CN205858357U - Shield range restraint measures the mounting structure of forced centering bracket - Google Patents

Shield range restraint measures the mounting structure of forced centering bracket Download PDF

Info

Publication number
CN205858357U
CN205858357U CN201620617946.7U CN201620617946U CN205858357U CN 205858357 U CN205858357 U CN 205858357U CN 201620617946 U CN201620617946 U CN 201620617946U CN 205858357 U CN205858357 U CN 205858357U
Authority
CN
China
Prior art keywords
otic placodes
bolt
gripper shoe
connecting plate
mounting structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620617946.7U
Other languages
Chinese (zh)
Inventor
汪志锋
张洪召
刘文丽
牛玉强
王子良
杜放
张干
曾松
林小帅
张其浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Stecol Corp
PowerChina Railway Construction Co Ltd
Original Assignee
PowerChina Railway Construction Co Ltd
Sinohydro Tianjin Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Railway Construction Co Ltd, Sinohydro Tianjin Engineering Co Ltd filed Critical PowerChina Railway Construction Co Ltd
Priority to CN201620617946.7U priority Critical patent/CN205858357U/en
Application granted granted Critical
Publication of CN205858357U publication Critical patent/CN205858357U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

Shield range restraint measures the mounting structure of forced centering bracket, bracket includes setting up and down two otic placode, two otic placodes form angle, the medial surface of two otic placodes forms locating surface and lower locating surface respectively, it is provided with connecting plate between two otic placodes, connecting plate connects near the position of upper end gripper shoe, the upper surface of gripper shoe forms measuring instrument mounting platform, position near middle part is welded with shank of bolt on the supporting plate, it is connected between connecting plate with gripper shoe and has tilt prop, make three form triangle joint structure;Two otic placodes pass through on the two ends locating surface of the two locating surfaces snap one group of prefabricated hoop bolt connecting hole in the two panels section of jurisdiction building block that existing tunnel is circumferentially-adjacent respectively, and by being fixed in the building block of two panels section of jurisdiction through the hoop segment bolt of the installing hole on this group prefabricated hoop bolt connecting hole and two otic placodes.This mounting structure avoid bury underground bottom tunnel duct piece observe mark, measure time saving and energy saving, do not affect construction progress, improve to measure point certainty of measurement.

Description

Shield range restraint measures the mounting structure of forced centering bracket
Technical field
This utility model engineering relates to tunneling shield field of measuring technique, measures strong particularly to a kind of shield range restraint The mounting structure of centering bracket processed.
Background technology
During tunneling shield, for obtain shield machine position coordinate figure, frequently with mode be by range restraint Measure.Traditional construction measuring method is to set up moveable support in integrated tunnel, places measuring instrument on support, and Bury observation mark in the bottom of existing tunnel duct piece building block, realize right along tunnel fore-and-aft direction of measuring instrument by observation mark In, leveling.The method is time-consuming, laborious, and bottom observation mark destructible, and in hindering hole bottom section of jurisdiction, electromobile comes in and goes out, thus Affect construction speed.
Summary of the invention
This utility model provides one to avoid bottom tunnel duct piece for solving technical problem present in known technology Bury underground observe mark, measure time saving and energy saving, do not affect construction progress and improve the shield range restraint of certainty of measurement measuring point Measure the mounting structure of forced centering bracket.
This utility model is adopted the technical scheme that by solving technical problem present in known technology:
Shield range restraint measures the mounting structure of forced centering bracket, and its feature exists: bracket includes setting up and down Two otic placodes, are provided with installing hole on two otic placodes, and two otic placodes form angle, and it is fixed that the medial surface of two otic placodes is formed respectively Plane and lower locating surface, be provided with connecting plate between two otic placodes, and connecting plate connects near the position of upper end to be had and horizontally outward extend Gripper shoe, the upper surface of gripper shoe forms measuring instrument mounting platform, on the supporting plate the position near middle part be welded with for The shank of bolt of fixation measuring instrument, is connected between connecting plate with gripper shoe and has tilt prop, and connecting plate, gripper shoe and tilt prop are formed Triangle joint structure;Two otic placodes pass through the snaps respectively of two locating surfaces in the two panels section of jurisdiction building block that existing tunnel is circumferentially adjacent One group of prefabricated hoop bolt connecting hole two ends locating surface on, and by through this group prefabricated hoop bolt connecting hole and two The hoop segment bolt of the connecting hole on otic placode is fixed in described two panels section of jurisdiction building block, and this group prefabricated hoop bolt connecting hole sets Put the position on the lower side at the middle part in tunnel or middle part.
Preferred: two otic placodes, connecting plate, gripper shoe, tilt prop and shank of bolt are all attached by welding manner.
This utility model has the advantage that with good effect:
Use this mounting structure, when carrying out range restraint measurement during tunneling shield, can walking along shield tunnel To, at interval of a certain distance, a pack support mounting structure is fixed on setting position on tunnel duct piece, thus protect Demonstrate,prove the measuring instrument being arranged on front and back support and be in the position of centering, so there is no need to bury observation underground in the bottom of section of jurisdiction Mark, makes measurement operation time saving and energy saving, owing to need not arrange observation mark bottom section of jurisdiction, this way it is ensured that electromobile is in tunnel Come in and go out smoothly, thus avoid and construction progress is impacted, it addition, this kind of mounting means of support, also improve measuring point Certainty of measurement.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation of bracket in Fig. 1;
Fig. 3 is the axonometric chart of bracket in Fig. 2.
In figure: 1, bracket;1-1, otic placode;1-1-1, installing hole;1-2, connecting plate;1-3, gripper shoe;1-4, shank of bolt;1- 5, tilt prop;2, section of jurisdiction building block;3, hoop segment bolt.
Detailed description of the invention
For summary of the invention of the present utility model, feature and effect can be further appreciated that, hereby enumerate following example, and coordinate Accompanying drawing describes in detail as follows:
Refer to Fig. 1-3, the mounting structure of shield range restraint measurement forced centering bracket:
Bracket 1 includes setting up and down two otic placode 1-1, is provided with installing hole 1-1-1, two otic placode shapes on two otic placodes Becoming angle, the medial surface of two otic placodes forms locating surface and lower locating surface respectively, is provided with connecting plate 1-2 between two otic placodes, Connecting plate connects near the position of upper end gripper shoe 1-3 horizontally outward extended, and the upper surface of gripper shoe forms measuring instrument peace Assembling platform, the position near middle part is welded with the shank of bolt 1-4 for fixation measuring instrument on the supporting plate, in connecting plate and support Connecting between plate and have tilt prop 1-5, connecting plate, gripper shoe and tilt prop form triangle joint structure.
Two otic placodes pass through two locating surfaces snaps respectively, in the two panels section of jurisdiction building block 2 that existing tunnel is circumferentially adjacent Organize on the two ends locating surface of prefabricated hoop bolt connecting hole, the angle of two side-locating faces formation of i.e. two otic placodes and two side-locating faces Between distance and shield tunnel in the location, two ends of prefabricated hoop bolt connecting hole in circumferentially adjacent two panels section of jurisdiction building block The distance between angle and two ends locating surface between face is the most consistent.And above-mentioned two otic placodes are by through this group prefabricated hoop bolt The hoop segment bolt 3 of the installing hole on connecting hole and two otic placodes is fixed in described two panels section of jurisdiction building block, the prefabricated ring of this group It is arranged in the middle part of tunnel to bolt connecting hole or position that middle part is on the lower side.
In said structure, two otic placodes, connecting plate, gripper shoe, tilt prop and shank of bolt are all attached by welding manner.
This mounting structure needs to carry out site operation, concrete, installation site at the one of first selected carrier, preferred position For the position that the middle part in existing tunnel and middle part are on the lower side, i.e. 3, clock~the position of 5 or 7~the position of 9;Then use The hoop segment bolt of the connection two section of jurisdiction building block of this position is unloaded and falls down by adjustable wrench;Then the snap respectively of two otic placodes On the end locating surface of the prefabricated hoop bolt connecting hole of two section of jurisdiction building blocks, original effect of both ends locating surface is: one end End locating surface for positioning the nut of hoop segment bolt bar, the end locating surface of the other end is joined with shank of bolt for location The nut closed;Put on hoop segment bolt the most again, by hoop bolt, two otic placodes are fixed in two section of jurisdiction building blocks;Then will Connecting plate, gripper shoe, tilt prop and shank of bolt weld successively, form the mounting structure of this bracket.Wherein, support in welding During plate, need horizon rule test level rear solderable;Finally stick the sign of " surveying marker notes protection ", spray control Point is numbered.During shield tunnel construction, along with shield machine advances, usual shield range restraint is measured forced centering and is used Bracket, installs at one every 150m-200m, and the installation process of its elsewhere is identical with above-mentioned installation process.Bracket is completed in tunnel Rear is dismountable.

Claims (2)

1. shield range restraint measures the mounting structure of forced centering bracket, and its feature exists: bracket includes setting up and down two Individual otic placode, is provided with installing hole on two otic placodes, and two otic placodes form angle, and the medial surface of two otic placodes forms location respectively Face and lower locating surface, be provided with connecting plate between two otic placodes, and connecting plate connects to have near the position of upper end and horizontally outward extends Gripper shoe, the upper surface of gripper shoe forms measuring instrument mounting platform, and the position near middle part is welded with for solid on the supporting plate Determining the shank of bolt of measuring instrument, be connected and have tilt prop between connecting plate with gripper shoe, connecting plate, gripper shoe and tilt prop form three Angle attachment structure;Two otic placodes pass through the snaps respectively of two locating surfaces in the two panels section of jurisdiction building block that existing tunnel is circumferentially adjacent On the two ends locating surface of one group of prefabricated hoop bolt connecting hole, and by through this group prefabricated hoop bolt connecting hole and two ears The hoop segment bolt of the connecting hole on plate is fixed in described two panels section of jurisdiction building block, and this group prefabricated hoop bolt connecting hole is arranged In the position that the middle part in tunnel or middle part are on the lower side.
Shield range restraint the most according to claim 1 measures the mounting structure of forced centering bracket, it is characterised in that: Two otic placodes, connecting plate, gripper shoe, tilt prop and shank of bolt are all attached by welding manner.
CN201620617946.7U 2016-06-21 2016-06-21 Shield range restraint measures the mounting structure of forced centering bracket Expired - Fee Related CN205858357U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620617946.7U CN205858357U (en) 2016-06-21 2016-06-21 Shield range restraint measures the mounting structure of forced centering bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620617946.7U CN205858357U (en) 2016-06-21 2016-06-21 Shield range restraint measures the mounting structure of forced centering bracket

Publications (1)

Publication Number Publication Date
CN205858357U true CN205858357U (en) 2017-01-04

Family

ID=57637432

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620617946.7U Expired - Fee Related CN205858357U (en) 2016-06-21 2016-06-21 Shield range restraint measures the mounting structure of forced centering bracket

Country Status (1)

Country Link
CN (1) CN205858357U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108663692A (en) * 2018-06-08 2018-10-16 湖南玛伽克蓝箭科技有限公司 Mounting structure of the global position system on carrier
CN109855612A (en) * 2019-04-02 2019-06-07 中铁十二局集团有限公司 A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel
CN111636877A (en) * 2020-04-29 2020-09-08 中交二航局第三工程有限公司 Manufacturing method of forced centering bracket with pre-buried sliding groove and T-shaped bolt
CN111854717A (en) * 2020-08-28 2020-10-30 广州市盾建地下工程有限公司 Bracket device for tunnel engineering wire net measurement and measurement method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108663692A (en) * 2018-06-08 2018-10-16 湖南玛伽克蓝箭科技有限公司 Mounting structure of the global position system on carrier
CN109855612A (en) * 2019-04-02 2019-06-07 中铁十二局集团有限公司 A kind of forced centering structure and its centering method for tunnel traverse survey inside tunnel
CN111636877A (en) * 2020-04-29 2020-09-08 中交二航局第三工程有限公司 Manufacturing method of forced centering bracket with pre-buried sliding groove and T-shaped bolt
CN111854717A (en) * 2020-08-28 2020-10-30 广州市盾建地下工程有限公司 Bracket device for tunnel engineering wire net measurement and measurement method thereof

Similar Documents

Publication Publication Date Title
CN205858357U (en) Shield range restraint measures the mounting structure of forced centering bracket
CN105673041B (en) A kind of general ring pipe sheet assembling point position of subway shield tunnel construction determines method
CN207048069U (en) A kind of pipe gallery segmental timbering
CN106638318B (en) The localization method and cable guide pipe installation method of cable-stayed bridge beam-ends anchor point
CN107633121B (en) Iron tower reinforcing support construction method based on BIM
CN107090775A (en) A kind of full framing space beam-ends cable guide pipe construction localization method
CN109281688B (en) Tunnel advanced pipe shed accurate positioning system and construction method
CN205858356U (en) Attitude of shield machine controls the mounting structure of total powerstation support hanging basket
CN105783925A (en) System and method for positioning drill jambo body
CN205120090U (en) Instrument is used in soil survey and drawing
CN107905108A (en) Tubular arch bolted web member hole group's accuracy control method
JP4596901B2 (en) Displacement measurement method and method
CN106289164A (en) A kind of cavern section method for fast measuring
CN110130413A (en) Pit retaining monitoring method based on underground datum mark arrangement
CN104964674A (en) Control net used for large structure building size
CN205556725U (en) Elevation detection auxiliary device is built by laying bricks or stones to blast furnace carbon brick
CN209067219U (en) Accurate positioning system for tunnel advanced pipe shed
CN208333482U (en) A kind of instrument support suitable for steel construction measurement correction
CN204959586U (en) Channel device of soft base face declivity
CN207622756U (en) A kind of cylinder pier measurement and positioning frame
CN215217462U (en) Calibration system of profile blast hole
CN115014304B (en) Station building and station moving method of coal mine underground total station positioning system
CN218762262U (en) Tool for erecting measuring instrument
CN218759921U (en) Forced centering structure for shield tunnel lead measurement
CN109269434A (en) A kind of straight mounted palisades deformation laser scanning system and its application method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170104