CN114612079A - Automatic checking method for monitoring information graph library of centralized control station - Google Patents

Automatic checking method for monitoring information graph library of centralized control station Download PDF

Info

Publication number
CN114612079A
CN114612079A CN202210525947.9A CN202210525947A CN114612079A CN 114612079 A CN114612079 A CN 114612079A CN 202210525947 A CN202210525947 A CN 202210525947A CN 114612079 A CN114612079 A CN 114612079A
Authority
CN
China
Prior art keywords
remote
remote control
primitive
configuration
signaling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210525947.9A
Other languages
Chinese (zh)
Other versions
CN114612079B (en
Inventor
钟逸铭
谢国强
余滢婷
周仕豪
潘本仁
万勇
熊华强
王冠南
桂小智
邹进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jiangxi Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jiangxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Jiangxi Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN202210525947.9A priority Critical patent/CN114612079B/en
Publication of CN114612079A publication Critical patent/CN114612079A/en
Application granted granted Critical
Publication of CN114612079B publication Critical patent/CN114612079B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00001Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the display of information or by user interaction, e.g. supervisory control and data acquisition systems [SCADA] or graphical user interfaces [GUI]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2218/00Aspects of pattern recognition specially adapted for signal processing
    • G06F2218/12Classification; Matching
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/40Display of information, e.g. of data or controls

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Human Computer Interaction (AREA)
  • Quality & Reliability (AREA)
  • Power Engineering (AREA)
  • Data Mining & Analysis (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Selective Calling Equipment (AREA)

Abstract

The invention discloses an automatic checking method for a monitoring information graph library of a centralized control station, which comprises the following steps: and acquiring remote control configuration and electric power primitives, and checking and accepting the remote control configuration and the electric power primitives. The method has the advantages that standard primitives and data model files can be analyzed, remote control signals are automatically associated with remote signaling points by adopting name rules, automatic closed-loop verification from a master station side to a station side is realized according to a remote signaling acceptance strategy, and finally quick acceptance of a centralized control station graph model library is realized, so that the work efficiency and quality of acceptance of the centralized control station graph model library can be improved, and the time for accepting monitoring information is shortened.

Description

Automatic checking method for monitoring information graph library of centralized control station
Technical Field
The invention belongs to the technical field of intelligent substations, and particularly relates to an automatic acceptance method of a monitoring information graph library of a centralized control station.
Background
At present, with the development of electric power technology, domestic reconstruction and extension of substations gradually tend to the development of intelligent substations. In an intelligent substation, a centralized control station monitoring system is used as an important ring for power grid regulation and control integrated operation, and a large amount of substation equipment operation state information such as primary equipment data, secondary equipment data, auxiliary equipment data and the like needs to be acquired, so that the difficulty of debugging and acceptance work is increased.
Traditional telemechanical information counter-point work is manual mode mostly, and master website, station personnel keep in time communicating and carry out one by one counter-point mode, and this makes debugging work efficiency low, influences the transformer substation construction progress. Most of the existing monitoring information point table acceptance systems only achieve unidirectional acceptance of signals from a plant station to a main station, closed loop tests of the signals are not formed, especially remote control and acceptance of a graph model library are always stopped in a manual acceptance mode, acceptance efficiency is low, and commissioning time of a transformer substation is seriously affected.
Disclosure of Invention
The invention provides an automatic acceptance method for a monitoring information graph-model library of a centralized control station, which is used for solving the technical problem of low acceptance efficiency of remote control and the graph-model library.
The invention provides an automatic checking method for a monitoring information graph library of a centralized control station, which comprises the following steps: obtaining remote control configuration and an electric power primitive, and checking and accepting the remote control configuration and the electric power primitive, wherein the checking and accepting of the electric power primitive specifically comprises the following steps:
Step 1.1, analyzing an SVG format graphic file and a data model file in a scheduling master station to respectively obtain an electric power primitive and remote signaling and remote monitoring configuration, and establishing an incidence relation between the electric power primitive and the remote signaling and remote monitoring configuration;
step 1.2, judging whether the configuration of a certain power primitive is correct or not, wherein the configuration of the certain power primitive comprises a primitive name of the certain power primitive and a remote signaling point or a remote measuring point associated with the certain power primitive;
step 1.3, if the configuration of a certain power primitive is correct, switching to a graphical interface, and initializing the initial state of the certain power primitive;
step 1.4, analyzing a remote signaling value or a remote measuring value associated with the initialized certain power primitive, and sending a remote signaling value or a non-0 remote measuring value containing an action;
step 1.5, generating a corresponding signal according to the received remote signaling value or the remote measurement value in a simulation mode, and sending the signal;
step 1.6, judging whether the time for receiving the signal is greater than a preset time threshold, if the signal is not received within the preset time threshold, failing to accept the certain power primitive, and if the signal is received within the preset time threshold, issuing a remote signaling value containing a reset or a remote measurement value of 0 again;
And step 1.7, after all the remote signaling values including actions and regressions or the remote measuring values which are not 0 or 0 are completely sent, comparing the remote signaling values or the remote measuring values in sequence, and if the remote signaling values or the remote measuring values are the same and the receiving sequence is consistent, checking and accepting the graphic elements correctly.
Further, in step 1.2, the determining whether the configuration of a certain power primitive is correct includes: comparing the primitive name of the certain power primitive with the primitive name marked in the remote signaling point or the remote measuring point in the standard information point table; comparing the remote signaling point or the remote measuring point associated with the certain power primitive with the remote signaling point or the remote measuring point in the standard information point table; and if the primitive name of the certain power primitive and the remote signaling point or remote measuring point associated with the certain power primitive are consistent, the configuration of the certain power primitive is correct.
Further, in step 1.3, the initializing the initial state of the certain power primitive comprises: setting the switch state in the certain power primitive to be a separated state; and setting the telemetry value in the certain power primitive to be a value of 0.
Further, the acceptance of the remote control configuration specifically includes:
step 2.1, acquiring remote control configuration from a scheduling master station, and analyzing the actual remote control configuration of the scheduling master station;
Step 2.2, comparing the analyzed actual remote control configuration with the remote control configuration in the standard information point table in sequence, if the actual remote control configuration is correctly compared with the remote control configuration in the standard information point table, entering step 2.3, and if the actual remote control configuration is wrong compared with the remote control configuration in the standard information point table, requiring the scheduling master station to modify the actual remote control configuration;
step 2.3, establishing an incidence relation between the actual remote control configuration and the remote signaling configuration according to a name fuzzy matching principle, checking whether the incidence relation is correct or not after the establishment is finished, and modifying the incidence relation between the actual remote control configuration and the remote signaling configuration if the incidence relation is incorrect;
step 2.4, selecting a remote control point to be checked and accepted, and automatically generating a remote control checking and accepting card;
step 2.5, acquiring a certain point to be checked and accepted from the remote control checking and accepting card, issuing a remote control command to the substation, and acquiring a remote control command return result;
step 2.6, the substation remotely controls the switch based on the remote control command, and returns the acquired associated remote signaling state value to the scheduling master station after the switch acts;
and 2.7, the scheduling master station judges whether the remote control command return result is correct and whether the received remote signaling state value is consistent with the remote control command, if the remote control command return result is correct and the received remote signaling state value is consistent with the remote control command, the whole remote control process is correct, and the remote control point is successfully checked and accepted.
According to the automatic checking and accepting method for the monitoring information graph library of the centralized control station, standard (manufacturer-defined) primitives and data model files can be analyzed, remote control signals are automatically associated with remote signaling points by adopting name rules, automatic closed-loop verification from a main station side to a sub-station is achieved according to a remote signaling checking and accepting strategy, and finally quick checking and accepting of the graph library of the centralized control station are achieved, so that the working efficiency and quality of checking and accepting of the graph library of the centralized control station can be improved, and the time for checking and accepting monitoring information is shortened.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the description below are some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
Fig. 1 is a block diagram of a structure of an automatic acceptance system of a monitoring information graph library of a centralized control station according to an embodiment of the present invention;
fig. 2 is a flowchart of automatically checking and accepting an electric power primitive in an automatic checking and accepting method for a monitoring information graph library of a centralized control station according to an embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be obtained by a person skilled in the art without inventive step based on the embodiments of the present invention, are within the scope of protection of the present invention.
Referring to fig. 1, a block diagram of a system for automatically checking and accepting a monitoring information graph library of a centralized control station according to the present application is shown.
As shown in fig. 1, the automatic checking and accepting system of the monitoring information graph library of the centralized control station comprises a configuration unit, a checking and accepting card generation unit connected with the configuration unit, a communication unit connected with the checking and accepting card generation unit, an automatic checking and accepting unit connected with the communication unit and a recording unit connected with the automatic checking and accepting unit; the configuration unit comprises a monitoring information point table module, a scheduling configuration loading module and a configuration checking module, the acceptance card generating unit comprises an automatic remote signaling acceptance card generating module, an automatic remote sensing acceptance card generating module, an automatic remote control acceptance card generating module and an automatic primitive acceptance card generating module, the communication unit comprises a client module 104 and a message real-time monitoring module, the automatic acceptance unit comprises an automatic remote signaling acceptance module, an automatic remote sensing acceptance module, an automatic remote control acceptance module and a primitive quick acceptance module, and the recording unit comprises an automatic result recording module and a derivation module.
Specifically, the configuration unit is used for comparing configuration data descriptions, such as remote signaling names, interval IDs (identity), voltage levels, alarm types, whether an optical character plate exists or not, remote measurement names, remote control names, interval IDs (identity), voltage levels and the like, by using the monitoring information point table and the point numbers of centralized control configuration as associated indexes, and specifically, the monitoring information point table module mainly imports and analyzes a standard monitoring information point table formulated by scheduling, comprises the remote signaling point table, the remote measurement point table and the remote control point table to generate standard configuration;
the acceptance card generating unit mainly comprises remote signaling, remote measuring and remote signal acceptance, and the acceptance card mainly comprises a signal sending rule, a forwarding table signal rule and a signal comparison rule. The automatic generation remote signaling acceptance check card module mainly generates a remote signaling acceptance check sequence, a remote signaling point number, a remote signaling action value, a reset value, a sending time interval and the like, the automatic generation remote signaling acceptance check card module mainly generates an acceptance check sequence, a remote signaling point number and a remote signaling value of a remote monitoring point, the automatic generation remote control acceptance check card module mainly generates a remote control acceptance check sequence, a remote control point number, a remote control joint state, an associated remote signaling signal and the like, the automatic generation primitive acceptance check card module mainly generates an acceptance check sequence, a primitive name, an associated remote signaling or remote monitoring point, a remote signaling value or remote monitoring value and the like of a primitive, and each acceptance check card station acceptance check device and the master station acceptance check module send and accept standards;
The communication unit is mainly a device simulation upper signal sending unit for simulating a main station side to send and receive signals and an automatic acceptance unit, a main communication protocol comprises DL/T634.5104, MMS and the like, the 104 client module mainly receives remote signaling and remote measuring values forwarded by the front-end processor of the dispatching main station and provides the values to the automatic acceptance unit, the automatic acceptance unit carries out verification according to the values, and the message real-time monitoring module mainly monitors messages between the front-end processor of the dispatching main station and the communication unit so as to check whether the communication between the modules is normal or not.
The automatic acceptance unit is mainly used for receiving 104 the remote signaling telemetering data sent by the client module, automatically comparing the remote signaling telemetering data according to the acceptance content of the acceptance card, and if the data and the sequence sent by the sub-station are completely consistent with the acceptance card, the acceptance is correct, otherwise, the acceptance is wrong.
The telesignaling automatic acceptance check module receives telesignaling information in real time, compares the uploaded data in sequence according to an acceptance sequence and an acceptance value in a telesignaling acceptance check card, automatically judges whether the telesignaling acceptance check is correct or not if the received telesignaling information is consistent with the sequence and the telesignaling value in the telesignaling acceptance check card, and if not, automatically gives the reason of the acceptance check failure; the telemetering automatic acceptance module receives telemetering information in real time, compares whether the uploaded telemetering information is consistent with the value in the acceptance card and the acceptance sequence or not in sequence according to the acceptance sequence and the telemetering value of acceptance in the teletesting acceptance card, and if the uploaded telemetering information is consistent with the value in the acceptance card and the acceptance sequence, the acceptance is correct; the remote control automatic acceptance module issues a remote control signal to the substation, the substation actually controls the switch in a remote mode and returns a remote control execution result command and a related remote signaling signal, if the returned remote control execution is successful and a state value corresponding to the related remote signaling signal is received, the remote control acceptance is correct, and if the returned remote control execution is failed, the remote control acceptance fails; and the primitive fast checking and accepting module receives the remote signaling value or the remote measuring value in real time, the received value is consistent with the associated primitive display value, the value of the checking and accepting card and the checking and accepting sequence, if the received value is correct, the receiving card fails, and the failure reason is automatically given.
The recording unit is based on the automatic acceptance unit, the automatic acceptance unit pushes the acceptance result to the result automatic recording module, the result automatic recording module records and stores the acceptance result in real time, and the export module leads the acceptance result recording file in the EXCEL or XML format according to the selection of the user.
In conclusion, the automatic acceptance system of the centralized control station monitoring information graph-model library realizes closed-loop debugging and acceptance of the main substation and the sub substation of the substation monitoring information and quick acceptance of the centralized control station side graph-model library, and solves the problems of large workload and low efficiency of the existing substation monitoring information acceptance.
Referring to fig. 2, a flowchart of an automatic acceptance of power primitives of an automatic acceptance method of a monitoring information graph library of a central control station according to the present application is shown.
As shown in fig. 2, the automatic acceptance of the power primitive specifically includes the following steps:
step 1.1, analyzing an SVG format graphic file and a data model file in a scheduling master station to respectively obtain an electric power primitive and remote signaling and remote monitoring configuration, and establishing an incidence relation between the electric power primitive and the remote signaling and remote monitoring configuration;
step 1.2, judging whether the configuration of a certain power primitive is correct, wherein the configuration of the certain power primitive comprises a primitive name of the certain power primitive and a remote signaling point or a remote measuring point associated with the certain power primitive;
Step 1.3, if the configuration of a certain power primitive is correct, switching to a graphical interface, and initializing the initial state of the certain power primitive;
step 1.4, analyzing a remote signaling value or a remote measuring value associated with the initialized certain power primitive, and sending the remote signaling value or the non-0 remote measuring value containing the action;
step 1.5, generating a corresponding signal according to the received remote signaling value or the remote measurement value in a simulation mode, and sending the signal;
step 1.6, judging whether the time for receiving the signal is greater than a preset time threshold, if the signal is not received within the preset time threshold, failing to accept the certain power primitive, and if the signal is received within the preset time threshold, issuing a remote signaling value containing a reset or a remote measurement value of 0 again;
and step 1.7, after all the remote signaling values including actions and regressions or the remote measuring values which are not 0 or 0 are completely sent, comparing the remote signaling values or the remote measuring values in sequence, and if the remote signaling values or the remote measuring values are the same and the receiving sequence is consistent, checking and accepting the graphic elements correctly.
In the embodiment, the method comprises the steps of acquiring an SVG format graphic file and a data model file from a scheduling master station, analyzing power primitives, graphically displaying graphics such as a light word board and a primary main wiring, analyzing the data model file, analyzing remote signaling and remote measuring configuration, establishing association with the power primitives, and analyzing remote signaling and remote measuring configuration displayed by the associated graphics; reading the primitive name and the associated remote signaling or remote measuring point of a single primitive, comparing the primitive name with the primitive name marked in the remote signaling or remote measuring point in the standard information point table, simultaneously comparing the remote signaling remote measuring point with the remote signaling or remote measuring point associated with the primitive, and if the primitive name is consistent with the remote signaling or remote measuring point, correctly configuring the primitive; switching to a graphical interface, initializing the initial state of each primitive, setting the switch state represented by the primitive to be a branch state, and setting the telemetering value represented by the primitive to be a 0 value; automatically taking out a certain primitive, analyzing a remote signaling or remote measuring value associated with the primitive, issuing an action value by the remote signaling value, and issuing a non-0 value to an automatic acceptance device by the remote measuring value; simulating corresponding signals to be sent to a scheduling main station front-end processor after receiving the point numbers and the values issued by the graph model library; receiving the remote signaling or telemetering value forwarded by the front-end processor of the dispatching master station, if the remote signaling or telemetering value is received, issuing a remote signaling reset value or telemetering 0 value again, and if the receiving is overtime, directly judging that the primitive acceptance fails; after the remote signaling action and the reset or the remote measurement value and the 0 value are completely sent, comparing the remote signaling or the remote measurement value in sequence, and if the sending and receiving sequences are consistent, checking and accepting the graphic elements correctly; and automatically generating a primitive acceptance report, and marking whether the primitive configuration is wrong or the remote signaling or remote measuring value related to the primitive is wrong if the primitive acceptance report has errors.
In summary, the method can analyze standard primitives and data model files, automatically associate remote control signals with remote signaling points by adopting name rules, realize automatic closed-loop verification from a main station side to a plant station side according to a remote signaling acceptance strategy, finally realize quick acceptance of the centralized control station graph model library, improve the work efficiency and quality of acceptance of the centralized control station graph model library and shorten the time of acceptance of monitoring information.
In one embodiment, the remote automatic acceptance comprises the following specific steps:
step 2.1, acquiring remote control configuration from a scheduling master station, and analyzing the actual remote control configuration of the scheduling master station;
step 2.2, comparing the analyzed actual remote control configuration with the remote control configuration in the standard information point table in sequence, if the actual remote control configuration is correctly compared with the remote control configuration in the standard information point table, entering step 2.3, and if the actual remote control configuration is wrong compared with the remote control configuration in the standard information point table, requiring the scheduling master station to modify the actual remote control configuration;
step 2.3, establishing an incidence relation between the actual remote control configuration and the remote signaling configuration according to a name fuzzy matching principle, checking whether the incidence relation is correct or not after the establishment is finished, and modifying the incidence relation between the actual remote control configuration and the remote signaling configuration if the incidence relation is incorrect;
Step 2.4, selecting a remote control point to be checked and accepted, and automatically generating a remote control checking and accepting card;
step 2.5, acquiring a certain point to be checked from the remote check card, issuing a remote control command to the substation, and acquiring a remote control command return result;
step 2.6, the substation remotely controls the switch based on the remote control command, and returns the acquired associated remote signaling state value to the scheduling main station after the switch acts;
step 2.7, the scheduling master station judges whether the remote control command return result is correct and whether the received remote signaling state value is consistent with the remote control command, if the remote control command return result is correct and the received remote signaling state value is consistent with the remote control command, the whole remote control process is correct, and the remote control point is successfully checked and accepted;
step 2.8, repeating the steps 2.5 to 2.7, and sequentially verifying the remote control signals;
and 2.9, after the automatic operation is finished, generating an acceptance record result.
Finally, it should be noted that: the above examples are only intended to illustrate the technical solution of the present invention, but not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (4)

1. A centralized control station monitoring information graph library automatic acceptance method is characterized by comprising the following steps:
obtaining remote control configuration and an electric power primitive, and checking and accepting the remote control configuration and the electric power primitive, wherein the checking and accepting of the electric power primitive specifically comprises the following steps:
step 1.1, analyzing an SVG format graphic file and a data model file in a scheduling master station to respectively obtain an electric power primitive and remote signaling and remote monitoring configuration, and establishing an incidence relation between the electric power primitive and the remote signaling and remote monitoring configuration;
step 1.2, judging whether the configuration of a certain power primitive is correct, wherein the configuration of the certain power primitive comprises a primitive name of the certain power primitive and a remote signaling point or a remote measuring point associated with the certain power primitive;
step 1.3, if the configuration of a certain power primitive is correct, switching to a graphical interface, and initializing the initial state of the certain power primitive;
step 1.4, analyzing a remote signaling value or a remote measuring value associated with the initialized certain power primitive, and sending a remote signaling value or a non-0 remote measuring value containing an action;
step 1.5, generating a corresponding signal according to the received remote signaling value or the remote measurement value in a simulation mode, and sending the signal;
Step 1.6, judging whether the time for receiving the signal is greater than a preset time threshold, if the signal is not received within the preset time threshold, failing to accept the certain power primitive, and if the signal is received within the preset time threshold, issuing a remote signaling value containing a reset or a remote measurement value of 0 again;
and step 1.7, after all the remote signaling values including actions and regressions or the remote measuring values which are not 0 and are 0 are sent, sequentially comparing the remote signaling values or the remote measuring values, and if the remote signaling values or the remote measuring values are the same and the receiving sequence is the same, checking and accepting the graphic elements correctly.
2. The method according to claim 1, wherein in step 1.2, the determining whether the configuration of a certain power primitive is correct includes:
comparing the primitive name of the certain power primitive with the primitive name marked in the remote signaling point or the remote measuring point in the standard information point table;
comparing the remote signaling point or the remote measuring point associated with the certain power primitive with the remote signaling point or the remote measuring point in the standard information point table;
and if the primitive name of the certain power primitive and the remote signaling point or remote measuring point associated with the certain power primitive are consistent, the configuration of the certain power primitive is correct.
3. The method for automatically checking and accepting the monitoring information graph library of the centralized control station according to claim 1, wherein in step 1.3, the initializing the initial state of the certain power primitive comprises:
setting the switch state in the certain power primitive to be a separated state;
and setting the telemetry value in the certain power primitive to be a value of 0.
4. The method for automatically checking and accepting the monitoring information graph library of the centralized control station according to claim 1, wherein the checking and accepting of the remote control configuration specifically comprises:
step 2.1, acquiring remote control configuration from a scheduling master station, and analyzing the actual remote control configuration of the scheduling master station;
step 2.2, comparing the analyzed actual remote control configuration with the remote control configuration in the standard information point table in sequence, if the actual remote control configuration is correctly compared with the remote control configuration in the standard information point table, entering step 2.3, and if the actual remote control configuration is wrong compared with the remote control configuration in the standard information point table, requiring the scheduling master station to modify the actual remote control configuration;
step 2.3, establishing an incidence relation between the actual remote control configuration and the remote signaling configuration according to a name fuzzy matching principle, checking whether the incidence relation is correct or not after the establishment is finished, and modifying the incidence relation between the actual remote control configuration and the remote signaling configuration if the incidence relation is incorrect;
Step 2.4, selecting a remote control point to be checked and accepted, and automatically generating a remote control checking and accepting card;
step 2.5, acquiring a certain point to be checked from the remote check card, issuing a remote control command to the substation, and acquiring a remote control command return result;
step 2.6, the substation remotely controls the switch based on the remote control command, and returns the acquired associated remote signaling state value to the scheduling main station after the switch acts;
and 2.7, the scheduling master station judges whether the remote control command return result is correct and whether the received remote signaling state value is consistent with the remote control command, if the remote control command return result is correct and the received remote signaling state value is consistent with the remote control command, the whole remote control process is correct, and the remote control point is successfully checked and accepted.
CN202210525947.9A 2022-05-16 2022-05-16 Automatic checking method for monitoring information graph library of centralized control station Active CN114612079B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210525947.9A CN114612079B (en) 2022-05-16 2022-05-16 Automatic checking method for monitoring information graph library of centralized control station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210525947.9A CN114612079B (en) 2022-05-16 2022-05-16 Automatic checking method for monitoring information graph library of centralized control station

Publications (2)

Publication Number Publication Date
CN114612079A true CN114612079A (en) 2022-06-10
CN114612079B CN114612079B (en) 2022-09-02

Family

ID=81870585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210525947.9A Active CN114612079B (en) 2022-05-16 2022-05-16 Automatic checking method for monitoring information graph library of centralized control station

Country Status (1)

Country Link
CN (1) CN114612079B (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104460589A (en) * 2014-10-23 2015-03-25 国家电网公司 Mobile debugging system with simulation dispatching master station
CN106329730A (en) * 2016-09-14 2017-01-11 国网江苏省电力公司连云港供电公司 Substation monitoring information automatic acceptance system based on intelligent power grid scheduling system
CN107612998A (en) * 2017-09-19 2018-01-19 国电南瑞科技股份有限公司 A kind of transformer station's telemechanical forwarding remote data nucleus correcting system and method
CN109193928A (en) * 2018-07-27 2019-01-11 国网浙江省电力有限公司温州供电公司 Ground county integral system joint debugging information checking method
CN109217470A (en) * 2018-09-07 2019-01-15 国网江苏省电力有限公司连云港供电分公司 It is checked and accepted automatically and check method and system based on the boss station monitoring information for checking and accepting card
WO2019165811A1 (en) * 2018-02-28 2019-09-06 国电南瑞科技股份有限公司 Master/slave station monitoring information check method, and main station and slave station
CN110571927A (en) * 2019-08-30 2019-12-13 深圳供电局有限公司 Four-remote signal parameter checking method
CN110659822A (en) * 2019-09-20 2020-01-07 云南恒协科技有限公司 Intelligent information monitoring and management system for transformer substation
CN110781241A (en) * 2019-10-15 2020-02-11 深圳供电局有限公司 Four-remote information acceptance method and system
CN111969717A (en) * 2020-06-30 2020-11-20 国网辽宁省电力有限公司电力科学研究院 Remote control combined automatic acceptance method and system between main station and sub-station of electric power automation system
CN112270373A (en) * 2020-11-06 2021-01-26 广东电网有限责任公司 Automatic three-remote change identification method for scheduling master station based on image identification technology
CN113128004A (en) * 2021-04-06 2021-07-16 国网湖南省电力有限公司 Automatic mapping method and device for substation auxiliary control system and storage medium
US20210318018A1 (en) * 2018-09-03 2021-10-14 Daikin Industries, Ltd. Air flow control apparatus
CN114049598A (en) * 2022-01-13 2022-02-15 国网浙江省电力有限公司宁波供电公司 State identification method and device of power primitive, storage medium and electronic equipment

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104460589A (en) * 2014-10-23 2015-03-25 国家电网公司 Mobile debugging system with simulation dispatching master station
CN106329730A (en) * 2016-09-14 2017-01-11 国网江苏省电力公司连云港供电公司 Substation monitoring information automatic acceptance system based on intelligent power grid scheduling system
CN107612998A (en) * 2017-09-19 2018-01-19 国电南瑞科技股份有限公司 A kind of transformer station's telemechanical forwarding remote data nucleus correcting system and method
WO2019165811A1 (en) * 2018-02-28 2019-09-06 国电南瑞科技股份有限公司 Master/slave station monitoring information check method, and main station and slave station
CN109193928A (en) * 2018-07-27 2019-01-11 国网浙江省电力有限公司温州供电公司 Ground county integral system joint debugging information checking method
US20210318018A1 (en) * 2018-09-03 2021-10-14 Daikin Industries, Ltd. Air flow control apparatus
CN109217470A (en) * 2018-09-07 2019-01-15 国网江苏省电力有限公司连云港供电分公司 It is checked and accepted automatically and check method and system based on the boss station monitoring information for checking and accepting card
CN110571927A (en) * 2019-08-30 2019-12-13 深圳供电局有限公司 Four-remote signal parameter checking method
CN110659822A (en) * 2019-09-20 2020-01-07 云南恒协科技有限公司 Intelligent information monitoring and management system for transformer substation
CN110781241A (en) * 2019-10-15 2020-02-11 深圳供电局有限公司 Four-remote information acceptance method and system
CN111969717A (en) * 2020-06-30 2020-11-20 国网辽宁省电力有限公司电力科学研究院 Remote control combined automatic acceptance method and system between main station and sub-station of electric power automation system
CN112270373A (en) * 2020-11-06 2021-01-26 广东电网有限责任公司 Automatic three-remote change identification method for scheduling master station based on image identification technology
CN113128004A (en) * 2021-04-06 2021-07-16 国网湖南省电力有限公司 Automatic mapping method and device for substation auxiliary control system and storage medium
CN114049598A (en) * 2022-01-13 2022-02-15 国网浙江省电力有限公司宁波供电公司 State identification method and device of power primitive, storage medium and electronic equipment

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
SERGEY N. KIRILLOV: "Algorithm of Telemetry Information Weighting Signal Processing from Territorially-Distributed Receiving Stations", 《IEEE XPLORE》 *
刘军等: "智能变电站的监控信息一体化自动验收***设计与实现", 《微型电脑应用》 *
户艳琴: "变电运行软仿真培训***研究", 《中国优秀硕士学位论文全文数据库 (工程科技Ⅱ辑)》 *
文涛: "浅谈变电站监控***验收", 《内江科技》 *
杜杰: "配电终端信息就地联调与自动化接入研究与实现", 《中国优秀硕士学位论文全文数据库 (工程科技Ⅱ辑)》 *
胡玲霞等: ""四遥"信息管理***的设计", 《科技资讯》 *
苏运光等: "基于存量图形拓扑分析的厂站接线图自动生成", 《电力***自动化》 *
高翔等: "变电站监控信息接入自动验收方法探索", 《电力与能源》 *

Also Published As

Publication number Publication date
CN114612079B (en) 2022-09-02

Similar Documents

Publication Publication Date Title
CN113422820B (en) Automatic joint debugging device and method for remote information of main station
CN104820635B (en) A kind of self-closing ring gauge about robustness testing method based on the semantic parsing of dynamic script
CN109193945B (en) Automatic closed-loop checking method for telecontrol data configuration of intelligent substation
CN105242164A (en) Automatic detection system and method of secondary virtual loop of intelligent transformer station
CN105824001B (en) Method and system for testing IEC61850 conformance of digital electric energy meter
CN110766263B (en) Automatic acceptance method for secondary equipment of transformer substation and terminal equipment
CN105279952A (en) Whole-event acquisition testing system of intelligent ammeter based on virtual ammeter module
CN113437798B (en) Master-substation data consistency verification method for master-substation telecontrol information
CN111478818A (en) Telecontrol checking method based on SCD file and RCD file
CN112230095B (en) Load identification module hardware interface detection equipment and automatic detection method thereof
CN110611312B (en) On-line simulation system and method for panoramic data of substation bay level
CN113300765A (en) Intelligent identification and diagnosis method for power digital link
CN113705026B (en) Digital modeling and intelligent detection system for power secondary equipment
CN106990312B (en) Testing device and testing method for digital relay protection device
CN111564827A (en) Automatic checking method for relay protection setting value of intelligent station
CN117439264A (en) Automatic acceptance checking system for monitoring information of substation of dispatching master station
CN110838946A (en) Automatic acceptance system and method based on simulation substation
CN114612079B (en) Automatic checking method for monitoring information graph library of centralized control station
CN106909615B (en) Method and device for verifying data information consistency between master station and substation
CN112737116A (en) Automatic checking and accepting method and system for telecontrol information
CN114785681B (en) Automatic checking and accepting system and method for monitoring information of transformer substation on-line equipment
CN112181726B (en) Redundant backup measurement and control and four-unified measurement and control consistency verification test system and method
CN115203287A (en) Remote checking method and system for version of relay protection device
CN108931694A (en) A kind of distribution terminal intelligent checking system and its detection method
CN113131620A (en) Telecontrol information joint debugging method for transformer substation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant