EP0541948A1 - Bridge - Google Patents

Bridge Download PDF

Info

Publication number
EP0541948A1
EP0541948A1 EP92116859A EP92116859A EP0541948A1 EP 0541948 A1 EP0541948 A1 EP 0541948A1 EP 92116859 A EP92116859 A EP 92116859A EP 92116859 A EP92116859 A EP 92116859A EP 0541948 A1 EP0541948 A1 EP 0541948A1
Authority
EP
European Patent Office
Prior art keywords
bridge
elements
lower chords
diagonal
roadway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP92116859A
Other languages
German (de)
French (fr)
Other versions
EP0541948B1 (en
Inventor
Herbert Hüther
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dornier GmbH
Original Assignee
Dornier GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dornier GmbH filed Critical Dornier GmbH
Publication of EP0541948A1 publication Critical patent/EP0541948A1/en
Application granted granted Critical
Publication of EP0541948B1 publication Critical patent/EP0541948B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • E01D15/133Portable or sectional bridges built-up from readily separable standardised sections or elements, e.g. Bailey bridges

Definitions

  • the invention relates to a collapsible bridge according to the preamble of claim 1.
  • a collapsible bridge which consists of several interconnectable bridge elements.
  • the bridge elements each contain a carriageway slab, lower chords and struts.
  • the bridge elements are designed either as central elements with a horizontally running lane or as ramp elements with an inclined lane. Ramp elements cannot be used as central elements, so that a relatively large number of parts must be carried when transporting the bridge.
  • DE-OS 38 14 502 discloses a bridge of the same type that can be dismantled from individual bridge elements that can be coupled together.
  • the bridge elements consist of a truss consisting of road slabs, lower chords and diagonal struts. Since the lower chords and the diagonal struts are telescopic in length or can be attached to certain coupling points, the height of the components can be adjusted.
  • the object of the invention is to improve such a bridge that it becomes lighter and simpler in construction.
  • the bridge according to the invention is lighter and simpler in construction than the one just described, since there are no telescopic parts (the double-walled design have to be) are more necessary.
  • the height and inclination of the bridge modules are freely selectable.
  • the articulation of the diagonal elements at the ends of the lower chords allows the lower chords to be constructed more easily than with a articulation in the middle.
  • the version with the very short diagonal elements (shorter than half the lower chords) further reduces the overall weight.
  • the shortness of the lower chords compared to the roadway automatically results in a higher bridge height (an arch) with the greater length.
  • the bridge module B here consists of a roadway element F , two lower chords U and four diagonal struts D.
  • the diagonal struts D and the lower flange U can be sunk into the track element F for space-saving transport.
  • the roadway element F has a U-shaped cross section, which leaves space in the middle for a stem support or a stem beak or a laying beam. It can be clearly seen that the lower flange U is shorter than the roadway element F , as a result of which the lower flange U can be completely "sunk" into the roadway element F.
  • the relatively short diagonal struts D can also be completely sunk in the roadway element F in the transport state or in the short bridge be.
  • the different fastening options for the diagonal elements D and the lower flange U in the carriageway element F can also be seen .
  • different fastening options 1, 2, 3, 0 for the diagonals D and for the lower flange U are shown at each end of the roadway element F.
  • the fastening options 1, 2, 3, 1 ', 2', and 3 ' for the lower chords U and the fastening options 1, 3, 1' and 3 ' are also provided for the diagonal struts D. If other heights or inclinations of the bridge elements B are desired, the attachment points are at different locations.
  • the upper end of the diagonal D is here (for example in rails) in the carriageway element F. In the folded state, the upper end is at point 0 ( 0 ' ). When F is raised , U and D unfold automatically. The attachment point 1 is removed from the attachment point 0 by the length of a diagonal D.
  • FIG. 2 shows three versions of bridges according to the invention, each of which is assembled from 1, 2 or 3 of the bridge modules B shown in FIG. 1.
  • 1 shows a short bridge at the top, the length of which corresponds to a bridge module B and the height of which corresponds to the height of the roadway element F.
  • the diagonals D and the lower chords U are, as shown in FIG. 1 above, sunk in the roadway element F.
  • Fig. 2 shows in the middle a bridge of medium span coupled together from two bridge modules B.
  • the lower chords U are no longer arranged at the outer fastening points 1 , but at the further inner fastening points 2 and 2 ' .
  • the other end of the lower chord is connected to the lower chord of the other bridge module.
  • the top The ends of the middle diagonal struts D shift from the points 0 or 0 ' to 3 or 3' during the unfolding.
  • the bridge has a greater height than the short bridge and thus a load capacity adapted to the greater length.
  • 2 shows a long bridge composed of three bridge modules B with the correspondingly larger height H3 .
  • the lower flange U is articulated at the attachment point 3 , which is farther from the end than the attachment point 2 .
  • the left diagonal D has no function in the lane F.
  • the right diagonal of the left bridge module B is articulated at the fastening point 1 'of the road element F. The same applies to the right bridge module B in mirror image.
  • the middle bridge module B is coupled between the two bridge modules B mentioned .
  • the lower chords U of the three bridge modules are directly connected to each other, as are the road elements, so that the desired higher curve results.
  • the diagonal struts D of the middle bridge module are fastened in the fastening points 3, 3 'of the roadway element F of the middle bridge module B.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Zerlegbare Brücke, insbesondere für militärische Zwecke, aus zusammenkuppelbaren Brückenelementen (B), deren Fahrbahnelemente (F), Diagonalstreben (D) und Untergurte (U) ein höhenverstellbares Fachwerk bilden. <IMAGE>Detachable bridge, in particular for military purposes, consisting of bridge elements (B) which can be coupled together and whose roadway elements (F), diagonal struts (D) and lower chords (U) form a height-adjustable truss. <IMAGE>

Description

Die Erfindung betrifft eine zerlegbare Brücke nach dem Oberbegriff des Anspruchs 1.The invention relates to a collapsible bridge according to the preamble of claim 1.

Aus der DE-AS 12 07 948 ist eine zerlegbare Brücke bekannt, die aus mehreren zusammenkuppelbaren Brückenelementen besteht. Die Brückenelemente enthalten je eine Fahrbahnplatte, Untergurte und Streben. Die Brückenelemente sind entweder als Zentralelemente mit horizontal verlaufender Fahrbahn oder als Rampenelemente mit geneigt verlaufender Fahrbahn ausgelegt. Rampenelemente können nicht als Zentralelemente verwendet werden, so daß beim Transport der Brücke relativ viele Teile mitzuführen sind.From DE-AS 12 07 948 a collapsible bridge is known, which consists of several interconnectable bridge elements. The bridge elements each contain a carriageway slab, lower chords and struts. The bridge elements are designed either as central elements with a horizontally running lane or as ramp elements with an inclined lane. Ramp elements cannot be used as central elements, so that a relatively large number of parts must be carried when transporting the bridge.

Aus der DE-OS 38 14 502 ist eine gattungsgleiche zerlegbare Brücke aus einzelnen zu- sammenkuppelbaren Brückenelementen bekannt. Die Brückenelemente bestehen aus einem Fachwerk aus Fahrbahnplatten, Untergurten und Diagonalstreben. Da die Untergurte und die Diagonalstreben in ihrer Länge teleskopierbar sind oder an bestimmten Kupplungsstellen befestigbar sind, kann die Höhe der Bauelemente verstellt werden. DE-OS 38 14 502 discloses a bridge of the same type that can be dismantled from individual bridge elements that can be coupled together. The bridge elements consist of a truss consisting of road slabs, lower chords and diagonal struts. Since the lower chords and the diagonal struts are telescopic in length or can be attached to certain coupling points, the height of the components can be adjusted.

Aufgabe der Erfindung ist es, eine solche Brücke dahingehend zu verbessern, daß sie leichter und einfacher im Aufbau wird.The object of the invention is to improve such a bridge that it becomes lighter and simpler in construction.

Diese Aufgabe wird erfindungsgemäß gelöst mit den kennzeichnenden Merkmalen im Anspruch 1. Besondere Ausführungsarten der Erfindung sind Gegenstände von Unteransprüchen.This object is achieved according to the invention with the characterizing features in claim 1. Special embodiments of the invention are the subject of subclaims.

Die erfindungsgemäße Brücke hat im wesentlichen die Vorteile der in der DE-OS 38 14 502 genannten Brücke, wie

  • wenig Windangriffsfläche
  • wenig Beschußfläche
  • große Variabilität, das heißt, es können entweder eine sehr lange oder mehrere kurze Brücken gleichzeitig von einem Fahrzeug gebaut werden
  • bis ca. 45 Meter kein Vorbauträger nötig
  • geringes Gewicht
  • geringes Transportvolumen
  • gute Brückensicht des Panzerfahrers bei Anfahrt auf der Brücke
  • bei Ausfall eines Brückenteils nur Reduzierung der Gesamtlänge und kein Ausfall des Gesamtsystems
  • offene Struktur, wodurch Sicht zu Kupplungsstellen und anderen kritischen Stellen frei ist
  • kein Aufrüsten hinter der Front, da alle Elemente austauschbar sind
  • keine taktische Einschränkung (Entscheidung am Ziel über Brückenlänge).
The bridge according to the invention essentially has the advantages of the bridge mentioned in DE-OS 38 14 502, such as
  • little wind exposure area
  • little bombardment area
  • great variability, which means that either a very long bridge or several short bridges can be built simultaneously by one vehicle
  • up to approx. 45 meters no porch girders required
  • light weight
  • low transport volume
  • good bridge view of the tank driver when approaching the bridge
  • in the event of failure of a bridge part, only a reduction in the overall length and no failure of the overall system
  • Open structure, which gives a clear view of coupling points and other critical points
  • no upgrading behind the front, as all elements are interchangeable
  • no tactical limitation (decision at the destination about bridge length).

Die erfindungsgemäße Brücke ist leichter und einfacher im Aufbau als die eben beschriebene, da keine teleskopierbaren Teile (die doppelwandig ausgelegt sein müssen) mehr notwendig sind. Höhe und Neigung der Brückenmodule sind in weitem Rahmen frei wählbar. Die Anlenkung der Diagonalelemente an den Enden der Untergurte erlaubt einen leichteren Aufbau der Untergurte als bei einer Anlenkung in der Mitte. Die Ausführung mit den sehr kurzen Diagonalelementen (kürzer als die halben Untergurte) reduziert nochmals das Gesamtgewicht. Durch die Kürze der Untergurte gegenüber der Fahrbahn ergibt sich eine grössere Höhe der Brücke (ein Bogen) ganz automatisch mit der grösseren Länge.The bridge according to the invention is lighter and simpler in construction than the one just described, since there are no telescopic parts (the double-walled design have to be) are more necessary. The height and inclination of the bridge modules are freely selectable. The articulation of the diagonal elements at the ends of the lower chords allows the lower chords to be constructed more easily than with a articulation in the middle. The version with the very short diagonal elements (shorter than half the lower chords) further reduces the overall weight. The shortness of the lower chords compared to the roadway automatically results in a higher bridge height (an arch) with the greater length.

Die Erfindung wird anhand der Zeichnung näher erläutert.The invention is explained in more detail with reference to the drawing.

Es zeigt

  • Fig. 1 ein erfindungsgemäßes Brückenmodul, und
  • Fig. 2 drei mögliche Brücken.
It shows
  • 1 shows a bridge module according to the invention, and
  • Fig. 2 three possible bridges.

Fig. 1 zeigt oben ein Brückenmodul B im Transportzustand (oder als Kurzbrücke) und in der Mitte und unten ein Brückenmodul B im entfalteten Zustand. Das Brückenmodul B besteht hier aus einem Fahrbahnelement F, zwei Untergurten U und vier Diagonalstreben D. Die Diagonalstreben D und der Untergurt U können für den platzsparenden Transport in das Fahrbahnelement F versenkt werden. Das Fahrbahnelemente F hat hier, wie unten zu sehen ist, einen U-förmigen Querschnitt, der in der Mitte Raum für einen Vorbauträger oder einen Vorbauschnabel oder einen Verlegebalken läßt. Es ist gut zu erkennen, daß der Untergurt U kürzer ist als Fahrbahnelement F, wodurch der Untergurt U vollständig in dem Fahrbahnelement F "versenkt" werden kann. Auch die relativ kurzen Diagonalstreben D können im Transportzustand oder in der Kurzbrücke vollständig im Fahrbahnelement F versenkt sein. Zu erkennen sind weiterhin die unterschiedlichen Befestigungsmöglichkeiten für die Diagonalelemente D und den Untergurt U in dem Fahrbahnelement F. In dieser Ausführung sind an jedem Ende des Fahrbahnelements F je unterschiedliche Befestigungsmöglichkeiten 1, 2, 3, 0 für die Diagonalen D und für den Untergurt U gezeigt. In diesem Beispiel sind die Befestigungsmöglichkeiten 1, 2, 3, 1', 2', und 3' für die Untergurte U und die Befestigungsmöglichkeiten 1, 3, 1' und 3' auch für die Diagonalstreben D vorgesehen.
Sollten andere Höhen oder Neigungsmöglichkeiten der Brückenelemente B erwünscht sein, liegen die Befestigungspunkte an anderen Stellen. Das obere Ende der Diagonalen D ist hier (z.B. in Schienen) in dem Fahrbahnelement F geführt. Im zusammengefalteten Zustand liegt das obere Ende beim Punkt 0 (0'). Beim Anheben von F entfaltet sich U und D automatisch. Der Befestigungspunktes 1 ist vom Befestigungspunkt 0 um die Länge einer Diagonale D entfernt.
1 shows a bridge module B in the transport state (or as a short bridge) at the top and a bridge module B in the unfolded state in the middle and below. The bridge module B here consists of a roadway element F , two lower chords U and four diagonal struts D. The diagonal struts D and the lower flange U can be sunk into the track element F for space-saving transport. Here, as can be seen below, the roadway element F has a U-shaped cross section, which leaves space in the middle for a stem support or a stem beak or a laying beam. It can be clearly seen that the lower flange U is shorter than the roadway element F , as a result of which the lower flange U can be completely "sunk" into the roadway element F. The relatively short diagonal struts D can also be completely sunk in the roadway element F in the transport state or in the short bridge be. The different fastening options for the diagonal elements D and the lower flange U in the carriageway element F can also be seen . In this embodiment, different fastening options 1, 2, 3, 0 for the diagonals D and for the lower flange U are shown at each end of the roadway element F. In this example, the fastening options 1, 2, 3, 1 ', 2', and 3 ' for the lower chords U and the fastening options 1, 3, 1' and 3 'are also provided for the diagonal struts D.
If other heights or inclinations of the bridge elements B are desired, the attachment points are at different locations. The upper end of the diagonal D is here (for example in rails) in the carriageway element F. In the folded state, the upper end is at point 0 ( 0 ' ). When F is raised , U and D unfold automatically. The attachment point 1 is removed from the attachment point 0 by the length of a diagonal D.

Fig. 2 zeigt drei Ausführungen von erfindungsgemäßen Brücken, die aus jeweils 1, 2 oder 3 der in Fig. 1 gezeigten Brückenmodule B montiert sind. Fig. 1 zeigt oben eine kurze Brücke, deren Länge einem Brückenmodul B und deren Höhe der Höhe des Fahrbahnelements F entspricht. Die Diagonalen D und die Untergurte U sind, wie in Fig. 1 oben gezeigt, in dem Fahrbahnelement F versenkt.
Fig. 2 zeigt in der Mitte eine aus zwei Brückenmodulen B zusammengekuppelte Brücke mittlerer Spannweite. Die Untergurte U sind nicht mehr an den äusseren Befestigungspunkten 1, sondern an den weiter innenliegenden Befestigungspunkten 2 und 2' angeordnet. Das andere Ende der Untergurte ist jeweils mit dem Untergurt des anderen Brückenmoduls verbunden. Die oberen Enden der mittleren Diagonalstreben D verschieben sich während des Entfaltens von den Punkten 0 oder 0' auf 3 oder 3'. Die Brücke weist gegenüber der kurzen Brücke eine grössere Höhe und damit eine der grösseren Länge angepasste Tragkraft auf.
Fig. 2 zeigt unten eine aus drei Brückenmodulen B zusammengesetzte lange Brücke mit der entsprechend grösseren Höhe H3. Im linken Brückenelement B ist der Untergurt U am Befestigungspunkt 3, der weiter vom Ende entfernt ist als der Befestigungspunkt 2, angelenkt. Die linke Diagonale D liegt ohne Funktion in der Fahrbahn F. Die rechte Diagonale des linken Brückenmoduls B ist im Befestigungspunkt 1' des Fahrbahnelements F angelenkt. Für das rechte Brückenmodul B gilt spiegelbildlich das gleiche. Das mittlere Brückenmodul B ist zwischen die beiden genannten Brückenmodule B gekuppelt. Die Untergurte U der drei Brückenmodule sind direkt miteinander verbunden, die Fahrbahnelemente ebenfalls, so daß sich der gewünschte höhere Bogen ergibt. Die Diagonalstreben D des mittleren Brückenmoduls sind in den Befestigungspunkten 3, 3' des Fahrbahnelements F des mittleren Brückenmoduls B befestigt.
FIG. 2 shows three versions of bridges according to the invention, each of which is assembled from 1, 2 or 3 of the bridge modules B shown in FIG. 1. 1 shows a short bridge at the top, the length of which corresponds to a bridge module B and the height of which corresponds to the height of the roadway element F. The diagonals D and the lower chords U are, as shown in FIG. 1 above, sunk in the roadway element F.
Fig. 2 shows in the middle a bridge of medium span coupled together from two bridge modules B. The lower chords U are no longer arranged at the outer fastening points 1 , but at the further inner fastening points 2 and 2 ' . The other end of the lower chord is connected to the lower chord of the other bridge module. The top The ends of the middle diagonal struts D shift from the points 0 or 0 ' to 3 or 3' during the unfolding. The bridge has a greater height than the short bridge and thus a load capacity adapted to the greater length.
2 shows a long bridge composed of three bridge modules B with the correspondingly larger height H3 . In the left bridge element B , the lower flange U is articulated at the attachment point 3 , which is farther from the end than the attachment point 2 . The left diagonal D has no function in the lane F. The right diagonal of the left bridge module B is articulated at the fastening point 1 'of the road element F. The same applies to the right bridge module B in mirror image. The middle bridge module B is coupled between the two bridge modules B mentioned . The lower chords U of the three bridge modules are directly connected to each other, as are the road elements, so that the desired higher curve results. The diagonal struts D of the middle bridge module are fastened in the fastening points 3, 3 'of the roadway element F of the middle bridge module B.

Es sind auch Brücken mit mehr als drei solcher Elemente B möglich.Bridges with more than three such elements B are also possible.

Claims (5)

Zerlegbare Brücke, insbesondere für militärische Zwecke, aus ein oder mehreren zusammenkuppelbaren Brückenmodulen (B), die ein oder mehrere Fahrbahnelemente (F), Untergurte (U) und Diagonalstreben (D) enthalten, wobei die Höhe des von den Fahrbahnelementen (F), Untergurten (U) und Diagonalstreben (D) gebildeten Fachwerks verstellbar ist, dadurch gekennzeichnet, daß die Untergurte (U) kürzer sind als die Fahrbahnelemente (F), daß die Fahrbahnelemente (F) verschieden weit von ihrem jeweiligen Ende entfernte Befestigungsmöglichkeiten (1, 2, 3) für die Diagonalstreben (D) oder die Untergurte (U) besitzen, daß die Fahrbahnelemente (F), die Untergurte (U) und die Diagonalelemente (D) konstante Längen haben und daß die Diagonalelemente (D) an den Enden der Untergurte (U) befestigt sind.Detachable bridge, in particular for military purposes, comprising one or more bridge modules ( B ) which can be coupled together and which contain one or more road elements ( F ), lower chords ( U ) and diagonal struts ( D ), the height of the of the road elements ( F ), lower chords ( U ) and diagonal struts ( D ) formed truss is adjustable, characterized in that the lower chords ( U ) are shorter than the roadway elements ( F ), that the roadway elements ( F ) fastening means ( 1, 2, 3 ) for the diagonal struts ( D ) or the lower chords ( U ) have that the road elements ( F ), the lower chords ( U ) and the diagonal elements ( D ) have constant lengths and that the diagonal elements ( D ) at the ends of the lower chords ( U ) are attached. Brücke nach Anspruch 1, dadurch gekennzeichnet, daß die Untergurte (U) wenigstens doppelt so lang sind als die Diagonalstreben (D).Bridge according to claim 1, characterized in that the lower chords ( U ) are at least twice as long as the diagonal struts ( D ). Brücke nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß die Fahrbahnelemente (F) trapezförmig sind und in ihrer Unterseite die Diagonalelemente (D) und die Untergurte (U) aufnehmen können.Bridge according to one of the preceding claims, characterized in that the roadway elements ( F ) are trapezoidal and can accommodate the diagonal elements ( D ) and the lower chords ( U ) in their underside. Brücke nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß die Fahrbahnelemente (F) an jedem Ende Schienen und mehrere unterschiedliche Befestigungsmöglichkeiten (1, 2, 3) für die oberen Enden der Diagonalstreben (D) haben.Bridge according to one of the preceding claims, characterized in that the roadway elements ( F ) have rails and several different fastening options at each end ( 1, 2, 3 ) for the upper ends of the diagonal struts ( D ). Brücke nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß zwei äussere Befestigungsmöglichkeiten (1, 1') eines Fahrbahnelements (F) voneinander um die Länge eines Untergurts (U) entfernt sind.Bridge according to one of the preceding claims, characterized in that two outer fastening options ( 1, 1 ' ) of a roadway element ( F ) are separated from one another by the length of a lower flange ( U ).
EP92116859A 1991-11-14 1992-10-02 Bridge Expired - Lifetime EP0541948B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE4137500A DE4137500C1 (en) 1991-11-14 1991-11-14
DE4137500 1991-11-14

Publications (2)

Publication Number Publication Date
EP0541948A1 true EP0541948A1 (en) 1993-05-19
EP0541948B1 EP0541948B1 (en) 1995-08-30

Family

ID=6444825

Family Applications (1)

Application Number Title Priority Date Filing Date
EP92116859A Expired - Lifetime EP0541948B1 (en) 1991-11-14 1992-10-02 Bridge

Country Status (3)

Country Link
US (1) US5293658A (en)
EP (1) EP0541948B1 (en)
DE (1) DE4137500C1 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4240271A1 (en) * 1992-12-01 1994-06-09 Krupp Foerdertechnik Gmbh Removable bridge
DE4240270A1 (en) * 1992-12-01 1994-06-09 Krupp Foerdertechnik Gmbh Removable bridge
EP0640722A1 (en) * 1993-08-31 1995-03-01 Krupp Fördertechnik GmbH Portable bridge
DE19528869C1 (en) * 1995-08-05 1997-04-10 Bundesrep Deutschland Modular bridge for emergency use, and especially by military for crossings in field
US6738096B1 (en) * 1998-07-10 2004-05-18 Silverbrook Research Pty Ltd Low-cost disposable camera including print media carrying indication of postage paid
DE19858328C1 (en) * 1998-12-17 2000-03-30 Dornier Gmbh Mobile road bridge has composite panels and reinforcing belts to support corrugated sidewalls
DE10307858B3 (en) * 2003-02-25 2004-06-09 Dornier Gmbh Transportable bridge structure has end sections compensating length differences between modular longitudinal supports and suspension arcs
CN106758763B (en) * 2016-12-13 2018-08-03 湖北华舟重工应急装备股份有限公司 A kind of artificial quick bridge of pin-connected panel bilayer highway

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1207948B (en) * 1962-07-14 1965-12-30 Maschf Augsburg Nuernberg Ag Dismountable bridge, especially a moat bridge
US4546591A (en) * 1983-11-23 1985-10-15 Beltz Thomas G Truss system and components thereof
DE3814502A1 (en) * 1988-04-29 1989-11-09 Dornier Gmbh BRIDGE
EP0407235A1 (en) * 1989-07-05 1991-01-09 Constructions Industrielles De La Mediterranee C.N.I.M. Bridging system for surmounting obstacles such as gaps

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4972538A (en) * 1980-03-04 1990-11-27 The Secretary Of State For Defence In Her Britannic Majesty's Government Of The United Kingdom Of Great Britain And Northern Ireland Launching apparatus for transportable bridges
US4745724A (en) * 1986-04-16 1988-05-24 Trus Joist Corporation Open web structural support member of adjustable length with incremental adjustment of end web member
DE4009639C2 (en) * 1990-03-26 1994-04-28 Dornier Gmbh Laying device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1207948B (en) * 1962-07-14 1965-12-30 Maschf Augsburg Nuernberg Ag Dismountable bridge, especially a moat bridge
US4546591A (en) * 1983-11-23 1985-10-15 Beltz Thomas G Truss system and components thereof
DE3814502A1 (en) * 1988-04-29 1989-11-09 Dornier Gmbh BRIDGE
EP0407235A1 (en) * 1989-07-05 1991-01-09 Constructions Industrielles De La Mediterranee C.N.I.M. Bridging system for surmounting obstacles such as gaps

Also Published As

Publication number Publication date
EP0541948B1 (en) 1995-08-30
DE4137500C1 (en) 1992-11-26
US5293658A (en) 1994-03-15

Similar Documents

Publication Publication Date Title
DE3814502C3 (en) bridge
EP0237937B1 (en) Self-erection tent
EP0541948B1 (en) Bridge
DE3510778C3 (en) Pontoon of a floating bridge
EP0600356A1 (en) Portable bridge
DE68908893T2 (en) FOLDABLE TRANSPORTABLE BRIDGE.
DE10242860B3 (en) Removable bridge
EP1021334A1 (en) Air passenger bridge
DE69806991T2 (en) Self erecting crane with laterally collapsible boom in transport position
EP0988424A1 (en) Modular bridge
EP0600330B2 (en) Dismountable bridge
EP0643172A2 (en) Bridge
EP0600329B1 (en) Dismountable bridge
CH689451A5 (en) Floating platform for harbour installations
AT390292B (en) Dismantlable stage for concerts, shows or the like
DE2052107C3 (en) Dismountable bridge
DE4325779C2 (en) Foldable and collapsible pedestrian bridge
DE2907260A1 (en) Universal demountable steel traffic bridge - has max. thirteen different components, regardless of size
DE19632741C2 (en) Trough bridge
DE1872020U (en) TRANSPORTABLE TRANSPORT FOR ROAD TRAFFIC.
DE19607317A1 (en) Collapsible but fixed road bridge
DE8912968U1 (en) Pivoting drive-over bridge for ramps
DE1709434A1 (en) MULTI-PURPOSE HALL
EP0600321A1 (en) Portable bridge
DE3601548A1 (en) Transportable spectator-stand element

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): CH FR GB IT LI SE

17P Request for examination filed

Effective date: 19930423

17Q First examination report despatched

Effective date: 19941028

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): CH FR GB IT LI SE

GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

Effective date: 19950829

ITF It: translation for a ep patent filed

Owner name: JACOBACCI & PERANI S.P.A.

ET Fr: translation filed
PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
REG Reference to a national code

Ref country code: GB

Ref legal event code: 746

Effective date: 20010529

REG Reference to a national code

Ref country code: FR

Ref legal event code: D6

REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

REG Reference to a national code

Ref country code: GB

Ref legal event code: 732E

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20041011

Year of fee payment: 13

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SE

Payment date: 20041012

Year of fee payment: 13

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: R. A. EGLI & CO. PATENTANWAELTE

Ref country code: CH

Ref legal event code: PUE

Owner name: EUROBRIDGE MOBILE BRUECKEN GMBH

Free format text: DORNIER GMBH#POSTFACH 1420#D-88004 FRIEDRICHSHAFEN (DE) -TRANSFER TO- EUROBRIDGE MOBILE BRUECKEN GMBH##88039 FRIEDRICHSHAFEN (DE)

REG Reference to a national code

Ref country code: FR

Ref legal event code: TP

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.

Effective date: 20051002

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20051003

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20051031

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20051031

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

EUG Se: european patent has lapsed
REG Reference to a national code

Ref country code: GB

Ref legal event code: 732E

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20101021

Year of fee payment: 19

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20111103

Year of fee payment: 20

REG Reference to a national code

Ref country code: GB

Ref legal event code: PE20

Expiry date: 20121001

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

Effective date: 20121001