CN204125829U - Half high-rise unsettled insulation maintenance gap bridge - Google Patents

Half high-rise unsettled insulation maintenance gap bridge Download PDF

Info

Publication number
CN204125829U
CN204125829U CN201420527130.6U CN201420527130U CN204125829U CN 204125829 U CN204125829 U CN 204125829U CN 201420527130 U CN201420527130 U CN 201420527130U CN 204125829 U CN204125829 U CN 204125829U
Authority
CN
China
Prior art keywords
platform
rise
bracing frame
gap bridge
half high
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420527130.6U
Other languages
Chinese (zh)
Inventor
李积捷
陈展超
钟文贵
郑中楠
徐建
翁晓锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Fuzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Fuzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Fuzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201420527130.6U priority Critical patent/CN204125829U/en
Application granted granted Critical
Publication of CN204125829U publication Critical patent/CN204125829U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of half high-rise unsettled insulation maintenance gap bridge, include the bracing frame of two groups, four stocks in each group bracing frame surround a vertical quadra, then utilized by each quarter butt frame padlock on four stocks, described platform travelling carriage be erected at two bracing frame middle and upper parts and be placed in each bracing frame be on conplane two quarter butts, described platform is propped up by landing slab and landing slab and is configured to, bracing frame top is provided with collapsible protection hurdle, also include the rail horizontal rod of protective guard above connection two bracing frames, rail horizontal rod and protective guard form one and enclose structure, the platform of half high-rise unsettled insulation maintenance gap bridge is also provided with height adjusting stool.The utility model has detachable, easy-to-assemble feature, when solving operation because of cannot cross over middle obstacle bring unnecessary difficulty, improve operating efficiency, safety factor, reduce the labour intensity of staff.

Description

Half high-rise unsettled insulation maintenance gap bridge
Technical field
The utility model relates to a kind of maintenance and passes a bridge, particularly a kind of half high-rise unsettled insulation maintenance gap bridge.
Background technology
Along with the development of economy, new challenge is proposed to electric power, ensure supply of electric power, reduce power off time, become the top priority of power industry.Traditional operating type can not meet the demand of economic development.As GIS substation bus bar both sides are difficult to cross when overhauling, particularly ascend a height during the overhaul of the equipments of bus overhead more difficult, traditional operating type needs operating personnel from the place of other clear around the opposite side to bus, as my office half high-rise unsettled transformer station, just necessary from second floor to Stall when need arrive another side operation during operation, again from Stall to second floor, sometimes overhaul a commute and want tens of times, not only reduce operating efficiency, but also add labour intensity and the power off time of operating personnel.
Utility model content
The purpose of this utility model is to overcome the deficiencies in the prior art part, and a kind of leap that can realize obstruction is provided, and a platform worked above obstruction can be provided for staff, thus save labour, and ensure that half of the safety of staff high-rise unsettled insulation maintenance gap bridge.
A kind of half high-rise unsettled insulation maintenance gap bridge, include the bracing frame of two groups, cat ladder, platform travelling carriage, platform, the bracing frame of two groups is by being made up of the quarter butt of four draw money on credit strut and complex roots respectively, four stocks in each group bracing frame surround a vertical quadra, then utilized by each quarter butt frame padlock on four stocks, described platform travelling carriage be erected at two bracing frame middle and upper parts and be placed in each bracing frame be on conplane two quarter butts, described platform travelling carriage utilizes frame padlock on quarter butt, the cross section of described platform travelling carriage is the structure of similar G type, described platform is propped up by landing slab and landing slab and is configured to, landing slab support is the cross section G type structure identical with the cross section of platform travelling carriage, both interlock with the use of, with the use of time by platform travelling carriage one end platform is pushed, landing slab is fixed on landing slab support, bracing frame top is provided with collapsible protection hurdle, also include the rail horizontal rod of protective guard above connection two bracing frames, rail horizontal rod and protective guard form one and enclose structure, the platform of half high-rise unsettled insulation maintenance gap bridge is also provided with height adjusting stool, described height adjusting stool is locked on landing slab, the platform both ends or one end of half high-rise unsettled insulation maintenance gap bridge are provided with side ladder.
Half high-rise unsettled insulation maintenance gap bridge of the present utility model, first two groups of bracing frames are assembled in respectively the obstruction both sides needing to cross over, then locking is used for the position of the quarter butt of support platform travelling carriage and locks as required, set up platform travelling carriage and locked, landing slab support is then utilized by platform to be pushed by platform in platform travelling carriage, then put up side ladder and mix up the height on collapsible protection hurdle according to the height situation used, connect rail horizontal rod, put the installation that namely height adjusting stool realizes this half high-rise unsettled insulation maintenance gap bridge well.
Described collapsible protection hurdle is be made up of the pipe fitting be nested between two together, locks after mixing up height with latch.
Described collapsible protection hurdle and the connection between bracing frame are docked frame and are tipped capable connection in for both adopt.
Described platform, for be made up of multistage, can lay one or more snippets flexibly as required, and the two ends landing slab of landing slab is fixed card and is located on platform travelling carriage.
Utilized by platform landing slab to be fixedly stuck in platform travelling carriage, the stability of this platform can be improved, avoid, along platform travelling carriage from two ends landing, causing security incident.
Described platform travelling carriage is locked on the quarter butt of bracing frame by platform slipway clamp.
Described stock is mutually assembled by several sections.
Stock is adopted several sections assembled, the length of a joint stock can be reduced, thus convenient carrying, store, transport.
Described rail horizontal rod is fixed on protective guard by universal fastener.
Height adjusting stool is provided with lap belt suspension arrangement.
In sum, the utility model following advantage compared to existing technology:
Half high-rise unsettled insulation maintenance gap bridge of the present utility model, there is detachable, easy-to-assemble feature, when solving operation because of cannot cross over middle obstacle bring unnecessary difficulty, improve operating efficiency, safety factor, reduce the labour intensity of staff.Bridge floor adopts sliding type, and according to the needs of site work, can build required bridge floor, bridge floor can fix Special high-low stool, and height adjusting stool is furnished with lap belt suspension arrangement, completely solves the safety problem of staff.Overall employing is detachable, convenient, fast when building.Multiple work-yard all adopts an insulating gap bridge, cost-saving.The use of insulating gap bridge, simplifies job step, improves operating efficiency and service technique level, has high using value and marketing prospect.
Accompanying drawing explanation
Fig. 1 is half high-rise unsettled insulation maintenance gap bridge structural representation of the present utility model.
Fig. 2 platform travelling carriage coordinates schematic diagram with landing slab support.
Fig. 3 is height adjusting stool schematic diagram.
Fig. 4 is landing slab fixing structure schematic diagram
Fig. 5 is platform slipway clamp structural representation
Fig. 6 is universal fastener structural representation.
Fig. 7 is side ladder structural representation.
Label declaration 1 bracing frame 11 is drawn money on credit strut 12 quarter butt 2 cat ladder 3 platform travelling carriage 4 platform 41 landing slab 42 landing slab support 5 collapsible protection hurdle 6 rail horizontal rod 7 height adjusting stool.
Detailed description of the invention
Below in conjunction with embodiment, the utility model is described in more detail.
Embodiment 1
A kind of half high-rise unsettled insulation maintenance gap bridge, include the bracing frame 1 of two groups, cat ladder 2, platform travelling carriage 3, platform 4, the bracing frame of two groups is by being made up of the quarter butt 12 of four draw money on credit strut 11 and complex roots respectively, four stocks in each group bracing frame surround a vertical quadra, then utilized by each quarter butt frame padlock on four stocks, described platform travelling carriage be erected at two bracing frame middle and upper parts and be placed in each bracing frame be on conplane two quarter butts, described platform travelling carriage utilizes frame padlock on quarter butt, the cross section of described platform travelling carriage is the structure of similar G type, described platform 4 is made up of landing slab 41 and landing slab support 42, landing slab support is the cross section G type structure identical with the cross section of platform travelling carriage, both interlock with the use of, with the use of time by platform travelling carriage one end platform is pushed, landing slab 41 is fixed on landing slab support 42, bracing frame top is provided with collapsible protection hurdle 5, also include the rail horizontal rod 6 of protective guard above connection two bracing frames, rail horizontal rod and protective guard form one and enclose structure, the platform of half high-rise unsettled insulation maintenance gap bridge is also provided with height adjusting stool 7, described height adjusting stool is locked on landing slab, the platform both ends or one end of half high-rise unsettled insulation maintenance gap bridge are provided with side ladder.Described collapsible protection hurdle is be made up of the pipe fitting be nested between two together, locks after mixing up height with latch.Described collapsible protection hurdle and the connection between bracing frame are docked frame and are tipped capable connection in for both adopt.Described platform, for be made up of multistage, can lay one or more snippets flexibly as required, and the two ends landing slab of landing slab is fixed card and is located on platform travelling carriage.Described platform travelling carriage is locked on the quarter butt of bracing frame by platform slipway clamp.Described stock is mutually assembled by several sections.Described rail horizontal rod is fixed on protective guard by universal fastener and connects.Height adjusting stool is provided with lap belt suspension arrangement.
It is same as the prior art that the present embodiment does not state part.

Claims (7)

1. one and half high-rise unsettled insulation maintenance gap bridges, it is characterized in that: the bracing frame including two groups, cat ladder, platform travelling carriage, platform, the bracing frame of two groups is by being made up of the quarter butt of four draw money on credit strut and complex roots respectively, four stocks in each group bracing frame surround a vertical quadra, then utilized by each quarter butt frame padlock on four stocks, described platform travelling carriage be erected at two bracing frame middle and upper parts and be placed in each bracing frame be on conplane two quarter butts, described platform travelling carriage utilizes frame padlock on quarter butt, the cross section of described platform travelling carriage is the structure of similar G type, described platform is propped up by landing slab and landing slab and is configured to, landing slab support is the cross section G type structure identical with the cross section of platform travelling carriage, both interlock with the use of, with the use of time by platform travelling carriage one end platform is pushed, landing slab is fixed on landing slab support, bracing frame top is provided with collapsible protection hurdle, also include the rail horizontal rod of protective guard above connection two bracing frames, rail horizontal rod and protective guard form one and enclose structure, the platform of half high-rise unsettled insulation maintenance gap bridge is also provided with height adjusting stool, described height adjusting stool is locked on landing slab, the platform both ends or one end of half high-rise unsettled insulation maintenance gap bridge are provided with side ladder.
2. half high-rise unsettled insulation maintenance gap bridge according to claim 1, is characterized in that: described collapsible protection hurdle is be made up of the pipe fitting be nested between two together, locks after mixing up height with latch.
3. half high-rise unsettled insulation maintenance gap bridge according to claim 2, is characterized in that: described collapsible protection hurdle and the connection between bracing frame are docked frame and tipped capable connection in for both adopt.
4. half high-rise unsettled insulation maintenance gap bridge according to claim 3, it is characterized in that: described platform is for be made up of multistage, can lay one or more snippets as required flexibly, the two ends landing slab of landing slab is fixed card and is located on platform travelling carriage.
5. half high-rise unsettled insulation maintenance gap bridge according to claim 4, is characterized in that: described platform travelling carriage is locked on the quarter butt of bracing frame by platform slipway clamp.
6. half high-rise unsettled insulation maintenance gap bridge according to claim 5, is characterized in that: described stock is for mutually assembled by several sections.
7. half high-rise unsettled insulation maintenance gap bridge according to claim 6, is characterized in that: described rail horizontal rod is fixed on protective guard by universal fastener.
CN201420527130.6U 2014-09-15 2014-09-15 Half high-rise unsettled insulation maintenance gap bridge Expired - Fee Related CN204125829U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420527130.6U CN204125829U (en) 2014-09-15 2014-09-15 Half high-rise unsettled insulation maintenance gap bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420527130.6U CN204125829U (en) 2014-09-15 2014-09-15 Half high-rise unsettled insulation maintenance gap bridge

Publications (1)

Publication Number Publication Date
CN204125829U true CN204125829U (en) 2015-01-28

Family

ID=52382199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420527130.6U Expired - Fee Related CN204125829U (en) 2014-09-15 2014-09-15 Half high-rise unsettled insulation maintenance gap bridge

Country Status (1)

Country Link
CN (1) CN204125829U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104810771A (en) * 2015-05-13 2015-07-29 国网辽宁省电力有限公司盘锦供电公司 Insulated gap bridge for bus sleeves
CN105644736A (en) * 2015-12-29 2016-06-08 广船国际有限公司 Side transverse seam construction platform
CN105666451A (en) * 2016-04-12 2016-06-15 安徽安凯汽车股份有限公司 Combined type gantry climbing frame with safety doors
CN108239917A (en) * 2018-02-02 2018-07-03 珠海及力高空作业设备有限公司 A kind of Zhongting splices the bridge that floats
CN108442233A (en) * 2018-02-02 2018-08-24 珠海及力高空作业设备有限公司 A kind of Zhongting floats the building method of bridge
CN109571342A (en) * 2018-11-22 2019-04-05 北京无线电测量研究所 A kind of phased array antenna assembly manipulation device of flexibility

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104810771A (en) * 2015-05-13 2015-07-29 国网辽宁省电力有限公司盘锦供电公司 Insulated gap bridge for bus sleeves
CN105644736A (en) * 2015-12-29 2016-06-08 广船国际有限公司 Side transverse seam construction platform
CN105666451A (en) * 2016-04-12 2016-06-15 安徽安凯汽车股份有限公司 Combined type gantry climbing frame with safety doors
CN108239917A (en) * 2018-02-02 2018-07-03 珠海及力高空作业设备有限公司 A kind of Zhongting splices the bridge that floats
CN108442233A (en) * 2018-02-02 2018-08-24 珠海及力高空作业设备有限公司 A kind of Zhongting floats the building method of bridge
CN108442233B (en) * 2018-02-02 2020-07-21 珠海及力高空作业设备有限公司 Construction method of atrium floating bridge
CN109571342A (en) * 2018-11-22 2019-04-05 北京无线电测量研究所 A kind of phased array antenna assembly manipulation device of flexibility

Similar Documents

Publication Publication Date Title
CN204125829U (en) Half high-rise unsettled insulation maintenance gap bridge
CN103711323B (en) Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing
CN202881852U (en) Suspension bridge cable installation system
CN202706503U (en) Electric lifting discharging platform for main building construction
CN204185120U (en) Mobile unit dolly in place
CN204282823U (en) Detachable discharging platform
CN203430009U (en) Construction hanging basket
CN204299157U (en) The mounted lifting device in attached lifting scaffold side
CN105603882A (en) Continuous beam mid-span closure construction method achieving uninterrupted power of contact line and structure of method
CN206887644U (en) A kind of medium-and low-speed maglev single line beam job platform and edge protection device
CN201722937U (en) Sliding platform for installation of net rack
CN104533092A (en) Truss roof ceiling construction method
CN204982628U (en) Horizontal drawing cable bridge
CN205442452U (en) Convenient hoisting accessory of substation equipment safety
CN204325944U (en) Intercity track cable stayed bridge Diamond-Shape Form Traveler
CN204983135U (en) Elevator discrepancy floor regularization passageway
CN203345999U (en) Special multifunctional lifting frame for busbar bridge
CN204959611U (en) A lifting device for highway construction bridge railing base template
CN204877488U (en) A bracket device that can walk that is used for tunnel no. 2 lining side wall operations
CN103896153A (en) Zig-zag derrick for replacing disconnecting link
CN204038917U (en) Dismountable external hanging service platform
CN202705932U (en) T-beam reinforced hanger frame structure
CN203755153U (en) Simply supported plate bridge bottom plate maintenance construction moving operation platform
CN101597956A (en) Suspended scaffold
CN205259558U (en) Novel scaffold for fitment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150128

Termination date: 20210915