CN108442233B - Construction method of atrium floating bridge - Google Patents

Construction method of atrium floating bridge Download PDF

Info

Publication number
CN108442233B
CN108442233B CN201810105845.5A CN201810105845A CN108442233B CN 108442233 B CN108442233 B CN 108442233B CN 201810105845 A CN201810105845 A CN 201810105845A CN 108442233 B CN108442233 B CN 108442233B
Authority
CN
China
Prior art keywords
bridge
plate
snake
building
atrium
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810105845.5A
Other languages
Chinese (zh)
Other versions
CN108442233A (en
Inventor
文会儒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Extreme Aerial Working Equipment Co ltd
Original Assignee
Zhuhai Extreme Aerial Working Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Extreme Aerial Working Equipment Co ltd filed Critical Zhuhai Extreme Aerial Working Equipment Co ltd
Priority to CN201810105845.5A priority Critical patent/CN108442233B/en
Publication of CN108442233A publication Critical patent/CN108442233A/en
Application granted granted Critical
Publication of CN108442233B publication Critical patent/CN108442233B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D18/00Bridges specially adapted for particular applications or functions not provided for elsewhere, e.g. aqueducts, bridges for supporting pipe-lines
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a method for building an atrium floating bridge, which comprises the following steps: placing two bridging machines on two opposite corridors respectively, and installing bridge seats on the bridging machines; erecting a snake rack along the bridge seat in the corridor; rotating the bridging machine to enable the two groups of snake racks to float out and face each other; assembling the combined plate bridge units in the inner cavity of the snake rack, pushing the plate bridge units in the floating direction, and repeating the steps until the floating lengths of the two groups of plate bridges meet the requirement of the butt joint length; pushing one group of the plate bridges to enable the rod piece on one group of the plate bridges to be butted and buckled with the locking buckle on the other group of the plate bridges; two sets of plate bridges are fastened using the connecting members. The building method starts to build on two opposite corridors, the floating bridge is hung and built in the middle court direction from the corridors, the floating bridge is extended in length and finally butted and fastened to form a complete bridge, so that the stand column is bypassed, the requirement of the middle court ceiling operation is met, the applicability is improved, the stand column is not limited, the occupied area is reduced, and the building method is safe and reliable.

Description

Construction method of atrium floating bridge
Technical Field
The invention relates to the field of atrium smallpox construction operation, in particular to a building method of an atrium floating bridge.
Background
With the rapid development of economy, large-scale consumption places such as shopping malls, hotels and the like are decorated very beautifully and complexly in order to attract customers, the most typical example is that a shopping mall atrium is designed into a hollow form, the design is already a basic design style of most large shopping malls at present, a ceiling or various decorations are often arranged on the ceiling of the atrium, and in later maintenance work, the maintenance work is difficult due to the fact that no standing surface exists; and many market atrium ground can reach more than 20 meters to smallpox height, if directly build vertical ascending scaffold frame then can greatly increased construction cost and time to occupy very big space, influence the market business.
The most common construction method at present is as follows: build the long bridge of a connection on the corridor of two opposite facades, transversely promote atrium department by the avris is whole again to the long bridge, and the workman stands and carries out maintenance work to the smallpox on the long bridge, and this kind of way has very big limitation, can only be used for atrium not have the condition of stand all around just can use, if there is the stand, can block the promotion process of long bridge. At present, shopping malls visiting various large cities find that more than half of the shopping malls have stand columns which are tightly attached to the hollow edge of the atrium, so that the long bridge of the building method cannot be pushed to the atrium.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention provides the method for building the atrium floating bridge, which is not limited by the stand column, has high applicability and meets the requirement of atrium ceiling operation.
The technical scheme adopted by the invention for solving the technical problems is as follows:
a building method of an atrium floating bridge comprises the following steps:
step one, respectively placing two bridging machines on two opposite corridors, and installing bridge seats on the bridging machines to form a firm frame;
step two, building a combined aluminum alloy frame along the bridge seat at the corridor until the building of the snake frame is completed;
rotating the bridging machine to enable the two groups of snake racks to float out and face each other;
step four, materials are conveyed to the inner cavity of the snake-shaped frame from the corridor, a combined plate bridge unit is assembled in the inner cavity of the snake-shaped frame, the plate bridge unit is pushed towards the drifting-out direction, after the space is vacated, the next plate bridge unit is continuously assembled, and the steps are repeated until the drifting-out length of the two groups of plate bridges meets the requirement of the butt joint length;
step five, pushing one group of the plate bridges to enable the rod piece on one group of the plate bridges to be in butt joint and buckling with the locking buckle on the other group of the plate bridges, and pre-tightening and assembling the two groups of the plate bridges;
and step six, the operator walks near the front end of the plate bridge, fastens the two groups of plate bridges by using the connecting piece, and completes the construction.
As an improvement of the above technical scheme, in the second step, the inner cavity of the snake rack is also paved with slide rails, and in the fourth step, the sheet bridge unit is pushed along the slide rails to the drifting direction.
As an improvement of the above technical solution, before or after the sixth step, the following steps are further performed: laying platform plates at the bottoms of the snake rack and the slab bridge, then installing protective guards on the left side and the right side of the slab bridge, and building a scaffold leading to the top of the atrium at the front end of the slab bridge.
As an improvement of the technical scheme, in the first step, the lower end of the bridge seat is provided with a supporting leg which can stretch up and down.
As an improvement of the technical scheme, the locking buckle is provided with a release handle for unlocking the locking buckle, and one end of the release handle is provided with a pull rope extending to the bridge seat.
As an improvement of the technical scheme, the sheet bridge is a combined aluminum alloy frame, and the weight of the sheet bridge is lighter than that of the snake rack.
The invention has the following beneficial effects:
the building method starts to build on two opposite corridors, the floating bridge is built by overhanging towards the atrium direction from the corridor, the floating bridge is extended in length and finally butted and fastened to form a complete bridge, so that the stand column is bypassed, the requirement of atrium ceiling operation is met, the applicability is improved, the side corridor does not need to be built and then pushed to a working surface, the limitation of the stand column is avoided, the floor area is reduced, and the building method is safe and reliable.
Drawings
The invention is further described with reference to the following detailed description of embodiments and drawings, in which:
FIG. 1 is a schematic diagram of the structure of an embodiment of the present invention before docking;
FIG. 2 is an enlarged view of a portion of FIG. 1 at A;
fig. 3 is a schematic structural diagram of a guard rail according to an embodiment of the present invention;
fig. 4 is a schematic structural diagram of an embodiment of the present invention.
Detailed Description
Referring to fig. 1 and 2, the method for building the atrium bridge comprises the following steps: step one, respectively placing two bridging machines 1 on two opposite corridors, and installing bridge seats 2 on the bridging machines 1 to form a firm frame; step two, building a combined aluminum alloy frame along the bridge seat 2 at the corridor until the building of the snake frame 3 is completed; step three, rotating the bridging machine 1 to enable the two groups of snake racks 3 to float out and face each other; step four, materials are sent to the inner cavity of the snake-shaped frame 3 from the corridor, the combined plate bridge unit 41 is assembled in the inner cavity of the snake-shaped frame 3, the plate bridge unit 41 is pushed towards the drifting-out direction, after the space is vacated, the next plate bridge unit 41 is continuously assembled, and the steps are repeated until the drifting-out length of the two groups of plate bridges 4 meets the requirement of the butt joint length; step five, pushing one group of the plate bridges 4 to enable the rod piece 5 on one group of the plate bridges 4 to be in butt joint and buckling with the locking buckle 6 on the other group of the plate bridges 4, and pre-tightening and assembling the two groups of the plate bridges 4; and step six, the operator walks near the front end of the sheet bridge 4, fastens the two sets of sheet bridges 4 by using the connecting piece, and completes the construction.
In order to facilitate pushing the sheet bridge unit 41, in the second step, the slide rail 7 is further laid in the inner cavity of the snake rack 3, and in the fourth step, the sheet bridge unit 41 is pushed along the slide rail 7 in the drifting direction.
With further reference to fig. 3 and 4, before or after step six, the following steps are also performed: laying the landing slab in the son frame 3 of snake and 4 bottoms of piece bridge, making things convenient for operating personnel to go up the bridge walking, then installing rail guard 8 in 4 left and right sides of piece bridge, playing safety protection and additional strengthening's effect, building the scaffold 9 that leads to the atrium top again at the front end of piece bridge 4, supplementary increasing, in addition in actual work, need stand on the scaffold 9 different height stand facade, make things convenient for operation and maintenance.
In addition, in step one, at the lower extreme installation of bridge pedestal 2 supporting legs 10 that can stretch out and draw back from top to bottom to the height of whole bridge that wafts of adjusting, piece bridge 4 is combination formula aluminum alloy frame, and the weight of piece bridge 4 is lighter than the young frame 3 of snake, and both perfect adaptation alleviates the load of bridge pedestal 2, can guarantee enough safety again.
As shown in fig. 1 and fig. 2, a release handle 11 for unlocking the locking buckle 6 is arranged on the locking buckle 6, a pull rope 12 extending to the bridge seat 2 is arranged at one end of the release handle 11, after the construction operation is completed, the flying bridge needs to be dismantled, at the moment, the bridging machine 1 needs to be reinstalled, an operator removes a connecting piece, the release handle 11 on the locking buckle 6 is remotely operated through the pull rope 12, the rod piece 5 is quickly released from the locking buckle 6, the plate bridge units 41 are pulled backwards one by one and the plate bridge units 41 are dismantled, after one plate bridge unit 41 is dismantled, the other plate bridge unit 41 is continuously pulled backwards until all the bridge units are dismantled, finally, the snake rack 3 is dismantled, the whole building and dismantling process is safe and reliable, the applicability of the splicing flying bridge is high, the flying bridge does not need to be pushed to a working face after a side corridor is built, the bridge is not limited by a stand column, the floor area is reduced, the requirement of the atrium ceiling operation is met.
The above description is only a preferred embodiment of the present invention, but the present invention is not limited to the above embodiments, and the present invention shall fall within the protection scope of the present invention as long as the technical effects of the present invention are achieved by any similar or identical means.

Claims (5)

1. A method for building an atrium floating bridge is characterized by comprising the following steps:
step one, respectively placing two bridging machines on two opposite corridors, and installing bridge seats on the bridging machines to form a firm frame;
step two, building a combined aluminum alloy frame along the bridge seat at the corridor until the building of the snake frame is completed;
rotating the bridging machine to enable the two groups of snake racks to float out and face each other;
step four, materials are conveyed to the inner cavity of the snake-shaped frame from the corridor, a combined plate bridge unit is assembled in the inner cavity of the snake-shaped frame, the plate bridge unit is pushed towards the drifting-out direction, after the space is vacated, the next plate bridge unit is continuously assembled, and the steps are repeated until the drifting-out length of the two groups of plate bridges meets the requirement of the butt joint length;
pushing one group of the plate bridges to enable a rod piece on one group of the plate bridges to be in butt joint buckling with a locking buckle on the other group of the plate bridges, and pre-tightening assembly of the two groups of the plate bridges is completed;
and step six, the operator walks near the front end of the plate bridge, fastens the two groups of plate bridges by using the connecting piece, and completes the construction.
2. The method for building the atrium floating bridge according to claim 1, wherein in the second step, sliding rails are further paved in the inner cavity of the snake rack, and in the fourth step, the sheet bridge unit is pushed along the sliding rails in the floating direction.
3. The method for building an atrium bridge according to claim 1, wherein before or after the sixth step, the following steps are further carried out: laying platform plates at the bottoms of the snake rack and the slab bridge, then installing protective guards on the left side and the right side of the slab bridge, and building a scaffold leading to the top of the atrium at the front end of the slab bridge.
4. The method for building the atrium floating bridge according to claim 1, wherein in the step one, supporting legs which can be extended and retracted up and down are installed at the lower end of the bridge base.
5. The method for building the atrium bay bridge according to claim 1, wherein the sheet bridge is a combined type aluminum alloy frame, and the weight of the sheet bridge is lighter than that of the snake cradle.
CN201810105845.5A 2018-02-02 2018-02-02 Construction method of atrium floating bridge Active CN108442233B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810105845.5A CN108442233B (en) 2018-02-02 2018-02-02 Construction method of atrium floating bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810105845.5A CN108442233B (en) 2018-02-02 2018-02-02 Construction method of atrium floating bridge

Publications (2)

Publication Number Publication Date
CN108442233A CN108442233A (en) 2018-08-24
CN108442233B true CN108442233B (en) 2020-07-21

Family

ID=63191280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810105845.5A Active CN108442233B (en) 2018-02-02 2018-02-02 Construction method of atrium floating bridge

Country Status (1)

Country Link
CN (1) CN108442233B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003253877A (en) * 2001-12-26 2003-09-10 Hitachi Building Systems Co Ltd Working scaffolding device
CN201865321U (en) * 2010-11-23 2011-06-15 中铁建工集团有限公司 Multifunctional movable protecting and isolating operating platform
CN203514750U (en) * 2013-09-16 2014-04-02 中建七局(上海)有限公司 Truss type operating platform for aloft work
CN204125829U (en) * 2014-09-15 2015-01-28 国家电网公司 Half high-rise unsettled insulation maintenance gap bridge
CN206769347U (en) * 2017-03-23 2017-12-19 中国建筑第二工程局有限公司 Special movable operating platform for pedestrian street

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003253877A (en) * 2001-12-26 2003-09-10 Hitachi Building Systems Co Ltd Working scaffolding device
CN201865321U (en) * 2010-11-23 2011-06-15 中铁建工集团有限公司 Multifunctional movable protecting and isolating operating platform
CN203514750U (en) * 2013-09-16 2014-04-02 中建七局(上海)有限公司 Truss type operating platform for aloft work
CN204125829U (en) * 2014-09-15 2015-01-28 国家电网公司 Half high-rise unsettled insulation maintenance gap bridge
CN206769347U (en) * 2017-03-23 2017-12-19 中国建筑第二工程局有限公司 Special movable operating platform for pedestrian street

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
及力21.5米蛇仔桥梁架;匿名;《百度》;20150612;第0:00-1:59 *

Also Published As

Publication number Publication date
CN108442233A (en) 2018-08-24

Similar Documents

Publication Publication Date Title
CN202324576U (en) Rail-mounted platform system used for installing cornice and ceiling aluminium sheet curtain wall
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN205296869U (en) Spatial grid structure thrustor that slides
CN109235902A (en) Positive quadrangular pyramid bolt-ball net frame multi-point support high-altitude dissipates splicing method
CN108442233B (en) Construction method of atrium floating bridge
CN209831613U (en) Building decoration moving platform
CN209568688U (en) A kind of elevating construction platform
CN114856144B (en) Scaffold for building construction and use method
CN203594212U (en) Prefabricated building supporting frame
CN202559618U (en) Multi-step connection type cage staircase
CN215670884U (en) Assembly type building staircase operation platform
CN210316278U (en) Multifunctional safety protection stair
CN106555438A (en) Superposed type moves the commercial house
CN207003972U (en) Movable construction operation platform
CN111997345A (en) Lifting scaffold hangs hoist system upside down
CN111519754A (en) Detachable green terrace for multi-storey building and manufacturing method thereof
CN220550830U (en) Working platform for scissors prefabricated stairs
CN214941801U (en) Assembled steel construction stair unit and multilayer steel construction stair
CN103590593A (en) Assembly type building supporting frame
CN205259622U (en) A operation platform for installing rack
CN210737392U (en) Movable truss device for bridge guardrail maintenance
CN208310162U (en) Movable operating platform system
CN213953108U (en) From taking formula and climbing frame stair passageway platform
CN216380326U (en) Prefabricated staircase based on building industrialization
CN220469308U (en) Steel structure additionally provided with elevator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant