CN106089254A - Major long tunnel construction inverted arch entirety mould bases - Google Patents

Major long tunnel construction inverted arch entirety mould bases Download PDF

Info

Publication number
CN106089254A
CN106089254A CN201610687186.1A CN201610687186A CN106089254A CN 106089254 A CN106089254 A CN 106089254A CN 201610687186 A CN201610687186 A CN 201610687186A CN 106089254 A CN106089254 A CN 106089254A
Authority
CN
China
Prior art keywords
inverted arch
steel
construction
mould bases
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610687186.1A
Other languages
Chinese (zh)
Inventor
王天成
刘勃
张智军
李文飞
姜延峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA REILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP NO6 ENGINEERING Co Ltd
Sixth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
CHINA REILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP NO6 ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA REILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP NO6 ENGINEERING Co Ltd filed Critical CHINA REILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP NO6 ENGINEERING Co Ltd
Priority to CN201610687186.1A priority Critical patent/CN106089254A/en
Publication of CN106089254A publication Critical patent/CN106089254A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of major long tunnel construction inverted arch entirety mould bases, belong to road engineering technical field, it is characterized in that: be respectively fixed at two ends with vertical I-steel at horizontal I-steel, it is respectively fixed with concrete balancing weight at vertical I-steel top, constitute door font mobile moldbase, inverted arch template is hung by scalable connection thick stick and is fixed on below horizontal I-steel, is fixed with horizontal I-steel by corresponding suspension leading screw at inverted arch template edge.A length of 15 25 meters of mobile moldbase, a length of 12 22 meters of inverted arch template, inverted arch template transverse section arc length is 2.3 5 meters.Providing the benefit that: Optimizing construction production procedure, update method, improve work efficiency, reducing material consumption, it is to avoid energy waste so that it is conformance with standard construction requirement, save labour force simultaneously, operation labor intensity is low.Mould bases convenience in place, location is simple, and speed is fast, and efficiency is high.Mould bases uses site to make, and expense is low, simple to operate, and operation side is clean and tidy, civilized, and efficiency of construction is high.Overall mould bases construction had both ensured engineering construction quality, was easy to again construction organization.

Description

Major long tunnel construction inverted arch entirety mould bases
Technical field
The invention belongs to road engineering technical field.
Background technology
The inverted arch construction of traditional tunnel is to use fritter combined steel section construction, and working procedure includes assembling, reinforces, waters Build, dismantle, transition, cleaning oiling, operation is numerous and diverse, and circulation time is long, reinforces and supports many, and globality is poor, the control of construction quality difficulty, Scope of operation Image is bad, and form work engineering construction cost is high.
Summary of the invention
It is an object of the invention to: provide a kind of major long tunnel construction inverted arch entirety mould bases, it can improve template globality, Simplify working procedure, accelerating construction progress, it is ensured that architecture quality.
The technical scheme is that and be respectively fixed at two ends with vertical I-steel at horizontal I-steel, at vertical I-steel Top is respectively fixed with concrete balancing weight, constitutes door font mobile moldbase, and inverted arch template hangs fixing by scalable connection thick stick Below horizontal I-steel, fixed with horizontal I-steel by corresponding suspension leading screw at inverted arch template edge.
Mobile moldbase a length of 15-25 rice, inverted arch template a length of 12-22 rice, inverted arch template transverse section arc length is 2.3-5 Rice.
The invention has the beneficial effects as follows: in order to improve template globality, simplify working procedure, accelerating construction progress, it is ensured that Architecture quality, saves engineering cost, and that designs and develops out the inverted arch construction quality requirement of applicable tunnel moves integrally mould bases, and optimization is executed Work production procedure, update method, improves work efficiency, reduces material consumption, it is to avoid energy waste so that it is conformance with standard Construction requirement, saves labour force simultaneously, and operation labor intensity is low.Mould bases convenience in place, location is simple, and speed is fast, and efficiency is high.Mould Frame uses site to make, and expense is low, simple to operate, and operation side is clean and tidy, civilized, and efficiency of construction is high.Overall mould bases is executed Work had both ensured engineering construction quality, was easy to again construction organization.
Accompanying drawing explanation
Fig. 1 is present configuration front view;
Fig. 2 is present configuration top view;
Fig. 3 is present configuration side view.
Detailed description of the invention
Embodiment 1
Below in conjunction with the accompanying drawings the present invention is described further:
As it can be seen, wherein, 1 is inverted arch template;2 is horizontal I-steel;3 is vertical I-steel;4 is concrete balancing weight;5 are Scalable connection thick stick;6 is suspension hook;7 is to hang leading screw.
A font travelling mold frame body, inverted arch template it is made up of horizontal I-steel 2, vertical I-steel 3 and concrete balancing weight 4 1 is fixed on below horizontal I-steel 2 by the suspension of scalable connection thick stick 5, before and after door font mobile moldbase drives inverted arch template 1 Mobile, hang leading screw 7 and can adjust inverted arch template 1 position.
Its construction procedure is as follows:
1. inverted arch template uses the overall punching block of bulk camber sizing;
2. by a kind of scalable connection thick stick the bulk camber overall punching block of sizing and move integrally rigid frame form one whole Body;
3. inverted arch template manufactures the mobile moldbase of long 17m and the supporting sizing arc formwork of long 12.1m arc length 2.5m;
4. template causes design height, by 12 scalable companies by 2 corresponding leading screw regulation inverted arch form height that hang Connecing the plan-position of thick stick regulation inverted arch stencil design, during location, template overlaps 10cm with the completeest inverted arch;
5. concrete first pours inverted arch flat concrete, after-pouring inverted arch side wall concrete, and inverted arch concreting completes Rear installation Central drain template, unclamps lower row and connects thick stick, uses bottle gouard moved by hands to promote pivot bottom inverted arch template, pours inverted arch and fill out Fill concrete.
2. above-mentioned steps step the camber overall punching block of sizing and moves integrally rigid frame group by a kind of scalable connection thick stick Become an entirety;Step 4. template causes design height, by 12 flexible silks by 2 suspension leading screw regulation inverted arch form height The plan-position of thick stick regulation inverted arch stencil design;During step 4. Template Location, template overlaps 10cm with the completeest inverted arch.

Claims (2)

1. a major long tunnel construction inverted arch entirety mould bases, is characterized in that: be respectively fixed at two ends with vertical work at horizontal I-steel Word steel, is respectively fixed with concrete balancing weight at vertical I-steel top, constitutes door font mobile moldbase, and inverted arch template is by stretching Contracting connects thick stick suspension and is fixed on below horizontal I-steel, by corresponding suspension leading screw and horizontal I-shaped at inverted arch template edge Steel is fixed.
A kind of major long tunnel construction inverted arch entirety mould bases the most as claimed in claim, is characterized in that: a length of 15-of mobile moldbase 25 meters, inverted arch template a length of 12-22 rice, inverted arch template transverse section arc length is 2.3-5 rice.
CN201610687186.1A 2016-08-19 2016-08-19 Major long tunnel construction inverted arch entirety mould bases Pending CN106089254A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610687186.1A CN106089254A (en) 2016-08-19 2016-08-19 Major long tunnel construction inverted arch entirety mould bases

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610687186.1A CN106089254A (en) 2016-08-19 2016-08-19 Major long tunnel construction inverted arch entirety mould bases

Publications (1)

Publication Number Publication Date
CN106089254A true CN106089254A (en) 2016-11-09

Family

ID=58070497

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610687186.1A Pending CN106089254A (en) 2016-08-19 2016-08-19 Major long tunnel construction inverted arch entirety mould bases

Country Status (1)

Country Link
CN (1) CN106089254A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201915972U (en) * 2010-12-31 2011-08-03 中铁二局股份有限公司 Movable mold bracket for gutter cable trough in tunnel
CN202531191U (en) * 2012-03-14 2012-11-14 中铁二十二局集团第一工程有限公司 Tunnel inverted arch integral move support system
CN203081466U (en) * 2013-03-01 2013-07-24 中铁十七局集团第四工程有限公司 Integrated moving framework for inverted arch of tunnel
CN103266900A (en) * 2013-03-25 2013-08-28 中交路桥建设有限公司 Integrated quick moving formwork for tunnel multi-longitudinal cable trough construction
CN203200664U (en) * 2013-04-11 2013-09-18 新疆北新路桥集团股份有限公司 Slip-form construction device for variable cross-section hollow high pier
CN204002841U (en) * 2014-04-02 2014-12-10 北京建鼎国铁工程设计有限公司 A kind of outrigger formula mobile formwork for support of tunnel wall pouring construction
CN204552758U (en) * 2014-11-24 2015-08-12 湖南五新机械有限公司 A kind of efficient movable mold bracket for gutter cable trough in tunnel
CN205876349U (en) * 2016-08-19 2017-01-11 中铁建大桥工程局集团第六工程有限公司 Whole die carrier of tunnel construction inverted arch of growing up

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201915972U (en) * 2010-12-31 2011-08-03 中铁二局股份有限公司 Movable mold bracket for gutter cable trough in tunnel
CN202531191U (en) * 2012-03-14 2012-11-14 中铁二十二局集团第一工程有限公司 Tunnel inverted arch integral move support system
CN203081466U (en) * 2013-03-01 2013-07-24 中铁十七局集团第四工程有限公司 Integrated moving framework for inverted arch of tunnel
CN103266900A (en) * 2013-03-25 2013-08-28 中交路桥建设有限公司 Integrated quick moving formwork for tunnel multi-longitudinal cable trough construction
CN203200664U (en) * 2013-04-11 2013-09-18 新疆北新路桥集团股份有限公司 Slip-form construction device for variable cross-section hollow high pier
CN204002841U (en) * 2014-04-02 2014-12-10 北京建鼎国铁工程设计有限公司 A kind of outrigger formula mobile formwork for support of tunnel wall pouring construction
CN204552758U (en) * 2014-11-24 2015-08-12 湖南五新机械有限公司 A kind of efficient movable mold bracket for gutter cable trough in tunnel
CN205876349U (en) * 2016-08-19 2017-01-11 中铁建大桥工程局集团第六工程有限公司 Whole die carrier of tunnel construction inverted arch of growing up

Similar Documents

Publication Publication Date Title
CN102230383B (en) All-hydraulic tunnel inverted arch trestle-type moving die frame
CN203768814U (en) High-pier minor-radius curve cast-in-situ box girder novel moving die carrier
CN206567423U (en) A kind of straight tube Bending Mould
CN204899941U (en) Whole movable tunnel ditch cable duct formworking jumbo
CN201666157U (en) Inverted arch integral type moving die carrier
CN202132052U (en) Fully-hydraulic tunnel inverted arch trestle-type mobile mold frame
CN202194071U (en) Adjustable inner die
CN203714698U (en) Clothes-hanger transporting device of intelligent clothing product-o-rial system
CN205876349U (en) Whole die carrier of tunnel construction inverted arch of growing up
CN202090932U (en) Universal template device for tunnel construction
CN203531923U (en) Moving framework for tunnel groove construction
CN207406351U (en) A kind of integral type easily moves tunnel Central drain mould bases
CN106089254A (en) Major long tunnel construction inverted arch entirety mould bases
CN205840892U (en) Ditch mould bases is surveyed in self-propelled tunnel
CN202228087U (en) Split-type movable formwork device for tunnel partition wall
CN108005114A (en) A kind of piping lane pours mould
CN202016109U (en) Hydraulic internal mold shared by inclined web box girders with different heights
CN103882992A (en) Connection piece with annular steel bar
CN207775925U (en) A kind of piping lane pours mold
CN205876345U (en) Platform truck system that transports of template is pour to tunnel lateral sulcus cable duct
CN203145327U (en) Pillar vertical steel bar mount apparatus
CN202781376U (en) Square cement flue molding equipment
CN203471913U (en) Concrete hollow block precasting machine
CN202088279U (en) Straight web box girders shared hydraulic internal mold
CN202031604U (en) Flexible side formwork retracting mechanism for tunnel lining cars

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161109