CN201644352U - Coating production line heat energy circulating system - Google Patents

Coating production line heat energy circulating system Download PDF

Info

Publication number
CN201644352U
CN201644352U CN 201020152916 CN201020152916U CN201644352U CN 201644352 U CN201644352 U CN 201644352U CN 201020152916 CN201020152916 CN 201020152916 CN 201020152916 U CN201020152916 U CN 201020152916U CN 201644352 U CN201644352 U CN 201644352U
Authority
CN
China
Prior art keywords
water
production line
coating production
pipe
heat energy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201020152916
Other languages
Chinese (zh)
Inventor
黄立明
吴思明
茅立安
黄中元
陈云
赵瑛
沈一平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Mingquan Industrial Coating Co Ltd
Original Assignee
Zhejiang Mingquan Industrial Coating Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Mingquan Industrial Coating Co Ltd filed Critical Zhejiang Mingquan Industrial Coating Co Ltd
Priority to CN 201020152916 priority Critical patent/CN201644352U/en
Application granted granted Critical
Publication of CN201644352U publication Critical patent/CN201644352U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Drying Of Solid Materials (AREA)

Abstract

The utility model relates to a coating production line heat energy circulating system which comprises a heating sink of a coating production line pre-treatment system and a drying box of a drying device of a coating production line. A stainless steel liner and an inflamer are fixed in a furnace body; the inflamer is fixed at the lower part of the stainless steel liner; an air outlet of a circulating hot air fan is connected with the furnace body; an atmosphere connection hole directly connected with the atmosphere is arranged at the top of the furnace body; a water outlet pipe and a water return pipe are arranged on the stainless steel liner; a hot water circulating water pump is arranged on the water outlet pipe; the water outlet pipe is connected with the heating sink of the coating production line pre-treatment system and a hot water inlet of the drying box of the drying device of the coating production line; and the heating sink of the coating production line pre-treatment system and a hot water outlet of the drying box of the drying device of the coating production line are connected with the water return pipe. The utility model has good permissibility, convenient maintenance and no phenomenon of loop and negative pressure of the water outlet pipe, and solves the problems of cavitation of the circulating water pump and system line shock.

Description

A kind of heat energy circulating system of coating production line
Technical field:
The utility model relates to the coating equipment technical field, more specifically to the heat energy EGR that is serially connected on the paint line.
Background technology:
Paint line mainly comprises pre-treatment purging system (pre-processing device), paint finishing (plastic-blasting complete set of equipments, electrostatic generator, powder spraying apparatus, paint spraying apparatus etc.), heat energy circulation pre-treatment and drying equipment, baking vanish antiknock device or the like.
In the pre-treatment purging system and the drying equipment course of work, need a large amount of hot water that use, general producer provides hot water for purging system and drying equipment by normal-pressure hot-water boiler, and its weak point is:
1, guarantees under any condition all problems of pressure-bearing not of boiler.Be to guarantee the most important specification requirement of normal-pressure hot-water boiler elimination blast, but at present a lot of normal-pressure boiler can't guarantee.
2, the vertical normal-pressure hot-water boiler that has is got a foothold and is enclosed no inspection opening, and incrustation scale is piled up at leftover bits and pieces circle place, and sediment can't be removed.
3, negative pressure problem appears in the loop.When the static pressure of normal-pressure hot-water boiler heating system during less than the height of system, negative pressure appearance appears in system, and it is more serious that negative pressure condition appears in single-point level pressure system circuit, if moving under the negative pressure appears in the loop, the possibility that sucks air is arranged, influence the operate as normal of water circulating pump.
4, negative pressure appears in the body of heater outlet pipe.The pressure of water is the system pressure lowest part in the boiler discharging tube, if outlet pipe installation site height, the outlet pipe drag losses is big, and negative pressure appearance will appear in outlet pipe, influences the water circulating pump operate as normal.
5, water circulating pump cavitation problem.Water circulating pump porch pressure is low, but water temperature is the highest, and water might be vaporized, and the cavitation problem appears in water pump.Cavitation is very big to water pump harm, and negative pressure appearance will appear in outlet pipe, influences the water circulating pump operate as normal.
6, system's water attack problem.When cutting off the water pump, drop in the boiler in order to prevent system water, must close the keying valve rapidly, prevent that the water of certain kinetic energy from producing impact (that is: water attack) to system.Water attack feeds through to fin along pipeline, can damage.
The utility model content
The technical problems to be solved in the utility model provides a kind of heat energy circulating system of coating production line, and its explosion-proof is good, and maintenance is convenient, stops loop, outlet pipe negative pressure appearance, has solved water circulating pump cavitation problem and system's water attack problem.
For solving the problems of the technologies described above, the utility model adopts following technical scheme:
Heat energy circulating system of coating production line, the drying baker that comprises the drying equipment that adds hot water storgae and paint line of paint line preprocessing system, be fixed with stainless steel inner container and burner in the body of heater, the bottom fixed combustion device of stainless steel inner container, the air outlet of cycling hot blower fan connects body of heater, and the body of heater top is provided with the atmosphere connection port that directly leads to atmosphere;
Set out water pipe and return pipe on the stainless steel inner container, hot-water circulating pump is installed on the outlet pipe, outlet pipe connects the hot water water inlet of drying baker of the drying equipment that adds hot water storgae and paint line of paint line preprocessing system, and the hot water outlet of the drying baker of the drying equipment that adds hot water storgae and paint line of paint line preprocessing system connects return pipe;
Stainless steel inner container has connected outside expansion tank, and expansion tank is provided with filling pipe, has connected breather pipe on the expansion tank, and the breather pipe height is no more than 2m.
The distance that described hot-water circulating pump center line of suction is lower than the lowest water level line of stainless steel inner container is not less than 2 meters.
Hot blast outlet pipeline in the drying baker of the drying equipment of described paint line leads to body of heater.
Water dirt separator, resistance control valve and keying valve are installed on the described return pipe.
The box height of described outside expansion tank is that volume is no more than 2m about 1 meter 3, more than the blow vent diameter 100mm of breather pipe, outside expansion tank is provided with overflow pipe.
Described hot-water circulating pump adopts R series of heat water pump, and the platform number should be no less than 2, an operation, and one is standby.
The bottom of described body of heater is provided with the blow-off pipe that connects with stainless steel inner container.
The smoke discharging pipe of described burner is fixed on the body of heater.
Advantage of the present utility model is:
1, the bottom of described body of heater is provided with blow-off pipe, the feasible incrustation scale of removing in the stainless steel inner container, and sediment is very convenient.
2, the utility model adopts the inner bag delivery port to link to each other with pump entry, circulating hot water is released from inner bag, after the heat-exchanger pump pressurization, be sent to Coating Pretreatment and drying system through pipe network, when circulating hot water returns inner bag, through dirt separator, resistance control valve and keying valve, be back to inner bag then.Wherein resistance control valve and keying valve are peculiar by the mechanical circulation type heating system.
Wherein resistance control valve can adopt stop valve, gate valve etc., when it can make the heat energy circulation center of water under returning atmospheric pressure state that pressure is arranged in the circulation line, with the backwater decompression, simultaneously, the continuous variation of operating mode in the operational system is had regulatory function.The function that opens and closes valve is unexpected when out of service at circulating pump, in time cuts off pipeline, prevents that negative pressure problem from appearring in the loop, negative pressure and system's water attack problem appear in the body of heater outlet pipe.
3, the distance between the lowest water level line of hot-water circulating pump center line of suction and stainless steel inner container is not less than 2 meters.Can avoid water circulating pump cavitation problem like this, because this distance can guarantee that cavitation phenomenons does not take place water circulating pump porch pressure.
Description of drawings
Fig. 1 is a structural representation of the present utility model
The specific embodiment:
Embodiment, see shown in Figure 1, heat energy circulating system of coating production line, the drying baker 2 that comprises the drying equipment that adds hot water storgae 1 and paint line of paint line preprocessing system, be fixed with stainless steel inner container 4 and burner 5 in the body of heater 3, the bottom fixed combustion device 5 of stainless steel inner container 4, the air outlet of cycling hot blower fan 6 connects body of heater 3, and body of heater 3 tops are provided with the atmosphere connection port 31 that directly leads to atmosphere;
Set out water pipe 41 and return pipe 42 on the stainless steel inner container 4, hot-water circulating pump 7 is installed on the outlet pipe 41, outlet pipe 41 connects the hot water water inlet of drying baker 2 of the drying equipment that adds hot water storgae 1 and paint line of paint line preprocessing system, and the hot water outlet of the drying baker 2 of the drying equipment that adds hot water storgae 1 and paint line of paint line preprocessing system connects return pipe 42.
Stainless steel inner container 4 has connected outside expansion tank 8, and expansion tank 8 is provided with filling pipe 81, has connected breather pipe 82 on the expansion tank 8, and breather pipe 82 highly is no more than 2m.
The distance that described hot-water circulating pump 7 center line of suction are lower than the lowest water level line of stainless steel inner container 4 is not less than 2 meters.
Hot blast outlet pipeline in the drying baker 2 of the drying equipment of described paint line leads to body of heater 3.
Water dirt separator 9, resistance control valve 421 are installed on the described return pipe 42 and open and close valve 422.
The box height of described outside expansion tank 8 is that volume is no more than 2m about 1 meter 3, more than the blow vent diameter 100mm of breather pipe 82, outside expansion tank 8 is provided with overflow pipe.
Described hot-water circulating pump 7 adopts R series of heat water pump, and the platform number should be no less than 2, an operation, and one is standby.
The bottom of described body of heater 3 is provided with the blow-off pipe 32 that connects with stainless steel inner container 4.
The smoke discharging pipe 51 of described burner 5 is fixed on the body of heater 3.
Burner 5 part-structures are as follows:
Manual ball valve: be combustion gas enters the control and regulation pipe-line system from supply air line gate.
Tar filters: filter by the grease that fuel produced, make the clean hot blast air of burning.
Middle pressure, micromanometer detect: guaranteeing pressure stability, is to monitor gas pressure in the pipeline, is pressed in about 0.5 ~ 1.5kg in the ordinary circumstance requirement gas pressure, and minute-pressure is in 250 ~ 380 millimeters of water.
Pressure regulator valve: the middle compression ignite gas gas of bringing in the pipeline is done suitably size adjustment, on the micromanometer of back one-level, present the stable air pressure counting that needs, to satisfy the needs of burner operation air pressure.
High-low pressure combustion gas sense switch: in the gas supply pipeline, minute-pressure has changed protection monitoring effect, and when combustion gas air pressure was high or low, sense switch sent the ultimate interlock protection of alarm signal.
The main fire and the gas control valve of lighting a fire: cut-off the air feed approach automatically, according to system's operation sequence control combustion gas tolerance break-make, its main task is to finish igniting to ignite, the combustion-supporting programme-control of main fire intensification.
Ratio governor motor and proportional control valve: along with the variation of water temperature, the command signal that provides according to the temperature monitor is suitably controlled the size of pipeline internal combustion entraining air stream amount, adjust the height of combustion gas value, temperature is controlled in the scope that needs, control is accurately effectively given system by sending action command after the micro computer calculation.
Blast switch: test combustion chamber circulating fan is pumped the wind pressure condition detection; when blast pressure is lower than the atmospheric pressure value that sets when blower fan operates; during anisotropy; can send a signal does to cut off control circuit and send alarm signal for the monitoring system center; stop the tempering accident to take place, play the safety interlocking protective effect.
Computer flame monitor: be the heart of whole system, in system, keep chain with the micro computer temperature controller.Be commander's maincenter that monitor protection starts operation, system normally started, safe operation, the temperature adjustment, control critical guarantee accurately arranged.
Ignition transformer: tie with spark in the burner and to connect, the chain program of ignition controller is finished system's ignition trigger jointly, and performance produces 6KV ~ 18KV high pressure, and the ignition trigger time is 10 seconds, and spark rate is 50 ~ 60HZ.
Safety device: control system is provided with the overtemperature alarm device, the combustion gas leak detection.When overtemperature, the auto controlled heater burning, when combustion gas was revealed, it can send alarm signal immediately, cut off the heating system working procedure.This shows that direct combustion hot blast stove system device security performance has reached strong technical guarantee.No matter which rank of breaks down, and all can close whole systems automatically, plays the ultimate protection of absolute system.
Burner 5 parts of the present utility model adopt three return structures, big capacity combustion chamber, and high-performance heat transfer components-threaded flue, the shell and tube burning, burning is complete, thermal efficiency height, energy-conserving and environment-protective realize intelligent control, the high-heat fiber is heat insulation layer, and is extremely efficient in preserving heat; Whole steel construction base, installation in position is convenient; The body of heater top is provided with atmosphere normal open mouth, and is safe in utilization; Is furnished with the high-voltage pulse igniting, flame-out overtemperature prote, temperature control, time control; Fuel is suitable for gas, liquid fuels such as light oil, heavy oil, town gas, natural gas; The configurable condensing heat exchanger of exhaust opening (can match), the water vapour in the condensation flue gas absorbs the latent heat of condensation, thereby improves the thermal efficiency of heat energy stove; Heat energy furnace body and atmosphere are connected, configuration expansion tank, normal pressure operation down, no hidden danger; Use advanced touch controller, digital inspection control system has timing controlled, and work record, leakage alarm function realize Automatic Control, regulate automatically going out hot water.

Claims (8)

1. heat energy circulating system of coating production line comprises it is characterized in that the drying baker (2) of the drying equipment that adds hot water storgae (1) and paint line of paint line preprocessing system:
Be fixed with stainless steel inner container (4) and burner (5) in the body of heater (3), the bottom fixed combustion device (5) of stainless steel inner container (4), the air outlet of cycling hot blower fan (6) connects body of heater (3), and body of heater (3) top is provided with the atmosphere connection port (31) that directly leads to atmosphere;
Set out water pipe (41) and return pipe (42) on the stainless steel inner container (4), hot-water circulating pump (7) is installed on the outlet pipe (41), outlet pipe (41) connects the hot water water inlet of drying baker (2) of the drying equipment that adds hot water storgae (1) and paint line of paint line preprocessing system, and the hot water outlet of the drying baker (2) of the drying equipment that adds hot water storgae (1) and paint line of paint line preprocessing system connects return pipe (42);
Stainless steel inner container (4) has connected outside expansion tank (8), and expansion tank (8) is provided with filling pipe (81), has connected breather pipe (82) on the expansion tank (8), and breather pipe (82) highly is no more than 2m.
2. heat energy circulating system of coating production line according to claim 1 is characterized in that: the distance that hot-water circulating pump (7) center line of suction is lower than the lowest water level line of stainless steel inner container (4) is not less than 2 meters.
3. heat energy circulating system of coating production line according to claim 1 is characterized in that: the hot blast outlet pipeline in the drying baker of the drying equipment of paint line (2) leads to body of heater (3).
4. heat energy circulating system of coating production line according to claim 1 is characterized in that: water dirt separator (9), resistance control valve (421) are installed on the return pipe (42) and open and close valve (422).
5. heat energy circulating system of coating production line according to claim 1 is characterized in that: the box height of outside expansion tank (8) is that volume is no more than 2m about 1 meter 3, more than the blow vent diameter 100mm of breather pipe (82), outside expansion tank (8) is provided with overflow pipe.
6. heat energy circulating system of coating production line according to claim 1 is characterized in that: hot-water circulating pump (7) adopts R series of heat water pump, and the platform number should be no less than 2, an operation, and one is standby.
7. heat energy circulating system of coating production line according to claim 1 is characterized in that: the bottom of described body of heater (3) is fixed with the blow-off pipe (32) that connects with stainless steel inner container (4).
8. heat energy circulating system of coating production line according to claim 1 is characterized in that: the smoke discharging pipe (51) of burner (5) is fixed on the body of heater (3).
CN 201020152916 2010-04-08 2010-04-08 Coating production line heat energy circulating system Expired - Lifetime CN201644352U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201020152916 CN201644352U (en) 2010-04-08 2010-04-08 Coating production line heat energy circulating system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201020152916 CN201644352U (en) 2010-04-08 2010-04-08 Coating production line heat energy circulating system

Publications (1)

Publication Number Publication Date
CN201644352U true CN201644352U (en) 2010-11-24

Family

ID=43109548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201020152916 Expired - Lifetime CN201644352U (en) 2010-04-08 2010-04-08 Coating production line heat energy circulating system

Country Status (1)

Country Link
CN (1) CN201644352U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101799204A (en) * 2010-04-08 2010-08-11 浙江明泉工业涂装有限公司 Heat energy circulating system of coating production line
CN104533387A (en) * 2014-11-04 2015-04-22 四川红光机械有限公司 Closed open-flow combustion device of gas well
CN106440359A (en) * 2016-11-18 2017-02-22 昆山资福机电工程有限公司 Hot water circulating system for coating production operation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101799204A (en) * 2010-04-08 2010-08-11 浙江明泉工业涂装有限公司 Heat energy circulating system of coating production line
CN101799204B (en) * 2010-04-08 2013-05-22 浙江明泉工业涂装有限公司 Heat energy circulating system of coating production line
CN104533387A (en) * 2014-11-04 2015-04-22 四川红光机械有限公司 Closed open-flow combustion device of gas well
CN106440359A (en) * 2016-11-18 2017-02-22 昆山资福机电工程有限公司 Hot water circulating system for coating production operation

Similar Documents

Publication Publication Date Title
CN201644352U (en) Coating production line heat energy circulating system
CN101799204B (en) Heat energy circulating system of coating production line
CN104654311B (en) A kind of marine incinerator processing system
CN201293329Y (en) Respective ignition type gas pulse sootblower
CN201041376Y (en) Environment-friendly, safe and split combination type alcohol group liquid fuel kitchen range
CN202598553U (en) Intelligent fuel gas pulse shock wave soot blower
CN206861887U (en) Integral vacuum phase transformation water batch heater
CN203116043U (en) Online shock ash removing device of crumple-type boiler
CN202598487U (en) Energy-saving environment-friendly coal gasification boiler
CN103216808A (en) Alcohol group steam generator
CN204201473U (en) A kind of BOG of LNG landing stage formula gas station reclaims power generation system
CN208687696U (en) A kind of three backhaul Split type gas steam generators
CN209026776U (en) A kind of biogas steam generator
CN105299606A (en) Temperature different water inlet afterheat circulating boiler
CN202613412U (en) Intelligent efficient environment-friendly energy absorbing device
CN205783749U (en) A kind of three backhaul water heaters in terms of hot-water boiler
CN201680369U (en) Combustor for heat energy circulating system of coating production line
CN206831533U (en) A kind of shock-wave ash blowing air distributing device
CN206875392U (en) A kind of scale protective type steam boiler
CN102072485B (en) Water and heavy oil hybrid burner
CN205137404U (en) Energy -efficient full -automatic gas vapor generation stove
CN205827769U (en) A kind of simulated explosion burning generating means
CN205402711U (en) Explosion burning simulation generating device
CN203571694U (en) Steam boiler
CN202066006U (en) Combustor using water and heavy oil in mixture

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20101124

Effective date of abandoning: 20130522

RGAV Abandon patent right to avoid regrant