CN205677623U CN201620633138.XU CN201620633138U CN205677623U CN 205677623 U CN205677623 U CN 205677623U CN 201620633138 U CN201620633138 U CN 201620633138U CN 205677623 U CN205677623 U CN 205677623U
Authority
CN
China
Prior art keywords
cable tunnel
armored concrete
compages
buttress
equipment foundations
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620633138.XU
Other languages
Chinese (zh)
Inventor
翟景国
韩根伟
陈兴伟
卢敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Electric Power Design and Consulting Co Ltd
Original Assignee
Sichuan Electric Power Design and Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Electric Power Design and Consulting Co Ltd filed Critical Sichuan Electric Power Design and Consulting Co Ltd
Priority to CN201620633138.XU priority Critical patent/CN205677623U/en
Application granted granted Critical
Publication of CN205677623U publication Critical patent/CN205677623U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model relates to cable tunnel and Equipment Foundations compages, including cable tunnel, described cable tunnel periphery is made up of armored concrete, and the armored concrete of cable tunnel is arranged on below ground, the armored concrete on top, cable tunnel is top board, described top board top is provided with bassets, and for installing the buttress of electrical equipment, the described buttress armored concrete peripheral with cable tunnel is structure as a whole.This cable tunnel and Equipment Foundations compages, by cable tunnel and large equipment base, the coadunation of upper and lower parallel arrangement, cable tunnel and Equipment Foundations associating pouring construction, it is possible to reduce quantities saves material, and reduces place and take.

Description

Cable tunnel and Equipment Foundations compages
Technical field
The utility model relates to big-and-middle-sized transformer substation construction, specifically a kind of cable tunnel being suitable to city use and ground The compages that Equipment Foundations are integrated.
Background technology
Incity, city transformer station mostly is indoor station now, and the way at general indoor station is: cable tunnel and comprehensive power distribution building In radiator, the large equipment base such as main transformer separately positioned, construction.This causes cable tunnel and equipment to install needs point She Zhi be not basic, and then increase quantities and material usage.And, cable tunnel is arranged on comprehensive power distribution building external demand and takies volume Outer place, this can dramatically increase cost in the city of an inch of land is an inch of gold, also result in land resource waste.
Utility model content
Technical problem to be solved in the utility model is: provide a kind of cable tunnel and Equipment Foundations compages, energy Reduce corresponding quantities, reduce place and take.
The utility model solves its technical problem and be the technical scheme is that
Cable tunnel and Equipment Foundations compages, including cable tunnel, described cable tunnel periphery is by armored concrete Constituting, and the armored concrete of cable tunnel being arranged on below ground, the armored concrete on top, cable tunnel is top board, described Top board top is provided with bassets, and for installing the buttress of electrical equipment, the steel of described buttress and cable tunnel periphery Reinforced concrete is structure as a whole.
Further, including paired described buttress, described cable tunnel cross section is rectangle, and described paired buttress is respectively It is positioned at the left and right sides armored concrete top of cable tunnel cross section rectangle.
Further, along described cable tunnel bearing of trend, being provided with at least two to described buttress, described electrical equipment is Radiator or main transformer.
The beneficial effects of the utility model are: this cable tunnel and Equipment Foundations compages, by cable tunnel and large-scale Equipment Foundations, the coadunation of upper and lower parallel arrangement, cable tunnel and Equipment Foundations combine pouring construction, it is possible to reduce engineering Amount saves material, and reduces place and take.
Brief description
Fig. 1 is cable tunnel of the present utility model and the schematic top plan view of Equipment Foundations compages;
Fig. 2 is that the master of cable tunnel of the present utility model and Equipment Foundations compages regards generalized section;
In figure, reference is: the 2nd, top board 21, buttress the 1st, cable tunnel.
Detailed description of the invention
With embodiment, the utility model is further illustrated below in conjunction with the accompanying drawings:
Cable tunnel and Equipment Foundations compages, including cable tunnel 2, described cable tunnel 2 periphery is by reinforced concrete Soil is constituted, and the armored concrete of cable tunnel 2 is arranged on below ground, and the armored concrete on top, cable tunnel 2 is top board 21, described top board 21 top is provided with bassets, and for installing the buttress 1 of electrical equipment, described buttress 1 and cable tunnel The armored concrete of road 2 periphery is structure as a whole.
As shown in Figure 1, 2: this cable tunnel and Equipment Foundations compages, its cable tunnel 2 is made up of armored concrete, And it is arranged on below ground, cable tunnel 2 is for the cable laying of transformer station, the reinforced concrete structure on top, cable tunnel 2 For top board 21, top board 21 top is provided with buttress 1, and buttress 1 bassets, for installing the equipment of transformer station, such as radiator Or main transformer.
Buttress 1 is structure as a whole with the armored concrete of cable tunnel 2 periphery, is i.e. buttress 1 and cable tunnel 2 periphery is adopted With overall bar-mat reinforcement, and water and build up an entirety, make cable tunnel 2 have Equipment Foundations function.
The layout type of buttress 1 is preferably it may be that include paired described buttress 1, and described cable tunnel 2 cross section is square Shape, described paired buttress 1 lays respectively at the left and right sides armored concrete top of cable tunnel 2 cross section rectangle.
According to main equipment feature to be mounted, can be along described cable tunnel 2 bearing of trend, be provided with at least two right Described buttress 1.Such as embodiment illustrated in fig. 1, is provided with altogether six pairs of buttresses 1, all buttresses 1 along cable tunnel 2 bearing of trend For jointly having supported ground equipment.

Claims (3)

1. cable tunnel and Equipment Foundations compages, it is characterised in that include cable tunnel (2), described cable tunnel (2) outward Enclose and be made up of armored concrete, and the armored concrete of cable tunnel (2) is arranged on below ground, cable tunnel (2) top Armored concrete is top board (21), and described top board (21) top is provided with bassets, and for install electrical equipment Pier (1), described buttress (1) is structure as a whole with the armored concrete of cable tunnel (2) periphery.
2. cable tunnel as claimed in claim 1 and Equipment Foundations compages, it is characterised in that include paired described Pier (1), described cable tunnel (2) cross section is rectangle, and described paired buttress (1) lays respectively at cable tunnel (2) cross section rectangle Left and right sides armored concrete top.
3. cable tunnel as claimed in claim 2 and Equipment Foundations compages, it is characterised in that along described cable tunnel (2) bearing of trend, is provided with at least two to described buttress (1), and described electrical equipment is radiator or main transformer.
CN201620633138.XU 2016-06-23 2016-06-23 Cable tunnel and equipment foundations compages Active CN205677623U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620633138.XU CN205677623U (en) 2016-06-23 2016-06-23 Cable tunnel and equipment foundations compages

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620633138.XU CN205677623U (en) 2016-06-23 2016-06-23 Cable tunnel and equipment foundations compages

Publications (1)

Publication Number Publication Date
CN205677623U true CN205677623U (en) 2016-11-09

Family

ID=57429504

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620633138.XU Active CN205677623U (en) 2016-06-23 2016-06-23 Cable tunnel and equipment foundations compages

Country Status (1)

Country Link
CN (1) CN205677623U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107171189A (en) * 2017-05-25 2017-09-15 国网山东省电力公司青岛供电公司 A kind of cable tunnel integrated with substation equipment basis

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107171189A (en) * 2017-05-25 2017-09-15 国网山东省电力公司青岛供电公司 A kind of cable tunnel integrated with substation equipment basis

Similar Documents

Publication Publication Date Title
CN203569579U (en) Building foundation
CN105019715A (en) Structure jointly constructed by subway station and buildings
CN201717589U (en) Square grounding device for power pole tower
CN104294845A (en) City comprehensive pipe gallery
CN205677623U (en) Cable tunnel and equipment foundations compages
CN104018513A (en) Method for calculating flexural deflection and cross section bending moment of protective plate foundation in coal mining subsidence area
CN204435337U (en) Workbench and single-pile foundation and offshore work platform
CN204098056U (en) Colliery minery UHV transmission steel tower agent on crack resistance of concrete distortion found
CN207017169U (en) A kind of high-filled subgrade culvert off-loading structure
CN206941562U (en) A kind of geotechnical grid for strengthening being fixedly connected
CN204928674U (en) Build solar photovoltaic power station on tailing storehouse
CN203924605U (en) Be applicable to the indoor built on stilts floor structure of transformer station's flood control transformation
CN103397638A (en) Tie bar for supporting system in high-rigidity integral prestressed fabricated foundation pit support
CN204163100U (en) The linkage of a kind of iron tower of power transmission line and iron tower foundation
CN209508954U (en) A kind of Construction of Civil Engineering small pile
CN203066097U (en) Piled raft foundation structure of stub-type pile bearing platform structure
CN208884300U (en) A kind of subsidence area resistance to deformation express highway pavement structure
CN202500147U (en) Power transmission line enlarged top filling pile base
CN201924370U (en) Valve hall of converter station and foundation of converter transformer area
CN207117060U (en) A kind of protection channel with protection cable
CN203034477U (en) Basic structure of compact type air blower
CN201730106U (en) Power transmission tower composite foundation
CN205063498U (en) Increase beam column
CN204139198U (en) Combination assembled mesolow electric fixtures basis
CN204826853U (en) Structure that subway station and building were built jointly