CN209339179U - Levelling pre-buried structure for large scale equipment installation - Google Patents

Levelling pre-buried structure for large scale equipment installation Download PDF

Info

Publication number
CN209339179U
CN209339179U CN201821982632.2U CN201821982632U CN209339179U CN 209339179 U CN209339179 U CN 209339179U CN 201821982632 U CN201821982632 U CN 201821982632U CN 209339179 U CN209339179 U CN 209339179U
Authority
CN
China
Prior art keywords
steel plates
base steel
deep hole
large scale
fixture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821982632.2U
Other languages
Chinese (zh)
Inventor
张文凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wisdri Engineering and Research Incorporation Ltd
Original Assignee
Wisdri Engineering and Research Incorporation Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wisdri Engineering and Research Incorporation Ltd filed Critical Wisdri Engineering and Research Incorporation Ltd
Priority to CN201821982632.2U priority Critical patent/CN209339179U/en
Application granted granted Critical
Publication of CN209339179U publication Critical patent/CN209339179U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model relates to a kind of levelling pre-buried structures for large scale equipment installation, including concrete foundation, final grouting concrete, base steel plates, pedestal steel plate and screw rod, concrete foundation top surface is equipped on sinking step and step surface and offers deep hole, base steel plates bottom surface is welded at least two anchor feet and at least three fixture nuts, anchor foot and deep hole are corresponded and are protruded into deep hole, screw rod stretches out after corresponding and passing through base steel plates and fixture nut cooperation with fixture nut, pedestal steel plate and fixture nut are corresponded and are placed on step surface, base steel plates are by screw support on pedestal steel plate, the fastening nut for compressing base steel plates is cased on screw rod, final grouting Concrete Filled is in deep hole and sinking step and height reaches base steel plates position.The structure can adjust the flatness of base steel plates, and installation effectiveness is high, easy for construction.

Description

Levelling pre-buried structure for large scale equipment installation
Technical field
The utility model belongs to large scale equipment installing area, and in particular to a kind of levelling for large scale equipment installation is pre- Bury structure.
Background technique
When large scale equipment is installed, generally there are built-in fitting, the absolute altitude control of built-in fitting is a time-consuming job, if Absolute altitude can leave security risk, and under the action of construction loads and concrete lateral pressure there are if relatively large deviation, if in advance If embedded part is not fixed firmly, the position of built-in fitting and absolute altitude can also generate relatively large deviation.
Utility model content
The purpose of the utility model is to provide a kind of levelling pre-buried structure for large scale equipment installation, which can be adjusted The flatness of whole base steel plates, installation effectiveness is high, easy for construction.
The technical scheme adopted by the utility model is
A kind of levelling pre-buried structure for large scale equipment installation, including concrete foundation, final grouting concrete, base Plinth steel plate, pedestal steel plate and screw rod, concrete foundation top surface are equipped on sinking step and step surface and offer deep hole, base steel plates Bottom surface is welded at least two anchor feet and at least three fixture nuts, and anchor foot and deep hole are corresponded and protruded into deep hole, Screw rod stretches out after corresponding and passing through base steel plates and fixture nut cooperation with fixture nut, pedestal steel plate and fixture nut one One is corresponding and be placed on step surface, and base steel plates are cased on pedestal steel plate, on screw rod by screw support for will be basic The fastening nut that steel plate compresses, final grouting Concrete Filled is in deep hole and sinking step and height reaches base steel plates position It sets.
Further, when three fixture nuts are welded and fixed in base steel plates bottom surface, one of fixture nut is located at basis On the lateral symmetry axis of steel plate, lateral symmetry axial symmetry of other two fixture nut about base steel plates, three fixture nuts It is distributed in the two sides of the longitudinally asymmetric axis of base steel plates.
Further, when two anchor feet are welded and fixed in base steel plates bottom surface, lateral symmetry axis of the anchor foot about base steel plates Symmetrically and along the longitudinally asymmetric axis of base steel plates arrange.
Further, the pouring mouth for pouring final grouting concrete is offered in base steel plates.
Further, mouth is poured at least to be provided with above deep hole.
The beneficial effects of the utility model are:
When installation foundation steel plate, by adjusting multiple screw rods, to control the spacing of base steel plates Yu pedestal steel plate, then Screwing fastening nut immobilizing foundation steel plate loosens it no longer, and the flatness of base steel plates can be adjusted, do not only reached required Installation accuracy, also improve in-site installation efficiency;When pouring final grouting concrete, due to base steel plates fixed it is additional from The flowing of body gravity, mud will not have any impact to fastener inserts, parch completely to mud, and cutting screw rod can be complete It is easy for construction at construction.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model embodiment.
Fig. 2 is the cross-sectional view of A-A in Fig. 1.
Fig. 3 is the top view of Fig. 1.
In figure: 1- concrete foundation;2- final grouting concrete;3- anchor foot;4- fixture nut;5- screw rod;The basis 6- steel Plate;7- pedestal steel plate;8- fastening nut;9- pours mouth.
Specific embodiment
The utility model is further described with reference to the accompanying drawings and examples.
As shown in Figure 1 to Figure 3, a kind of levelling pre-buried structure for large scale equipment installation, including concrete foundation 1, Final grouting concrete 2, base steel plates 6, pedestal steel plate 7 and screw rod 5,1 top surface of concrete foundation are equipped with sinking step and step Deep hole is offered on face, 6 bottom surface of base steel plates is welded at least two anchor feet 3 and at least three fixture nuts 4, anchor foot 3 It corresponds and is protruded into deep hole with deep hole, screw rod 5 and fixture nut 4 correspond and pass through base steel plates 6 and fixture nut 4 It is stretched out after cooperation, pedestal steel plate 7 and fixture nut 4 are corresponded and be placed on step surface, and base steel plates 6 pass through screw rod 5 Support is cased with the fastening nut 8 for compressing base steel plates 6 on pedestal steel plate 7 on screw rod 5, final grouting concrete 2 is filled In deep hole and sinking step and height reaches 6 position of base steel plates.When installation foundation steel plate 6, by adjusting multiple screw rods 5, To control the spacing of base steel plates 6 Yu pedestal steel plate 7, then screwing 8 immobilizing foundation steel plate 6 of fastening nut keeps it no longer loose It is dynamic, the flatness of base steel plates 6 can be adjusted, do not only reached required installation accuracy, also improve in-site installation efficiency;It pours When building final grouting concrete 2, since base steel plates 6 have fixed additional self gravitation effect, the flowing of mud will not be to pre-buried Component has any impact, and parches completely to mud, and cutting screw rod 5 can be completed construction, easy for construction.
As shown in figure 3, in the present embodiment, when three fixture nuts 4 are welded and fixed in 6 bottom surface of base steel plates, one of them Fixture nut 4 is located on the lateral symmetry axis of base steel plates 6, other two fixture nut 4 is about the lateral symmetry of base steel plates 6 Axial symmetry, three fixture nuts 4 are distributed in the two sides of the longitudinally asymmetric axis of base steel plates 6.Before pouring final grouting concrete 2, When adjusting base steel plates 6, using three groups of fixture nuts 4, fastening nut 8, screw rod 5 and pedestal steel plate 7, supporting & stablizing, adjustment time Number is few.
As shown in figure 3, in the present embodiment, when two anchor feet 3 are welded and fixed in 6 bottom surface of base steel plates, anchor foot 3 is about basis The lateral symmetry axial symmetry of steel plate 6 and along the longitudinally asymmetric axis of base steel plates 6 arrange.
As shown in figure 3, in the present embodiment, the pouring for pouring final grouting concrete 2 is offered in base steel plates 6 Mouth 9.There are gaps with step at base steel plates 6 edge, usually pour final grouting concrete 2 from gap, but basic steel 6 area of plate is larger, and if only pouring from edge, middle section molding is bad, opens up in base steel plates 6 and pours mouth 9, improves two Planarization after secondary 2 pouring molding of placing concrete.
As shown in figure 3, in the present embodiment, pouring mouth 9 and being at least provided with above deep hole, deep hole is facilitated to pour.
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description, And all these modifications and variations all should belong to the protection scope of the appended claims for the utility model.

Claims (5)

1. a kind of levelling pre-buried structure for large scale equipment installation, it is characterised in that: including concrete foundation, final grouting Concrete, base steel plates, pedestal steel plate and screw rod, concrete foundation top surface are equipped on sinking step and step surface and offer depth Hole, base steel plates bottom surface are welded at least two anchor feet and at least three fixture nuts, anchor foot and deep hole correspond and It protrudes into deep hole, screw rod stretches out after corresponding and passing through base steel plates and fixture nut cooperation with fixture nut, pedestal steel plate It corresponds and is placed on step surface with fixture nut, base steel plates on pedestal steel plate, are covered by screw support on screw rod There is the fastening nut for compressing base steel plates, final grouting Concrete Filled is in deep hole and sinking step and height reaches Base steel plates position.
2. the levelling pre-buried structure for large scale equipment installation as described in claim 1, it is characterised in that: base steel plates bottom When three fixture nuts are welded and fixed in face, one of fixture nut is located on the lateral symmetry axis of base steel plates, other two Lateral symmetry axial symmetry of the fixture nut about base steel plates, three fixture nuts are distributed in the longitudinally asymmetric axis of base steel plates Two sides.
3. the levelling pre-buried structure for large scale equipment installation as described in claim 1, it is characterised in that: base steel plates bottom When two anchor feet are welded and fixed in face, lateral symmetry axial symmetry of the anchor foot about base steel plates and the longitudinally asymmetric axis along base steel plates Arrangement.
4. the levelling pre-buried structure for large scale equipment installation as described in claim 1, it is characterised in that: in base steel plates Offer the pouring mouth for pouring final grouting concrete.
5. the levelling pre-buried structure for large scale equipment installation as claimed in claim 4, it is characterised in that: pour mouth at least It is provided with above deep hole.
CN201821982632.2U 2018-11-28 2018-11-28 Levelling pre-buried structure for large scale equipment installation Active CN209339179U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821982632.2U CN209339179U (en) 2018-11-28 2018-11-28 Levelling pre-buried structure for large scale equipment installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821982632.2U CN209339179U (en) 2018-11-28 2018-11-28 Levelling pre-buried structure for large scale equipment installation

Publications (1)

Publication Number Publication Date
CN209339179U true CN209339179U (en) 2019-09-03

Family

ID=67749887

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821982632.2U Active CN209339179U (en) 2018-11-28 2018-11-28 Levelling pre-buried structure for large scale equipment installation

Country Status (1)

Country Link
CN (1) CN209339179U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114754232A (en) * 2022-03-24 2022-07-15 中国船舶重工集团公司第七一九研究所 Leveling device and method for T-shaped guide rail

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114754232A (en) * 2022-03-24 2022-07-15 中国船舶重工集团公司第七一九研究所 Leveling device and method for T-shaped guide rail
CN114754232B (en) * 2022-03-24 2024-06-18 中国船舶重工集团公司第七一九研究所 Leveling device and method for T-shaped guide rail

Similar Documents

Publication Publication Date Title
CN101871265B (en) Flat shim plate-adjustable grouting installation method
CN203452266U (en) Fixing and leveling structure of H section steel column
CN207331736U (en) A kind of foundation bolt once grouting fixture
CN201896365U (en) Installing and fixing device for flat plate pre-embedded piece on surface of concrete
CN201326876Y (en) Tail regulator
CN102587410B (en) Design and construction method of reinforced concrete retaining wall
CN209339179U (en) Levelling pre-buried structure for large scale equipment installation
JP5635048B2 (en) Basics for installing solar panels
CN107386316A (en) A kind of foundation bolt once grouting fixture and its construction method
CA2597054A1 (en) System for stabilizing gravity-based offshore structures
CN203924103U (en) The outdoor GIS post-install of a kind of assembled height-adjustable
CN204151820U (en) Stone bolt location and installation support
CN207244435U (en) A kind of anchor and height-adjustable supports suitable for beam bridge
CN209384274U (en) A kind of adjustable well lid of height with flap-type splicing pedestal
CN209384275U (en) A kind of height-adjustable manhole cover structure
CN103669383A (en) Method for installing and leveling caisson on seabed ground
CN103850513A (en) Outdoor rod body construction method
CN203346897U (en) Foundation raft embedded steel column positioning support
CN203769317U (en) Complete adjustable water stopping screw kit
CN203639934U (en) Pre-buried positioning device for equipment foundation bolt
CN201455643U (en) Leveling device for installation of equipment
CN103422429B (en) Bridge pier separate type subtracts the construction method of shock insulation support system
CN102653947B (en) Underground embedded steel component limiting straightening construction method
CN204690786U (en) Prefabricated pit shaft
CN105484282A (en) Leveling device inside cup-shaped foundation of pipe steel support and usage method of leveling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant