CN114346191B - 一种预防厚板坯快换水口期间漏钢预报***重报警的方法 - Google Patents
一种预防厚板坯快换水口期间漏钢预报***重报警的方法 Download PDFInfo
- Publication number
- CN114346191B CN114346191B CN202111491129.3A CN202111491129A CN114346191B CN 114346191 B CN114346191 B CN 114346191B CN 202111491129 A CN202111491129 A CN 202111491129A CN 114346191 B CN114346191 B CN 114346191B
- Authority
- CN
- China
- Prior art keywords
- quick
- water gap
- replacement
- controlled
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P10/00—Technologies related to metal processing
- Y02P10/20—Recycling
Landscapes
- Continuous Casting (AREA)
Abstract
一种预防厚板坯快换水口期间漏钢预报***重报警的方法,包括如下方法:控制快换罐次钢水硫磺含量、锰硫比、锰硅比及钢水碳含量,增加钢水过热度;快换水口前降低拉速,并调整渣线位置、中包礠尺位置、结晶器液位、水口氩气流量,塞棒氩气流量;备换水口自安装在更换装置上后要在8s内完成快换,快换时关闭塞棒时间控制在2s~3s,更换后3s内卸下的水口;快换水口后控制拉速并对结晶器内冷渣条进行清理,调整结晶器液位至800mm,而后升至标准拉速,快换后调整回水口氩气流量和塞棒氩气流量。采用本发明方法后,快换水口前后的粘结重报警次数减少至改良前的50%,浇注状态趋于平稳,生产稳定性提高。
Description
技术领域
本发明涉及钢铁冶金领域,特别涉及一种预防厚板坯快换水口期间漏钢预报***重报警的方法。
背景技术
某钢铁公司一分厂厚板坯铸机改造后,大浇次生产得到极大提高,这种大浇次生产,在现有的侵入式水口条件下无法得到满足,生产中必须在适当时间进行在线快换中包浸入式水口操作。由于快换水口期间对结晶器内钢水产生了较大的扰动,导致液渣流入极度不均、钢水温度场极度紊乱,最终导致快换水口前后频发地发生重报警。
发明内容
本发明的目的在于提供一种预防厚板坯快换水口期间漏钢预报***重报警的方法,本发明的方法可以大幅度提高快换水口期间结晶器内各项工艺参数的稳定性,减少重报警次数,提高成材率。
为了达到上述目的,本发明采用以下技术方案实现:
一种预防厚板坯快换水口期间漏钢预报***重报警的方法,包括如下方法:
1)备换水口在快换操作前保证2小时以上的煤气烘烤,煤气流量设定为80m3/h~90m3/h,保证水口处于红热状态;
2)快换罐次确保钢水硫磺含量小于0.005wt%,锰硫比大于40,锰硅比大于3,包晶钢钢水碳含量控制在0.08wt%~0.1wt%,中碳钢碳含量要控制在0.18wt%~0.20wt%,中包钢水过热度控制在15℃~20℃;
3)快换水口前拉速降至0.50m/min~0.55m/min,渣线控制在距浸入式水口下沿164mm~198mm位置,结晶器液位控制在820mm~830mm位置,水口氩气流量设定在1.5NL/min~2.0NL/min,塞棒氩气流量设定在1.0NL/min~1.5NL/min,氩气流量维持时间均控制在1min以上,保证液渣层厚度14mm~16mm之间,上述操作总用时不超过3mim;
4)备换水口自安装在更换装置上后要在8s内完成快换,快换时关闭塞棒时间控制在2s~3s,目测钢水液位刚出现下降迹象时启动液压缸进行快换,更换后3s内用水口夹平缓去除卸下的水口;
5)快换水口时要确保备换水口自煤气关火至完成快换时间间隔不大于2min,快换水口后拉速在0.50m/min~0.55m/min维持2min~3min,在该时间内对结晶器内冷渣条进行清理,并调整结晶器液位至800mm~820mm,调整结晶器液位时间控制在30s~40s,而后再进行自动升速升至标准拉速,升速梯度为0.05m/30s~0.05m/45s,快换后水口氩气流量由1.5NL/min~2.0NL/min逐步调整到1.0NL/min~1.5NL/min,塞棒氩气流量由1.0NL/min~1.5NL/min逐步调整到0.8NL/min~1.2NL/min。
上述步骤4)中的标准拉速为1.1m/min~1.3m/min。
上述步骤4)中升速梯度为0.05m/30s。
上述步骤2)中快换水口前拉速降至0.5m/min;上述步骤4)中快换水口后拉速在0.5m/min维持2min~3min。
与现有技术相比,本发明的有益效果是:
1、本发明液渣层可以稳定控制在14mm~16mm之间,现有技术液渣层不稳定,渣膜不均匀,通过专家***热成像图可以明显看出差异;
2、本发明的液位及氩气控制可以很好抑制快换前后期间结晶器钢水液面卷渣,提高渣钢界面稳定性,现有技术卷渣严重,钢渣液面极不平稳;
3、本发明通过钢水碳锰硅成分调整及中包过热度调整,可以降低钢水裂纹敏感性,改善钢水浇铸特性,提高快换期间钢水自身的稳定性,现有技术未做明确要求,成分稳定控制不精确,钢水浇铸性能及力学性能差。
采用本发明方法后,快换水口前后的粘结重报警次数减少至改良前的50%,浇注状态趋于平稳,生产稳定性提高。
具体实施方式
下面通过实施例对本发明进行更详细的描述,这些实施例仅仅是对本发明最佳实施方式的描述,并不对本发明的范围有任何的限制。
实施例1:
钢种:中碳钢,碳成分区间为0.17%≤C≤0.25%。
具体实施方案:
1)备换水口在快换操作前保证2小时以上的煤气烘烤,煤气流量设定为80m3/h,保证水口处于红热状态;
2)快换罐次确保钢水硫磺含量小于0.005%,锰硫比大于40,锰硅比大于3,中碳钢碳含量要控制在0.18%~0.20%,中包钢水过热度控制在15℃~20℃;
3)快换水口前拉速降至0.5m/min,保持该拉速时间在2min~3min,在该时间内完成以下操作:调整渣线控制在距浸入式水口下沿164mm~198mm位置,调整中包礠尺位置设定在14Cm~41cm位置,调整结晶器液位控制在820mm~830mm位置,调整水口氩气流量设定在1.5NL/min~2.0NL/min,调整塞棒氩气流量设定在1.0NL/min~1.5NL/min,以上氩气流量维持时间控制在1min以上,保证液渣层厚度14mm~16mm之间;
4)快换水口时要确保备换水口自煤气关火至完成快换时间间隔不大于2min,备换水口自安装在更换装置上后要在8s内完成快换,快换时关闭塞棒时间控制在2s~3s,目测钢水液位刚出现下降迹象时启动液压缸进行快换,更换后3s内用水口夹平缓去除卸下的水口;
5)快换水口后拉速0.5m/min维持2min~3min,在该时间内对结晶器内冷渣条进行清理,并调整结晶器液位至800mm,结晶器液位调整时间控制在30s~40s,而后再进行自动升速升至标准拉速,升速梯度为0.05m/30s,快换后水口氩气流量由1.5NL/min~1.8NL/min逐步调整到1~1.3NL/min,塞棒氩气流量由1.0NL/min~1.3NL/min逐步调整到0.8NL/min~1.2NL/min。
Claims (6)
1.一种预防厚板坯快换水口期间漏钢预报***重报警的方法,其特征在于,包括如下步骤:
1)快换罐次确保钢水硫磺含量小于0.005wt%,锰硫比大于40,锰硅比大于3,包晶钢钢水碳含量控制在0.08wt%~0.1wt%,中碳钢碳含量要控制在0.18wt%~0.20wt%,中包钢水过热度控制在15℃~20℃;
2)快换水口前拉速降至0.50 m/min~0.55m/min,渣线控制在距浸入式水口下沿164mm~198mm位置,结晶器液位控制在820mm~830mm位置,水口氩气流量设定在1.5NL/min~2.0NL/min,塞棒氩气流量设定在1.0NL/min~1.5NL/min,氩气流量维持时间均控制在1min以上,保证液渣层厚度14mm~16mm之间,上述操作总用时不超过3min;
3)备换水口自安装在更换装置上后要在8s内完成快换,快换时关闭塞棒时间控制在2s~3s,钢水液位下降时进行快换,更换后3s内去除卸下的水口;
4)快换水口后拉速在0.50 m/min~0.55m/min维持2min~3min,在该时间内对结晶器内冷渣条进行清理,并调整结晶器液位至800mm~820mm,调整结晶器液位时间控制在30s~40s,而后再进行升速升至标准拉速,升速梯度为0.05m/30s~0.05m/45s,快换后水口氩气流量由1.5NL/min~2.0NL/min调整到1.0NL/min~1.5NL/min,塞棒氩气流量由1.0NL/min~1.5NL/min调整到0.8NL/min~1.2NL/min。
2.根据权利要求1所述的一种预防厚板坯快换水口期间漏钢预报***重报警的方法,其特征在于,备换水口在快换操作前保证2小时以上的煤气烘烤。
3.根据权利要求2所述的一种预防厚板坯快换水口期间漏钢预报***重报警的方法,其特征在于,煤气流量设定为80m3/h~90m3/h。
4.根据权利要求2所述的一种预防厚板坯快换水口期间漏钢预报***重报警的方法,其特征在于,上述步骤4)中的标准拉速为1.1m/min~1.3m/min。
5.根据权利要求1所述的一种预防厚板坯快换水口期间漏钢预报***重报警的方法,其特征在于,上述步骤4)中升速梯度为0.05m/30s。
6.根据权利要求1所述的一种预防厚板坯快换水口期间漏钢预报***重报警的方法,其特征在于,上述步骤2)中快换水口前拉速降至0.5m/min;上述步骤4)中快换水口后拉速在0.5m/min维持2min~3min。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111491129.3A CN114346191B (zh) | 2021-12-08 | 2021-12-08 | 一种预防厚板坯快换水口期间漏钢预报***重报警的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111491129.3A CN114346191B (zh) | 2021-12-08 | 2021-12-08 | 一种预防厚板坯快换水口期间漏钢预报***重报警的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114346191A CN114346191A (zh) | 2022-04-15 |
CN114346191B true CN114346191B (zh) | 2023-08-18 |
Family
ID=81097998
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111491129.3A Active CN114346191B (zh) | 2021-12-08 | 2021-12-08 | 一种预防厚板坯快换水口期间漏钢预报***重报警的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114346191B (zh) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1342848A (en) * | 1971-02-22 | 1974-01-03 | Concast Ag | Method for controlling a continuous casting plant |
KR20030034961A (ko) * | 2001-10-29 | 2003-05-09 | 주식회사 포스코 | 침지노즐 폐쇄장치 |
KR20030052755A (ko) * | 2001-12-21 | 2003-06-27 | 주식회사 포스코 | 몰드내 용강 유동패턴 운용방법 |
CN105855494A (zh) * | 2015-01-23 | 2016-08-17 | 鞍钢股份有限公司 | 一种低碳铝钢钢水上小方坯铸机的处理方法 |
CN107282902A (zh) * | 2016-04-04 | 2017-10-24 | 鞍钢股份有限公司 | 一种浸入式水口的更换方法 |
CN109332625A (zh) * | 2018-11-08 | 2019-02-15 | 武汉钢铁有限公司 | 一种改善塞棒控流Al脱氧钢水口堵塞的浇铸方法 |
CN111761038A (zh) * | 2019-04-01 | 2020-10-13 | 南京钢铁股份有限公司 | 一种超宽板坯连铸机生产包晶钢的工艺 |
CN112296293A (zh) * | 2020-09-11 | 2021-02-02 | 柳州钢铁股份有限公司 | 双流板坯连铸机浇注中换断面的方法 |
CN113351837A (zh) * | 2021-06-04 | 2021-09-07 | 河南科技大学 | 一种大型钢锭的多包连续浇注方法 |
-
2021
- 2021-12-08 CN CN202111491129.3A patent/CN114346191B/zh active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1342848A (en) * | 1971-02-22 | 1974-01-03 | Concast Ag | Method for controlling a continuous casting plant |
KR20030034961A (ko) * | 2001-10-29 | 2003-05-09 | 주식회사 포스코 | 침지노즐 폐쇄장치 |
KR20030052755A (ko) * | 2001-12-21 | 2003-06-27 | 주식회사 포스코 | 몰드내 용강 유동패턴 운용방법 |
CN105855494A (zh) * | 2015-01-23 | 2016-08-17 | 鞍钢股份有限公司 | 一种低碳铝钢钢水上小方坯铸机的处理方法 |
CN107282902A (zh) * | 2016-04-04 | 2017-10-24 | 鞍钢股份有限公司 | 一种浸入式水口的更换方法 |
CN109332625A (zh) * | 2018-11-08 | 2019-02-15 | 武汉钢铁有限公司 | 一种改善塞棒控流Al脱氧钢水口堵塞的浇铸方法 |
CN111761038A (zh) * | 2019-04-01 | 2020-10-13 | 南京钢铁股份有限公司 | 一种超宽板坯连铸机生产包晶钢的工艺 |
CN112296293A (zh) * | 2020-09-11 | 2021-02-02 | 柳州钢铁股份有限公司 | 双流板坯连铸机浇注中换断面的方法 |
CN113351837A (zh) * | 2021-06-04 | 2021-09-07 | 河南科技大学 | 一种大型钢锭的多包连续浇注方法 |
Also Published As
Publication number | Publication date |
---|---|
CN114346191A (zh) | 2022-04-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102218512B (zh) | 一种结晶器高液位更换中间包的方法 | |
CN109079114B (zh) | 一种采用板坯二冷区电磁搅拌生产耐磨钢的方法 | |
CN111390130B (zh) | 一种中碳加硼钢连铸坯皮下针孔气泡控制方法 | |
CN114393185A (zh) | 一种提高连铸高拉速下无取向电工钢铸坯等轴晶率的方法 | |
CN109420747B (zh) | 一种高收得率的板坯连铸机自动封顶工艺 | |
CN113020559A (zh) | 连铸中间包复开工艺 | |
CN114346191B (zh) | 一种预防厚板坯快换水口期间漏钢预报***重报警的方法 | |
CN111363972A (zh) | 耐候钢q355nhd的生产方法 | |
CN112296299A (zh) | 一种减少超宽板坯连铸机粘结报警的方法 | |
CN115213366B (zh) | 一种大断面连铸生产线快速更换钢种的方法 | |
CN113649538B (zh) | 板坯连铸机基于钢水温度控制的自动变渣线*** | |
JP4749997B2 (ja) | 連続鋳造方法 | |
CN113000800B (zh) | 一种采用电磁搅拌改善板坯表面及皮下质量的方法 | |
CN114472835A (zh) | 一种宽厚板坯连铸中间包热交换操作方法 | |
CN110695325B (zh) | 一种亚包晶钢板坯的连铸方法 | |
Kimura | Advances in high-purity IF steel manufacturing technology | |
CN115502356B (zh) | 一种铸造中期浸入式水口渣线变更方法及应用 | |
JPS6340628B2 (zh) | ||
CN114540581B (zh) | 一种rh真空处理的调控方法 | |
CN116352063A (zh) | 一种降低双流大板坯连铸机快换中间包时间的方法 | |
CN114210939B (zh) | 一种消除铁铬铝板坯连铸过程结渣条的方法 | |
CN116140568A (zh) | 一种包晶高铝钢连铸坯皮下纵裂控制方法 | |
JPH11192539A (ja) | 耐内部欠陥に優れたクロム含有溶鋼の連続鋳造方法 | |
CN117444190A (zh) | 一种连铸机水口快速更换方法 | |
CN118080794A (zh) | 一种立弯型板坯铸机的热轧合金工具钢x32开浇生产工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |