DE20320033U1 - Concrete sleeper, has first track secured via screw dowels and second track secured to anchor rails by hammerhead screws - Google Patents
Concrete sleeper, has first track secured via screw dowels and second track secured to anchor rails by hammerhead screws Download PDFInfo
- Publication number
- DE20320033U1 DE20320033U1 DE20320033U DE20320033U DE20320033U1 DE 20320033 U1 DE20320033 U1 DE 20320033U1 DE 20320033 U DE20320033 U DE 20320033U DE 20320033 U DE20320033 U DE 20320033U DE 20320033 U1 DE20320033 U1 DE 20320033U1
- Authority
- DE
- Germany
- Prior art keywords
- track
- rail
- rails
- concrete
- sleeper
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B9/00—Fastening rails on sleepers, or the like
- E01B9/02—Fastening rails, tie-plates, or chairs directly on sleepers or foundations; Means therefor
- E01B9/04—Fastening on wooden or concrete sleepers or on masonry without clamp members
- E01B9/14—Plugs, sleeves, thread linings, or other inserts for holes in sleepers
- E01B9/18—Plugs, sleeves, thread linings, or other inserts for holes in sleepers for concrete sleepers
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B3/00—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails
- E01B3/28—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails made from concrete or from natural or artificial stone
- E01B3/42—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails made from concrete or from natural or artificial stone combined with inserts of wood or other material
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Abstract
Description
Die Erfindung betrifft eine für alle vorkommenden Spurweiten einsetzbare Gleisschwelle aus Beton, deren Anwendung sich besonders für Versuchsgleisstrecken anbietet.The invention relates to one that occurs for all Track sleepers made of concrete, their application especially for Offers trial tracks.
Die Erfindung ermöglicht es, Gleise für Straßen-, Stadt- und schmal- sowie normalspurige Eisenbahnen ohne weiteres herzustellen und in kürzesten Fristen auf andere Spurweiten umzurüsten. Damit können auf nur einer Gleisanlage, jedwede Fahrzeuge mit den verschiedensten Spurweiten praxisgerecht getestet werden; wesentlich ist, daß hierfür alle Schienenprofile und Schienenbefestigungen zum Einsatz kommen können.The invention enables tracks for street, urban and to easily produce narrow and standard gauge railways and in the shortest possible time to convert to other gauges. So that can on just one track system, any vehicle with the most varied Track gauges are tested in practice; it is essential that all rail profiles and rail fasteners can be used.
Gleisschwellen, die für zwei Spurweiten geeignet sind, sind seit längerem bekannt. Vordergründig sind im Zuge einer Verbesserung des länderübergreifenden Verkehrs diesbezüglich Vorschläge entwickelt worden. Aber auch die in jünger Zeit zunehmend anzutreffende gemeinsame Nutzung eines Gleisbettes durch eine schmalspurige Straßen- oder Stadtbahn einerseits und einer normalspurigen Eisenbahn anderseits im innerstädtischen Bereich haben entsprechende Entwicklungen hervorgebracht. Diese innerstädtischen Lösungen nutzen nahezu ausschließlich für zwei Spuren nur drei Schienen.Track sleepers for two gauges have been suitable for a long time known. superficial proposals have been developed in this regard as part of an improvement in cross-border traffic Service. But also the younger ones Time increasingly common sharing of a track bed through a narrow-lane road or Stadtbahn on the one hand and a standard gauge railway on the other in the inner city Relevant developments. This inner-city solutions use almost exclusively for two Tracks only three rails.
Grundsätzlich sind solche Lösungen dadurch charakterisiert, daß die für die Schienenbefestigung der Gleise für beide Spuren bzw. die auf der Schwelle benötigten Mittel und Flächen von vornherein getrennt nebeneinander vorgesehen werden. Eine derartige Schwelle, bei der die Schienen und die Schienenbefestigungsmittel beim Spurwechsel nur in die geänderte Position umgesetzt werden, ist aus dem brasilianischen Patent 1 74 00 449 bekannt.In principle, such solutions are characterized that the for the Rail fastening of the tracks for both tracks or the means and areas required on the threshold of be provided separately next to each other in advance. Such one Threshold at which the rails and the rail fasteners when changing lanes only in the changed one Position to be implemented is from Brazilian patent 1 74 00 449 known.
Auch für den Fall, daß für eine ungehinderte getrennte Montage der Schienen für die beiden Gleisspuren der Platz auf der Schiene nicht vorhanden ist, sind seit geraumer Zeit Vorschläge für Schienenkonstruktionen bekannt, die zwar die Aufgabe, für zwei Spurweiten geeignet zu sein, theoretisch lösen, jedoch im praktischen Bahnbetrieb, namentlich auf Hochleistungsstrecken, nicht verwendbar sind. Beispielsweise ist aus GB-A-20249 eine Schwellenkonstruktion entnehmbar, bei der die Schienenbefestigung mit Hammerkopfschrauben in Ankerschienen in der Schwelle gehalten werden und die Spurweitenveränderung durch Verschiebung der Hammerkopfschraube in der Ankerschiene bewerkstelligt wird. Die Schraub- und/oder Dübelelemente sind hier jedoch nicht formschlüssig in der Schwelle verankert und auch sonst nicht in irgendwelcher Weise zusätzlich fixiert. Die mangelnde Sicherheit dieser Verbindung gegen seitliche Verschiebung bei Dauerbelastung hat ihre praktische Anwendung ausgeschlossen.Even in the event that for an unhindered separate Assembly of the rails for the two track tracks the space on the rail does not exist suggestions for rail constructions have been known for some time, which is the job for two Track gauges to be suitable, theoretically solve, but in practice Railway operations, especially on high-performance routes, cannot be used are. For example, GB-A-20249 is a sleeper construction removable, with the rail fastening with hammer head screws in anchor channels are kept in the threshold and the track width change accomplished by moving the hammer head screw in the anchor channel becomes. The screw and / or dowel elements are however not form-fitting here anchored in the threshold and not otherwise in any Way in addition fixed. The lack of security of this connection against lateral Postponement under constant load has excluded their practical application.
Die in
Der Stand der Technik ist mithin sowohl hinsichtlich der Betonschwellen als auch der Schienenbefestigungen bei mehreren Spurweiten in einem Gleis dadurch charakterisiert, daß er ausschließlich nur Lösungen vorstellt bzw. anregt, die auf zwei, für die gesamte Lebensdauer der Gleisanlage zueinander fixierte Spurweiten hinzielt. Dies ist sowohl für Gleisanlagen, die zweispurig – etwa gleichzeitig für eine Eisenbahn und eine Straßenbahn – betrieben werden, als auch für Vorratslösungen, wonach zu einem späteren Zeitpunkt von einer auf eine andere Spur übergegangen werden soll, der Fall.The state of the art is therefore both with regard to the concrete sleepers and the rail fastenings characterized by multiple track gauges in one track, that he exclusively only solutions imagines or suggests that on two, for the entire life of the Track system aimed at fixed track gauges. This is both for track systems, the two-lane - about at the same time for one Railway and a tram - operated for as well Stock solutions, after which to a later Point in time from one track to another, the Case.
Aus dem Stand der Technik ist die nachfolgend beschriebene Erfindung nicht angeregt.From the state of the art invention described below not suggested.
Aufgabe der Erfindung ist es, eine lagestabile, für Achslasten bis zu 250 kN (25 t) geeignete Betonschwelle vorzuschlagen, die es ermöglicht, mit vergleichsweise geringem Aufwand und in kurzen Fristen die Spurweite eines oder mehrerer Gleise im Bereich von 600 und 1.676 mm zu ändern und sicher zu fixieren. Es soll dabei möglich sein, alle gängigen Schienenprofile mit den üblichen Schienenbefestigungen zu verwenden.The object of the invention is to propose a positionally stable concrete sleeper suitable for axle loads up to 250 kN (25 t), which enables the track width of one or more tracks in the track to be carried out with comparatively little effort and in short periods Change the range from 600 and 1,676 mm and fix it securely. It should be possible to use all common rail profiles with the usual rail fastenings.
Erfindungsgemäß wird die Aufgabe durch die Merkmale des Hauptanspruches gelöst. Zweckmäßige Ausgestaltungen der Erfindung ergeben sich aus den Merkmalen der Ansprüche 2 bis 9.According to the invention, the object is achieved by Features of the main claim solved. Appropriate configurations the invention result from the features of claims 2 to 9th
Nach Maßgabe der Erfindung wird somit eine Betonquerschwelle, die eine praktisch stufenlose Einstellung der Spurweite eines Gleises erlaubt, zur Verfü gung gestellt. Die Einstellung erfolgt im Gleis durch Verschiebung einer Schiene einschließlich der Mittel für die Schienenbefestigung; hierfür sind nur Hammerkopfschrauben, die in einer Ankerschiene geführt werden, zu lösen und gleichfalls lösbare Spurhalter zu entnehmen bzw. einzusetzen. Die mittels Schrauben befestigten Spurhalter sind in ihrer Länge durch die einzustellende Spurweite bestimmt. Neben der Fixierung der Spurweite des Gleises dienen sie auch dazu, ein seitliches Wandern der verschiebbaren Schiene im Betrieb sicher zu verhindern.According to the invention a concrete cross sleeper which is a practically stepless adjustment the track gauge of a track, provided. The setting takes place in the track by moving a rail including the means for the Rail fastening; therefor are just hammer head screws that are guided in an anchor channel, to solve and detachable track holders to remove or insert. The attached with screws Track holders are in their length determined by the track width to be set. In addition to the fixation the track gauge of the track also serve to hike sideways to reliably prevent the sliding rail during operation.
Erfindungsgemäß ist auch vorgesehen, zwei verschiebbare Schienen auf der Schwelle zu befestigen und somit zwei verschiedene Spurweiten zu realisieren. Besonders für Versuchsgleisstrecken, mit denen zeitbegrenzt bestimmte Spurweiten vorgehalten werden müssen, bieten sich hierfür optimierte Varianten an, so z. B. die Spurweiten 900 mm/1 .435 mm oder 600 mm/1.676 mm. Dem Wesen der Erfindung folgend ist, eine Bevorratung mit entsprechend langen Spurhaltern vorausgesetzt, jede andere Kombination der benötigten Spurweiten möglich.According to the invention, there are also two displaceable Fix rails on the threshold and thus two different ones Realize track gauges. Especially for test track sections with which certain gauges must be kept available for a limited time yourself for this optimized variants, e.g. B. the track widths 900 mm / 1 .435 mm or 600 mm / 1,676 mm. Following the essence of the invention, one Stocking with appropriately long track supports provided each other combination of the required Gauges possible.
Auf der Schwelle können alle Schienenprofile über spezielle, in ihren Grundabmessungen jedoch gleiche Rippenprofile befestigt werden. Damit zeichnet sich die erfindungsgemäße Betonschwelle durch eine hohe Universalität aus, da so nicht nur Fahrzeuge mit verschiedensten Spurweiten getestet werden können, sondern auch allen Anforderungen hinsichtlich der Kombination Rad/Schiene entsprochen werden kann.Everyone can on the threshold Rail profiles over special rib profiles with the same basic dimensions be attached. The concrete sleeper according to the invention is thus distinguished through a high level of universality from, because not only vehicles with a wide range of gauges have been tested can be but also all requirements regarding the wheel / rail combination can be met.
Die Schwellen sind vorzugsweise 2.600 mm lang und 300 mm breit (bezogen auf die Auflagefläche, ihre Höhe beträgt bevorzugt 220 mm. So dimensioniert können sie ohne Probleme Achslasten bis zu 250 kN (25 t) tragen.The thresholds are preferably 2,600 mm long and 300 mm wide (based on the contact surface, your Height is preferred 220 mm. So dimensioned they can support axle loads of up to 250 kN (25 t) without any problems.
Die Erfindung wird nachfolgend von mehreren Ausführungsbeispielen näher erläutert.The invention is described below by several embodiments explained in more detail.
Aus
Die
Die
Die grundsätzliche Gestaltung der Rippenplatten
Die Spurhalter
Mit den
- 11
- Betonschwelleconcrete sleeper
- 22
- Bohrungen für Schraubenverdübelungdrilling for screw anchoring
- 33
- Ankerschieneanchor rail
- 44
- Schraubendübelscrew anchors
- 55
- HammerkopfschraubeT-head bolt
- 66
- Rippenplatterib plate
- 77
- Zwischenlageliner
- 88th
- SpurhalterAnchor arm
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE20320033U DE20320033U1 (en) | 2003-12-24 | 2003-12-24 | Concrete sleeper, has first track secured via screw dowels and second track secured to anchor rails by hammerhead screws |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE20320033U DE20320033U1 (en) | 2003-12-24 | 2003-12-24 | Concrete sleeper, has first track secured via screw dowels and second track secured to anchor rails by hammerhead screws |
Publications (1)
Publication Number | Publication Date |
---|---|
DE20320033U1 true DE20320033U1 (en) | 2004-03-11 |
Family
ID=32010870
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE20320033U Expired - Lifetime DE20320033U1 (en) | 2003-12-24 | 2003-12-24 | Concrete sleeper, has first track secured via screw dowels and second track secured to anchor rails by hammerhead screws |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE20320033U1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
ES2380963A1 (en) * | 2012-04-04 | 2012-05-22 | Tecsa Empresa Constructora, S.A. | Device for the installation of a third lane on an existing railway travie. (Machine-translation by Google Translate, not legally binding) |
ES2397026R1 (en) * | 2011-03-25 | 2013-07-04 | Vias Y Construcciones S A | Prestressed concrete sleeper for three simultaneous track widths with a common thread. |
ES2452479R1 (en) * | 2012-02-21 | 2014-05-13 | Prefabricaciones Y Contratas, S.A.U. (Precon, S.A.U.) | MIXED WIDTH CROSSBOARD WITH SYNTHETIC FASTENERS FOR RAILS |
GB2554348A (en) * | 2016-09-13 | 2018-04-04 | Univ Nottingham | Tram, light rail and guided bus systems and components |
RU197625U1 (en) * | 2020-03-16 | 2020-05-18 | Общество с ограниченной ответственностью "ГРУППА ОТР" | Reinforced concrete rail base with a U-shaped profile |
RU198291U1 (en) * | 2020-03-16 | 2020-06-30 | Общество с ограниченной ответственностью "ГРУППА ОТР" | Reinforced concrete rail base with a U-shaped profile |
-
2003
- 2003-12-24 DE DE20320033U patent/DE20320033U1/en not_active Expired - Lifetime
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
ES2397026R1 (en) * | 2011-03-25 | 2013-07-04 | Vias Y Construcciones S A | Prestressed concrete sleeper for three simultaneous track widths with a common thread. |
ES2452479R1 (en) * | 2012-02-21 | 2014-05-13 | Prefabricaciones Y Contratas, S.A.U. (Precon, S.A.U.) | MIXED WIDTH CROSSBOARD WITH SYNTHETIC FASTENERS FOR RAILS |
ES2380963A1 (en) * | 2012-04-04 | 2012-05-22 | Tecsa Empresa Constructora, S.A. | Device for the installation of a third lane on an existing railway travie. (Machine-translation by Google Translate, not legally binding) |
GB2554348A (en) * | 2016-09-13 | 2018-04-04 | Univ Nottingham | Tram, light rail and guided bus systems and components |
GB2554348B (en) * | 2016-09-13 | 2021-10-20 | Univ Nottingham | Tram, light rail and guided bus systems and components |
RU197625U1 (en) * | 2020-03-16 | 2020-05-18 | Общество с ограниченной ответственностью "ГРУППА ОТР" | Reinforced concrete rail base with a U-shaped profile |
RU198291U1 (en) * | 2020-03-16 | 2020-06-30 | Общество с ограниченной ответственностью "ГРУППА ОТР" | Reinforced concrete rail base with a U-shaped profile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2133467B1 (en) | Laterally adjustable fixing of a rail to a sleeper | |
DE19607339A1 (en) | Device for the highly elastic fastening of railroad tracks to standard concrete sleepers | |
DE4115935C2 (en) | Track construction for magnetic levitation vehicles | |
DE202006020567U1 (en) | System for fastening a rail | |
DE2727644C2 (en) | Level crossing at the same level as the rails | |
EP3337928B1 (en) | Device for forming a level crossing | |
DE8533479U1 (en) | Fastening device for running rails | |
EP0794290A1 (en) | Laterally adjustable elastic rail fastening | |
DE20320033U1 (en) | Concrete sleeper, has first track secured via screw dowels and second track secured to anchor rails by hammerhead screws | |
EP0920554B1 (en) | Frog for point switches und crossings | |
EP0298904B1 (en) | Arrangement for securing the position of steel sleepers | |
DE6905246U (en) | SHAPED BODY FOR EQUAL RAIL TRANSITION | |
DE3536966A1 (en) | RAIL BASE | |
DE19931048A1 (en) | Track for rail-bound vehicles and soundproofing element therefor | |
EP0718438A1 (en) | Track superstructure comprising a continuous supporting slab and individual rail fastening means | |
DE3840959A1 (en) | Noise protection device for railway rails | |
DE19813258C1 (en) | Steel railway bridging frame | |
DE29520973U1 (en) | Ballastless track system | |
WO1999037861A1 (en) | Collar coach screw | |
DE10128844B4 (en) | Device for fastening rails on a solid surface | |
DE19517112A1 (en) | Track superstructure with continuous support plate and individual fastening devices for the rails | |
DE10148727A1 (en) | Arrangement for mounting rails, in particular, in tunnels comprises a plurality of sleepers which only partially rest on the base structure, and are provided with rail clamping/positioning elements | |
DE10032437A1 (en) | Manufacturing process for derailment guard for railways with derailment guard profiles positioned on substructure on either side of rails, and with asphalt/concrete filling the gaps | |
DE3329788C2 (en) | Lane for lane buses | |
DE4004452A1 (en) | METHOD FOR TRACKING STABLE STABILITY OF AT LEAST THREE TRACKS LAYED AT A SMALL DISTANCE |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R207 | Utility model specification |
Effective date: 20040415 |
|
R081 | Change of applicant/patentee |
Owner name: RAILBETON LEONHARDT & HAAS KG, DE Free format text: FORMER OWNER: LEONHARDT & SOHN KG, 09114 CHEMNITZ, DE Effective date: 20040304 |
|
R150 | Term of protection extended to 6 years |
Effective date: 20061129 |
|
R157 | Lapse of ip right after 6 years |
Effective date: 20100701 |