CN113496391A - Project completion expense prediction method and device, terminal and storage medium - Google Patents

Project completion expense prediction method and device, terminal and storage medium Download PDF

Info

Publication number
CN113496391A
CN113496391A CN202110811644.9A CN202110811644A CN113496391A CN 113496391 A CN113496391 A CN 113496391A CN 202110811644 A CN202110811644 A CN 202110811644A CN 113496391 A CN113496391 A CN 113496391A
Authority
CN
China
Prior art keywords
cost
work package
work
cpi
completion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110811644.9A
Other languages
Chinese (zh)
Other versions
CN113496391B (en
Inventor
纪璠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mountop Group Co ltd
Original Assignee
Mountop Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mountop Group Co ltd filed Critical Mountop Group Co ltd
Priority to CN202110811644.9A priority Critical patent/CN113496391B/en
Publication of CN113496391A publication Critical patent/CN113496391A/en
Application granted granted Critical
Publication of CN113496391B publication Critical patent/CN113496391B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0201Market modelling; Market analysis; Collecting market data
    • G06Q30/0206Price or cost determination based on market factors

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Human Resources & Organizations (AREA)
  • Development Economics (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Finance (AREA)
  • Accounting & Taxation (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Data Mining & Analysis (AREA)
  • Game Theory and Decision Science (AREA)
  • Tourism & Hospitality (AREA)
  • Operations Research (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a project completion expense prediction method and device, a terminal and a storage medium, wherein the method comprises the following steps: respectively determining a completed work package, an un-started work package and an ongoing work package according to the current process of each work package in the project; the cost of completed work packages is calculated according to the actual cost, the cost of work packages which are not started to be carried out is calculated according to the planned cost, and the cost of the work packages which are carried out is budgeted: the costs of completed work packages, un-started work packages, and ongoing work packages are aggregated. The invention utilizes the work package process weighting prediction function to calculate the ongoing work package completion cost, not only can predict the situation when the earned check point is positioned at the initial stage of the work package and generate more accurate results, but also can predict the situation when the earned check point is close to the planned completion time of the work package and generate more accurate results.

Description

Project completion expense prediction method and device, terminal and storage medium
Technical Field
The invention relates to the field of engineering project management, in particular to a project completion expense prediction method and device, a terminal and a storage medium.
Background
In the earned value method analysis, the cost of project completion prediction is a very important link. The earned value method is not only a cost control mode of correcting deviation of cost or progress found at earned value check points, but also embodies an important advanced control method by the concept of predicting project completion cost. The prior control, the middle control and the after control are all important composition stages of cost control.
In the process of developing projects, many enterprises usually pay more attention to the control in the middle and the control after the events, and the control before the events is relatively neglected. However, accurate pre-control by predicting the cost is often as important as in-process control and post-process control, which is not only beneficial to quantitative management of the cost, but also convenient for implementation of cost control in the whole process, thereby more effectively controlling the cost of the project.
Project Completion cost prediction (EAC) is performed according to an earned method, and currently, there are mainly the following three methods:
the first method assumes that the cost situation of the finished part of the project can reflect the cost situation of the unfinished part of the project, and the unfinished part of the project is predicted according to the uniform cost execution indexes of the finished part, namely:
EAC=ACWP+(BAC-BCWP)/CPI;
the second method assumes that the unfinished part of the project is predicted according to the residual cost of the project, and the method has the following prediction formula:
EAC=ACWP+BAC-BCWP;
the third method is that the cost situation of the finished part of the project is not enough to estimate the cost of the unfinished part of the project, and the unfinished part of the project is estimated in a comprehensive re-estimation mode, and the prediction formula is as follows:
EAC ═ ACWP + re-estimated remaining operating cost;
wherein BAC is the total cost of the project plan, ACWP is the actual cost of the completed workload, BCWP is the budget cost of the completed workload, and 1/CPI is the uniform cost performance indicator of the performed part.
Both the first and second methods are established under certain assumptions, which are not satisfied in many cases during the actual project progress.
In view of the limitations of the two assumptions, it has been analyzed that cost prediction for project completion is a significant link to cost prediction for an ongoing work package. For an ongoing work package, the predicted completion cost of the work package may be the predicted completion cost when the earned checkpoint is at the beginning of the work package, and the calculated CPI-based completion cost prediction may be more accurate when the earned checkpoint is near the planned completion time of the ongoing work package. For the Work packages which are not developed yet, statistics is more reasonable by using the planned Work budget Cost or the planned engineering investment amount (BCWS). Based on this consideration, it is necessary to develop a method capable of more reasonably predicting completion costs, as well as predicting the completion period of an ongoing work package.
Disclosure of Invention
The purpose of the invention is as follows: aiming at the defects of the existing project completion cost prediction method, the invention aims to provide a project completion cost prediction method and device, a terminal and a storage medium, so that the completion cost can be predicted more reasonably.
In order to achieve the purpose, the invention adopts the following technical scheme:
a method of project completion fee prediction, the method comprising: respectively determining a completed work package, an un-started work package and an ongoing work package according to the current process of each work package in the project; the cost of completed work packages is calculated according to the actual cost, the cost of work packages which are not started to be carried out is calculated according to the planned cost, and the cost of the work packages which are carried out is budgeted: aggregating the costs of completed work packages, the costs of non-started work packages, and the costs of ongoing work packages;
the cost budgeting steps of the ongoing work package are as follows:
defining the following weighted prediction function considering the progress of the work package:
w1(λ)=e-αλ (1)
w2(λ)=1/CPIi×(1-e-αλ) (2)
wa(λ)=w1(λ)+w2(λ)=e-αλ+1/CPIi×(1-e-αλ) (3)
wherein λ ═ ATi/BTiThe ratio of the number of days that the ith work package has started at the checkpoint to the number of days scheduled to complete is a quantity reflecting the time course of the work package; ATiThe number of days that the ith work package has started working at the checkpoint; BT (BT)iPlanning the completion days for the ith work package; α is a constant that controls the decay rate of the exponential function, CPI is a cost performance indicator, known as 1/CPIi=ACWPi/BCWPi
The following calculation equation is proposed for the projected completion cost of a single work package in progress:
EACi=ACWPi+(BACi-BCWPi)×wa(λ) (4)
wherein: w is aa(λ)=e-αλ+1/CPIi×(1-e-αλ)=e-αλ+ACWPi/BCWPi×(1-e-αλ) Substituting equation (3) into equation (4) to obtain the predicted completion cost of the work package as follows:
EACi=ACWPi+(BACi-BCWPi)×(e-αλ+ACWPi/BCWPi×(1-e-αλ)) (5)
wherein BACiFor planned cost of work package i, ACWPiFor the actual cost of the work package i of the amount of work done, BCWPiBudget cost for completed workload of work Package i, EACiThe predicted completion cost for work package i.
Further, the value of the constant α controlling the decay rate of the exponential function is determined by the following requirements:
when λ is 0.99, let w2(λ)=0.99×1/CPIiWhen the value of the weighted prediction function is almost equal to 1/CPIiAt this time, there are:
1-e-αλ0.99, i.e.: e.g. of the type-0.99αWhen the value is 0.01, the solution is obtained: α ═ ln (0.01)/0.99 ═ 4.652.
A project completion fee prediction apparatus comprising:
the determining module is used for respectively determining completed work packages, un-started work packages and ongoing work packages according to the current process of each work package in the project;
the budget module is used for calculating the cost of the completed work package according to the actual cost, calculating the cost of the work package which is not started to be carried out according to the planned cost, and budgeting the cost of the work package which is carried out:
a summary module to summarize costs of completed work packages, costs of un-started work packages, and costs of ongoing work packages.
The cost budgeting steps for an ongoing work package are as follows:
defining the following weighted prediction function considering the progress of the work package:
w1(λ)=e-αλ (1)
w2(λ)=1/CPIi×(1-e-αλ) (2)
wa(λ)=w1(λ)+w2(λ)=e-αλ+1/CPIi×(1-e-αλ) (3)
wherein λ ═ ATi/BTiThe ratio of the number of days that the ith work package has started at the checkpoint to the number of days scheduled to complete is a quantity reflecting the time course of the work package; ATiThe number of days that the ith work package has started working at the checkpoint; BT (BT)iPlanning the completion days for the ith work package; α is a constant that controls the decay rate of the exponential function, CPI is a cost performance indicator, known as 1/CPIi=ACWPi/BCWPi
The following calculation equation is proposed for the projected completion cost of a single work package in progress:
EACi=ACWPi+(BACi-BCWPi)×wa(λ) (4)
wherein: w is aa(λ)=e-αλ+1/CPIi×(1-e-αλ)=e-αλ+ACWPi/BCWPi×(1-e-αλ) Substituting equation (3) into equation (4) to obtain the predicted completion cost of the work package as follows:
EACi=ACWPi+(BACi-BCWPi)×(e-αλ+ACWPi/BCWPi×(1-e-αλ)) (5)
wherein BACiFor planned cost of work package i, ACWPiFor the actual cost of the work package i of the amount of work done, BCWPiBudget cost for completed workload of work Package i, EACiThe predicted completion cost for work package i.
Further, the value of the constant α controlling the decay rate of the exponential function is determined by the following requirements:
when λ is 0.99, let w2(λ)=0.99×1/CPIiWhen the value of the weighted prediction function is almost equal to 1/CPIiAt this time, there are:
1-e-αλ0.99, i.e.: e.g. of the type-0.99αWhen the value is 0.01, the solution is obtained: α ═ ln (0.01)/0.99 ═ 4.652.
A terminal comprising a processor and a memory, the memory having instructions stored therein, which when executed by the processor, cause the terminal to perform the method of forecasting time-to-completion fees as described above.
A storage medium storing a computer program comprising program instructions which, when executed by a computer, cause the computer to execute the project completion fee prediction method described above.
Has the advantages that: compared with the current project completion expense prediction method, the method utilizes the work package process weighting prediction function to calculate the ongoing work package completion cost, can predict the situation when the earned value check point is positioned at the initial stage of the work package and generate more accurate results, and can predict the situation when the earned value check point is close to the planned completion time of the work package and generate more accurate results.
Drawings
FIG. 1 is a flow chart of a project completion fee prediction method of the present invention;
FIG. 2 is a graph of a weighted prediction function for a 1/CPI of 1;
FIG. 3 is a graph of a weighted prediction function for a 1/CPI of 0.8;
FIG. 4 is a graph of a weighted prediction function for a 1/CPI of 1.2;
FIG. 5 is a comparison of predicted results of a conventional prediction method and the process weighted work package completion cost prediction method of the present invention.
FIG. 6 is a block diagram of a project completion fee prediction apparatus according to the present invention;
the specific implementation mode is as follows:
the invention is further explained below with reference to the drawings.
As shown in fig. 1, a project completion fee prediction method of the present invention includes: respectively determining a completed work package, an un-started work package and an ongoing work package according to the current process of each work package in the project; calculating the cost of the completed work package according to the actual cost, calculating the cost of the work package which is not started to be carried out according to the planned cost, and budgeting the cost of the work package which is carried out; the costs of completed work packages, un-started work packages, and ongoing work packages are aggregated.
The cost budgeting steps for an ongoing work package are as follows:
defining the following weighted prediction function considering the progress of the work package:
w1(λ)=e-αλ (1)
w2(λ)=1/CPIi×(1-e-αλ) (2)
w(λ)=w1(λ)+w2(λ)=e-αλ+1/CPIi×(1-e-αλ) (3)
wherein λ ═ ATi/BTiChecking points for ith work packageThe ratio of the number of days that the time has begun to the number of days that the plan is over is an amount that reflects the time course of the work package; ATiThe number of days that the ith work package has started working at the checkpoint; BT (BT)iPlanning the completion days for the ith work package; α is a constant that controls the decay rate of the exponential function, CPI is a cost performance indicator that indicates the ratio of the earned value to the actual cost value, which is the ratio between the budget cost for the project to have completed the work and the actual cost to have completed the work. Calculating the formula: CPI is BCWP/ACWP, a concept in earner value law. Known 1/CPIi=ACWPi/BCWPi
The α value is determined by the following requirements: when λ is 0.99, let w2(λ)=0.99×1/CPIiWhen the value of the weighted prediction function is almost equal to 1/CPIi. This time is: 1-e-αλ0.99, i.e.: e.g. of the type-0.99αWhen the value is 0.01, the solution is obtained: α ═ ln (0.01)/0.99 ═ 4.652.
Figures 2 to 4 show the weighted prediction function versus the ratio of the actual time to planned time to start working at the checkpoint for values of 1/CPI calculated at the checkpoint of 1, 0.8 and 1.2 respectively.
The following calculation equation is proposed for the projected completion cost of a single work package in progress:
EACi=ACWPi+(BACi-BCWPi)×wa(λ) (4)
wherein: w is aa(λ)=e-αλ+1/CPIi×(1-e-αλ)=e-αλ+ACWPi/BCWPi×(1-e-αλ) Substituting equation (3) into equation (4) to obtain the predicted completion cost of the work package as follows:
EACi=ACWPi+(BACi-BCWPi)×(e-αλ+ACWPi/BCWPi×(1-e-αλ)) (5)
equation (5) relates to the progress of the work package, and is therefore referred to as the progress weighted prediction of the completion cost of the work package, where BACiFor planned cost of work package i, ACWPiAs a work bagi actual cost of already performed work, BCWPiBudget cost for completed workload of work Package i, EACiThe predicted completion cost of the work package i;
now, simulation comparative analysis is performed by taking a work package with a budget cost of 30 ten thousand yuan and planned completion for 30 days as an example. The total workload of the work package is to install 100 tons of equipment. The unit price of the budget ton is 30/100-0.3 ten thousand yuan/ton.
The following analysis and comparison was made using the existing method of prediction with uniform cost performance index assumptions (existing first method) and the process weighted prediction method proposed herein, see table below and fig. 5.
Comparing results of the existing method and the process weighted prediction method
Figure BDA0003168509340000061
Figure BDA0003168509340000071
As can be seen from the above table and FIG. 4, the new process weighted work package completion cost prediction method presented herein outperforms the results presented by existing prediction methods.
Aiming at the limitation of the existing project completion cost prediction method in project actual application, the project completion cost prediction method provided by the invention predicts the overall completion cost of the project according to the following ideas: the cost of the completed work package is calculated according to the actual cost ACWP, the cost of the work package which is not started to be carried out is calculated according to the planned cost BCWS, and the cost of the work package which is carried out is calculated by adopting a new process weighted work package completion cost prediction method provided by the text. The new process weighting work package completion cost prediction method can predict the situation when the earned value check point is positioned at the initial stage of the work package and generate a more accurate result, and can predict the situation when the earned value check point is close to the planned completion time of the work package and generate a more accurate result, wherein the total project completion cost is the sum of the three items. Namely:
Figure BDA0003168509340000072
wherein: p + m + q ═ N, EAC is the total predicted cost of the project; ACWPiFor the ith actual cost of the work Package, EACjFor the predicted cost of the jth ongoing work Package, BCWSkBudgeting cost for the kth not-yet-done work package; p is the number of completed work packages, m is the number of work packages in progress, q is the number of work packages not in progress, and N is the total number of work packages for the project.
As shown in fig. 5, a project completion fee prediction apparatus of the present invention includes: the determining module is used for respectively determining completed work packages, un-started work packages and ongoing work packages according to the current process of each work package in the project; the budget module is used for calculating the cost of the completed work package according to the actual cost, calculating the cost of the work package which is not started to be carried out according to the planned cost, and budgeting the cost of the work package which is carried out: a summary module to summarize costs of completed work packages, costs of un-started work packages, and costs of ongoing work packages.
The cost budgeting steps for an ongoing work package are as follows:
defining the following weighted prediction function considering the progress of the work package:
w1(λ)=e-αλ (1)
w2(λ)=1/CPIi×(1-e-αλ) (2)
wa(λ)=w1(λ)+w2(λ)=e-αλ+1/CPIi×(1-e-αλ) (3)
wherein λ ═ ATi/BTiThe ratio of the number of days that the ith work package has started at the checkpoint to the number of days that the plan has been completed is a response to the time course of the work packageAn amount of (d); ATiThe number of days that the ith work package has started working at the checkpoint; BT (BT)iPlanning the completion days for the ith work package; α is a constant that controls the decay rate of the exponential function, CPI is a cost performance indicator, known as 1/CPIi=ACWPi/BCWPi
The α value is determined by the following requirements: when λ is 0.99, let w2(λ)=0.99×1/CPIiWhen the value of the weighted prediction function is almost equal to 1/CPIiAt this time, there are: 1-e-αλ0.99, i.e.: e.g. of the type-0.99αWhen the value is 0.01, the solution is obtained: α ═ ln (0.01)/0.99 ═ 4.652;
the following calculation equation is proposed for the projected completion cost of a single work package in progress:
EACi=ACWPi+(BACi-BCWPi)×wa(λ) (4)
wherein: w is aa(λ)=e-αλ+1/CPIi×(1-e-αλ)=e-αλ+ACWPi/BCWPi×(1-e-αλ) Substituting equation (3) into equation (4) to obtain the predicted completion cost of the work package as follows:
EACi=ACWPi+(BACi-BCWPi)×(e-αλ+ACWPi/BCWPi×(1-e-αλ)) (5)
wherein BACiFor planned cost of work package i, ACWPiFor the actual cost of the work package i of the amount of work done, BCWPiBudget cost for completed workload of work Package i, EACiThe predicted completion cost for work package i.
The terminal comprises a processor and a memory, wherein the memory stores instructions, and the processor executes the instructions to cause the terminal to execute the project completion expense prediction method.
A storage medium storing a computer program comprising program instructions which, when executed by a computer, cause the computer to execute the project completion fee prediction method described above.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, various modifications and decorations can be made without departing from the principle of the present invention, and these modifications and decorations should also be regarded as the protection scope of the present invention.

Claims (7)

1. A method for predicting completion costs of a project, the method comprising: respectively determining a completed work package, an un-started work package and an ongoing work package according to the current process of each work package in the project; the cost of completed work packages is calculated according to the actual cost, the cost of work packages which are not started to be carried out is calculated according to the planned cost, and the cost of the work packages which are carried out is budgeted: aggregating the costs of completed work packages, the costs of non-started work packages, and the costs of ongoing work packages;
the cost budgeting steps of the ongoing work package are as follows:
defining the following weighted prediction function considering the progress of the work package:
w1(λ)=e-αλ (1)
w2(λ)=1/CPIi×(1-e-αλ) (2)
wa(λ)=w1(λ)+w2(λ)=e-αλ+1/CPIi×(1-e-αλ) (3)
wherein λ ═ ATi/BTiThe ratio of the number of days that the ith work package has started at the checkpoint to the number of days scheduled to complete is a quantity reflecting the time course of the work package; ATiThe number of days that the ith work package has started working at the checkpoint; BT (BT)iPlanning the completion days for the ith work package; α is a constant that controls the decay rate of the exponential function, CPI is a cost performance indicator, known as 1/CPIi=ACWPi/BCWPi
The following calculation equation is proposed for the projected completion cost of a single work package in progress:
EACi=ACWPi+(BACi-BCWPi)×wa(λ) (4)
wherein: w is aa(λ)=e-αλ+1/CPIi×(1-e-αλ)=e-αλ+ACWPi/BCWPi×(1-e-αλ) Substituting equation (3) into equation (4) to obtain the predicted completion cost of the work package as follows:
EACi=ACWPi+(BACi-BCWPi)×(e-αλ+ACWPi/BCWPi×(1-e-αλ)) (5)
wherein BACiFor planned cost of work package i, ACWPiFor the actual cost of the work package i of the amount of work done, BCWPiBudget cost for completed workload of work Package i, EACiThe predicted completion cost for work package i.
2. A project completion expense prediction method as claimed in claim 1, wherein the constant α value controlling the decay rate of the exponential function is determined by the following requirements:
when λ is 0.99, let w2(λ)=0.99×1/CPIiWhen the value of the weighted prediction function is almost equal to 1/CPIiAt this time, there are:
1-e-αλ0.99, i.e.: e.g. of the type-0.99αWhen the value is 0.01, the solution is obtained: α ═ ln (0.01)/0.99 ═ 4.652.
3. A project completion fee prediction apparatus, comprising:
the determining module is used for respectively determining completed work packages, un-started work packages and ongoing work packages according to the current process of each work package in the project;
the budget module is used for calculating the cost of the completed work package according to the actual cost, calculating the cost of the work package which is not started to be carried out according to the planned cost, and budgeting the cost of the work package which is carried out:
a summary module to summarize costs of completed work packages, costs of un-started work packages, and costs of ongoing work packages.
4. The project completion fee prediction apparatus as claimed in claim 3, wherein the cost budgeting step of the ongoing work package is as follows:
defining the following weighted prediction function considering the progress of the work package:
w1(λ)=e-αλ (1)
w2(λ)=1/CPIi×(1-e-αλ) (2)
wa(λ)=w1(λ)+w2(λ)=e-αλ+1/CPIi×(1-e-αλ) (3)
wherein λ ═ ATi/BTiThe ratio of the number of days that the ith work package has started at the checkpoint to the number of days scheduled to complete is a quantity reflecting the time course of the work package; ATiThe number of days that the ith work package has started working at the checkpoint; BT (BT)iPlanning the completion days for the ith work package; α is a constant that controls the decay rate of the exponential function, CPI is a cost performance indicator, known as 1/CPIi=ACWPi/BCWPi
The following calculation equation is proposed for the projected completion cost of a single work package in progress:
EACi=ACWPi+(BACi-BCWPi)×wa(λ) (4)
wherein: w is aa(λ)=e-αλ+1/CPIi×(1-e-αλ)=e-αλ+ACWPi/BCWPi×(1-e-αλ) Substituting equation (3) into equation (4) to obtain the predicted completion cost of the work package as follows:
EACi=ACWPi+(BACi-BCWPi)×(e-αλ+ACWPi/BCWPi×(1-e-αλ)) (5)
wherein BACiFor the projected cost of the work package i,ACWPifor the actual cost of the work package i of the amount of work done, BCWPiBudget cost for completed workload of work Package i, EACiThe predicted completion cost for work package i.
5. The project completion fee prediction apparatus as set forth in claim 4, wherein the value of the constant α controlling the decay rate of the exponential function is determined by the following requirements:
when λ is 0.99, let w2(λ)=0.99×1/CPIiWhen the value of the weighted prediction function is almost equal to 1/CPIiAt this time, there are:
1-e-αλ0.99, i.e.: e.g. of the type-0.99αWhen the value is 0.01, the solution is obtained: α ═ ln (0.01)/0.99 ═ 4.652.
6. A terminal comprising a processor and a memory, the memory having stored therein instructions that, when executed by the processor, cause the terminal to perform the method of any of claims 1-2.
7. A storage medium, characterized in that the storage medium stores a computer program comprising program instructions which, when executed by a computer, cause the computer to perform the method according to any one of claims 1-2.
CN202110811644.9A 2021-07-19 2021-07-19 Project completion expense prediction method and device, terminal and storage medium Active CN113496391B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110811644.9A CN113496391B (en) 2021-07-19 2021-07-19 Project completion expense prediction method and device, terminal and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110811644.9A CN113496391B (en) 2021-07-19 2021-07-19 Project completion expense prediction method and device, terminal and storage medium

Publications (2)

Publication Number Publication Date
CN113496391A true CN113496391A (en) 2021-10-12
CN113496391B CN113496391B (en) 2024-05-28

Family

ID=77996551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110811644.9A Active CN113496391B (en) 2021-07-19 2021-07-19 Project completion expense prediction method and device, terminal and storage medium

Country Status (1)

Country Link
CN (1) CN113496391B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101529679B1 (en) * 2014-02-28 2015-06-18 연세대학교 산학협력단 Integrated co2-cost-schedule management system and method for building construction projects using the earned value management theory
CN105139159A (en) * 2015-10-12 2015-12-09 南京富士通南大软件技术有限公司 Project cost management and control method in power industry
CN108416477A (en) * 2018-03-15 2018-08-17 国家电网公司 It is a kind of that multi-dimensional optimization method is implemented based on the distribution network engineering for improving Earned Value

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101529679B1 (en) * 2014-02-28 2015-06-18 연세대학교 산학협력단 Integrated co2-cost-schedule management system and method for building construction projects using the earned value management theory
CN105139159A (en) * 2015-10-12 2015-12-09 南京富士通南大软件技术有限公司 Project cost management and control method in power industry
CN108416477A (en) * 2018-03-15 2018-08-17 国家电网公司 It is a kind of that multi-dimensional optimization method is implemented based on the distribution network engineering for improving Earned Value

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蒋孝军;张守梅;秦升平;: "挣值法在软件项目监理中的应用", 信息技术与信息化, no. 02, 15 April 2013 (2013-04-15), pages 99 - 101 *

Also Published As

Publication number Publication date
CN113496391B (en) 2024-05-28

Similar Documents

Publication Publication Date Title
US7328129B2 (en) Performance control apparatus and method for data processing system
US6088678A (en) Process simulation technique using benefit-trade matrices to estimate schedule, cost, and risk
US20060236310A1 (en) Methods and apparatus to iteratively compile software to meet user-defined criteria
US8484060B2 (en) Project estimating system and method
US20100049570A1 (en) Method and system for determining resource usage of each tenant in a multi-tenant architecture
CN111310998A (en) Method and device for generating critical path, electronic equipment and medium
US20050283761A1 (en) Method and framework for test case management
KR102108541B1 (en) Apparatus and method for managing counselor schedule
Ferens et al. Calibrating software cost models to department of defense databases—a review of ten studies
CN113496391A (en) Project completion expense prediction method and device, terminal and storage medium
Walter et al. Further analysis of a computing center environment
Reinschmidt et al. Construction cash flow management system
CN115829736A (en) Model parameter testing method and device, storage medium and electronic equipment
CN109800975A (en) A kind of stock assessment method, apparatus, computer equipment and storage medium
Stanley Measurement of system operational statistics
RU199084U1 (en) A device for analyzing and evaluating the progress of the program for the development of complex technical systems
Downing et al. A Neuber's rule fatigue analysis procedure for use with a mobile computer
Bogle et al. Stochastic optimization of water supply expansion
CN101201751B (en) Method for planning capacity of multiple machines aiming at OLTP application
RU210788U1 (en) A device for assessing the risk of implementing a program for the development of complex technical systems
CN117033399B (en) Method and system for managing engineering quantity change
Vestal On the accuracy of predicting rate monotonic scheduling performance
CN111277665B (en) 3D application scheduling method, device, terminal and storage medium based on interference measurement
CN117455387A (en) Research and development management approval system
CN116993386A (en) Quota design management method and system for constructional engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant