し、昇降路1内において巻上機によるロープの巻き上げ下げに応じてこのロープの一端に固定された新設の乗りかごを新設のガイドレールに沿って昇降させるロープ式エレベータにリニューアルしようとする場合を示している。   In the elevator renewal work method according to the present embodiment, the existing hydraulic elevator that lifts and lowers the existing car 2 along the existing main rail 3 using the existing plunger 4 in the hoistway 1 is removed and lifted. It shows a case where a new elevator car fixed to one end of this rope is to be renewed to a rope type elevator that moves up and down along a new guide rail in accordance with the hoisting and lowering of the rope in the road 1 .

まず、着工・安全対策がなされ(ステップS1)、製品が搬入される(ステップS2)。図1に示すように乗場ドア8の昇降路1の反対側に仮囲い9が設置される(ステップS3)。このような仮囲い9により、リニューアル作業中に昇降路1内から粉塵等が建屋内に流入することを防止することができる。その後、既設の出入り口が撤去され(ステップS4)、最上部に位置する既設のメインレール3が切断される(ステップS5)。   First, construction / safety measures are taken (step S1), and the product is carried in (step S2). As shown in FIG. 1, the temporary enclosure 9 is installed on the opposite side of the hoistway 1 of the landing door 8 (step S3). Such a temporary enclosure 9 can prevent dust and the like from flowing into the building from the hoistway 1 during the renewal work. Thereafter, the existing doorway is removed (step S4), and the existing main rail 3 located at the top is cut (step S5).

次に、図3に示すように昇降路1内のほぼ最上部に位置させた既設の乗りかご2を足場として、昇降路1内の頂部に吊りビーム10が取り付けられるとともにこの吊りビーム10に昇降装置11が昇降装置取付金具12を介して取り付けられる(ステップS6,S7)。   Next, as shown in FIG. 3, a suspension beam 10 is attached to the top of the hoistway 1 with the existing car 2 positioned substantially at the top of the hoistway 1 as a scaffold, and the lifting beam 10 is raised and lowered. The device 11 is attached via the lifting device mounting bracket 12 (steps S6 and S7).

昇降装置11を取り付けた後、この昇降装置11の駆動を制御する制御盤11bが昇降路1の底部に設置され、既設の乗りかご2を足場として、昇降装置11と制御盤11bを接続する制御ケーブル11cが設置される(ステップS7)。続いて、昇降装置ロープ11aが昇降装置11に取付けられる。   After the lifting device 11 is attached, a control panel 11b for controlling the driving of the lifting device 11 is installed at the bottom of the hoistway 1, and a control for connecting the lifting device 11 and the control panel 11b using the existing car 2 as a scaffold. The cable 11c is installed (step S7). Subsequently, the lifting device rope 11 a is attached to the lifting device 11.

続いて、メインレール3についてテンプレートが設置される(ステップS8)。既設の乗りかご2を足場として、新設のレールブラケットが取り付けられる(ステップS9)。仮設のガバナプーリー及び仮設のガバナロープが取り付けられる(ステップS10)。   Subsequently, a template is installed for the main rail 3 (step S8). A new rail bracket is attached using the existing car 2 as a scaffold (step S9). A temporary governor pulley and a temporary governor rope are attached (step S10).

次に、既設の乗りかご2を足場として、例えば、図示しない非常用下降弁を操作することにより既設の乗りかご2を昇降路1の最上部に位置させる(ステップS11)。その後建屋の電源が切り離される(ステップS12)。下部テンプが解体される(ステップS13)。   Next, using the existing car 2 as a scaffold, the existing car 2 is positioned at the top of the hoistway 1 by operating an emergency descent valve (not shown), for example (step S11). Thereafter, the power supply of the building is disconnected (step S12). The lower balance is disassembled (step S13).

次に、非常用下降弁を操作して、図3及び図4に示すように最上部から既設の乗りかご2を下降させながら、既設の乗りかご2用のメインレール3、メインレールブラケット3a及び配線が併せて徐々に撤去される(ステップS14)。   Next, the emergency lowering valve is operated to lower the existing car 2 from the top as shown in FIGS. 3 and 4, while the main rail 3 for the existing car 2, the main rail bracket 3a, The wiring is gradually removed together (step S14).

次に、既設の乗りかご2が昇降路1の最下部まで下降されると、図5に示すように既設の乗りかご2が撤去されるとともに配線が撤去される(ステップS15)。さらに昇降路1内におけるメインレール3の最下部が撤去される(ステップS16)。その後、既設のピットベースが撤去され(ステップS17)、下部テンプが張り直しされ(ステップS18)、新設ピットベースの芯出しが行われる(ステップS19)。   Next, when the existing car 2 is lowered to the lowermost part of the hoistway 1, the existing car 2 is removed and the wiring is removed as shown in FIG. 5 (step S15). Further, the lowermost part of the main rail 3 in the hoistway 1 is removed (step S16). Thereafter, the existing pit base is removed (step S17), the lower balance is re-stretched (step S18), and the new pit base is centered (step S19).

次に、図6に示すように、昇降路1の最下部に、新設のメインレール14を昇降路1の壁面に固定するための新設のメインレールブラケット14aのうち最下部を取り付けるために最下部足場13が組み立てられる(ステップS20)。その後、最下部足場13を利用して、後述する新設の乗りかご17を案内するために取り付けられる新設のメインレール14と、新設のメインレールブラケット14aと、が昇降路1の底部から頂部に向けて昇降路1の内壁に取り付けられる(ステップS21)。   Next, as shown in FIG. 6, the lowermost part of the newly installed main rail bracket 14 a for fixing the newly installed main rail 14 to the wall surface of the hoistway 1 is attached to the lowermost part of the hoistway 1. The scaffold 13 is assembled (step S20). Thereafter, a new main rail 14 and a new main rail bracket 14a which are attached to guide a new car 17 described later using the lowermost scaffold 13 are directed from the bottom of the hoistway 1 to the top. Is attached to the inner wall of the hoistway 1 (step S21).

次に、既述のように組み立てられた最下部足場13が、図7に示すように解体されて昇降路1から搬出される(ステップS22)。その後、スリングが分割される(ステップS23)。新設のかご床15が、昇降路1内に搬入されるとともにこの昇降路1に設置した新設のメインレール14に組み込まれ、昇降装置ロープ11aが取り付けられる(ステップS24)。新設のかご床15は、後述する新設のロープ式エレベータにおける新設の乗りかご17のかご床を構成することになる。新設のかご床15には、安全確保のため、作業用手すり15a及び作業用中さん15bが取り付けられる。なお、以下の説明においては一例として、作業用手すり15a及び作業用中さん15bが取り付けられた新設のかご床15を以降において足場として利用するが、新設のかご床15にさらに必要な部品を取り付けて新設の乗りかご17自体を足場として利用するようにしても良い。   Next, the lowermost scaffold 13 assembled as described above is disassembled and carried out of the hoistway 1 as shown in FIG. 7 (step S22). Thereafter, the sling is divided (step S23). The new car floor 15 is carried into the hoistway 1 and is incorporated into the new main rail 14 installed in the hoistway 1, and the elevating device rope 11 a is attached (step S 24). The new car floor 15 constitutes a car floor of a new car 17 in a new rope type elevator described later. A work handrail 15a and a work middle 15b are attached to the new car floor 15 to ensure safety. In the following description, as an example, the new car floor 15 to which the handrail 15a for work and the middle door 15b for work are attached will be used as a scaffold in the following, but further necessary parts are attached to the new car floor 15. The new car 17 itself may be used as a scaffold.

続いて、新設のかご床15に取付けられた作業用手すり15aに昇降装置11の操作盤11dが取り付けられる。操作盤11dと制御盤11bとが操作ケーブル11eを用いて接続される。操作盤11dの操作に応じて操作ケーブル11eを介して制御盤11bを制御することが可能となり、この制御盤11bが昇降装置11の駆動を制御することができるようになる。これにより、作業用の足場としての新設のかご床15が昇降装置11によって昇降可能となる。その後、試運転が行われ、組み立てチェックがなされ、社内検査が終了する(ステップS25)。   Subsequently, the operation panel 11 d of the elevating device 11 is attached to the work handrail 15 a attached to the new car floor 15. The operation panel 11d and the control panel 11b are connected using an operation cable 11e. The control panel 11b can be controlled via the operation cable 11e in accordance with the operation of the operation panel 11d, and the control panel 11b can control the driving of the lifting device 11. As a result, the new car floor 15 as a working scaffold can be raised and lowered by the lifting device 11. Thereafter, a trial run is performed, an assembly check is performed, and the in-house inspection is completed (step S25).

次に、図7に示すように、昇降装置11を用いて新設のかご床15を上昇させながら、新設のメインレール14を順次上方に向けて取り付けていく(ステップS26)。図示しない新設のガバナプーリー及び新設のガバナロープが取り付けられる(ステップS27)。ガバナを盛り替え、仮設のガバナが撤去される(ステップS28)。   Next, as shown in FIG. 7, the new main rail 14 is sequentially attached upward while raising the new car floor 15 using the lifting device 11 (step S <b> 26). A new governor pulley (not shown) and a new governor rope are attached (step S27). The governor is replaced, and the temporary governor is removed (step S28).

次に、図8に示すように新設のかご床15を所定の位置に停止させる。既設の油圧エレベータのプランジャー4は、昇降路1の頂部に設置する揚重機16を用いて一旦吊り上げられる。その際、プランジャー4は、そのように吊られながら、昇降装置11により昇降可能な新設のかご床15を足場として、図9に示すように破線で図示した各切断部100において下端から徐々に切断される。   Next, as shown in FIG. 8, the new car floor 15 is stopped at a predetermined position. The plunger 4 of the existing hydraulic elevator is once lifted by using a lifting machine 16 installed at the top of the hoistway 1. At this time, the plunger 4 is gradually suspended from the lower end in each cutting portion 100 shown by a broken line as shown in FIG. 9 using a new car floor 15 that can be raised and lowered by the lifting device 11 while being suspended as described above. Disconnected.

その後、プランジャー4は、図10に示すように昇降路1の底部でさらに次の切断部100で切断されることにより解体され、昇降路1の最下部に位置する乗場から昇降路1の外部へ搬出され撤去される(ステップS29)。このようにすると、既設の油圧エレベータにおいて大型で重い機材であるプランジャー4を従来よりも容易に撤去することができ、工期の短縮を図ることができる。   Thereafter, as shown in FIG. 10, the plunger 4 is disassembled by being further cut at the bottom of the hoistway 1 by the next cutting part 100, and from the landing located at the lowermost part of the hoistway 1 to the outside of the hoistway 1. And removed (step S29). If it does in this way, the plunger 4 which is large and heavy equipment in the existing hydraulic elevator can be removed more easily than before, and the construction period can be shortened.

続いて、図11に示すようにプランジャー4のシリンダー5もプランジャー4と同様に、揚重機16を用いて吊上げられ、各切断部100で切断、解体され、昇降路1の外部へ搬出される(ステップS30)。   Subsequently, as shown in FIG. 11, the cylinder 5 of the plunger 4 is also lifted by using the lifting machine 16, cut and disassembled by each cutting unit 100, and carried out of the hoistway 1, similarly to the plunger 4. (Step S30).

続いて、上述した新設のかご床15を足場として、図12に示すようにプランジャー4を案内しているプランジャーレール6と、このプランジャーレール6を昇降路1の内壁に固定しているプランジャーレールブラケット6aとが解体される。これらプランジャーレール6及びプランジャーレールブラケット6aは揚重機16を用いて昇降路1内で吊り下げられて下ろされ、昇降路1の外部へ搬出される。その後、仮囲い9が撤去される(ステップS31)。   Subsequently, using the new car floor 15 as a scaffold, the plunger rail 6 guiding the plunger 4 as shown in FIG. 12, and the plunger rail 6 are fixed to the inner wall of the hoistway 1. The plunger rail bracket 6a is disassembled. The plunger rail 6 and the plunger rail bracket 6 a are suspended and lowered in the hoistway 1 using the lifting machine 16, and are carried out of the hoistway 1. Thereafter, the temporary enclosure 9 is removed (step S31).

以上のように既設の油圧エレベータが撤去されると、その後、必要な新設の設備として、例えば、次のような新設のロープ式エレベータが設置され、検査などがなされる(ステップS32〜S50)。なお、本実施の形態によるエレベータのリニューアル作業方法は、主として既設の油圧エレベータの取り外し方に特徴があるため、以下に示すロープ式エレベータの取り付け方法の説明については適宜一部を省略したり図2に示すフローチャートの各手順とは多少の変更が許容される。   When the existing hydraulic elevator is removed as described above, for example, the following new rope type elevator is installed as necessary new equipment, and inspection is performed (steps S32 to S50). Note that the elevator renewal work method according to the present embodiment is mainly characterized by how to remove the existing hydraulic elevator. Therefore, a part of the description of the method of attaching the rope type elevator shown below is omitted as appropriate. A slight change is allowed for each procedure in the flowchart shown in FIG.

新設のロープ式エレベータの設置方法としては、まず、図13に示すようにかご下プーリ17aなどが新設のかご床15に組み付けられて新設の乗りかご17が構成される。このようにすると、上述した撤去作業における作業床として専用の足場を用意して使用後にその足場を撤去する必要がなくなる。次に新設の乗場ドア18が取り付けられる。昇降路1内の下部にはロープを巻き上げ下げ可能な巻上機19が設置される。さらにカウンターウェイト(以下「C.wt」と省略する)レール20がC.wtレールブラケット20aを介して昇降路1の内壁に取り付けられる。その後、C.wt21にC.wtプーリ21aが取り付けられた状態で、C.wtレール20がこれらに組み入れられる。さらに複数の上部プーリ23がそれぞれ新設のかご床15を足場として取り付けられた後、新設の主索22が図示の状態に巻き回されれば、新設のロープ式エレベータへのリニューアル作業が完了する。なお、巻上機19などを含む必要な新設の設備が設置された後に、新設の乗りかご2を足場として仮設の昇降装置11等が撤去される。   As a method of installing a new rope type elevator, first, as shown in FIG. 13, a car lower pulley 17 a and the like are assembled to a new car floor 15 to constitute a new car 17. If it does in this way, it will become unnecessary to prepare a special scaffold as a work floor in the above-mentioned removal work, and to remove the scaffold after use. Next, a new landing door 18 is attached. A hoisting machine 19 capable of hoisting and lowering a rope is installed in the lower part of the hoistway 1. Further, the counterweight (hereinafter abbreviated as “C.wt”) rail 20 is C.I. It is attached to the inner wall of the hoistway 1 via the wt rail bracket 20a. Thereafter, C.I. wt 21 to C.I. With the wt pulley 21a attached, C.I. The wt rail 20 is incorporated in these. Further, after the plurality of upper pulleys 23 are respectively attached to the newly installed car floor 15 as a scaffolding, the renewal operation to the newly installed rope type elevator is completed when the newly installed main rope 22 is wound in the state shown in the drawing. In addition, after the necessary new equipment including the hoisting machine 19 and the like is installed, the temporary lifting device 11 and the like are removed using the new car 2 as a scaffold.

(2)本実施の形態の効果等
以上のように本実施の形態によるエレベータのリニューアル作業方法によれば、まず、最上部に位置させた既設の乗りかご2を利用して下降させながら既設の一部の各設備を撤去するとともに、さらに、新設のかご床15などの一部の新設の設備を利用して既設の他の各設備を撤去するため、効率良く既設の全ての設備を撤去することができ、従来よりも工期を短縮することができる。
(2) Effects of the present embodiment and the like As described above, according to the elevator renewal work method according to the present embodiment, the existing car 2 positioned at the top is first lowered while being lowered. In addition to removing some of the equipment, in addition to removing some of the existing equipment using some of the new equipment such as the new car floor 15, all the existing equipment is removed efficiently. The construction period can be shortened compared to the conventional method.

さらに、例えばプランジャー4を切断する際には、新設のかご床15を足場として作業できるため、プランジャー4の切断撤去作業も効率化し、工期を短縮することができる。昇降路1の底部において、切断して解体したプランジャー4、及び、シリンダー5を昇降路1の外へ搬出する際、新設のかご床15を上昇させれば、搬出作業の障害とならず、その結果、さらに効率的な作業が望め、より工期を短縮することができる。   Further, for example, when the plunger 4 is cut, the new car floor 15 can be used as a scaffold, so that the work of cutting and removing the plunger 4 can be made more efficient and the construction period can be shortened. At the bottom of the hoistway 1, when the plunger 4 and the cylinder 5 that are cut and disassembled are carried out of the hoistway 1, if the new car floor 15 is raised, it will not be an obstacle to carrying out work, As a result, more efficient work can be expected and the construction period can be further shortened.

以上説明したように本実施の形態によれば、早期に新設のかご床15を昇降可能にして、プランジャー4を効率良く撤去することにより、全体として工期を短縮することができる。   As described above, according to the present embodiment, the construction period can be shortened as a whole by enabling the new car floor 15 to be moved up and down at an early stage and efficiently removing the plunger 4.

(3)その他の実施形態
上記実施形態は、本発明を説明するための例示であり、本発明をこれらの実施形態にのみ限定する趣旨ではない。本発明は、その趣旨を逸脱しない限り、様々な形態で実施することができる。例えば、上記実施形態では、各種プログラムの処理をシーケンシャルに説明したが、特にこれにこだわるものではない。従って、処理結果に矛盾が生じない限り、処理の順序を入れ替え又は並行動作するように構成しても良い。
(3) Other Embodiments The above embodiment is an example for explaining the present invention, and is not intended to limit the present invention only to these embodiments. The present invention can be implemented in various forms without departing from the spirit of the present invention. For example, in the above-described embodiment, the processing of various programs is described sequentially, but this is not particularly concerned. Therefore, as long as there is no contradiction in the processing result, the processing order may be changed or the operation may be performed in parallel.

本発明は、老朽化した油圧エレベータを新しいロープ式エレベータにリニューアルするに広く適用することができる。   The present invention can be widely applied to renewing an old hydraulic elevator to a new rope type elevator.

1……昇降路、2……乗りかご、3……メインレール、3a……メインレールブラケット、4……プランジャー、5……シリンダー、6……プランジャーレール、6a……プランジャーレールブラケット、7……主索、9……仮囲い、10……吊りビーム、11……昇降装置、11a……昇降装置ロープ、11b……制御盤、11c……制御ケーブル、11d……操作盤、11e……操作ケーブル、12……昇降装置取付金具、13……最下部足場、14……メインレール、14a……メインレールブラケット、15……かご床、15a……作業用手すり、15b……作業用中さん、16……揚重機、16a……揚重ロープ、17……乗りかご、17a……かご下プーリ、18……乗場ドア、19……巻上機、20……C.wtレール、20a……C.wtレールブラケット、21……C.wt、21a……C.wtプーリ、22……主索、23……上部プーリ、100……切断部。   1 ... hoistway, 2 ... car, 3 ... main rail, 3a ... main rail bracket, 4 ... plunger, 5 ... cylinder, 6 ... plunger rail, 6a ... plunger rail bracket 7 ... main rope, 9 ... temporary enclosure, 10 ... hanging beam, 11 ... lifting device, 11a ... lifting device rope, 11b ... control panel, 11c ... control cable, 11d ... control panel, 11e: Operation cable, 12: Lifting device mounting bracket, 13: Lowermost scaffolding, 14: Main rail, 14a: Main rail bracket, 15: Car floor, 15a: Handrail for work, 15b ... Medium for work, 16 ... lifter, 16a ... lift rope, 17 ... car, 17a ... car lower pulley, 18 ... landing door, 19 ... hoist, 20 ... C. wt rail, 20a ... C. wt rail bracket, 21. wt, 21a C.I. wt pulley, 22 ... main rope, 23 ... upper pulley, 100 ... cutting part.

Claims (3)

昇降路内において既存のプランジャーを用いて既設の乗りかごを既設のガイドレールに沿って昇降させる既設の油圧エレベータを撤去し、前記昇降路内において巻上機によるロープの巻き上げ下げに応じて前記ロープの一端に固定された新設の乗りかごを新設のガイドレールに沿って昇降させるロープ式エレベータへリニューアルするエレベータのリニューアル作業方法において、
前記昇降路内における最上部に位置させた前記既設の乗かごを足場として前記昇降路内の頂部に仮設の昇降装置を取り付け、
前記既設の乗かごを前記最上部から下降させながら前記既設の乗かごを足場として前記既設のガイドレールを撤去し、その後、前記既設の乗かごを撤去するとともに、前記昇降路の底部において前記新設のガイドレールの一部を前記昇降路内に設置し、
前記新設の乗りかご、又は前記新設の乗りかごの一部を構成する新設のかご床を、前記新設のガイドレールの一部に装着するとともに、前記仮設の昇降装置から前記底部に延びるロープの一端に固定した状態で、前記仮設の昇降装置による前記ロープの巻き上げに応じて前記新設の乗りかご又は前記新設のかご床を上昇させながら前記新設のガイドレールの一部の続きである前記新設のガイドレールの残りを前記昇降路内に設置し、
前記昇降路の上部に設けられた揚重機によって前記既存のプランジャーを吊り下げ、前記仮設の昇降装置により前記新設の乗りかご又は前記新設のかご床を昇降させながら前記既存のプランジャーを撤去し、
前記巻上機を含む必要な新設の設備を設置し、その後前記新設の乗りかごを足場として前記仮設の昇降装置を撤去して前記ロープ式エレベータを構成する
ことを特徴とするエレベータのリニューアル作業方法。
In the hoistway, the existing hydraulic elevator that lifts and lowers the existing car along the existing guide rail using the existing plunger is removed, and the rope is lifted and lowered by the hoisting machine in the hoistway. In the renewal work method of the elevator that renews the new elevator car fixed to one end of the rope to the rope type elevator that moves up and down along the new guide rail,
A temporary lifting device is attached to the top of the hoistway using the existing car positioned at the top of the hoistway as a foothold,
While lowering the existing car from the top, the existing guide rail is removed using the existing car as a foothold, and then the existing car is removed, and the new installation is provided at the bottom of the hoistway A part of the guide rail is installed in the hoistway,
One end of a rope that extends from the temporary lifting device to the bottom, and is mounted on a part of the new guide rail and a new car floor that constitutes a part of the new car or a part of the new car The new guide which is a continuation of a part of the new guide rail while raising the new passenger car or the new car floor in response to the winding of the rope by the temporary lifting device Install the rest of the rail in the hoistway,
The existing plunger is suspended by a lifting machine provided in the upper part of the hoistway, and the existing plunger is removed while the new elevator car or the new car floor is raised and lowered by the temporary lifting device. ,
An elevator renewal work method comprising: installing the necessary new equipment including the hoisting machine, and then removing the temporary lifting device using the newly installed car as a scaffold to configure the rope type elevator. .
前記既存のプランジャーは、前記昇降路の上部に設けられた揚重機によって吊り下げられながら、前記仮設の昇降装置により昇降可能な前記新設のかご床を足場として切断されることにより撤去されることを特徴とする請求項1に記載のエレベータのリニューアル作業方法。   The existing plunger is removed by being cut by the new car floor that can be raised and lowered by the temporary lifting device while being suspended by a lifting machine provided at the upper part of the hoistway. The elevator renewal work method according to claim 1. 前記新設の乗りかごは、前記新設のかご床に前記新設の乗りかごを構成すべき残りの部分が組み込まれることによって構成されることを特徴とする請求項1また請求項2に記載のエレベータのリニューアル作業方法。   3. The elevator according to claim 1, wherein the new car is configured by incorporating a remaining part of the new car on the new car floor to constitute the new car. 4. Renewal work method.
JP2016197819A 2016-10-06 2016-10-06 Elevator renewal work method Active JP6626809B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016197819A JP6626809B2 (en) 2016-10-06 2016-10-06 Elevator renewal work method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016197819A JP6626809B2 (en) 2016-10-06 2016-10-06 Elevator renewal work method

Publications (2)

Publication Number Publication Date
JP2018058673A true JP2018058673A (en) 2018-04-12
JP6626809B2 JP6626809B2 (en) 2019-12-25

Family

ID=61908208

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016197819A Active JP6626809B2 (en) 2016-10-06 2016-10-06 Elevator renewal work method

Country Status (1)

Country Link
JP (1) JP6626809B2 (en)

Also Published As

Publication number Publication date
JP6626809B2 (en) 2019-12-25

Similar Documents

Publication Publication Date Title
JP5538471B2 (en) Lift extension method for construction elevators
JPWO2020035933A1 (en) How to apply elevator head extension technology
JP5538470B2 (en) Lift extension method for construction elevators
JP6626809B2 (en) Elevator renewal work method
JP5050741B2 (en) How to upgrade existing elevators
JP2013245033A (en) Method of installing hoisting machine
JP3844944B2 (en) Demolition method of construction elevator
JP2009196786A (en) Elevator repairing method
JPWO2017168695A1 (en) Elevator equipment
JP5806166B2 (en) Elevator repair equipment installation method
JP2000095456A (en) Temporary operation device for elevator
JP2016008131A (en) Elevator and remodeling method of existing elevator
JP2022150841A (en) Renewal method of elevator and elevator
JP5535055B2 (en) Elevator apparatus repair method and elevator apparatus
JP2011051795A (en) Renewal method for hydraulic elevator
JPH072453A (en) Improving method for elevator
JP2877593B2 (en) Elevator installation method
JP2006001739A (en) Installation method of rise-up elevator
JP5718837B2 (en) Rope elevator and renewal method to this rope elevator
JP2015009967A (en) Elevator device and repair method for the same
JP2939064B2 (en) Elevator installation template
JP2012056735A (en) Method for renewing hydraulic elevator, and rope-type elevator renewed from hydraulic elevator
JP2023177370A (en) Installation assisting device and installation method for elevator hoisting machine
JPH09235082A (en) Elevator modification method
JP2022126286A (en) Replacement assist device of governor rope and replacement method of governor rope

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190116

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20191126

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20191129

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20191202

R150 Certificate of patent or registration of utility model

Ref document number: 6626809

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150