CN204125829U - Half high-rise unsettled insulation maintenance gap bridge - Google Patents
Half high-rise unsettled insulation maintenance gap bridge Download PDFInfo
- Publication number
- CN204125829U CN204125829U CN201420527130.6U CN201420527130U CN204125829U CN 204125829 U CN204125829 U CN 204125829U CN 201420527130 U CN201420527130 U CN 201420527130U CN 204125829 U CN204125829 U CN 204125829U
- Authority
- CN
- China
- Prior art keywords
- platform
- rise
- bracing frame
- gap bridge
- half high
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000012423 maintenance Methods 0.000 title claims abstract description 26
- 238000009413 insulation Methods 0.000 title claims abstract description 25
- 230000001681 protective effect Effects 0.000 claims abstract description 11
- 241000282326 Felis catus Species 0.000 claims description 4
- 238000010586 diagram Methods 0.000 description 3
- 239000000725 suspension Substances 0.000 description 3
- 230000007812 deficiency Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of half high-rise unsettled insulation maintenance gap bridge, include the bracing frame of two groups, four stocks in each group bracing frame surround a vertical quadra, then utilized by each quarter butt frame padlock on four stocks, described platform travelling carriage be erected at two bracing frame middle and upper parts and be placed in each bracing frame be on conplane two quarter butts, described platform is propped up by landing slab and landing slab and is configured to, bracing frame top is provided with collapsible protection hurdle, also include the rail horizontal rod of protective guard above connection two bracing frames, rail horizontal rod and protective guard form one and enclose structure, the platform of half high-rise unsettled insulation maintenance gap bridge is also provided with height adjusting stool.The utility model has detachable, easy-to-assemble feature, when solving operation because of cannot cross over middle obstacle bring unnecessary difficulty, improve operating efficiency, safety factor, reduce the labour intensity of staff.
Description
Technical field
The utility model relates to a kind of maintenance and passes a bridge, particularly a kind of half high-rise unsettled insulation maintenance gap bridge.
Background technology
Along with the development of economy, new challenge is proposed to electric power, ensure supply of electric power, reduce power off time, become the top priority of power industry.Traditional operating type can not meet the demand of economic development.As GIS substation bus bar both sides are difficult to cross when overhauling, particularly ascend a height during the overhaul of the equipments of bus overhead more difficult, traditional operating type needs operating personnel from the place of other clear around the opposite side to bus, as my office half high-rise unsettled transformer station, just necessary from second floor to Stall when need arrive another side operation during operation, again from Stall to second floor, sometimes overhaul a commute and want tens of times, not only reduce operating efficiency, but also add labour intensity and the power off time of operating personnel.
Utility model content
The purpose of this utility model is to overcome the deficiencies in the prior art part, and a kind of leap that can realize obstruction is provided, and a platform worked above obstruction can be provided for staff, thus save labour, and ensure that half of the safety of staff high-rise unsettled insulation maintenance gap bridge.
A kind of half high-rise unsettled insulation maintenance gap bridge, include the bracing frame of two groups, cat ladder, platform travelling carriage, platform, the bracing frame of two groups is by being made up of the quarter butt of four draw money on credit strut and complex roots respectively, four stocks in each group bracing frame surround a vertical quadra, then utilized by each quarter butt frame padlock on four stocks, described platform travelling carriage be erected at two bracing frame middle and upper parts and be placed in each bracing frame be on conplane two quarter butts, described platform travelling carriage utilizes frame padlock on quarter butt, the cross section of described platform travelling carriage is the structure of similar G type, described platform is propped up by landing slab and landing slab and is configured to, landing slab support is the cross section G type structure identical with the cross section of platform travelling carriage, both interlock with the use of, with the use of time by platform travelling carriage one end platform is pushed, landing slab is fixed on landing slab support, bracing frame top is provided with collapsible protection hurdle, also include the rail horizontal rod of protective guard above connection two bracing frames, rail horizontal rod and protective guard form one and enclose structure, the platform of half high-rise unsettled insulation maintenance gap bridge is also provided with height adjusting stool, described height adjusting stool is locked on landing slab, the platform both ends or one end of half high-rise unsettled insulation maintenance gap bridge are provided with side ladder.
