CN207091890U - A kind of steady elevation control device of new type water - Google Patents
A kind of steady elevation control device of new type water Download PDFInfo
- Publication number
- CN207091890U CN207091890U CN201721087508.5U CN201721087508U CN207091890U CN 207091890 U CN207091890 U CN 207091890U CN 201721087508 U CN201721087508 U CN 201721087508U CN 207091890 U CN207091890 U CN 207091890U
- Authority
- CN
- China
- Prior art keywords
- brace rod
- steel
- control device
- channel
- elevation control
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The utility model provides a kind of steady elevation control device of new type water, belongs to the steady elevation control device field of water.It solves the problems, such as the steady elevation control device low construction efficiency of existing water.The steady elevation control device of this new type water includes Steel-bar Pile, fixes sleeve is cased with Steel-bar Pile, fixing bolt one is bolted with fixes sleeve, also include gusseted, gusseted includes the brace rod and reinforcement that one end is connected with fixes sleeve outer wall, brace rod is vertical with Steel-bar Pile, the brace rod other end connects with the reinforcement other end, also include channel-section steel, channel-section steel includes two blocks of side plates and bottom plate, bottom plate is located at below brace rod, and brace rod is set through two blocks of side plates, and channel-section steel length direction is vertical with brace rod and Steel-bar Pile, channel-section steel is provided with fixed mechanism, and can be along brace rod length direction mobile beam channel, and fixed by fixed mechanism.The present apparatus substantially increases the Efficiency and accuracy of absolute altitude measuring, accelerates construction speed.
Description
Technical field
The utility model belongs to the steady elevation control device technical field of water, is related to a kind of steady elevation control device of new type water.
Background technology
Cement soil additive is as stockyard, the basic unit of road, and its thickness, the control of absolute altitude are particularly significant, directly
Connect and be related to whole stockyard, the service life of road.In work progress, because storage space is big, mileages of transport route length, water is surely applied
Work needs to be layered, divide secondary, Discrete control again, and the control of its absolute altitude, thickness is as construction quality, the key of construction speed.Tradition
Slotting reinforcing bar thread-ligating therapy, it is poor control accuracy to be present, the shortcomings of fixed wire difficulty, and is not easy to judge whether wire draws completely
Tightly, construction quality and construction speed are affected greatly, it is therefore necessary to be improved.
The content of the invention
The purpose of this utility model is to be directed to the above-mentioned problems in the prior art, there is provided one kind is repeatable to be utilized,
It is easy to control the steady absolute altitude of water, the steady elevation control device of the new type water of thickness.
The purpose of this utility model can be realized by following technical proposal:A kind of steady elevation control device of new type water, bag
Include the pointed Steel-bar Pile in bottom, in Steel-bar Pile activity be cased with fixes sleeve, being bolted with end in fixes sleeve holds out against in reinforcing bar
Fixing bolt one in stake, in addition to the gusseted being connected with fixes sleeve, gusseted are included outside one end and fixes sleeve
The brace rod and reinforcement of wall connection, brace rod is vertical with Steel-bar Pile, and the brace rod other end connects with the reinforcement other end, and it is special
Sign is:Also include channel-section steel, channel-section steel include two blocks of side plates being parallel to each other and both sides long side respectively with long sides on the downside of two blocks of side plates
The bottom plate of connection, bottom plate are located at below brace rod, and brace rod is set through two blocks of side plates, and channel-section steel length direction and brace rod
Vertical with Steel-bar Pile, described channel-section steel is provided with fixed mechanism, and described channel-section steel can be moved along brace rod length direction, and
Fixed by fixed mechanism.
After the completion of the arrangement of ballast bed course, the elevation control of surveying and locating first layer steady layer of water is needed.One is stood surely every 10m
Steel-bar Pile, it is high with the steady top mark of spirit level measuring first layer water, mobile fixes sleeve, the brace rod of gusseted is marked for control
Height, be then tightened bolt one, successively fixes all gusseteds, adjusts channel-section steel afterwards, makes some channel-section steel length directions
Alignment, then wire is placed on brace rod, two sections of tensions, wire is supported using brace rod, and the side of wire and channel-section steel
Whether plate and bottom plate are arranged at intervals, touched by side plate and bottom plate with wire, to judge whether wire tenses completely, therefore
The Efficiency and accuracy of absolute altitude measuring is substantially increased, accelerates construction speed.
In a kind of above-mentioned steady elevation control device of new type water, described fixed mechanism includes being screwed onto consolidating on bottom plate
Determine bolt two, described brace rod is thin plate-shaped structure, and the top of fixing bolt two is withstood on brace rod bottom surface.
Therefore structure is more stable.
In a kind of above-mentioned steady elevation control device of new type water, described brace rod top surface is two pieces of sides with bottom plate distance
Twice of plate opposite side distance.
Therefore steel wire rope can accurately be placed.
In a kind of above-mentioned steady elevation control device of new type water, described Steel-bar Pile is fixed with interval 10m range distributions
On the ground.
In a kind of above-mentioned steady elevation control device of new type water, described brace rod, reinforcement and fixes sleeve are mutual
Junction is by being welded and fixed.
Compared with prior art, the utility model has the following advantages that:
After the completion of the arrangement of ballast bed course, the elevation control of surveying and locating first layer steady layer of water is needed.One is stood surely every 10m
Steel-bar Pile, it is high with the steady top mark of spirit level measuring first layer water, mobile fixes sleeve, the brace rod of gusseted is marked for control
Height, be then tightened bolt one, successively fixes all gusseteds, adjusts channel-section steel afterwards, makes some channel-section steel length directions
Alignment, then wire is placed on brace rod, two sections of tensions, wire is supported using brace rod, and the side of wire and channel-section steel
Whether plate and bottom plate are arranged at intervals, touched by side plate and bottom plate with wire, to judge whether wire tenses completely, therefore
The Efficiency and accuracy of absolute altitude measuring is substantially increased, accelerates construction speed.
Brief description of the drawings
Fig. 1 and Fig. 2 is this control device use state front view and partial top view respectively.
In figure,
1st, Steel-bar Pile;11st, fixes sleeve;12nd, fixing bolt one;
2nd, gusseted;21st, brace rod;22nd, reinforcement;
3rd, channel-section steel;31st, side plate;32nd, bottom plate;33rd, fixing bolt two;
4th, wire.
Embodiment
It is specific embodiment of the utility model and with reference to accompanying drawing below, the technical solution of the utility model is made further
Description, but the utility model is not limited to these embodiments.
As depicted in figs. 1 and 2, the steady elevation control device of a kind of new type water of the utility model, including the steel that bottom is pointed
Muscle stake 1, in Steel-bar Pile 1 activity be cased with fixes sleeve 11, end is bolted with fixes sleeve 11 and holds out against the fixation in Steel-bar Pile 1
Bolt 1, in addition to the gusseted 2 being connected with fixes sleeve 11, gusseted 2 include one end and the outer wall of fixes sleeve 11
The brace rod 21 and reinforcement 22 of connection, brace rod 21 is vertical with Steel-bar Pile 1, the other end of brace rod 21 and the other end of reinforcement 22
Connection, in addition to channel-section steel 3, channel-section steel 3 include two blocks of side plates 31 being parallel to each other and both sides long side respectively with two pieces of downsides of side plates 31
The bottom plate 32 of long side connection, bottom plate 32 is located at the lower section of brace rod 21, and brace rod 21 is set through two blocks of side plates 31, and channel-section steel 3
Length direction is vertical with brace rod 21 and Steel-bar Pile 1, and channel-section steel 3 is provided with fixed mechanism, and can be along the length direction of brace rod 21
Mobile beam channel 3, and fixed by fixed mechanism.
Further, fixed mechanism includes the fixing bolt 2 33 being screwed onto on bottom plate 32, and brace rod 21 is lamellar knot
Structure, and the top of fixing bolt 2 33 is withstood on the bottom surface of brace rod 21.The top surface of brace rod 21 and bottom plate 32 are apart from for two blocks of side plates 31
Twice of opposite side distance.Steel-bar Pile 1 is fixed on the ground with interval 10m range distributions.Brace rod 21, reinforcement 22 and solid
Determine at the interconnection of sleeve 11 by being welded and fixed.
After the completion of the arrangement of ballast bed course, the elevation control of surveying and locating first layer steady layer of water is needed.One is stood surely every 10m
Steel-bar Pile 1, mobile fixes sleeve 11 high with the steady top mark of spirit level measuring first layer water, the brace rod 21 for making gusseted 2 are
Elevation control, be then tightened bolt 1, successively fixes all gusseteds 2, adjusts channel-section steel 3 afterwards, makes some grooves
The length direction of steel 3 is alignd, then wire 4 is placed on brace rod 21, and two sections of tensions, wire 4 is supported using brace rod 21, and
Whether the side plate 31 and bottom plate 32 of wire 4 and channel-section steel 3 are arranged at intervals, touched by side plate 31 and bottom plate 32 with wire 4, with
Judge whether wire 4 tenses completely, therefore substantially increase the Efficiency and accuracy of absolute altitude measuring, accelerate construction speed.
Specific embodiment described herein is only to the utility model spirit explanation for example.The utility model institute
Category those skilled in the art can make various modifications or supplement to described specific embodiment or using similar
Mode substitute, but without departing from spirit of the present utility model or surmount scope defined in appended claims.
Although Steel-bar Pile 1, fixes sleeve 11, fixing bolt 1, gusseted 2, brace rod have more been used herein
21st, the term such as reinforcement 22, channel-section steel 3, side plate 31, bottom plate 32, fixing bolt 2 33, wire 4, but be not precluded from using other
The possibility of term.It is used for the purpose of more easily describing and explaining essence of the present utility model using these terms;Them
Any additional limitation is construed to all to disagree with the utility model spirit.
Claims (5)
1. a kind of steady elevation control device of new type water, including the Steel-bar Pile (1) that bottom is pointed, in Steel-bar Pile (1) activity be cased with
Fixes sleeve (11), end is bolted with fixes sleeve (11) and holds out against the fixing bolt one (12) in Steel-bar Pile (1), in addition to
The gusseted (2) being connected with fixes sleeve (11), gusseted (2) include the branch that one end is connected with fixes sleeve (11) outer wall
Muscle (21) and reinforcement (22) are supportted, brace rod (21) is vertical with Steel-bar Pile (1), and brace rod (21) other end and reinforcement (22) are another
One end connects, it is characterised in that:Also include channel-section steel (3), channel-section steel (3) includes two pieces of side plates (31) and the both sides long side being parallel to each other
The bottom plate (32) being connected respectively with long side on the downside of two pieces of side plates (31), bottom plate (32) is located at below brace rod (21), and brace rod
(21) set through two pieces of side plates (31), and channel-section steel (3) length direction is vertical with brace rod (21) and Steel-bar Pile (1), it is described
Channel-section steel (3) is provided with fixed mechanism, and described channel-section steel (3) can be moved along brace rod (21) length direction, and passes through fixation
Mechanism is fixed.
A kind of 2. steady elevation control device of new type water according to claim 1, it is characterised in that:Described fixed mechanism bag
Include the fixing bolt two (33) being screwed onto on bottom plate (32), described brace rod (21) is thin plate-shaped structure, and fixing bolt two
(33) top is withstood on brace rod (21) bottom surface.
A kind of 3. steady elevation control device of new type water according to claim 2, it is characterised in that:Described brace rod (21)
Top surface is with bottom plate (32) apart from twice for two pieces of side plate (31) opposite side distances.
A kind of 4. steady elevation control device of new type water according to claim 3, it is characterised in that:Described Steel-bar Pile (1)
Fixed on the ground with interval 10m range distributions.
A kind of 5. steady elevation control device of new type water according to claim 4, it is characterised in that:Described brace rod
(21), by being welded and fixed at reinforcement (22) and fixes sleeve (11) interconnection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721087508.5U CN207091890U (en) | 2017-08-28 | 2017-08-28 | A kind of steady elevation control device of new type water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721087508.5U CN207091890U (en) | 2017-08-28 | 2017-08-28 | A kind of steady elevation control device of new type water |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207091890U true CN207091890U (en) | 2018-03-13 |
Family
ID=61538998
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721087508.5U Active CN207091890U (en) | 2017-08-28 | 2017-08-28 | A kind of steady elevation control device of new type water |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207091890U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108978409A (en) * | 2018-08-18 | 2018-12-11 | 重庆交通大学 | Thread-laying device |
CN110424228A (en) * | 2019-08-19 | 2019-11-08 | 中国二十二冶集团有限公司 | Construction site temporary road height controller and control method |
CN111236023A (en) * | 2020-03-24 | 2020-06-05 | 中冶天工集团天津有限公司 | Device and method for controlling road construction elevation and edge boundary position |
CN114855567A (en) * | 2022-04-08 | 2022-08-05 | 山东九强集团有限公司 | Novel elevation control that paves of basic unit device |
-
2017
- 2017-08-28 CN CN201721087508.5U patent/CN207091890U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108978409A (en) * | 2018-08-18 | 2018-12-11 | 重庆交通大学 | Thread-laying device |
CN108978409B (en) * | 2018-08-18 | 2021-05-25 | 重庆交通大学 | Wire hanging device |
CN110424228A (en) * | 2019-08-19 | 2019-11-08 | 中国二十二冶集团有限公司 | Construction site temporary road height controller and control method |
CN111236023A (en) * | 2020-03-24 | 2020-06-05 | 中冶天工集团天津有限公司 | Device and method for controlling road construction elevation and edge boundary position |
CN114855567A (en) * | 2022-04-08 | 2022-08-05 | 山东九强集团有限公司 | Novel elevation control that paves of basic unit device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207091890U (en) | A kind of steady elevation control device of new type water | |
CN206267152U (en) | Prefabricated pipe gallery installs alignment system | |
CN101081986B (en) | Coke oven masonry construction method employing upright line rod | |
CN207048069U (en) | A kind of pipe gallery segmental timbering | |
CN203247603U (en) | High-order rag bolt positioner | |
CN108979130A (en) | A kind of the side wall unilateral side vertical mold device and construction method of adjustable formwork height | |
CN207295764U (en) | City integrated piping lane self-propelled hydraulic trolley formwork | |
EP1075397B1 (en) | Support structure for elevated railed-vehicle guideway | |
CN105951616A (en) | Construction method for large-diameter assembled steel corrugated pipe culvert | |
CN109235292A (en) | Railroad bridge changes beam process and changes girder system system | |
CN107338810A (en) | City integrated piping lane self-propelled hydraulic trolley formwork and its construction method | |
CN113622316A (en) | Steel truss girder multipoint traction type pushing construction system and construction method thereof | |
CN112281900A (en) | Construction method of cement tank | |
CN206772307U (en) | A kind of measurement apparatus for coordinating total powerstation to check the positioning of concrete steel trolley formwork | |
CN103344214A (en) | 1.6-degree parabolic extralarge pier measuring and pier body linear control method | |
CN109024676A (en) | A kind of formwork bracing system and its construction method of cast-in-place pipe gallery | |
CN112854004A (en) | Fish-bellied box girder column type support construction method | |
CN108867316A (en) | Single-tower self-anchored suspension bridge Large-span Steel Box Beam walking incremental launching construction technique | |
CN206205012U (en) | A kind of SMW engineering methods stake inclinometer pipe installation aiding device | |
CN210658028U (en) | Continuous rigid frame bridge 0# block support with decorative plate | |
CN211599721U (en) | Pipe jacking direction calibration system for underground pipeline laying engineering | |
CN108132034A (en) | A kind of evacuation platform, one fluid measurement device of looped network cable bearer | |
CN108277826A (en) | Single cabin piping lane and the spelling flat underground pipe gallery in the more cabins of cabin formula | |
CN109707397B (en) | Pipe curtain construction method | |
CN207317808U (en) | It is used for the auxiliary device of monitoring and controlling center line in railway box culvert jack-in process |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |