CN203081466U - Integrated moving framework for inverted arch of tunnel - Google Patents

Integrated moving framework for inverted arch of tunnel Download PDF

Info

Publication number
CN203081466U
CN203081466U CN 201320094186 CN201320094186U CN203081466U CN 203081466 U CN203081466 U CN 203081466U CN 201320094186 CN201320094186 CN 201320094186 CN 201320094186 U CN201320094186 U CN 201320094186U CN 203081466 U CN203081466 U CN 203081466U
Authority
CN
China
Prior art keywords
tunnel
inverted arch
side wall
arch
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320094186
Other languages
Chinese (zh)
Inventor
郭松坚
李传刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority to CN 201320094186 priority Critical patent/CN203081466U/en
Application granted granted Critical
Publication of CN203081466U publication Critical patent/CN203081466U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses an integrated moving framework for an inverted arch of a tunnel. The integrated moving framework comprises an end head supporting frame and a side edge arched framework; the end head supporting frame comprises a tunnel bottom truss an at to two ends of the tunnel bottom truss; the side edge arched framework comprises a short side wall arched frame and an arc-shaped arch bottom framework which is hinged to the lower end of the short side wall arched frame; and the short side wall arched frame is fixedly connected to the side edge arched framework fixing frames through connecting rods. According to the integrated moving framework for the inverted arch of the tunnel, the inverted arch and a side wall are poured firstly; after the concrete poured in the inverted arch and the side wall reaches initial set, the arc-shaped arch bottom framework is turned to a vertical position, and then the concrete used for filling the inverted arch and the side wall can be poured, therefore, the time interval of pouring the inverted arch and the side wall is greatly reduced, and the pouring efficiency is high; simultaneously, the position of the short side wall arched frame can be conveniently adjusted by adjusting the length of the connecting rods, so that the short side wall arched frame can be conveniently and quickly positioned and fixed, and as a result, the construction efficiency can be further improved.

Description

Tunnel monolithic inverted arch mobile formwork
Technical field
The utility model relates to a kind of tunnel invert and short side wall concrete formwork for placing, particularly a kind of tunnel monolithic inverted arch mobile formwork.
Background technology
Along with national in recent years the input energetically, particularly high-speed railway of infrastructure construction, the large tracts of land of passenger dedicated railway line construction are carried out.Limited by geologic condition, tunnel proportion in mountain route increases gradually.Conventional construction method is that the inverted arch framing is built, and builds the inverted arch fill concrete again after the final set of inverted arch concrete, and short abutment wall is cast separately also.For improving the application life and the structural safety in tunnel, at present inverted arch and short abutment wall adopt the monolithic one-time-concreting more during constructing tunnel, in tunnel monolithic inverted arch and the construction of short abutment wall, exist Template Location difficulty, inverted arch and the requirement of inverted arch fill concrete separately build blanking time long, build problems such as efficient is low.For guaranteeing that inverted arch and short abutment wall satisfy the construction quality requirement, it is quick, accurate, firm, easy to use to make a kind of location, can effectively raise labour efficiency, reduce the template of workman's operation intensity, and what just show is particularly important.
The utility model content
In view of this, the purpose of this utility model provides a kind of tunnel monolithic inverted arch mobile formwork, and Template Location difficulty, inverted arch and inverted arch fill concrete require separately to build length blanking time, build problems such as efficient is low in the construction to solve.
The utility model tunnel monolithic inverted arch mobile formwork, comprise termination bracing frame and side arch mould bases, described termination bracing frame comprises the tunnel bottom truss and is fixed on the side arch mould fixed mount at tunnel bottom truss two ends, described side arch mould bases comprises short abutment wall arched frame and is hinged on the arc arch bed die frame of short abutment wall arched frame low side that described short abutment wall arched frame is fixedly connected on the side arch mould fixed mount by connecting rod.
Further, described tunnel bottom truss comprises crossbeam, is fixed on the arc beam and the brace summer that is connected crossbeam and arc beam of crossbeam below;
Further, described side arch mould fixed mount comprises vertical beam that is fixed on the crossbeam end face and the raker beam that is connected vertical beam upper end and crossbeam;
Further, the adjustable length of described connecting rod, and the two ends of connecting rod are hinged on respectively on short abutment wall arched frame and the side arch mould fixed mount;
Further, described connecting rod is made up of sleeve pipe and two screw rods that are arranged at the sleeve pipe two ends.
The beneficial effects of the utility model: the utility model tunnel monolithic inverted arch mobile formwork, termination bracing frame and side arch mould bases link into an integrated entity, building inverted arch and abutment wall, after treating inverted arch and side wall concrete initial set, arc is encircleed the bed die frame turn to vertical position, can build inverted arch and abutment wall fill concrete, make shorten greatly both blanking times of building, build the efficient height; Can regulate the position of short abutment wall arched frame simultaneously by the length of regulating connecting rod easily, make that the location of short abutment wall arched frame and convenient fixing are quick, can further improve efficiency of construction.
Description of drawings
Fig. 1 is the structural representation of termination bracing frame;
Fig. 2 is the structural representation of the utility model tunnel monolithic inverted arch mobile formwork;
Fig. 3 is the structural representation of connecting rod.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further described.
As shown in the figure, present embodiment tunnel monolithic inverted arch mobile formwork, comprise termination bracing frame and side arch mould bases, described termination bracing frame comprises tunnel bottom truss 1 and is fixed on the side arch mould fixed mount 2 at tunnel bottom truss 1 two ends, described side arch mould bases comprises short abutment wall arched frame 3 and is hinged on the arc arch bed die frame 4 of short abutment wall arched frame 3 low sides that described short abutment wall arched frame 3 is fixedly connected on the side arch mould fixed mount 2 by connecting rod 5.
During construction, this tunnel monolithic inverted arch mobile formwork is moved in the tunnel, the termination bracing frame is positioned over tunnel ends, regulates the position of short abutment wall arched frame 3, can build inverted arch and abutment wall.After treating inverted arch and side wall concrete initial set, arc is encircleed bed die frame 4 turn to vertical position, can build inverted arch and abutment wall fill concrete, make shorten greatly both blanking times of building, build the efficient height.
As improvement to present embodiment, described tunnel bottom truss 1 comprises crossbeam 11, is fixed on the arc beam 12 and the brace summer 13 that is connected crossbeam 11 and arc beam 12 of crossbeam below, arc beam 12 is adaptive with the tunnel bottom shape of cross section, the good rigidly of this structure tunnel bottom truss 1, bearing capacity is big, long service life.
As the improvement to present embodiment, described side arch mould fixed mount 2 comprises vertical beam 21 that is fixed on crossbeam 11 end faces and the raker beam 22 that is connected vertical beam 21 upper ends and crossbeam 11, and this structure side arch mould fixed mount 2 structural strengths are good, and the life-span is long.
As improvement to present embodiment, the adjustable length of described connecting rod 5, and the two ends of connecting rod 5 are hinged on respectively on short abutment wall arched frame 3 and the side arch mould fixed mount 2; By regulating the length of connecting rod 5, can regulate the position of short abutment wall arched frame 3, easy to adjust quick, can further shorten the engineering time, improve efficiency of construction.
As the improvement to present embodiment, described connecting rod 5 is made up of sleeve pipe 51 and two screw rods 52 that are arranged at sleeve pipe 51 two ends, can regulate length of connecting rod by revoling tube 51, and is easy to adjust quick.
Explanation is at last, above embodiment is only unrestricted in order to the explanation the technical solution of the utility model, although the utility model is had been described in detail with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, can make amendment or be equal to replacement the technical solution of the utility model, and not breaking away from the aim and the scope of technical solutions of the utility model, it all should be encompassed in the middle of the claim scope of the present utility model.

Claims (5)

1. tunnel monolithic inverted arch mobile formwork, it is characterized in that: comprise termination bracing frame and side arch mould bases, described termination bracing frame comprises the tunnel bottom truss and is fixed on the side arch mould fixed mount at tunnel bottom truss two ends, described side arch mould bases comprises short abutment wall arched frame and is hinged on the arc arch bed die frame of short abutment wall arched frame low side that described short abutment wall arched frame is fixedly connected on the side arch mould fixed mount by connecting rod.
2. tunnel according to claim 1 monolithic inverted arch mobile formwork is characterized in that: described tunnel bottom truss comprises crossbeam, is fixed on the arc beam and the brace summer that is connected crossbeam and arc beam of crossbeam below.
3. tunnel according to claim 2 monolithic inverted arch mobile formwork is characterized in that: described side arch mould fixed mount comprises vertical beam that is fixed on the crossbeam end face and the raker beam that is connected vertical beam upper end and crossbeam.
4. according to arbitrary described tunnel monolithic inverted arch mobile formwork among the claim 1-3, it is characterized in that: the adjustable length of described connecting rod, and the two ends of connecting rod are hinged on respectively on short abutment wall arched frame and the side arch mould fixed mount.
5. tunnel according to claim 4 monolithic inverted arch mobile formwork is characterized in that: described connecting rod is made up of sleeve pipe and two screw rods that are arranged at the sleeve pipe two ends.
CN 201320094186 2013-03-01 2013-03-01 Integrated moving framework for inverted arch of tunnel Expired - Fee Related CN203081466U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320094186 CN203081466U (en) 2013-03-01 2013-03-01 Integrated moving framework for inverted arch of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320094186 CN203081466U (en) 2013-03-01 2013-03-01 Integrated moving framework for inverted arch of tunnel

Publications (1)

Publication Number Publication Date
CN203081466U true CN203081466U (en) 2013-07-24

Family

ID=48827315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320094186 Expired - Fee Related CN203081466U (en) 2013-03-01 2013-03-01 Integrated moving framework for inverted arch of tunnel

Country Status (1)

Country Link
CN (1) CN203081466U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005775A (en) * 2014-06-18 2014-08-27 余波 Integrated formwork for tunnel inverted arch backfill construction, and constructing process of integrated formwork
CN106089254A (en) * 2016-08-19 2016-11-09 中铁建大桥工程局集团第六工程有限公司 Major long tunnel construction inverted arch entirety mould bases
CN106499411A (en) * 2016-11-29 2017-03-15 中铁隧道集团二处有限公司 A kind of single-track tunnel macroportion inverted arch self-propelled hangs template and construction method
CN106761825A (en) * 2016-12-23 2017-05-31 泰安东岳重工有限公司 For the inverted arch trestle device in tunnel
CN107191205A (en) * 2017-06-20 2017-09-22 中铁二十局集团第三工程有限公司 Tunnel side wall inverted arch concrete cyclization cast automatic moving full arc template
CN110318776A (en) * 2019-07-05 2019-10-11 甘肃省交通规划勘察设计院股份有限公司 Method for tunnel construction based on inverted arch and inverted arch filled layer substitution steel-concrete combined structure
CN110656953A (en) * 2019-10-18 2020-01-07 中铁八局集团第六工程有限公司 Reinforcing method for enhancing stability of inverted arch structure of high-ground-stress soft rock tunnel

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005775A (en) * 2014-06-18 2014-08-27 余波 Integrated formwork for tunnel inverted arch backfill construction, and constructing process of integrated formwork
CN104005775B (en) * 2014-06-18 2016-02-03 余波 Tunnel invert backfill construction integrated template and construction technology thereof
CN106089254A (en) * 2016-08-19 2016-11-09 中铁建大桥工程局集团第六工程有限公司 Major long tunnel construction inverted arch entirety mould bases
CN106499411A (en) * 2016-11-29 2017-03-15 中铁隧道集团二处有限公司 A kind of single-track tunnel macroportion inverted arch self-propelled hangs template and construction method
CN106499411B (en) * 2016-11-29 2019-02-12 中铁隧道集团二处有限公司 A kind of single-track tunnel macroportion inverted arch self-propelled suspension template and construction method
CN106761825A (en) * 2016-12-23 2017-05-31 泰安东岳重工有限公司 For the inverted arch trestle device in tunnel
CN106761825B (en) * 2016-12-23 2018-08-31 泰安东岳重工有限公司 Inverted arch trestle device for tunnel
CN107191205A (en) * 2017-06-20 2017-09-22 中铁二十局集团第三工程有限公司 Tunnel side wall inverted arch concrete cyclization cast automatic moving full arc template
CN107191205B (en) * 2017-06-20 2024-01-09 中铁二十一局集团第三工程有限公司 Self-moving full-arc template for loop casting of tunnel side wall inverted arch concrete
CN110318776A (en) * 2019-07-05 2019-10-11 甘肃省交通规划勘察设计院股份有限公司 Method for tunnel construction based on inverted arch and inverted arch filled layer substitution steel-concrete combined structure
CN110318776B (en) * 2019-07-05 2021-02-05 甘肃省交通规划勘察设计院股份有限公司 Tunnel construction method based on inverted arch and inverted arch filling layer replacing steel-concrete composite structure
CN110656953A (en) * 2019-10-18 2020-01-07 中铁八局集团第六工程有限公司 Reinforcing method for enhancing stability of inverted arch structure of high-ground-stress soft rock tunnel

Similar Documents

Publication Publication Date Title
CN203081466U (en) Integrated moving framework for inverted arch of tunnel
CN204899941U (en) Whole movable tunnel ditch cable duct formworking jumbo
CN201666157U (en) Inverted arch integral type moving die carrier
CN205805577U (en) A kind of arch wall type open cut tunnel chassis
CN207700067U (en) A kind of packaged type box culvert construct trolley
CN204357117U (en) A kind of after-pouring band beam-slab template and lattice column thereof
CN113417455B (en) Self-reinforcing supporting rod for slip form construction
CN206625553U (en) For pouring the formwork bracing system of high-low bay structure simultaneously
CN108005114A (en) A kind of piping lane pours mould
CN104164882B (en) Side slope builds construction method and the structure on supporting and protection structure beam basis
CN202946193U (en) Tunnel center gutterway formwork
CN207775925U (en) A kind of piping lane pours mold
CN201367730Y (en) A die plate supporting device convenient for dismounting die plates
CN204081475U (en) A kind of adjustable floor one-piece keel structure
CN203904785U (en) Multifunctional pressing rod of track slab of CRTS III plate type ballastless track
CN103195448B (en) A kind of tunnel concrete longitudinal joint treatment method and equipment
CN206859684U (en) A kind of support frame structure of reinforcing template connection
CN108098979A (en) A kind of PK sections concrete box girder precast segment template
CN113445739A (en) Adjustable unilateral template supporting device
CN211948026U (en) Cast-in-place splayed wall template system of apron culvert
CN209537993U (en) A kind of concrete road shoulder construction equipment for cutting
CN208038981U (en) A kind of concrete row formula vibrator assisting guide frame
CN208056001U (en) It is a kind of non-to drawing cast-in-place aqueduct plate device
CN202644483U (en) Pier large steel template
CN205532627U (en) Highway tunnel cable duct formworking jumbo

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130724