CN113482489A - House door and window installation construction process - Google Patents

House door and window installation construction process Download PDF

Info

Publication number
CN113482489A
CN113482489A CN202110594795.3A CN202110594795A CN113482489A CN 113482489 A CN113482489 A CN 113482489A CN 202110594795 A CN202110594795 A CN 202110594795A CN 113482489 A CN113482489 A CN 113482489A
Authority
CN
China
Prior art keywords
door
polyurethane foam
window
plastering
gap filler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110594795.3A
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Ruihua Haoshu Technology Co ltd
Original Assignee
Guangdong Ruihua Haoshu Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Ruihua Haoshu Technology Co ltd filed Critical Guangdong Ruihua Haoshu Technology Co ltd
Priority to CN202110594795.3A priority Critical patent/CN113482489A/en
Publication of CN113482489A publication Critical patent/CN113482489A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B1/00Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
    • E06B1/56Fastening frames to the border of openings or to similar contiguous frames
    • E06B1/58Fastening frames to the border of openings or to similar contiguous frames by filling up the joints, e.g. by cementing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B1/00Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
    • E06B1/62Tightening or covering joints between the border of openings and the frame or between contiguous frames
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B1/00Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
    • E06B1/62Tightening or covering joints between the border of openings and the frame or between contiguous frames
    • E06B2001/626Tightening or covering joints between the border of openings and the frame or between contiguous frames comprising expanding foam strips

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Door And Window Frames Mounted To Openings (AREA)
  • Building Environments (AREA)

Abstract

The invention provides a house door and window installation and construction process, which relates to the technical field of house door and window installation and construction, and comprises the following steps: s1, cleaning, namely, after the building of the house main body is completed, pre-forming a hole for accommodating a door and a window, and then cleaning the inner wall and the periphery of the hole of the house main body by using a hard brush; and S2, preparing for tools and doors and windows of corresponding models, and setting aside for standby. The construction process adopted by the invention is that the door and window outer frame is directly installed after the building of the house main body is finished, and the plastering construction of the inner wall and the outer wall is carried out after the installation of the door and window outer frame is finished, so that the firmness of the joint of the wall body and the door and window is improved, the plastering construction progress of the wall body is accelerated, no closing-up exists, the appearance is attractive, the water impermeability of the joint of the window and the outer wall surface is effectively improved, the practical use is facilitated, and the innovation is remarkable.

Description

House door and window installation construction process
Technical Field
The invention relates to the technical field of house door and window installation construction, in particular to a house door and window installation construction process.
Background
A window is architecturally defined as an opening made in a wall or roof, and is generally used to allow light or air to enter a room. In the process of building door and window construction, a corresponding construction process is needed to install the building door and window.
At present, the existing building door and window installation and construction process is in practical application, generally, the door and window are installed after plastering of the inner wall and the outer wall is finished, so that the joint of the wall body and the door and window is insecure, the construction progress is slow, the closing part is not attractive, flaws exist, the window is likely to leak water and the like, the actual use is not facilitated, and the improvement is needed.
Disclosure of Invention
The invention aims to solve the defects in the prior art and provides a house door and window installation construction process.
In order to achieve the purpose, the invention adopts the following technical scheme: the house door and window installation and construction process comprises the following steps:
s1, cleaning, namely, after the building of the house main body is completed, pre-forming a hole for accommodating a door and a window, and then cleaning the inner wall and the periphery of the hole of the house main body by using a hard brush;
s2, preparing tools needed to be used and doors and windows of corresponding models, and putting aside for standby;
s3, installing doors and windows, taking out the doors and windows with the corresponding models, and installing the door and window outer frames in the holes;
s4, preparing for sealing, preparing a spray gun and a polyurethane foam gap filler, and when the polyurethane foam gap filler is used, firstly shaking the polyurethane foam gap filler uniformly, and then filling the polyurethane foam gap filler into the spray gun;
s5, sealing, then, injecting a spray gun for a circle aiming at the gap between the hole and the door and window outer frame, and then, filling the gap between the hole and the door and window outer frame with polyurethane foam gap filler due to the expansion effect of the polyurethane foam gap filler;
s6, finishing sealing, spraying water mist to the gap after the sealing work is finished, and fully assisting the expansion of the polyurethane foam gap filler through the water mist;
s7, preparing plastering, namely treating the wall surface of the house main body, mainly removing attachments such as dust, dirt, mortar blocks and the like on the wall surface, and simultaneously fully mixing and stirring cement and building glue to form bottom layer slurry;
and S8, plastering construction, namely, using a plastering slurry throwing device, immersing the plastering slurry throwing device into the bottom layer slurry for adhering, plastering the wall through the plastering slurry throwing device, and finishing construction after plastering is finished.
Further, in step S5, before using the polyurethane foam caulking agent, the size of the gap between the opening and the window and door outer frame is measured, and the polyurethane foam caulking agent only needs to be filled into 20-40% of the size of the gap.
Further, in step S4, the polyurethane foam caulking agent should be of a type corresponding to the type of the spray gun.
Further, in the step S4, the time of the polyurethane foam caulking agent is 10 to 20 seconds, and the polyurethane foam caulking agent is repeatedly shaken for 1 to 2 times, thereby making the polyurethane foam caulking agent sufficiently uniform.
Further, in step S6, the operation of spraying the water mist should be completed within 1-2min after the sealing operation is completed.
Further, in step S1, the material of the bristle brush is PVC plastic.
Compared with the prior art, the construction process adopted by the invention is that the door and window outer frame is directly installed after the building of the house main body is finished, and the plastering construction of the inner wall and the outer wall is carried out after the installation of the door and window outer frame is finished, so that the firmness of the joint of the wall body and the door and window can be improved, the construction progress of the plastering of the wall body is accelerated, no closing-in exists, the appearance is attractive, the water impermeability of the joint of the window and the outer wall surface is effectively improved, the practical use is facilitated, and the innovation is remarkable.
Additional features and advantages of the invention will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by practice of the invention. The objectives and other advantages of the invention will be realized and attained by the structure particularly pointed out in the written description and claims hereof as well as the appended drawings.
The technical solution of the present invention is further described in detail by the accompanying drawings and embodiments.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a step diagram of a house door and window installation construction process provided by the invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In a first embodiment, referring to fig. 1, the process for installing and constructing the door and window of the house includes the following steps:
s1, cleaning, namely, after the building of the house main body is completed, pre-forming a hole for accommodating a door and a window, and then cleaning the inner wall and the periphery of the hole of the house main body by using a hard brush;
s2, preparing tools needed to be used and doors and windows of corresponding models, and putting aside for standby;
s3, installing doors and windows, taking out the doors and windows with the corresponding models, and installing the door and window outer frames in the holes;
s4, preparing for sealing, preparing a spray gun and a polyurethane foam gap filler, and when the polyurethane foam gap filler is used, firstly shaking the polyurethane foam gap filler uniformly, and then filling the polyurethane foam gap filler into the spray gun;
s5, sealing, then, injecting a spray gun for a circle aiming at the gap between the hole and the door and window outer frame, and then, filling the gap between the hole and the door and window outer frame with polyurethane foam gap filler due to the expansion effect of the polyurethane foam gap filler;
s6, finishing sealing, spraying water mist to the gap after the sealing work is finished, and fully assisting the expansion of the polyurethane foam gap filler through the water mist;
s7, preparing plastering, namely treating the wall surface of the house main body, mainly removing attachments such as dust, dirt, mortar blocks and the like on the wall surface, and simultaneously fully mixing and stirring cement and building glue to form bottom layer slurry;
and S8, plastering construction, namely, using a plastering slurry throwing device, immersing the plastering slurry throwing device into the bottom layer slurry for adhering, plastering the wall through the plastering slurry throwing device, and finishing construction after plastering is finished.
Preferably, in step S5, before the polyurethane foam caulking agent is used, the size of the gap between the opening and the window and door outer frame is measured, and the polyurethane foam caulking agent only needs to be filled into 20-40% of the size of the gap.
Preferably, in step S4, the polyurethane foam caulking agent should be of a type that matches the type of the spray gun.
Preferably, in the step S4, the time for the polyurethane foam caulking agent is 10S, and the shaking is repeated 2 times, thereby making the polyurethane foam caulking agent sufficiently uniform.
Preferably, in step S6, the operation of spraying the water mist should be completed within 1min after the sealing operation is completed.
Preferably, in step S1, the material of the rigid brush is PVC plastic.
In a second embodiment, referring to fig. 1, the process for installing and constructing the door and window of the house includes the following steps:
s1, cleaning, namely, after the building of the house main body is completed, pre-forming a hole for accommodating a door and a window, and then cleaning the inner wall and the periphery of the hole of the house main body by using a hard brush;
s2, preparing tools needed to be used and doors and windows of corresponding models, and putting aside for standby;
s3, installing doors and windows, taking out the doors and windows with the corresponding models, and installing the door and window outer frames in the holes;
s4, preparing for sealing, preparing a spray gun and a polyurethane foam gap filler, and when the polyurethane foam gap filler is used, firstly shaking the polyurethane foam gap filler uniformly, and then filling the polyurethane foam gap filler into the spray gun;
s5, sealing, then, injecting a spray gun for a circle aiming at the gap between the hole and the door and window outer frame, and then, filling the gap between the hole and the door and window outer frame with polyurethane foam gap filler due to the expansion effect of the polyurethane foam gap filler;
s6, finishing sealing, spraying water mist to the gap after the sealing work is finished, and fully assisting the expansion of the polyurethane foam gap filler through the water mist;
s7, preparing plastering, namely treating the wall surface of the house main body, mainly removing attachments such as dust, dirt, mortar blocks and the like on the wall surface, and simultaneously fully mixing and stirring cement and building glue to form bottom layer slurry;
and S8, plastering construction, namely, using a plastering slurry throwing device, immersing the plastering slurry throwing device into the bottom layer slurry for adhering, plastering the wall through the plastering slurry throwing device, and finishing construction after plastering is finished.
Preferably, in step S5, before the polyurethane foam caulking agent is used, the size of the gap between the opening and the window and door outer frame is measured, and the polyurethane foam caulking agent only needs to be filled into 20-40% of the size of the gap.
Preferably, in step S4, the polyurethane foam caulking agent should be of a type that matches the type of the spray gun.
Preferably, in the step S4, the time for the polyurethane foam caulking agent is 15S, and the shaking is repeated 2 times, thereby making the polyurethane foam caulking agent sufficiently uniform.
Preferably, in step S6, the operation of spraying the water mist should be completed within 2min after the sealing operation is completed.
Preferably, in step S1, the material of the rigid brush is PVC plastic.
In a third embodiment, referring to fig. 1, the process for installing and constructing the door and window of the house includes the following steps:
s1, cleaning, namely, after the building of the house main body is completed, pre-forming a hole for accommodating a door and a window, and then cleaning the inner wall and the periphery of the hole of the house main body by using a hard brush;
s2, preparing tools needed to be used and doors and windows of corresponding models, and putting aside for standby;
s3, installing doors and windows, taking out the doors and windows with the corresponding models, and installing the door and window outer frames in the holes;
s4, preparing for sealing, preparing a spray gun and a polyurethane foam gap filler, and when the polyurethane foam gap filler is used, firstly shaking the polyurethane foam gap filler uniformly, and then filling the polyurethane foam gap filler into the spray gun;
s5, sealing, then, injecting a spray gun for a circle aiming at the gap between the hole and the door and window outer frame, and then, filling the gap between the hole and the door and window outer frame with polyurethane foam gap filler due to the expansion effect of the polyurethane foam gap filler;
s6, finishing sealing, spraying water mist to the gap after the sealing work is finished, and fully assisting the expansion of the polyurethane foam gap filler through the water mist;
s7, preparing plastering, namely treating the wall surface of the house main body, mainly removing attachments such as dust, dirt, mortar blocks and the like on the wall surface, and simultaneously fully mixing and stirring cement and building glue to form bottom layer slurry;
and S8, plastering construction, namely, using a plastering slurry throwing device, immersing the plastering slurry throwing device into the bottom layer slurry for adhering, plastering the wall through the plastering slurry throwing device, and finishing construction after plastering is finished.
Preferably, in step S5, before the polyurethane foam caulking agent is used, the size of the gap between the opening and the window and door outer frame is measured, and the polyurethane foam caulking agent only needs to be filled into 20-40% of the size of the gap.
Preferably, in step S4, the polyurethane foam caulking agent should be of a type that matches the type of the spray gun.
Preferably, in the step S4, the time for the polyurethane foam caulking agent is 19S, and the shaking is repeated 2 times, thereby making the polyurethane foam caulking agent sufficiently uniform.
Preferably, in step S6, the operation of spraying the water mist should be completed within 2min after the sealing operation is completed.
Preferably, in step S1, the material of the rigid brush is PVC plastic.
The embodiment shows that the door and window outer frame is directly installed after the building of the house main body is finished, and the plastering construction of the inner wall and the outer wall is carried out after the door and window outer frame is installed, so that the firmness of the joint of the wall body and the door and window is improved, the plastering construction progress of the wall body is accelerated, the door and window outer frame is free of closing up and attractive, the water permeability resistance of the joint of the window and the outer wall surface is effectively improved, the practical use is facilitated, and the innovation is remarkable.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (6)

1. The house door and window installation and construction process is characterized by comprising the following steps:
s1, cleaning, namely, after the building of the house main body is completed, pre-forming a hole for accommodating a door and a window, and then cleaning the inner wall and the periphery of the hole of the house main body by using a hard brush;
s2, preparing tools needed to be used and doors and windows of corresponding models, and putting aside for standby;
s3, installing doors and windows, taking out the doors and windows with the corresponding models, and installing the door and window outer frames in the holes;
s4, preparing for sealing, preparing a spray gun and a polyurethane foam gap filler, and when the polyurethane foam gap filler is used, firstly shaking the polyurethane foam gap filler uniformly, and then filling the polyurethane foam gap filler into the spray gun;
s5, sealing, then, injecting a spray gun for a circle aiming at the gap between the hole and the door and window outer frame, and then, filling the gap between the hole and the door and window outer frame with polyurethane foam gap filler due to the expansion effect of the polyurethane foam gap filler;
s6, finishing sealing, spraying water mist to the gap after the sealing work is finished, and fully assisting the expansion of the polyurethane foam gap filler through the water mist;
s7, preparing plastering, namely treating the wall surface of the house main body, mainly removing attachments such as dust, dirt, mortar blocks and the like on the wall surface, and simultaneously fully mixing and stirring cement and building glue to form bottom layer slurry;
and S8, plastering construction, namely, using a plastering slurry throwing device, immersing the plastering slurry throwing device into the bottom layer slurry for adhering, plastering the wall through the plastering slurry throwing device, and finishing construction after plastering is finished.
2. The house door and window installation and construction process according to claim 1, characterized in that: in step S5, before using the polyurethane foam caulking agent, the size of the gap between the opening and the window and door outer frame is measured, and the polyurethane foam caulking agent only needs to be filled into 20-40% of the size of the gap.
3. The house door and window installation and construction process according to claim 1, characterized in that: in step S4, the polyurethane foam caulking agent should be of a type that matches the type of the spray gun.
4. The house door and window installation and construction process according to claim 1, characterized in that: in the step S4, the time of the polyurethane foam gap filler is 10-20S, and the polyurethane foam gap filler is repeatedly shaken for 1-2 times, so that the polyurethane foam gap filler is fully uniform.
5. The house door and window installation and construction process according to claim 1, characterized in that: in step S6, the operation of spraying the water mist should be completed within 1-2min after the sealing operation is completed.
6. The house door and window installation and construction process according to claim 1, characterized in that: in step S1, the hard brush is made of PVC plastic.
CN202110594795.3A 2021-05-28 2021-05-28 House door and window installation construction process Pending CN113482489A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110594795.3A CN113482489A (en) 2021-05-28 2021-05-28 House door and window installation construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110594795.3A CN113482489A (en) 2021-05-28 2021-05-28 House door and window installation construction process

Publications (1)

Publication Number Publication Date
CN113482489A true CN113482489A (en) 2021-10-08

Family

ID=77933581

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110594795.3A Pending CN113482489A (en) 2021-05-28 2021-05-28 House door and window installation construction process

Country Status (1)

Country Link
CN (1) CN113482489A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060143996A1 (en) * 2004-12-30 2006-07-06 Jorge Alvarado Universal fenestration cap system and method
CN1851224A (en) * 2006-05-25 2006-10-25 深圳市啟盛新型建材技术开发有限公司 Method for mounting door-window
CN101761286A (en) * 2008-10-13 2010-06-30 侯向煜 Installation method of aluminum alloy door/window
CN102704792A (en) * 2012-05-30 2012-10-03 福建省泷澄建设集团有限公司 Building door and window mounting rigid foamed polyurethane filling construction process
EP2511465B1 (en) * 2011-04-13 2016-07-20 Ranit Austria GmbH Method and end profile for fitting a windowsill
CN108585638A (en) * 2018-04-02 2018-09-28 山西四建集团有限公司 A kind of interior wall thin limed construction technique
CN111236795A (en) * 2020-01-10 2020-06-05 广西建工集团联合建设有限公司 Plastering-free construction method for embedded aluminum alloy window frame fixing piece

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060143996A1 (en) * 2004-12-30 2006-07-06 Jorge Alvarado Universal fenestration cap system and method
CN1851224A (en) * 2006-05-25 2006-10-25 深圳市啟盛新型建材技术开发有限公司 Method for mounting door-window
CN101761286A (en) * 2008-10-13 2010-06-30 侯向煜 Installation method of aluminum alloy door/window
EP2511465B1 (en) * 2011-04-13 2016-07-20 Ranit Austria GmbH Method and end profile for fitting a windowsill
CN102704792A (en) * 2012-05-30 2012-10-03 福建省泷澄建设集团有限公司 Building door and window mounting rigid foamed polyurethane filling construction process
CN108585638A (en) * 2018-04-02 2018-09-28 山西四建集团有限公司 A kind of interior wall thin limed construction technique
CN111236795A (en) * 2020-01-10 2020-06-05 广西建工集团联合建设有限公司 Plastering-free construction method for embedded aluminum alloy window frame fixing piece

Similar Documents

Publication Publication Date Title
CN207017857U (en) A kind of broken-bridge aluminum alloy exterior window closing-in structure
CN107255007A (en) A kind of broken-bridge aluminum alloy exterior window closing in construction method
CN211287246U (en) Window attaches frame structure
CN208934297U (en) A kind of hollowing cracking falls off maintenance and renovation renewing outer wall
CN103343655A (en) Wall window construction method
CN105909122A (en) Mounting method of plastic steel door and window
CN113482489A (en) House door and window installation construction process
CN201209368Y (en) Water-proof structure
CN108533125B (en) A kind of installation method of energy conservation auxiliary frame antiseep
CN201857858U (en) Door and window with water retaining skirt on outer frame
CN209539044U (en) Closing-in structure outside a kind of exterior window room
CN208502100U (en) Inversion-type waterproof heat-retaining roof and parapet connecting node with side row's inlet for stom water
CN109339634A (en) Window side preventing and controlling seepage engineering method for building decoration
CN217326944U (en) Anti-leakage structure for gap between door and window opening and door and window frame
CN211258252U (en) Assembly type PC waterproof sill type windowsill coping structure
EP1990497A2 (en) Renovation frame for windows and doors
CN217175237U (en) Waterproof construction at building gap position
KR200384079Y1 (en) Molding material tape for protecting rain water
CN102094522B (en) Process for constructing joints between bottom of window on outer wall and inside as well as outside of windowsill
TWI599708B (en) A caulking method of metal door or window frame
CN214196064U (en) Concrete tongue-and-groove joint waterproof structure for external wall windowsill
JPS5915349Y2 (en) Watertight structure of panel fitting groove
CN217400689U (en) High-precision theme externally-mounted TCP (transmission control protocol) horn mouth window bealock
CN220769302U (en) Non-frame window anti-seepage node
CN219910549U (en) Home decoration timber with anti-corrosion function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211008

RJ01 Rejection of invention patent application after publication