CN1749484A - Construction method for prefabricated tubular pile with expanding head - Google Patents

Construction method for prefabricated tubular pile with expanding head Download PDF

Info

Publication number
CN1749484A
CN1749484A CN 200510094851 CN200510094851A CN1749484A CN 1749484 A CN1749484 A CN 1749484A CN 200510094851 CN200510094851 CN 200510094851 CN 200510094851 A CN200510094851 A CN 200510094851A CN 1749484 A CN1749484 A CN 1749484A
Authority
CN
China
Prior art keywords
pile
prefabricated tubular
tubular pile
enlarged footing
point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200510094851
Other languages
Chinese (zh)
Other versions
CN100516377C (en
Inventor
卫龙武
徐冬生
吕福明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wei Longwu
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2005100948518A priority Critical patent/CN100516377C/en
Publication of CN1749484A publication Critical patent/CN1749484A/en
Application granted granted Critical
Publication of CN100516377C publication Critical patent/CN100516377C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The construction method of prefabricated tubular pile with expanded head is for reinforcing foundation in building base engineering. The expanded head is formed through explosion. The construction method includes the steps of: depositing the prefabricated tubular pile and hollow pile tip to set depth; setting explosive through the central hole of the hollow pile tip; detonating explosive to form the expanded head in the pile tip; throwing stuffing to the expanded head and tamping; and depositing concrete to form the pile end reinforcing area and expanded head. The said method can raise the bearing capacity of the pile, improve the mechanical performance of the soil in the pile end, avoids softening of the soil in the pile end and lower engineering cost.

Description

The job practices that has the prefabricated tubular pile of enlarged footing
Technical field
The present invention is a kind of method that building foundation engineering is reinforced ground that is used for, and belongs to the technical field of civil engineering pile foundation construction method.
Background technology
In building foundation engineering, adopt various pileworks in a large number, because prefabricated tubular pile has intensity height, material province, plurality of advantages such as speed of application is fast, cost is relatively low, the easy assurance of quality, therefore be most widely used.Pile tube is divided into various ways such as pile for prestressed pipe, high intensity thinner tube pile tube.Because of mostly prefabricated tubular pile is to sink in the soil by the method for static pressure or hammering, so it is an orthoscopic entirely.In order to increase the bearing capacity of prefabricated tubular pile, the technology of the minority enlarged footing of can constructing in the ground of stake bottom is arranged at present, but these job practicess or needs band water pore-forming, this brings difficulty for concrete perfusion, be to ram expansion in the pipe in that concrete is dropped in, this causes the damage of prefabricated tubular pile easily, and the stake point sinks seldom, be difficult to form enlarged footing, the difficult quality guarantee of engineering.
Summary of the invention
Technical problem: the prefabricated tubular pile that the objective of the invention is to have enlarged footing at the stake end, a kind of job practices that has the prefabricated tubular pile of enlarged footing is provided, use this method can greatly improve the bearing capacity of stake, improve the mechanics index of physics of stake end soil, avoid the softening of stake end soil, easy construction reduces construction costs.
Technical scheme: the present invention is directed to stake and hold the construction technology of the prefabricated tubular pile that has enlarged footing to design.The composition that the stake end has the prefabricated tubular pile of enlarged footing comprises: tubulose precast pile, hollow pile point, enlarged footing.
Its basic construction technology has explosion method and companding method, and wherein the construction technology of explosion method is as follows:
(1) utilize pile sinking machinery that prefabricated tubular pile and hollow pile point are sink to predetermined absolute altitude;
(2) utilize the middle hole of hollow pile point to throw in explosive;
(3) ignition charge;
(4) form enlarged footing at the stake end;
(5) in the explosive expansion head, throw in filler (rubble etc.), and compacting;
(6) pouring concrete forms the stake end and enlarges the reinforcement district;
In construction technology, the method that forms enlarged footing at the stake end can also be the companding method:
1) utilize pile sinking machinery that prefabricated tubular pile and hollow pile point are sink to predetermined absolute altitude,
2) in prefabricated tubular pile, with the downward hammering of depression bar hollow pile point is continued to pressing down, and make the hollow pile point around to extending out out,
4) between hollow pile point and prefabricated tubular pile, throw in filler,
5) press down to make with depression bar again and throw in filler and enlarge downwards and towards periphery, and compacting, form the stake end and enlarge and strengthen the district, form enlarged footing at the stake end.
Beneficial effect: the present invention holds the prefabricated tubular pile that has enlarged footing for stake, and the pile sinking mode adopts static pressure method or hammering method, quick construction.Because the form of explosion is adopted in the reaming of stake end, it is more quick construct, also better to the compacted effect of stake end soil simultaneously, thereby has increased a kind of novel, type efficiently for pile foundation engineering.Compare with common prefabricated tubular pile, the stake end area of the prefabricated tubular pile of band enlarged footing increases, greatly improved the bearing capacity of stake, secondly, again because of having improved the mechanics index of physics of stake end soil, to strong-weathered rock, also avoid the softening of stake end soil, further reduced the sedimentation of stake, reduced the quantity of stake, reduce the size and the arrangement of reinforcement of cushion cap, reduced construction costs.
Description of drawings
Fig. 1 is the schematic flow sheet of the construction technology step of explosion method of the present invention.
Fig. 2 is the schematic flow sheet of companding method construction technology step of the present invention.
Have among the figure: prefabricated tubular pile 1, hollow pile point 2, explosive 3 is ignited lead 4, explosive expansion 5, filler 6, back pouring concrete 7, depression bar 8.
The specific embodiment
Explosion method embodiment: prefabricated tubular pile external diameter Φ 500mm, internal diameter Φ 340mm, the long 10m of stake, soil layer is a silty clay, bearing course at pile end is a strong-weathered rock.During construction, measure the pile positioning unwrapping wire earlier, put special hollow pile point well, with 400 tons Static pressure pile driver prefabricated tubular pile and hollow pile point are depressed into predetermined absolute altitude then, put into quick-fried medicine of 0.8kg and ignition, record an explosive expansion diameter of phi 1000mm, insert filler 0.4m such as rubble at last 3, after water C30 concrete 0.3m 3Finish the construction of the prefabricated tubular pile that has enlarged footing.
Companding method embodiment: prefabricated tubular pile external diameter Φ 500mm, internal diameter Φ 340mm, the long 12m of stake, soil layer is followed successively by: miscellaneous fill, silty clay, bearing course at pile end are plastic clay.Behind the measurement and positioning unwrapping wire, put special stake point well, with 400 tons Static pressure pile driver prefabricated tubular pile and special stake point are depressed into predetermined absolute altitude then, and be the weight impact pile point of 300mm with diameter, make stake sharp sinking 700mm (can make the gap that 700mm is arranged between a point and the pile tube like this), insert the high rubble of 800mm then, ram rubble with weight again, make its to around prolong expansion, so repeated multiple times reaches design standard until the hammering pile penetration, irritates at last again and puts 0.2 cubic metre of C30 concrete, so just form enlarged footing, finished the construction of the prefabricated tubular pile that has enlarged footing.

Claims (2)

1. a job practices that has the prefabricated tubular pile of enlarged footing is characterized in that the enlarged footing of prefabricated tubular pile bottom adopts the method for blast to form, and its concrete construction technology is as follows:
1) utilize pile sinking machinery that prefabricated tubular pile (1) and hollow pile point (2) are sink to predetermined absolute altitude;
2) utilize the middle hole of hollow pile point (2) to throw in explosive (3);
3) ignition charge (3);
4) form explosive expansion head (5) at the stake end;
5) in explosive expansion head (5), throw in filler (6), and compacting;
6) pouring concrete (7) forms the stake end and enlarges the reinforcement district.
2. the job practices that has the prefabricated tubular pile of enlarged footing according to claim 1 is characterized in that in construction technology, and the method that forms enlarged footing at the stake end is:
1) utilize pile sinking machinery that prefabricated tubular pile (1) and hollow pile point (2) are sink to predetermined absolute altitude,
2) in prefabricated tubular pile (1), with depression bar (8) hammering downwards hollow pile point (2) is continued to pressing down, and make hollow pile point (2) around to extending out out,
4) between hollow pile point (2) and prefabricated tubular pile (1), throw in filler,
5) use depression bar (8) hammering downwards to make again and throw in the downward and expansion towards periphery of filler, and compacting, form an end expansion and strengthen the district, at stake end formation enlarged footing.
CNB2005100948518A 2005-10-17 2005-10-17 Construction method for prefabricated tubular pile with expanding head Expired - Fee Related CN100516377C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100948518A CN100516377C (en) 2005-10-17 2005-10-17 Construction method for prefabricated tubular pile with expanding head

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100948518A CN100516377C (en) 2005-10-17 2005-10-17 Construction method for prefabricated tubular pile with expanding head

Publications (2)

Publication Number Publication Date
CN1749484A true CN1749484A (en) 2006-03-22
CN100516377C CN100516377C (en) 2009-07-22

Family

ID=36605123

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100948518A Expired - Fee Related CN100516377C (en) 2005-10-17 2005-10-17 Construction method for prefabricated tubular pile with expanding head

Country Status (1)

Country Link
CN (1) CN100516377C (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100429353C (en) * 2006-06-27 2008-10-29 中国矿业大学 Explosion-enlarging stake construction process
CN101153489B (en) * 2006-09-21 2010-06-16 王国奋 Bottom expanding and piling method by demolishing of pipe sank prefabricated steel concrete bottom expansion pile
CN101153490B (en) * 2006-09-21 2010-06-23 王国奋 Bottom expanding and piling method by demolishing of pipe sank prefabricated steel concrete bottom expansion pile
CN101936004A (en) * 2010-08-25 2011-01-05 张继红 Precast expanding pile as well as construction method and construction mechanical equipment thereof
CN102051877A (en) * 2010-12-01 2011-05-11 张继红 Prefabricated squeezing-expanding pile and construction method thereof
CN103290837A (en) * 2013-06-06 2013-09-11 金陵科技学院 Construction method of explosive expanding of cast-in-place pile and air exhausting device thereof
CN103821146A (en) * 2014-02-12 2014-05-28 杭州建工集团有限责任公司 Pile detonating and cutting construction process for PC (prestressed concrete) tubular piles
CN104727309A (en) * 2015-02-02 2015-06-24 中国电力工程顾问集团中南电力设计院有限公司 Construction technology of squeeze-in expanded-base pipe pile
CN105113501A (en) * 2015-08-14 2015-12-02 太原理工大学 External expansion type large-diameter cylinder suction pile provided with explosive enlargement device
CN105649015A (en) * 2016-02-01 2016-06-08 安徽理工大学 Anti-sedimentation tubular pile for blasting grouting
CN112144522A (en) * 2020-10-20 2020-12-29 王继忠 Construction method of prestressed pipe pile and special prestressed pipe pile thereof
CN112482357A (en) * 2020-12-04 2021-03-12 浙大城市学院 Drilling tool for pre-blasting cement mixing pile suitable for hard soil layer and application method thereof

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100429353C (en) * 2006-06-27 2008-10-29 中国矿业大学 Explosion-enlarging stake construction process
CN101153489B (en) * 2006-09-21 2010-06-16 王国奋 Bottom expanding and piling method by demolishing of pipe sank prefabricated steel concrete bottom expansion pile
CN101153490B (en) * 2006-09-21 2010-06-23 王国奋 Bottom expanding and piling method by demolishing of pipe sank prefabricated steel concrete bottom expansion pile
CN101936004A (en) * 2010-08-25 2011-01-05 张继红 Precast expanding pile as well as construction method and construction mechanical equipment thereof
CN102051877A (en) * 2010-12-01 2011-05-11 张继红 Prefabricated squeezing-expanding pile and construction method thereof
CN102051877B (en) * 2010-12-01 2012-05-30 张继红 Prefabricated squeezing-expanding pile and construction method thereof
CN103290837A (en) * 2013-06-06 2013-09-11 金陵科技学院 Construction method of explosive expanding of cast-in-place pile and air exhausting device thereof
CN103821146B (en) * 2014-02-12 2015-08-19 杭州建工集团有限责任公司 A kind of explosion cutting piles technique of PC pile tube
CN103821146A (en) * 2014-02-12 2014-05-28 杭州建工集团有限责任公司 Pile detonating and cutting construction process for PC (prestressed concrete) tubular piles
CN104727309A (en) * 2015-02-02 2015-06-24 中国电力工程顾问集团中南电力设计院有限公司 Construction technology of squeeze-in expanded-base pipe pile
CN105113501A (en) * 2015-08-14 2015-12-02 太原理工大学 External expansion type large-diameter cylinder suction pile provided with explosive enlargement device
CN105113501B (en) * 2015-08-14 2017-05-31 太原理工大学 Formula large diameter cylinder suction anchor is extended out with explosive expansion device
CN105649015A (en) * 2016-02-01 2016-06-08 安徽理工大学 Anti-sedimentation tubular pile for blasting grouting
CN105649015B (en) * 2016-02-01 2017-06-16 安徽理工大学 A kind of blasting grouting anti-settling pile tube
CN112144522A (en) * 2020-10-20 2020-12-29 王继忠 Construction method of prestressed pipe pile and special prestressed pipe pile thereof
CN112482357A (en) * 2020-12-04 2021-03-12 浙大城市学院 Drilling tool for pre-blasting cement mixing pile suitable for hard soil layer and application method thereof

Also Published As

Publication number Publication date
CN100516377C (en) 2009-07-22

Similar Documents

Publication Publication Date Title
CN100516377C (en) Construction method for prefabricated tubular pile with expanding head
CN102011399B (en) PHC pile-based multiple high jet pedestal pile construction method
CN102733376A (en) Composite pile and construction method thereof
CN106192999A (en) The construction method of uplift pile
CN103015396A (en) Construction method of soft foundation
CN1052284C (en) Method for construction of concrete pile
CN104711974A (en) Steel tube recycled concrete composite bearing base pile and manufacturing method thereof
CN102409667B (en) Construction device and construction process of extruded and expanded cast-in-place pile
CN103835292B (en) High frequency vibrating rushes the construction method of base-extending deposited pile tube
CN1488818A (en) Jacketed disc pile and piling method, extruding-expanding device, pile sinking machine and use
CN104762956B (en) Method for forming pile based on construction waste recycled aggregate
CN101936004A (en) Precast expanding pile as well as construction method and construction mechanical equipment thereof
CN211646445U (en) Riprap layer pile
CN104895078B (en) A kind of to hold the construction method of the prefabricated pile of holding capacity
CN113863294B (en) PHC pipe pile internally provided with pile end grouting device and construction process thereof
CN201679450U (en) Bidirectional spiral extruding reaming drill with soil guiding grooves
CN113106969A (en) Stiff carrier pile and construction process
CN100387789C (en) Concrete pile construction method
CN101672036B (en) Construction method of static pressure high-tonnage precast end-bearing pile
CN1029526C (en) Pile-forming method by hole-leading mud-jacking pile-sinking
CN1053723C (en) Punched pressure-pipe type rammed rubble pile construction method
CN103410141A (en) Process for forming piles on mine dumping field
CN219261087U (en) Offshore wind power annular drilling rock-socketed single pile foundation
CN2695485Y (en) Pre-tensioning system prestressed concrete pile
CN103215959B (en) The support construction method that V-arrangement preformed pile is combined with agitation pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 210037 Jiangsu Province, Nanjing City Central Lake Garden Room 401 13

Patentee after: Wei Longwu

Address before: 210037 Jiangsu Province, Nanjing City Central Lake Garden Room 401 13

Patentee before: Wei Longwu

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Construction method for prefabricated tubular pile with expanding head

Effective date of registration: 20120713

Granted publication date: 20090722

Pledgee: Bank of Communications Ltd Jiangsu branch

Pledgor: Wei Longwu

Registration number: 2012990000371

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090722

Termination date: 20121017

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20131106

Granted publication date: 20090722

Pledgee: Bank of Communications Ltd Jiangsu branch

Pledgor: Wei Longwu

Registration number: 2012990000371

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model