Half high-rise unsettled insulation maintenance gap bridge of the present utility model, first two groups of bracing frames are assembled in respectively the obstruction both sides needing to cross over, then locking is used for the position of the quarter butt of support platform travelling carriage and locks as required, set up platform travelling carriage and locked, landing slab support is then utilized by platform to be pushed by platform in platform travelling carriage, then put up side ladder and mix up the height on collapsible protection hurdle according to the height situation used, connect rail horizontal rod, put the installation that namely height adjusting stool realizes this half high-rise unsettled insulation maintenance gap bridge well.
Described collapsible protection hurdle is be made up of the pipe fitting be nested between two together, locks after mixing up height with latch.
Described collapsible protection hurdle and the connection between bracing frame are docked frame and are tipped capable connection in for both adopt.
Described platform, for be made up of multistage, can lay one or more snippets flexibly as required, and the two ends landing slab of landing slab is fixed card and is located on platform travelling carriage.
Utilized by platform landing slab to be fixedly stuck in platform travelling carriage, the stability of this platform can be improved, avoid, along platform travelling carriage from two ends landing, causing security incident.
Described platform travelling carriage is locked on the quarter butt of bracing frame by platform slipway clamp.
Described stock is mutually assembled by several sections.
Stock is adopted several sections assembled, the length of a joint stock can be reduced, thus convenient carrying, store, transport.
Described rail horizontal rod is fixed on protective guard by universal fastener.
Height adjusting stool is provided with lap belt suspension arrangement.
In sum, the utility model following advantage compared to existing technology:
Half high-rise unsettled insulation maintenance gap bridge of the present utility model, there is detachable, easy-to-assemble feature, when solving operation because of cannot cross over middle obstacle bring unnecessary difficulty, improve operating efficiency, safety factor, reduce the labour intensity of staff.Bridge floor adopts sliding type, and according to the needs of site work, can build required bridge floor, bridge floor can fix Special high-low stool, and height adjusting stool is furnished with lap belt suspension arrangement, completely solves the safety problem of staff.Overall employing is detachable, convenient, fast when building.Multiple work-yard all adopts an insulating gap bridge, cost-saving.The use of insulating gap bridge, simplifies job step, improves operating efficiency and service technique level, has high using value and marketing prospect.
Accompanying drawing explanation
Fig. 1 is half high-rise unsettled insulation maintenance gap bridge structural representation of the present utility model.
Fig. 2 platform travelling carriage coordinates schematic diagram with landing slab support.
Fig. 3 is height adjusting stool schematic diagram.
Fig. 4 is landing slab fixing structure schematic diagram
Fig. 5 is platform slipway clamp structural representation
Fig. 6 is universal fastener structural representation.
Fig. 7 is side ladder structural representation.
Label declaration 1 bracing frame 11 is drawn money on credit strut 12 quarter butt 2 cat ladder 3 platform travelling carriage 4 platform 41 landing slab 42 landing slab support 5 collapsible protection hurdle 6 rail horizontal rod 7 height adjusting stool.
Detailed description of the invention
Below in conjunction with embodiment, the utility model is described in more detail.
Embodiment 1
A kind of half high-rise unsettled insulation maintenance gap bridge, include the bracing frame 1 of two groups, cat ladder 2, platform travelling carriage 3, platform 4, the bracing frame of two groups is by being made up of the quarter butt 12 of four draw money on credit strut 11 and complex roots respectively, four stocks in each group bracing frame surround a vertical quadra, then utilized by each quarter butt frame padlock on four stocks, described platform travelling carriage be erected at two bracing frame middle and upper parts and be placed in each bracing frame be on conplane two quarter butts, described platform travelling carriage utilizes frame padlock on quarter butt, the cross section of described platform travelling carriage is the structure of similar G type, described platform 4 is made up of landing slab 41 and landing slab support 42, landing slab support is the cross section G type structure identical with the cross section of platform travelling carriage, both interlock with the use of, with the use of time by platform travelling carriage one end platform is pushed, landing slab 41 is fixed on landing slab support 42, bracing frame top is provided with collapsible protection hurdle 5, also include the rail horizontal rod 6 of protective guard above connection two bracing frames, rail horizontal rod and protective guard form one and enclose structure, the platform of half high-rise unsettled insulation maintenance gap bridge is also provided with height adjusting stool 7, described height adjusting stool is locked on landing slab, the platform both ends or one end of half high-rise unsettled insulation maintenance gap bridge are provided with side ladder.Described collapsible protection hurdle is be made up of the pipe fitting be nested between two together, locks after mixing up height with latch.Described collapsible protection hurdle and the connection between bracing frame are docked frame and are tipped capable connection in for both adopt.Described platform, for be made up of multistage, can lay one or more snippets flexibly as required, and the two ends landing slab of landing slab is fixed card and is located on platform travelling carriage.Described platform travelling carriage is locked on the quarter butt of bracing frame by platform slipway clamp.Described stock is mutually assembled by several sections.Described rail horizontal rod is fixed on protective guard by universal fastener and connects.Height adjusting stool is provided with lap belt suspension arrangement.
It is same as the prior art that the present embodiment does not state part.
Claims (7)
1. one and half high-rise unsettled insulation maintenance gap bridges, it is characterized in that: the bracing frame including two groups, cat ladder, platform travelling carriage, platform, the bracing frame of two groups is by being made up of the quarter butt of four draw money on credit strut and complex roots respectively, four stocks in each group bracing frame surround a vertical quadra, then utilized by each quarter butt frame padlock on four stocks, described platform travelling carriage be erected at two bracing frame middle and upper parts and be placed in each bracing frame be on conplane two quarter butts, described platform travelling carriage utilizes frame padlock on quarter butt, the cross section of described platform travelling carriage is the structure of similar G type, described platform is propped up by landing slab and landing slab and is configured to, landing slab support is the cross section G type structure identical with the cross section of platform travelling carriage, both interlock with the use of, with the use of time by platform travelling carriage one end platform is pushed, landing slab is fixed on landing slab support, bracing frame top is provided with collapsible protection hurdle, also include the rail horizontal rod of protective guard above connection two bracing frames, rail horizontal rod and protective guard form one and enclose structure, the platform of half high-rise unsettled insulation maintenance gap bridge is also provided with height adjusting stool, described height adjusting stool is locked on landing slab, the platform both ends or one end of half high-rise unsettled insulation maintenance gap bridge are provided with side ladder.
2. half high-rise unsettled insulation maintenance gap bridge according to claim 1, is characterized in that: described collapsible protection hurdle is be made up of the pipe fitting be nested between two together, locks after mixing up height with latch.
3. half high-rise unsettled insulation maintenance gap bridge according to claim 2, is characterized in that: described collapsible protection hurdle and the connection between bracing frame are docked frame and tipped capable connection in for both adopt.
4. half high-rise unsettled insulation maintenance gap bridge according to claim 3, it is characterized in that: described platform is for be made up of multistage, can lay one or more snippets as required flexibly, the two ends landing slab of landing slab is fixed card and is located on platform travelling carriage.
5. half high-rise unsettled insulation maintenance gap bridge according to claim 4, is characterized in that: described platform travelling carriage is locked on the quarter butt of bracing frame by platform slipway clamp.
6. half high-rise unsettled insulation maintenance gap bridge according to claim 5, is characterized in that: described stock is for mutually assembled by several sections.
7. half high-rise unsettled insulation maintenance gap bridge according to claim 6, is characterized in that: described rail horizontal rod is fixed on protective guard by universal fastener.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420527130.6U CN204125829U (en) | 2014-09-15 | 2014-09-15 | Half high-rise unsettled insulation maintenance gap bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420527130.6U CN204125829U (en) | 2014-09-15 | 2014-09-15 | Half high-rise unsettled insulation maintenance gap bridge |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204125829U true CN204125829U (en) | 2015-01-28 |
Family
ID=52382199
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420527130.6U Expired - Fee Related CN204125829U (en) | 2014-09-15 | 2014-09-15 | Half high-rise unsettled insulation maintenance gap bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204125829U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104810771A (en) * | 2015-05-13 | 2015-07-29 | 国网辽宁省电力有限公司盘锦供电公司 | Insulated gap bridge for bus sleeves |
CN105644736A (en) * | 2015-12-29 | 2016-06-08 | 广船国际有限公司 | Side transverse seam construction platform |
CN105666451A (en) * | 2016-04-12 | 2016-06-15 | 安徽安凯汽车股份有限公司 | Combined type gantry climbing frame with safety doors |
CN108239917A (en) * | 2018-02-02 | 2018-07-03 | 珠海及力高空作业设备有限公司 | A kind of Zhongting splices the bridge that floats |
CN108442233A (en) * | 2018-02-02 | 2018-08-24 | 珠海及力高空作业设备有限公司 | A kind of Zhongting floats the building method of bridge |
CN109571342A (en) * | 2018-11-22 | 2019-04-05 | 北京无线电测量研究所 | A kind of phased array antenna assembly manipulation device of flexibility |
-
2014
- 2014-09-15 CN CN201420527130.6U patent/CN204125829U/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104810771A (en) * | 2015-05-13 | 2015-07-29 | 国网辽宁省电力有限公司盘锦供电公司 | Insulated gap bridge for bus sleeves |
CN105644736A (en) * | 2015-12-29 | 2016-06-08 | 广船国际有限公司 | Side transverse seam construction platform |
CN105666451A (en) * | 2016-04-12 | 2016-06-15 | 安徽安凯汽车股份有限公司 | Combined type gantry climbing frame with safety doors |
CN108239917A (en) * | 2018-02-02 | 2018-07-03 | 珠海及力高空作业设备有限公司 | A kind of Zhongting splices the bridge that floats |
CN108442233A (en) * | 2018-02-02 | 2018-08-24 | 珠海及力高空作业设备有限公司 | A kind of Zhongting floats the building method of bridge |
CN108442233B (en) * | 2018-02-02 | 2020-07-21 | 珠海及力高空作业设备有限公司 | Construction method of atrium floating bridge |
CN109571342A (en) * | 2018-11-22 | 2019-04-05 | 北京无线电测量研究所 | A kind of phased array antenna assembly manipulation device of flexibility |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204125829U (en) | Half high-rise unsettled insulation maintenance gap bridge | |
CN103711323B (en) | Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing | |
CN202881852U (en) | Suspension bridge cable installation system | |
CN202706503U (en) | Electric lifting discharging platform for main building construction | |
CN204185120U (en) | Mobile unit dolly in place | |
CN204282823U (en) | Detachable discharging platform | |
CN203430009U (en) | Construction hanging basket | |
CN204299157U (en) | The mounted lifting device in attached lifting scaffold side | |
CN105603882A (en) | Continuous beam mid-span closure construction method achieving uninterrupted power of contact line and structure of method | |
CN206887644U (en) | A kind of medium-and low-speed maglev single line beam job platform and edge protection device | |
CN201722937U (en) | Sliding platform for installation of net rack | |
CN104533092A (en) | Truss roof ceiling construction method | |
CN204982628U (en) | Horizontal drawing cable bridge | |
CN205442452U (en) | Convenient hoisting accessory of substation equipment safety | |
CN204325944U (en) | Intercity track cable stayed bridge Diamond-Shape Form Traveler | |
CN204983135U (en) | Elevator discrepancy floor regularization passageway | |
CN203345999U (en) | Special multifunctional lifting frame for busbar bridge | |
CN204959611U (en) | A lifting device for highway construction bridge railing base template | |
CN204877488U (en) | A bracket device that can walk that is used for tunnel no. 2 lining side wall operations | |
CN103896153A (en) | Zig-zag derrick for replacing disconnecting link | |
CN204038917U (en) | Dismountable external hanging service platform | |
CN202705932U (en) | T-beam reinforced hanger frame structure | |
CN203755153U (en) | Simply supported plate bridge bottom plate maintenance construction moving operation platform | |
CN101597956A (en) | Suspended scaffold | |
CN205259558U (en) | Novel scaffold for fitment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150128 Termination date: 20210915 |