CN109855612A - A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel - Google Patents

A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel Download PDF

Info

Publication number
CN109855612A
CN109855612A CN201910262686.4A CN201910262686A CN109855612A CN 109855612 A CN109855612 A CN 109855612A CN 201910262686 A CN201910262686 A CN 201910262686A CN 109855612 A CN109855612 A CN 109855612A
Authority
CN
China
Prior art keywords
tunnel
steel plate
stainless steel
forced centering
traverse survey
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910262686.4A
Other languages
Chinese (zh)
Inventor
彭东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201910262686.4A priority Critical patent/CN109855612A/en
Publication of CN109855612A publication Critical patent/CN109855612A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel, including bar steel plate, built-in type expansion bolt, shelf bracket, stainless steel bolt, stainless steel plate pedestal.Shelf bracket is fixed on tunnel double-lining or section of jurisdiction by setscrew, bar steel plate, and stainless steel plate is welded on pallet top, welds a stainless steel bolt among steel plate.Forced centering apparatus is placed in away from 1.8~2.0m high of tunnel internal rail top when use, on the lining of left and right side two of same mileage or section of jurisdiction, constructing tunnel is detachable after being completed, recycling.The present apparatus has easy to operate, at low cost, traverse survey precision height, stability good, survivable.Card prism head is come with the use of 360 °, prism direction need not be rotated, high-precision range measurement within the scope of 360 °, for tunnel traverse survey inside tunnel, influence of the gun parallax of error of centralization when measurement, camera lens and instrument sight to Measurement results precision can be reduced, be widely used in subway, tunnel construction control measurement.

Description

A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel
Technical field
The invention belongs to measuring tool technical fields, and in particular to a kind of forced centering for tunnel traverse survey inside tunnel Structure and its centering method.
Background technique
In underground engineering, Tunnel construction survey work, due to polygon leg length, the error of centralization plays in traverse survey Key effect, especially in Urban Metro Construction, subterranean tunnel design curve is more, radius is small, using conventional common cross A series of problems, such as mark carries out traverse layout, and it is inconvenient that not only the error of centralization is big, instrument is set up, but also prism frequently rotates makes tunnel Road measurement is extremely difficult to the piercing error of code requirement.
Summary of the invention
In order to overcome the above-mentioned deficiencies of the prior art, the object of the present invention is to provide one kind to be used for tunnel traverse survey inside tunnel Forced centering structure and its centering method, the installation cost is low, easy to make, can be mass, the biggest advantage is to disappear Influence in addition to the error of centralization to Measurement results, the flat pedestal of cooperation essence, 360 ° of prism heads use simultaneously, make measurement direction of visual lines without Any dead angle greatly improves work efficiency and controls precision without rotating frequently prism direction.
In order to overcome the above-mentioned deficiencies of the prior art, the technical solution adopted by the present invention is that:
A kind of forced centering structure for tunnel traverse survey inside tunnel, including bar steel plate, steel plate are two pieces of setscrew peaces Loaded on the molded section of jurisdiction of subway or on tunnel double-lining, the upper and lower angle of bracket, bracket upper horizontal is respectively welded in two pieces of bar steel plates Soldering stainless steel plate, stainless steel plate centre soldering stainless steel bolt, stainless steel bolt connect total station or the flat pedestal of essence, total station Or 360 ° of prism heads are installed on the flat pedestal of essence.
It is reinforced between the setscrew and steel plate using double nut.
The steel plate and bracket uses two-sided welding.
The stainless steel plate size is 200mm × 200mm × 5mm, is square shape
The stainless steel bolt is having a size of φ 16mm.
The bracket all uses φ 20mm round steel to carry out processing welding.
The stainless steel bolt should be greater than 300mm apart from tunnel duct piece or two lining distances, to reduce light folding by tube wall Projection is rung.
The stainless steel bolt and stainless steel plate welding position must be polished flat, in order to total station pedestal or accurate adjustment base Seat bottom surface connects closely connected with steel plate device top surface.
A kind of forced centering method for tunnel traverse survey inside tunnel, comprising the following steps:
Measuring point and fixed forced centering apparatus are arranged on completed two lining or tunnel segment structure from small mileage toward big mileage first, When controlling net repetition measurement by equipment placement on measuring point, while observing the flat pedestal of essence in the adjacent measuring point of front and back, first group of measuring point with Last group of measuring point only observes the flat pedestal of essence of above or below, this observation method can mainly be formed inside entire repetition measurement net Multiple triangulation networks or four side net forms, the inside for increasing entire control net check condition.And so on, it observes always to tunnel digging Carry sets point and forms closed polygon.
Compared with prior art, the advantageous effect of present invention is that:
A kind of detachable forced centering apparatus for tunnel traverse survey inside tunnel, device noumenon using live material processing and At processing cost is low;Cooperate 360 ° of prisms that can meet any observation angle requirement under extreme conditions;Shelf bracket is using pre- It buries expansion bolt and is attached fixation, may be reused;It drills in suitable targets position, using anchoring adhesive by expanding screw Bolt is embedded on section of jurisdiction in advance, then entire bracket is installed on above pre-buried good expansion bolt, adjusts bracket water by spacer for bolt Level state can tighten four bolts after bracket meets level requirement.After anchoring adhesive solidification, measurement target can be used as Point uses.Measurement target multi-angle observation may be implemented in the present apparatus, applicability is wide, structure is simple, easy for installation, stability is strong, Processing cost is low, occupies little space, easily recognizes, and has good promotion and application value.
Detailed description of the invention
Fig. 1 is front elevation of the invention;
Fig. 2 is side view of the invention;
Fig. 3 is top view of the invention;
Fig. 4 is live usage state diagram of the invention.
In figure: 1 bar steel plate, 2 built-in type expansion bolts, 3 Bracket for steel bar, 4 stainless steel bolts, 5 stainless steel plate pedestals, 6 The flat pedestal of essence, 7 360 degree of prism heads.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in figures 1-4, a kind of forced centering structure for tunnel traverse survey inside tunnel, including bar steel plate 1, It is characterized in that, steel plate 1 is that two pieces of setscrews 2 are installed on the molded section of jurisdiction of subway or on tunnel double-lining, two pieces of bar steel plates 1 Inferior horn on bracket 3 is respectively welded, level welding stainless steel plate 5 on bracket 3, the intermediate soldering stainless steel bolt 4 of stainless steel plate 5, no The steel bolt 4 that becomes rusty connects total station or the flat pedestal 6 of essence, installs 360 ° of prism heads 7 on total station or the flat pedestal 6 of essence.
It is reinforced between the setscrew 2 and steel plate 1 using double nut.
The steel plate 1 and bracket 3 uses two-sided welding.
The stainless steel plate 5 is square shape having a size of 200mm × 200mm × 5mm
The stainless steel bolt 4 is having a size of φ 16mm.
The bracket 3 all carries out processing welding using φ 20mm round steel.
The stainless steel bolt 4 should be greater than 300mm apart from tunnel duct piece or two lining distances, to reduce light folding by tube wall Projection is rung.
The stainless steel bolt 4 and 5 welding position of stainless steel plate must be polished flat, in order to total station pedestal or accurate adjustment 6 bottom surface of pedestal connects closely connected with 5 device top surface of steel plate.
A kind of forced centering method for tunnel traverse survey inside tunnel, comprising the following steps:
Measuring point and fixed forced centering apparatus are arranged on completed two lining or tunnel segment structure from small mileage toward big mileage first, When controlling net repetition measurement by equipment placement on measuring point, while observing the flat pedestal of essence in the adjacent measuring point of front and back, first group of measuring point with Last group of measuring point only observes the flat pedestal of essence of above or below, this observation method can mainly be formed inside entire repetition measurement net Multiple triangulation networks or four side net forms, the inside for increasing entire control net check condition.And so on, it observes always to tunnel digging Carry sets point and forms closed polygon.
By taking certain sharp radius curve as an example, in all point layouts and fixed forced centering apparatus, first will when controlling net repetition measurement For equipment placement in disposing the flat pedestal of 3# and 4# essence in No. Z1 control point, above measuring point Z2 and Y2 simultaneously, instrument and pedestal essence are flat Afterwards using whole station view Free Station observation method successively from the angle and distance of the flat pedestal of in-motion viewing 3# and 4# essence, measurement is finished and is examined After looking into qualification, by equipment placement in the angle for the angle and distance in No. Y1 control point, equally observing the flat pedestal of 3# and 4# essence And distance.When in No. Z2 control point of equipment placement, the angle and distance of the flat pedestal of 1#, 2#, 6#, 5# essence is successively observed, when When in No. Y2 control point of equipment placement, the angle and distance of the flat pedestal of 1#, 2#, 6#, 5# essence, this observation side are equally successively observed Method can mainly form multiple triangulation networks or four side net forms inside entire repetition measurement net, and the inside for increasing entire control net checks Condition.And so on, it observes always to tunnel piercing position point and forms closed polygon.

Claims (9)

1. a kind of forced centering structure for tunnel traverse survey inside tunnel, including bar steel plate (1), which is characterized in that steel plate (1) it is installed on the molded section of jurisdiction of subway or on tunnel double-lining for two pieces of setscrews (2), two pieces of bar steel plates (1) are welded respectively Connect inferior horn on bracket (3), bracket (3) upper horizontal soldering stainless steel plate (5), the intermediate soldering stainless steel bolt of stainless steel plate (5) (4), stainless steel bolt (4) connection total station or the flat pedestal (6) of essence, measure and install 360 ° of prism heads on Shi Jingping pedestal (6) (7).
2. a kind of forced centering structure for tunnel traverse survey inside tunnel according to claim 1, which is characterized in that institute It is reinforced between the setscrew (2) stated and steel plate (1) using double nut.
3. a kind of forced centering structure for tunnel traverse survey inside tunnel according to claim 1, which is characterized in that institute The steel plate (1) and bracket (3) stated use two-sided welding.
4. a kind of forced centering structure for tunnel traverse survey inside tunnel according to claim 1, which is characterized in that institute The stainless steel plate (5) stated is square shape having a size of 200mm × 200mm × 5mm.
5. a kind of forced centering structure for tunnel traverse survey inside tunnel according to claim 1, which is characterized in that institute The stainless steel bolt (4) stated is having a size of φ 16mm.
6. a kind of forced centering structure for tunnel traverse survey inside tunnel according to claim 1, which is characterized in that institute The bracket (3) stated all carries out processing welding using φ 20mm round steel.
7. a kind of forced centering structure for tunnel traverse survey inside tunnel according to claim 1, which is characterized in that institute The stainless steel bolt (4) stated should be greater than 300mm apart from tunnel duct piece or two lining distances, to reduce tube wall side anaclasis to measurement The influence of sight.
8. a kind of forced centering structure for tunnel traverse survey inside tunnel according to claim 1, which is characterized in that institute The stainless steel bolt (4) and stainless steel plate (5) welding position stated must be polished flat, in order to total station pedestal or accurate adjustment pedestal (6) bottom surface connects closely connected with steel plate (5) device top surface.
9. a kind of forced centering method for tunnel traverse survey inside tunnel, which comprises the following steps:
Measuring point and fixed forced centering apparatus are arranged on completed two lining or tunnel segment structure from small mileage toward big mileage first, When controlling net repetition measurement by equipment placement on measuring point, while observing the flat pedestal of essence in the adjacent measuring point of front and back, first group of measuring point with Last group of measuring point only observes the flat pedestal of essence of above or below, this observation method can mainly be formed inside entire repetition measurement net Multiple triangulation networks or four side net forms, the inside for increasing entire control net check condition;
And so on, it observes always to tunnel piercing position point and forms closed polygon.
CN201910262686.4A 2019-04-02 2019-04-02 A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel Pending CN109855612A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910262686.4A CN109855612A (en) 2019-04-02 2019-04-02 A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910262686.4A CN109855612A (en) 2019-04-02 2019-04-02 A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel

Publications (1)

Publication Number Publication Date
CN109855612A true CN109855612A (en) 2019-06-07

Family

ID=66902979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910262686.4A Pending CN109855612A (en) 2019-04-02 2019-04-02 A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel

Country Status (1)

Country Link
CN (1) CN109855612A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173270A (en) * 2019-06-28 2019-08-27 晏强 A kind of shield measurement total station hanging basket equipment
CN110332928A (en) * 2019-08-14 2019-10-15 中铁隧道局集团有限公司 A kind of mobile forced centering tray rack and its application method
CN111636877A (en) * 2020-04-29 2020-09-08 中交二航局第三工程有限公司 Manufacturing method of forced centering bracket with pre-buried sliding groove and T-shaped bolt
CN111854717A (en) * 2020-08-28 2020-10-30 广州市盾建地下工程有限公司 Bracket device for tunnel engineering wire net measurement and measurement method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201964889U (en) * 2011-01-26 2011-09-07 中铁一局集团有限公司 Forced centering tray of plane control points in shield tunnel
CN102174893A (en) * 2011-03-16 2011-09-07 中铁第一勘察设计院集团有限公司 Testing method for laying ballastless tracks in early stage before overall completion of super long tunnel
CN205858357U (en) * 2016-06-21 2017-01-04 中国电建集团铁路建设有限公司 Shield range restraint measures the mounting structure of forced centering bracket
CN106681374A (en) * 2017-02-20 2017-05-17 中铁二十四局集团浙江工程有限公司 Full-automatic collimation control method
CN106895820A (en) * 2017-02-09 2017-06-27 中铁二十四局集团浙江工程有限公司 The reverse coordinate transmission cultellation measuring method of tunnel shaft
CN207622748U (en) * 2017-10-25 2018-07-17 杜志刚 A kind of high-precision Tunnel construction survey backsight forced centering apparatus
CN109357667A (en) * 2018-09-30 2019-02-19 陕西省引汉济渭工程建设有限公司 The method of network forming form tunnel plane connection survey

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201964889U (en) * 2011-01-26 2011-09-07 中铁一局集团有限公司 Forced centering tray of plane control points in shield tunnel
CN102174893A (en) * 2011-03-16 2011-09-07 中铁第一勘察设计院集团有限公司 Testing method for laying ballastless tracks in early stage before overall completion of super long tunnel
CN205858357U (en) * 2016-06-21 2017-01-04 中国电建集团铁路建设有限公司 Shield range restraint measures the mounting structure of forced centering bracket
CN106895820A (en) * 2017-02-09 2017-06-27 中铁二十四局集团浙江工程有限公司 The reverse coordinate transmission cultellation measuring method of tunnel shaft
CN106681374A (en) * 2017-02-20 2017-05-17 中铁二十四局集团浙江工程有限公司 Full-automatic collimation control method
CN207622748U (en) * 2017-10-25 2018-07-17 杜志刚 A kind of high-precision Tunnel construction survey backsight forced centering apparatus
CN109357667A (en) * 2018-09-30 2019-02-19 陕西省引汉济渭工程建设有限公司 The method of network forming form tunnel plane connection survey

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173270A (en) * 2019-06-28 2019-08-27 晏强 A kind of shield measurement total station hanging basket equipment
CN110332928A (en) * 2019-08-14 2019-10-15 中铁隧道局集团有限公司 A kind of mobile forced centering tray rack and its application method
CN111636877A (en) * 2020-04-29 2020-09-08 中交二航局第三工程有限公司 Manufacturing method of forced centering bracket with pre-buried sliding groove and T-shaped bolt
CN111854717A (en) * 2020-08-28 2020-10-30 广州市盾建地下工程有限公司 Bracket device for tunnel engineering wire net measurement and measurement method thereof

Similar Documents

Publication Publication Date Title
CN109855612A (en) A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel
CN105973141B (en) A kind of duct pieces of shield tunnel faulting of slab ends measuring device
CN103292748A (en) Multi-substrate combining detection method based on laser measurement
CN105083305A (en) Tunnel state detection vehicle
CN101081986A (en) Coke oven masonry construction method employing upright line rod
CN106500677B (en) Quick and accurate bolt positioning method
CN207091890U (en) A kind of steady elevation control device of new type water
CN102419155B (en) Concrete diameter construction survey control method for cooling tower and large-scale construction barrel
CN104457788A (en) Large-size mobile base line pile and calibration method thereof
CN103940414B (en) Orientation tool
CN103016914A (en) Multifunctional forced centering leg bracket
CN206752852U (en) A kind of batter post bar reinforcement positioning device
CN204329957U (en) Transect layout device
CN209706811U (en) A kind of forced centering structure for tunnel traverse survey inside tunnel
CN207194480U (en) A kind of wall is laid bricks perpendicularity fixator
CN107764249B (en) Using method of movable tripod leveling bearing platform device
CN102759350A (en) High-altitude measuring method for construction of crane beams
CN106760227A (en) A kind of batter post bar reinforcement positioning device
CN105698755A (en) Extension-type invar bar code rod and precise leveling method thereof
CN104776840B (en) A kind of Elastic Deformation of Foundation Pit observation monument being easy to observation and observation procedure
CN203023751U (en) Multifunctional forced centering foot stool
CN203247718U (en) Steel column butt-joint mounting device
CN203256744U (en) Device for correcting perpendicularity of concrete-filled steel tubular column through reverse construction method
CN111790759A (en) Control method for continuous rolling mill installation measurement
CN207095554U (en) A kind of Wavelike steel webplate speed surveys locator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination