CN110781241A - Four-remote information acceptance method and system - Google Patents
Four-remote information acceptance method and system Download PDFInfo
- Publication number
- CN110781241A CN110781241A CN201910976878.1A CN201910976878A CN110781241A CN 110781241 A CN110781241 A CN 110781241A CN 201910976878 A CN201910976878 A CN 201910976878A CN 110781241 A CN110781241 A CN 110781241A
- Authority
- CN
- China
- Prior art keywords
- remote
- verification
- card
- acceptance
- acceptance card
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 18
- 238000012795 verification Methods 0.000 claims abstract description 198
- 230000011664 signaling Effects 0.000 claims abstract description 71
- 238000012360 testing method Methods 0.000 claims abstract description 45
- 230000007246 mechanism Effects 0.000 claims description 13
- 230000001105 regulatory effect Effects 0.000 claims description 9
- 238000012544 monitoring process Methods 0.000 claims description 7
- 230000001172 regenerating effect Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 3
- 238000005516 engineering process Methods 0.000 description 4
- 230000001276 controlling effect Effects 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 230000001360 synchronised effect Effects 0.000 description 2
- 238000013473 artificial intelligence Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/27—Replication, distribution or synchronisation of data between databases or within a distributed database system; Distributed database system architectures therefor
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/22—Indexing; Data structures therefor; Storage structures
- G06F16/2282—Tablespace storage structures; Management thereof
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/23—Updating
- G06F16/2365—Ensuring data consistency and integrity
Landscapes
- Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- Databases & Information Systems (AREA)
- Data Mining & Analysis (AREA)
- Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Security & Cryptography (AREA)
- Computing Systems (AREA)
- Software Systems (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
The invention provides a method and a system for checking and accepting a four-remote signal, wherein the method comprises the following steps: generating a remote signaling check and acceptance card, a remote test check and acceptance card, a remote control check and acceptance card and a remote regulation check and acceptance card according to the four-remote information base; performing master station verification on the remote signaling verification and acceptance card, the remote test acceptance card, the remote control verification and acceptance card and the remote regulation verification and acceptance card, and generating a master station verification and acceptance card verification library according to a verification result; performing substation verification on the remote signaling verification and acceptance card, the remote test and acceptance card, the remote verification and acceptance card and the remote modulation verification and acceptance card after the verification is successful, and generating a substation verification and acceptance card verification library according to the result; and receiving the four-remote signals to be checked and accepted, checking and accepting the four-remote signals to be checked and accepted according to the master station check and acceptance card check library and the substation check and acceptance card check library, and generating a check and acceptance report. The method avoids the problem of information deviation caused by asynchronous construction time of the OMS of the master station system and the substation system and lack of unified rules of the model, provides an acceptance basis for self-acceptance of four-remote signals, effectively reduces the intensity of acceptance work, and greatly improves the acceptance efficiency.
Description
Technical Field
The invention relates to the technical field of power system operation and automation, in particular to a four-remote information acceptance method and system.
Background
With the continuous and deep application of information technology in power grid scheduling mechanisms, after scheduling master station systems (OCS, hereinafter referred to as master station systems), substation monitoring systems (hereinafter referred to as substation systems) and production management systems (OMS, hereinafter referred to as OMS systems) of each level of scheduling mechanisms are put into operation, the service collaboration of models, moving device models and management information systems is increasingly strengthened. With the development of the times, the artificial intelligence technology and the automation technology are deepened continuously, the data collaborative application requirements among different system equipment libraries are increasingly outstanding, a standardized equipment information model is urgently needed to solve the problem of model data interaction among different systems, and the synchronous application of the four-remote model parameters of the transformer substation is realized.
Disclosure of Invention
The invention aims to solve the technical problem of providing a four-remote information acceptance method, so as to solve the problem of model data interaction between Zhang hong different systems in the prior art and realize synchronous application of four-remote model parameters of a transformer substation.
In order to solve the technical problem, the invention provides a four-remote information acceptance method, which comprises the following steps:
generating a remote signaling check and acceptance card, a remote test check and acceptance card, a remote control check and acceptance card and a remote regulation check and acceptance card according to the four-remote information base;
performing master station verification on the remote signaling verification and acceptance card, the remote test acceptance card, the remote control verification and acceptance card and the remote regulation verification and acceptance card, and generating a master station verification and acceptance card verification library according to verification results;
performing substation verification on the remote signaling verification and acceptance card, the remote test and acceptance card, the remote verification and acceptance card and the remote modulation verification and acceptance card after the verification is successful, and generating a substation verification and acceptance card verification library according to the result;
and receiving the four-remote signals to be checked and accepted, checking and accepting the four-remote signals to be checked and accepted according to the main station card checking and accepting verification library and the sub-station card checking and accepting verification library, and generating a checking and accepting report.
The remote signaling acceptance card, the remote testing acceptance card and the remote adjusting acceptance card are all in extensible markup language format, and each acceptance card comprises an attribute and a corresponding attribute description.
The remote signaling check card, the remote test check card, the remote control check card and the remote control check card are subjected to master station check, and a master station check card check library is generated according to check results, wherein the master station check card check library specifically comprises the following steps:
respectively reading the information point tables of the remote test receiving card, the remote signaling checking receiving card, the remote control checking receiving card and the remote control checking receiving card,
and judging whether the read information point table is consistent with the information stored in the master station, if so, the verification is successful, generating a master station verification and acceptance card verification library according to the verification successful in verification, otherwise, the verification fails, modifying the four-remote information library, regenerating a remote signaling verification and acceptance card, a remote testing acceptance card and a remote adjusting and acceptance card according to the modified four-remote information library, and performing master station verification on the regenerated remote signaling verification and acceptance card, remote testing acceptance card and remote adjusting and acceptance card until the verification is successful.
Wherein, the judging whether the read information point table is consistent with the information stored in the master station specifically comprises:
if the acceptance information is a remote measuring signal, a remote control signal or a remote regulating signal, correspondingly judging whether the number of the acceptance card exists in the master station system, judging whether the name of each acceptance card is consistent with the name stored in the master station system database, if the judgment result is yes, the master station of the acceptance card is successfully verified, and if not, the verification fails;
and if the acceptance information is a remote signaling signal, judging whether the point number of the remote signaling acceptance card exists in the master station system, whether the name of the acceptance card is consistent with the name stored in the master station database and whether the alarm grade is consistent with the grade stored in the master station database, if the judgment result is yes, the remote signaling acceptance card is verified to be successful in master station verification, and if the judgment result is not yes, the verification fails.
The substation verification is carried out on the remote signaling verification and acceptance card, the teletesting acceptance card, the remote control verification card and the remote modulation verification and acceptance card after the verification is successful, and the generation of the substation verification and acceptance card verification library according to the result specifically comprises the following steps:
and analyzing the information of the remote signaling check and acceptance card, the remote test check and acceptance card, the remote control check and acceptance card and the remote regulation check and acceptance card after the master station successfully checks, and automatically checking the analyzed information and the telecontrol forwarding table.
The invention also provides a four-remote information acceptance system, which comprises: each level of scheduling mechanism schedules a master station system, a transformer substation monitoring system and a production management system, wherein,
the production management system is used for generating a remote signaling check and acceptance card, a remote test acceptance card, a remote control check and acceptance card and a remote control check and acceptance card according to the four-remote information base; the system is also used for receiving the four-remote signal to be verified and archiving an acceptance report sent by the main station and an acceptance report sent by the substation;
the dispatching master station system of each level of dispatching mechanism is used for verifying the remote signaling acceptance card, the remote testing acceptance card and the remote regulating acceptance card and generating a master station acceptance card verification library according to verification results; the master station check system is also used for carrying out master station check on the four remote signals to be checked according to the master station check card check library, generating a master station check report and sending the master station check report to the production management system;
the substation monitoring system is used for performing substation verification on the remote signaling verification and acceptance card, the remote test and acceptance card, the remote control verification and acceptance card and the remote modulation verification and acceptance card after the verification is successful, and generating a substation verification and acceptance card verification library according to the result; and the sub-station verification system is also used for carrying out sub-station verification on the four-remote signal to be verified according to the sub-station verification card verification library, generating a sub-station verification report and sending the sub-station verification report to the production management system.
The remote signaling acceptance card, the remote testing acceptance card and the remote adjusting acceptance card are all in extensible markup language format, and each acceptance card comprises an attribute and a corresponding attribute description.
The system of the master scheduling station of each scheduling mechanism specifically comprises an information point table acquisition unit and a judgment unit, wherein:
the information point table acquisition unit is used for reading the information point tables of the teletesting receiving card, the remote signaling checking receiving card, the remote control checking receiving card and the remote modulation checking receiving card,
the judging unit is used for judging whether the read information point table is consistent with the information stored in the master station, if so, the verification is successful, a master station verification and acceptance card verification library is generated according to the verification successful in verification, otherwise, the verification fails, the four-remote information library is modified, the remote signaling verification and acceptance card, the remote testing and acceptance card, the remote control verification and acceptance card and the remote adjustment and acceptance card are regenerated according to the modified four-remote information library, and the master station verification is carried out on the regenerated remote signaling verification and acceptance card, remote testing and acceptance card, remote control verification card and remote adjustment and acceptance card until the verification is successful.
Wherein, the judging whether the read information point table is consistent with the information stored in the database specifically comprises:
if the acceptance information is a remote measuring signal, a remote control signal or a remote regulating signal, correspondingly judging whether the number of the acceptance card exists in the master station system, judging whether the name of each acceptance card is consistent with the name stored in the master station system database, if the judgment result is yes, the master station of the acceptance card is successfully verified, and if not, the verification fails;
and if the acceptance information is a remote signaling signal, judging whether the point number of the remote signaling acceptance card exists in the master station system, whether the name of the acceptance card is consistent with the name stored in the master station database and whether the alarm grade is consistent with the grade stored in the master station database, if the judgment result is yes, the remote signaling acceptance card is verified to be successful in master station verification, and if the judgment result is not yes, the verification fails.
The embodiment of the invention has the beneficial effects that: according to the embodiment of the invention, the production management system establishes the acceptance card according to the four-remote database, the master station verification and the sub-station verification are carried out on the acceptance card, the master station acceptance card verification library and the sub-station acceptance card verification library are respectively generated, and the acceptance report is generated by verifying the four-remote information to be accepted according to the master station acceptance card verification library and the sub-station acceptance card verification library. The method avoids the problem of information deviation caused by asynchronous construction time of the master station system and the substation system OMS and lack of unified rules of the model, provides an acceptance basis for follow-up four-remote signal self-acceptance, effectively reduces the intensity of acceptance work, and greatly improves the acceptance efficiency.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
Fig. 1 is a schematic flow chart of a four-remote information acceptance method according to an embodiment of the present invention.
Detailed Description
The following description of the embodiments refers to the accompanying drawings, which are included to illustrate specific embodiments in which the invention may be practiced.
Referring to fig. 1 below, an embodiment of the present invention provides a four-remote information acceptance method, including the following steps:
and S1, generating a remote signaling check and acceptance card, a remote test acceptance card, a remote control check and acceptance card and a remote regulation check and acceptance card according to the four-remote information base.
The checking and receiving card is generated by the OMS side according to a four-remote information base, the four-remote information is respectively remote signaling, remote measuring, remote controlling and remote adjusting, the remote signaling checking and receiving card is generated according to the remote signaling information base, the remote testing receiving card is generated according to the remote measuring information base, the remote control checking and receiving card is generated according to the remote controlling information, and the remote adjusting checking and receiving card is generated according to the remote adjusting information. The check cards are all in extensible markup language format, and the following tables 1-3 are remote signaling check cards, remote testing check cards and remote control check cards, respectively.
TABLE 1 remote signalling acceptance card
TABLE 2 telemetering acceptance card
Table 3 remote control acceptance card
After the acceptance card is generated, the acceptance card serves as the only source of the four-remote information and is transferred among the master station system, the substation system and the OMS system, so that the condition that the equipment cannot be matched due to the modeling difference of three sets of systems is avoided.
And S2, performing master station verification on the remote signaling verification and acceptance card, the remote test acceptance card, the remote control verification card and the remote regulation verification and acceptance card, and generating a master station verification and acceptance card verification library according to verification results.
After the OMS system generates the acceptance card, the acceptance card automatically transmits in two directions among the OMS system, the three areas of the master station system and the one area of the master station system by adopting a file service transmission technology of the master station system. The OMS generates a remote measurement, remote signaling, remote control and remote regulation check card according to the four-remote information base, and then sends the check card to the master station OCS, and the OCS corrects the contents of the check card with the pre-set parameters and checks an OCS real-time base; if the verification fails, modifying the four-remote information base, regenerating a verification card according to the modified four-remote information base, and re-verifying; and after the verification is successful, the OMS transmits the acceptance card to the substation by using the station-side OMS client.
And after the acceptance card flow is transferred to the master station, the comparison work of the acceptance card information and the database is carried out, and the comparison is carried out by reading an acceptance information point table and the preposed database. For the remote measurement information, the information to be controlled and the remote regulation information, whether the point number of the verification card exists in the master station system or not and whether the names are consistent or not need to be compared, if the judgment results are yes, the verification is successful, and otherwise, the verification fails. For a common remote signaling signal, whether the point number of the verification card exists in the master station system and whether the name of the verification card is consistent or not needs to be judged, whether the alarm level is consistent or not needs to be judged, if yes, the verification is successful, and if not, the verification fails. For the protection signal in the remote signaling signal, on the basis of judging the remote signaling signal, whether the protection signal is a photon plate needs to be judged, if so, the verification is successful, and otherwise, the verification fails.
And when the verification of the acceptance card fails, the four-remote information base needs to be modified, the acceptance card is regenerated according to the modified four-remote information base, and the master station verification is carried out on the new acceptance card until the verification is successful.
And S3, performing substation verification on the remote signaling verification and acceptance card, the remote test and acceptance card, the remote control verification and acceptance card and the remote modulation verification and acceptance card after the main station is successfully verified, and generating a substation verification and acceptance card verification library according to the result.
And after the check card flow is transferred to the substation system, substation check is carried out on the check card. And extracting the information of the check card, comparing the information of the check card with the telecontrol forwarding table, and realizing the automatic check of the check card and the motion forwarding table to the maximum extent by various means such as complete matching, fuzzy matching, manual intervention and the like.
S4, receiving the four-remote signals to be checked and accepted, checking and accepting the four-remote signals to be checked and accepted according to the main station checking and accepting card checking library and the sub-station checking and accepting card checking library, and generating a checking and accepting report.
After the check cards pass through the master station and the sub-station for checking, the four-remote information is guided into the master station system and the sub-station system, the master station system conducts master station checking on the four-remote signals to be checked according to the master station check card checking library and sends check reports to the OMS system, and the sub-station system conducts sub-station checking on the four-remote signals to be checked according to the sub-station check card checking library and sends the check reports to the OMS system. And the OMS system files the verification reports uploaded by the master station system and the substation system.
According to the four-remote information acceptance method, the production management system establishes the acceptance card according to the four-remote database, the master station verification and the substation verification are carried out on the acceptance card, the master station acceptance card verification library and the substation acceptance card verification library are respectively generated, and the acceptance report is generated by verifying the four-remote information to be accepted according to the master station acceptance card verification library and the substation acceptance card verification library. The method avoids the problem of information deviation caused by asynchronous construction time of the master station system and the substation system OMS and lack of unified rules of the model, provides an acceptance basis for follow-up four-remote signal self-acceptance, effectively reduces the intensity of acceptance work, and greatly improves the acceptance efficiency.
Based on the first embodiment of the present invention, the second embodiment of the present invention provides a four-remote information acceptance system, including: each level of scheduling mechanism schedules a master station system, a transformer substation monitoring system and a production management system, wherein,
the production management system is used for generating a remote signaling check and acceptance card, a remote test acceptance card, a remote control check and acceptance card and a remote control check and acceptance card according to the four-remote information base; the system is also used for receiving the four-remote signal to be verified and archiving an acceptance card report sent by the main station and an acceptance card report sent by the substation;
the dispatching master station system of each level of dispatching mechanism is used for verifying the remote signaling acceptance card, the remote testing acceptance card and the remote regulating acceptance card and generating a master station acceptance card verification library according to verification results; the master station check system is also used for carrying out master station check on the four remote signals to be checked according to the master station check card receiving check library, generating a master station check card receiving report and sending the master station check card receiving report to the production management system;
the substation monitoring system is used for verifying the remote signaling acceptance card, the remote testing acceptance card and the remote adjusting acceptance card after successful detection, and generating a substation acceptance card verification library according to the result; and the sub-station checking and accepting card checking library is also used for carrying out sub-station checking on the four-remote signal to be checked, generating a sub-station checking and accepting card report and sending the sub-station checking and accepting card report to the production management system.
The remote signaling acceptance card, the remote testing acceptance card and the remote adjusting acceptance card are all in extensible markup language format, and each acceptance card comprises corresponding attributes and attribute description.
The system comprises a scheduling master station system of each level of scheduling mechanism, a scheduling master station system of each level of scheduling mechanism and a scheduling control unit, wherein the scheduling master station system of each level of scheduling mechanism specifically comprises an information point table acquisition unit and a judgment unit, wherein:
the information point table acquisition unit is used for reading the information point tables of the teletesting receiving card, the remote signaling checking receiving card, the remote control checking receiving card and the remote modulation checking receiving card,
the judging unit is used for judging whether the read information point table is consistent with the information stored in the database, if so, the verification is successful, the master station verification card verification library is generated according to the verification card which is successfully verified, otherwise, the verification fails, the four-remote information library is modified, the remote signaling verification receiving card, the remote testing receiving card, the remote control verification receiving card and the remote adjustment verification receiving card are regenerated according to the modified four-remote information library, and the regenerated remote signaling verification receiving card, the remote testing receiving card, the remote control verification receiving card and the remote adjustment verification receiving card are verified until the verification is successful.
Wherein, the judging whether the read information point table is consistent with the information stored in the database specifically comprises: if the acceptance information is a remote measuring signal, a remote control signal or a remote regulating signal, correspondingly judging whether the point number of the acceptance card exists in the master station system, respectively judging whether the name of each acceptance card is consistent with the name stored in the database, if the judgment result is yes, the acceptance card is successfully verified in the master station, otherwise, the verification fails; and if the acceptance information is a remote signaling signal, judging whether the point number of the remote signaling acceptance card exists in the master station system, whether the name of the acceptance card is consistent with the name stored in the database and whether the alarm grade is consistent with the grade stored in the database, if the judgment result is yes, the remote signaling acceptance card is verified successfully, and if the judgment result is not yes, the verification fails.
The above disclosure is only for the purpose of illustrating the preferred embodiments of the present invention, and it is therefore to be understood that the invention is not limited by the scope of the appended claims.
Claims (9)
1. A four-remote information acceptance method is characterized by comprising the following steps:
generating a remote signaling check and acceptance card, a remote test check and acceptance card, a remote control check and acceptance card and a remote regulation check and acceptance card according to the four-remote information base;
performing master station system verification on the remote signaling acceptance card, the remote test acceptance card and the remote control acceptance card, and generating a master station acceptance card verification library according to a verification result;
the sub-station system verification is carried out on the remote signaling verification acceptance card, the remote test acceptance card, the remote control verification acceptance card and the remote regulation verification acceptance card after the main station system is successfully verified, and a sub-station verification acceptance card verification library is generated according to the result;
and receiving the four-remote signals to be checked and accepted, checking and accepting the four-remote signals to be checked and accepted according to the main station card checking and accepting verification library and the sub-station card checking and accepting verification library, and generating a checking and accepting report.
2. The method of claim 1, wherein the remote signaling acceptance card, the remote testing acceptance card, and the remote tuning acceptance card are in extensible markup language format, each of the acceptance cards including attributes and corresponding attribute descriptions.
3. The method of claim 2, wherein the performing the master station system verification on the remote signaling acceptance card, the remote testing acceptance card and the remote regulating acceptance card, and the generating the master station acceptance card verification library according to the verification result specifically comprises:
respectively reading the information point tables of the remote test receiving card, the remote signaling checking receiving card, the remote control checking receiving card and the remote control checking receiving card,
and judging whether the read information point table is consistent with the information stored in the master station, if so, the verification is successful, generating a master station verification and acceptance card verification library according to the verification successful in verification, otherwise, the verification fails, modifying the four-remote information library, regenerating a remote signaling verification and acceptance card, a remote testing acceptance card and a remote adjusting and acceptance card according to the modified four-remote information library, and performing master station verification on the regenerated remote signaling verification and acceptance card, remote testing acceptance card and remote adjusting and acceptance card until the verification is successful.
4. The method according to claim 3, wherein the determining whether the read information point table is consistent with the information stored in the master station specifically comprises:
if the acceptance information is a remote measuring signal, a remote control signal or a remote regulating signal, correspondingly judging whether the number of the acceptance card exists in the master station system, judging whether the name of each acceptance card is consistent with the name stored in the master station system database, if the judgment result is yes, the master station of the acceptance card is successfully verified, and if not, the verification fails;
and if the acceptance information is a remote signaling signal, judging whether the point number of the remote signaling acceptance card exists in the master station system, whether the name of the acceptance card is consistent with the name stored in the master station database and whether the alarm grade is consistent with the grade stored in the master station database, if the judgment result is yes, the remote signaling acceptance card is verified to be successful in master station verification, and if the judgment result is not yes, the verification fails.
5. The method according to claim 1, wherein the sub-station system verification is performed on the remote signaling acceptance card, the remote testing acceptance card and the remote debugging acceptance card after the verification is successful, and the generation of the sub-station acceptance card verification library according to the result specifically comprises:
and analyzing the information of the remote signaling check and acceptance card, the remote test check and acceptance card, the remote control check and acceptance card and the remote regulation check and acceptance card after the master station successfully checks, and automatically checking the analyzed information and the telecontrol forwarding table.
6. A four-remote information acceptance system, comprising: each level of scheduling mechanism schedules a master station system, a transformer substation monitoring system and a production management system, wherein,
the production management system is used for generating a remote signaling check and acceptance card, a remote test acceptance card, a remote control check and acceptance card and a remote control check and acceptance card according to the four-remote information base; the system is also used for receiving the four-remote signal to be verified and archiving an acceptance report sent by the main station and an acceptance report sent by the substation;
the dispatching master station system of each level of dispatching mechanism is used for verifying the remote signaling acceptance card, the remote testing acceptance card and the remote regulating acceptance card and generating a master station acceptance card verification library according to verification results; the master station check system is also used for carrying out master station check on the four remote signals to be checked according to the master station check card check library, generating a master station check report and sending the master station check report to the production management system;
the substation monitoring system is used for performing substation verification on the remote signaling verification and acceptance card, the remote test and acceptance card, the remote control verification and acceptance card and the remote modulation verification and acceptance card after the verification is successful, and generating a substation verification and acceptance card verification library according to the result; and the sub-station verification system is also used for carrying out sub-station verification on the four-remote signal to be verified according to the sub-station verification card verification library, generating a sub-station verification report and sending the sub-station verification report to the production management system.
7. The system of claim 6, wherein: the remote signaling acceptance card, the remote testing acceptance card and the remote adjusting acceptance card are all in extensible markup language format, and each acceptance card comprises an attribute and a corresponding attribute description.
8. The system according to claim 7, wherein the scheduling master station system of each level of the scheduling mechanism specifically comprises an information point table obtaining unit and a judging unit, wherein:
the information point table acquisition unit is used for reading the information point tables of the teletesting receiving card, the remote signaling checking receiving card, the remote control checking receiving card and the remote modulation checking receiving card,
the judging unit is used for judging whether the read information point table is consistent with the information stored in the master station, if so, the verification is successful, a master station verification and acceptance card verification library is generated according to the verification successful in verification, otherwise, the verification fails, the four-remote information library is modified, the remote signaling verification and acceptance card, the remote testing and acceptance card, the remote control verification and acceptance card and the remote adjustment and acceptance card are regenerated according to the modified four-remote information library, and the master station verification is carried out on the regenerated remote signaling verification and acceptance card, remote testing and acceptance card, remote control verification card and remote adjustment and acceptance card until the verification is successful.
9. The system according to claim 8, wherein the determining whether the read information point table is consistent with the information stored in the database specifically comprises:
if the acceptance information is a remote measuring signal, a remote control signal or a remote regulating signal, correspondingly judging whether the number of the acceptance card exists in the master station system, judging whether the name of each acceptance card is consistent with the name stored in the master station system database, if the judgment result is yes, the master station of the acceptance card is successfully verified, and if not, the verification fails;
and if the acceptance information is a remote signaling signal, judging whether the point number of the remote signaling acceptance card exists in the master station system, whether the name of the acceptance card is consistent with the name stored in the master station database and whether the alarm grade is consistent with the grade stored in the master station database, if the judgment result is yes, the remote signaling acceptance card is verified to be successful in master station verification, and if the judgment result is not yes, the verification fails.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910976878.1A CN110781241A (en) | 2019-10-15 | 2019-10-15 | Four-remote information acceptance method and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910976878.1A CN110781241A (en) | 2019-10-15 | 2019-10-15 | Four-remote information acceptance method and system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110781241A true CN110781241A (en) | 2020-02-11 |
Family
ID=69385564
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910976878.1A Pending CN110781241A (en) | 2019-10-15 | 2019-10-15 | Four-remote information acceptance method and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110781241A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111641264A (en) * | 2020-05-22 | 2020-09-08 | 国网河北省电力有限公司电力科学研究院 | Performance evaluation method for transformer substation monitoring system |
CN112260400A (en) * | 2020-09-29 | 2021-01-22 | 许继电源有限公司 | Ship shore power monitoring control system and method |
CN114612079A (en) * | 2022-05-16 | 2022-06-10 | 国网江西省电力有限公司电力科学研究院 | Automatic checking method for monitoring information graph library of centralized control station |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105576831A (en) * | 2015-12-30 | 2016-05-11 | 北京四方继保自动化股份有限公司 | Automatic verification method for security control of master station and sub station |
CN107450445A (en) * | 2017-09-05 | 2017-12-08 | 国网山东省电力公司 | A kind of unified check of electric power supervisory control signal multistation and acceptance method |
CN109032051A (en) * | 2018-06-21 | 2018-12-18 | 国网江苏省电力有限公司徐州供电分公司 | A kind of automatic acceptance method of monitoring signal |
CN109217470A (en) * | 2018-09-07 | 2019-01-15 | 国网江苏省电力有限公司连云港供电分公司 | It is checked and accepted automatically and check method and system based on the boss station monitoring information for checking and accepting card |
-
2019
- 2019-10-15 CN CN201910976878.1A patent/CN110781241A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105576831A (en) * | 2015-12-30 | 2016-05-11 | 北京四方继保自动化股份有限公司 | Automatic verification method for security control of master station and sub station |
CN107450445A (en) * | 2017-09-05 | 2017-12-08 | 国网山东省电力公司 | A kind of unified check of electric power supervisory control signal multistation and acceptance method |
CN109032051A (en) * | 2018-06-21 | 2018-12-18 | 国网江苏省电力有限公司徐州供电分公司 | A kind of automatic acceptance method of monitoring signal |
CN109217470A (en) * | 2018-09-07 | 2019-01-15 | 国网江苏省电力有限公司连云港供电分公司 | It is checked and accepted automatically and check method and system based on the boss station monitoring information for checking and accepting card |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111641264A (en) * | 2020-05-22 | 2020-09-08 | 国网河北省电力有限公司电力科学研究院 | Performance evaluation method for transformer substation monitoring system |
CN112260400A (en) * | 2020-09-29 | 2021-01-22 | 许继电源有限公司 | Ship shore power monitoring control system and method |
CN114612079A (en) * | 2022-05-16 | 2022-06-10 | 国网江西省电力有限公司电力科学研究院 | Automatic checking method for monitoring information graph library of centralized control station |
CN114612079B (en) * | 2022-05-16 | 2022-09-02 | 国网江西省电力有限公司电力科学研究院 | Automatic checking method for monitoring information graph library of centralized control station |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110781241A (en) | Four-remote information acceptance method and system | |
CN104483842B (en) | One kind regulation and control one automation main website comparison method | |
CN108923953A (en) | A kind of virtual main station system of power remote machine debugging | |
CN104460589B (en) | Mobile debugging system with simulation dispatching master station | |
CN112366818B (en) | Automatic checking and accepting method and system for monitoring information of intelligent substation | |
CN110401692B (en) | Integrated automatic checking and accepting system and method for monitoring information of transformer substation | |
CN110568284B (en) | Intelligent substation one-key sequential control automatic test verification method, device and system | |
US20200117151A1 (en) | Outage and switch management for a power grid system | |
CN111160795B (en) | Management system and method for distribution network pattern abnormal operation and power failure lean assessment | |
CN105069587A (en) | Mobile Internet-based relay protection verification device | |
CN103905275A (en) | Electric power telecontrol equipment testing method based on IEC61850 replacement services | |
CN105929277A (en) | Method and system for standardizing automatic testing schemes of replay protection device | |
CN109117526A (en) | One kind being suitable for mechanical system maintenance of equipment and guides data record and analysis system | |
CN111327468A (en) | Operation method and system for edge computing platform of power system | |
CN115599750A (en) | Intelligent substation virtual circuit checking method, system, equipment and storage medium | |
CN109038820A (en) | A kind of anti-misoperation system and a kind of method for preventing misoperation based on image inspection based on image inspection | |
CN111507635A (en) | Power transformation operation and inspection intelligent mobile operation system and method based on power internet of things | |
CN105591471A (en) | Transformer station and main station data consistency comparison and calibration method | |
CN106529842A (en) | Control operation quantitative evaluation system and method for power grid | |
CN110516828B (en) | Monitoring information processing system and method | |
CN107577789A (en) | Province based on information interactive bus ground artwork interconnected method | |
CN115086209A (en) | Signal system digital intelligent test method based on edge computing platform | |
CN113794754A (en) | Electronic operation ticket control system and method based on mobile application | |
CN114123482A (en) | Main plant station information joint debugging decoupling method | |
CN115001133B (en) | Intelligent power-off and power-on switching operation method and system in traction power supply system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200211 |
|
RJ01 | Rejection of invention patent application after publication |